US Army Corps of Engineers Kansas City District You Matter - We Care

SCOPE OF WORK (SOW)

CONCRETE TRUNNION GIRDER JOINT SEALANT REPAIR

HARRY S. TRUMAN LAKE PROJECT OFFICE

U. S. ARMY CORPS OF ENGINEERS

01 June 2018

1.0 Project Scope:

The purpose of this project is to remove and replace the joint sealant around the caps of the Trunnion

Girders and at the locations where the Trunnion Girders meet the piers. The contractor will be responsible for furnishing all labor, equipment, materials, and transportation to provide sealed trunnion girders. The contractor shall ensure that all work is in compliance with the referenced codes and specifications listed in this scope of work.

2.0 Project Location:

Harry S. Truman Project Office

15968 Truman Road

Warsaw, MO 65355

3.0 Harry S. Truman Contacts:

Primary Point of Contact (POC) and Harry S. Truman Assistant Superintendent

Daniel Franklin, Daniel.C.Franklin@usace.army.mil

816-389-3682

Operations Program Manager (OPM) at Harry S. Truman Lake

James Sandberg james.d.sandberg@usace.army.mil

816-389-3869

4.0 Site Visit:

Bidders who wish to request a site visit should contact the primary POC or the OPM to schedule an appointment. When calling or emailing, please identify yourself as a bidder for the CONCRETE

TRUNNION GIRDER JOINT SEALANT REPAIR contract.

5.0 References:

References pertain to standard specifications of any technical society, organization or association, or to codes, manuals, or regulations. The latest edition of these codes and standards shall be used for this contract. When any reference refers to the “government authority” or the authority having

“jurisdiction”, this reference will be interpreted as referring to the Contracting Officer. The

Contractor must also abide by the safety regulations listed in the engineering manual mentioned below. Copies of this manual are available electronically on the USACE Safety and Occupational

Health Office web site: http://www.usace.army.mil/Safety-and-Occupational-Health/. All the joint sealant shall be placed in accordance with the documents listed below as well as by using the manufacturer’s installation requirements. The existing components and new joint sealant shall work together to form a fully functioning system.

EM 385-1-1 Safety and Health Requirements - English

EM 1110-2-2102 Waterstops and Other Preformed Joint Materials for Civil Works Structures

Kansas City District

6.0 Project Discussion:

There are a total of five Trunnion Girders in this project. Each trunnion girder has caps located around the perimeter. Please see attached drawings for cap locations. The concrete cap covers prevent potential corrosion of the prestressing bars in the trunnion girder.

The trunnion girders are best accessed from above. A government approved method of access is required to access the trunnion girder cap sealants. The chosen method shall be in compliance with the US Army Corps of Engineers (USACE) EM 385-1-1 Safety and Health Requirements. The trunnion girders are not accessible from the non-overflow section (left embankment) and are accessible by catwalk from the powerhouse or stairs from the roadway. Access to the girders must be obtained by a catwalk, climbing a ladder, and going up stairs to the pier. Photos are provided in

Part 13 of this scope of work.

7.0 Contractor Requirements:

The contractor will be responsible for (but not limited to) the following requirements:

7.1. The Contractor shall be responsible for videoing the initial condition of the trunnion girders prior to starting any work. The contractor shall also complete a final video showing that the condition of the trunnion girders is equal to or better than the initial condition after the repair is completed.

7.2. Prior to the new joint sealant installation, the joint shall be prepared for the new sealant according to the manufacturer’s specifications. The Contractor shall provide safe access for a government representative to inspect the conditions of the prepared joint prior to sealing.

7.3. If during joint sealant removal, concrete surrounding the joint begins spalling or cracking, then the Contractor shall immediately stop sealant removal and shall provide safe access for a contracting officer representative (COR) to inspect the conditions of the joint.

7.4. The Contractor will be responsible for removing and disposal of the waste materials from the work site. Measures shall be taken to prevent waste materials from falling onto the spillway below. All unused, unopened materials shall be returned to the government.

7.5. The contractor shall provide all necessary electrical power and compressed air capabilities not otherwise identified in these specifications. The contractor shall coordinate electrical power needs with the Contracting Officer or the COR.

8.0 Working Hours:

Arrangement and scheduling of working hours and crews shall be coordinated with the Government.

The Power Plant staff work hours are 6:30 a.m. to 4:30 p.m., Monday through Friday. Contractor personnel are permitted to work between the hours of 6:30 a.m. and 4:00 p.m., Monday through

Friday. Saturdays, Sundays and federal holidays are non-work days. Working hours which are proposed to be different from that suggested above shall be coordinated and approved by the COR.

9.0 Period of Performance:

Field work shall start within 30 calendar days from the date the Notice to Proceed (NTP) is issued and be completed within 60 days of the issued NTP date.

Kansas City District

9.1 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER: Once outdoor work begins, adverse weather that causes delays to the work will be granted on a day-for-day basis. Adverse weather delays are based on National Oceanic and atmospheric

Administration (NOAA) or similar data for the project location and will constitute the base line for weather time evaluations. These delays shall be coordinated with the contracting officer.

10.0 Logistics:

The logistics for storage space and restrooms shall be coordinated with the Harry S. Truman staff indicated above.

11.0 Emergency Removal of Equipment:

The U.S. Government reserves the right to inform the contractor that they have 24 hours to vacate the powerhouse. All equipment and material that is not permanently placed shall be removed in this timeframe.

12.0 Traffic Control:

If the Contractor deems necessary, the roadway on the dam shall be closed during the duration of the work. However, after normal working hours, the roadway must be reopened. Traffic control and roadway closure will be provided by the Powerhouse staff, upon request, of the Contractor. If road closure is necessary, please provide, at minimum, a seven (7) day notice to both of the contacts mentioned below.

13.0 Power Availability:

Electrical power 120v, 20 amp capabilities are available on the catwalk over the spillway at each tainter gate. The contractor shall provide all necessary compressed air capabilities and electrical power or means to use the available electrical power capabilities. The contractor shall coordinate electrical power needs with the POC.

14.0 Security Requirements:

The Power Plant gates are locked during normal duty hours. The Contractors on-site supervisor shall work with the Truman Power Plant personnel for entry procedures. An Employee Identification and

Control Procedure shall be submitted for approval for identification and control of employees entering or leaving the Power Plant. After the stated Government personnel working hours, the

Power Plant gate accesses are locked. Contractor's personnel will not have access into the work area except during approved work hours. The security of the Contractor's property and items furnished under this contract, until accepted, are the responsibility of the Contractor whether stored inside or outside the power plant security gate.

14.1 Identification of Contractor's Employees:

A. The Contractor shall comply with the Power Plant's security policy that requires everyone to have an Identification Badge. The Contractor shall furnish employees with government approved Identification badges. As a minimum, the following information shall be shown on the badges:

Name of Contractor

Name of Employee

Birth date

Weight

Hair Color

Kansas City District

Eye Color

B. A photograph of each Contractor employee shall be displayed on the employee's badge. At all times, while working at the Power Plant, the Contractor employee shall wear this ID card visibly. The Contractor shall submit a complete List of Personnel on Site listing of all personnel and their titles that will be working on the project at the weekly Coordination Meeting. This listing shall be revised and resubmitted when personnel changes occur. The Contractor shall recover all badges from employees that will no longer be working at the site.

14.2 Physical and Cyber Security:

The contractor shall be responsible for safeguarding all Government equipment, information and property provided for contractor use and copies of programming performed by Contractor. At the close of each work period, Government facilities, equipment, and materials shall be secured.

The Contractors' personnel that will be entering the Powerhouse will be required to have a

7-year Background Investigation (BI) at the local police department. All personnel shall obtain a BI and submit to the Contracting Officer prior to working on this project.

Personnel who already have an OPM background investigation shall submit evidence to document the clearance. Social Security Numbers will be required for background investigation verification.

Escort Requirements - Contractor's personnel not cleared for authorized unescorted access to the Powerhouse may be escorted by Contractor's personnel that have authorized unescorted access to the Powerhouse. Escorts must remain within arm’s reach of the person they are escorting. Escorts are discouraged and should only be used for brief periods of time when work is not being performed. Prior to access, coordination with the Power Plant

Superintendent is required, including but not limited to:

(1) Verification of identity via picture identification

(2) Name of escorting individual and verification of unescorted status

(3) Time of entry into the Powerhouse

(4) Time exiting the Powerhouse

The contractor's Superintendent shall monitor, train, retain record, and initiates background investigations for all on-site personnel. The Superintendent will initiate background investigations: train subordinates on NWK Cyber Security policies: retain records for audit purposes: issue and control workers badges as a security control. The Superintendent will be the POC for the COR to verify compliance with Physical and Cyber Security Policies described above.

14.3 Contractor's Personnel Background Investigation:

A minimum of fifteen days prior to engaging in work, the Contractor shall submit, to the

COR, a Background Investigation (BI) for each personnel requiring authorized unescorted access to the Powerhouse. The Contractor's personnel will only be allowed authorized unescorted physical access after the BI is submitted to and approved by the Government.

Kansas City District

Contractor's personnel shall not be on parole or have been convicted of a felony within the last seven years or be a foreign national. If a foreign national is designated by the Contractor as a Subject Matter Expert, the District Commander must approve their appointment and the

Department of State must approve the background investigation (in addition to the NACI and

PSIP requirements above). Foreign national background investigations may take 3-4 weeks longer to obtain than a NACI, therefore, the Contractor should plan accordingly. The

Government reserves the right to screen any and all Contractor's personnel on security and to reject those who do not meet the qualifications.

The Contractor shall be responsible for identifying any foreign-born non-US citizen among his employees. The Contractor shall then submit this list of persons along with photocopies of their valid US driver's license and either passport or green card 30 days in advance of the expected date of the employee(s) beginning work at the Power Plant. This information shall be submitted to the COR. These non-citizen employees will only be permitted to work at the

Power Plant after they have gone through security examination.

15.0 Submittal Requirements:

Government approval is required for submittals. Allow 7 business days (Monday – Friday) for

Government review of submittals prior to commencement of work. Rejected submittals shall be resubmitted. The approval of submittals shall not be construed as a complete check and will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work.

15.1 Format of submittals: Mark each copy of each submittal identically, with the following:

A. Project title and location.

B. Construction contract number.

C. Submittal description.

D. When a resubmission, indicate resubmission number.

E. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with the submittal.

F. Product identification and location in project.

15.2 Copies: An electronic copy and One (1) hard copy of each submittal shall be submitted for review to the following recipient(s).

Engineering Technician, Harry S. Truman Power Plant

Paul Burns

Paul.E.Burns@usace.army.mil

US Army Corps of Engineers

Harry S. Truman Project Office

15968 Truman Road

Warsaw, MO 65355

Structural Engineer, Kansas City District Office

Paul Muller

Paul.D.Muller@usace.army.mil

US Army Corps of Engineers: ED-DS, RM 502

601 E. 12th Street

Kansas City, MO 64106

Kansas City District

15.3 Pre-construction Submittal Requirements: The contractor shall provide the following for government approval at least seven (7) days prior to beginning field work unless otherwise noted.

A. The Contractor shall submit their work schedule based on the limitations noting the following items.

1. The contractor shall provide the work schedule within fourteen (14) calendar days after receiving the notice to proceed (NTP).

2. Field Work Start Date: Start within thirty (30) calendar days after the contractor is given NTP.

3. Field Work End Date: Sixty (60) calendar days after the contractor is given

NTP.

B. Provide a work plan.

C. Provide a site and trunnion girder access plan.

D. Provide a plan of the measures that will be taken to protect the unsealed joints from moisture.

E. Provide an Accident Prevention Plan and Activity Hazard Analysis (AHA) per EM 385-

1-1.

F. Provide a Quality Control Plan.

15.4 Construction Submittal Requirements: The contractor shall provide the following for government approval at least seven (7) days prior to beginning field work unless otherwise noted.

A. The manufacturer’s written product information, installation procedures and instructional information for the chosen sealant and waterproofing system.

16.0 Submittal Descriptions: The following information is intended to provide detailed information on what shall be submitted for each submittal.

16.1 Work Plan: Submit a detailed work plan to perform the work on the five (5) trunnion girders in accordance with these specifications. Information shall include accessing the joint sealant locations, removal, replacements, repairs and waterproofing required, road closures, power sources, collection and removal of debris, etc. Submit a list of proposed equipment to be used in performance of construction work including descriptive data. Submit detailed information on the method to be used to access the trunnion girders. Note: The top of the roadway is at elevation 758.6 feet, the top of the trunnion girder is at elevation 711.53, and the bottom of the trunnion girders is at elevation 704.53.

16.2 Schedule: Submit a work schedule based on the following limitations:

a. Normal duty hours for work shall be from 6:30 a.m. to 4:00 p.m., Monday through

Friday (excluding holidays).

b. Requests for additional duty hours shall require written approval from the Contracting

Officer seven (7) days in advance of the proposed work period.

16.3 Product Data: Submit manufacturer’s literature from supplier, such as catalog cuts, illustrations, specifications that detail the material products to be used.

A. Manufacturer's Recommendations: Where installation procedures, or any part thereof, are required to be in accordance with the manufacturer's recommendations, printed copies of these recommendations shall be submitted. Installation of the material will not be allowed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.

Kansas City District

16.4 Accident Prevention Plan: Submit detailed information on safety measures of the equipment and other safety measures to be taken in accordance with the latest version of the

USACE safety manual EM 385-1-1. An outline of the safety plan is provided in EM 385-1-

1. Specifically identify who the designated Site Safety and Health Officer will be and address personal protective equipment, tools, and hoists/climbing equipment necessary to this work.

16.5 Quality Control Plan:

The Contractor is responsible for providing and maintaining an effective Quality Control

Program. A Quality Control Plan shall be provided within 10 days of Notice to Proceed, prior to the start of work and shall include the following:

A. Identification of the designated Quality Control Manager/Site Superintendent who will be onsite during construction operations and who will have the authority to act for the Contractor to include the authority to stop work which is not in compliance with the contract.

B. Key personnel phone numbers.

C. Description of the procedures the Contractor will implement to identify, prevent, and ensure non-recurrence of defective work. Procedures for tracking construction deficiencies from identification through acceptable corrective action shall be identified. Establish verification procedures that identified deficiencies have been corrected.

D. Acknowledgement that the Contractor will maintain a daily Quality Control

Report identifying work accomplished for the day, any deficiencies noted, the number of workers onsite, etc. These reports will be submitted to the COR by

COB the following business day.

E. Provide statements of procedure to ensure joint preparation is adequate, concrete monoliths are not damaged, and verification that the caulk cures adequately.

Submit detailed information on measures that will be used to protect the exposed joint from moisture.

17.0 Price and Payment: Payment items for the work of this contract for which contract job payments will be made are described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

17.1 Payment Items:

A. Joint Sealant Removal

B. Joint Sealant Replacement

17.2 Payment Item Descriptions:

A. The joint sealant removal consists of all work associated with removing the joint material from the locations as shown in the drawings included with this scope of work.

B. The joint sealant replacement consists of all work associated with replacing the sealant in the concrete joints on the trunnion girders.

C. Each payment items will be paid in lump sum.

Kansas City District

18.0 Trunnion Girder Repair Execution: The following sections form the minimum standards for the sealant and other materials, all equipment and installation for work specified in this Scope of Work.

18.1 Access:

A. A plan of the means of access shall be submitted with the Work Plan for review and approval. The means of access shall comply with the US Army Corps of Engineers

Safety Manual. The contractor shall submit for review a verification of safety measures of the selected equipment.

B. A pier ladder, by way of the catwalk, is available for use to access the trunnion girders.

The catwalk is accessible via the power house and/or by access from the roadway. If the contractor deems necessary to gain access using the ladder, it must be coordinated with the POC and the OPM.

C. Fall Hazard Protection: The following requirements apply to general work performed by the Contractor. In the event that the Contractor plans to utilize industrial rope access for any aspect of the work, Section C.3 shall apply.

Establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. Within the program include company policy, identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures in accordance with

ASSE/SAFE Z359.1.

1. Training: Institute a fall protection training program. As part of the Fall

Hazard Protection and Prevention Program, provide training for each employee who might be exposed to fall hazards. Provide training by a competent person for fall protection in accordance with USACE EM 385-1-

1, Section 21.B.

2. Fall Protection Equipment and Systems: Enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan and/or AHA at all times when an employee is exposed to a fall hazard.

Protect employees from fall hazards as specified in EM 385-1-1, Section 21.

In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, Paragraphs 21.N through

21.N.04. Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase.

The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with

29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and ASSE/SAFE

A10.32.

a. Personal Fall Arrest Equipment: Personal fall arrest equipment, systems, subsystems, and components shall meet ASSE/SAFE

Z359.1.

Kansas City District

b. Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system

(for uses such as steel reinforcing assembly and in addition to an approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support (usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system.

Only locking snap hooks and carabiners shall be used. Webbing, straps, and ropes shall be made of synthetic fiber. The maximum free fall distance when using fall arrest equipment shall not exceed

6 feet.

c. The total fall distance and any swinging of the worker (pendulum-like motion) that can occur during a fall shall always be taken into consideration when attaching a person to a fall arrest system.

3. Industrial Rope Access: In the event the Contractor plans to utilize industrial rope access for any aspect of the work, the following provisions shall apply. The rope access personnel, procedures and equipment must be in accordance with latest version of EM 385-1-1, Society of Professional

Rope Access Technicians (SPRAT) and/or Industrial Rope Access Trade

Association (IRATA) industry standards, and applicable OSHA and ANSI requirements. The Contractor personnel shall follow comprehensive safety guidelines for rope access in accordance with IRATA and/or SPRAT requirements as applicable for quality assurance, safety, training, documentation and working practices. Personnel SPRAT/IRATA

Certifications for all proposed personnel shall be submitted prior to beginning work.

a. Rope Access Work Plan and Activity Hazard Analysis (AHA): The

Contractor shall develop and submit a Rope Access Work Plan and

AHA/ Job safety analysis specific to the proposed rope access activities and host a pre-work safety briefing on site before rope access work commences. The AHA shall be developed to the extent possible with information available prior to the work and submitted to the Government. The Work Plan/AHA shall address, but shall not be limited to, the following minimum aspects of the rope access activities: date and location, purpose, personnel and qualifications, emergency contact information, work methods and rigging plan, communications, lock out/tag out procedures, anticipated hazards and mitigation measures, and the rescue plan. The AHA shall be completed on site by the Contractor with Government Construction and Facility staff input, reviewed and signed by all applicable parties at the pre-work safety briefing prior to the inspection. Prior to conducting any rope access work before each shift, the

Contractor shall hold documented safety meetings, rescue pre-planning, and complete and provide AHA forms. The Contractor shall provide copies of all safety meeting documentation to the

Government.

b. Equipment: The Contractor shall provide all rigging and rope access equipment as necessary for all Contractor personnel to perform required work activities specified herein.

Kansas City District

c. Personal Qualifications and Safety Supervision: All personnel to perform work utilizing rope access shall be minimum Level 1 certified under SPRAT or IRATA. The Contractor shall provide safety supervision of all rope access activities by SPRAT or IRATA certified Level 3 Team Leader/Rope Access Supervisor. The safety supervision will include, but not be limited to, ensuring proper rigging strategies and all actions are in accordance with requirements outlined in SPRAT or IRATA industry standards and as outlined in the EM 385-1-1. The names, qualifications, and previous experience records of the proposed technicians that may be assigned to this project, to include SPRAT or IRATA certifications and work experience shall be submitted to the Government prior to beginning work.

4. Guardrails and Safety Nets: Design, install and use guardrails and safety nets in accordance with EM 385-1-1 and 29 CFR 1926 Subpart M.

5. Rescue and Evacuation Procedures: When personal fall arrest systems are used, ensure that the mishap victim can self-rescue or can be rescued promptly should a fall occur. Prepare a Rescue and Evacuation Plan and include a detailed discussion of the following: methods of rescue; methods of self-rescue; equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance;

and transportation routes to a medical facility. Include the Rescue and

Evacuation Plan within the Activity Hazard Analysis (AHA) for the phase of work, in the Fall Protection and Prevention (FP&P) Plan, and the

Accident Prevention Plan PP).

18.2 Existing Joint Sealant:

A. The joint sealant is located around the caps and where the trunnion girder meets the pier as shown in the drawings. The contractor shall field verify that the lengths of sealant as specified in the drawings are correct.

B. The existing joint sealant material at locations as shown on the attached plans and as described in these specifications shall be removed using methods which will not damage, mark, discolor, or otherwise impact the integrity of the existing structure.

C. The contractor is responsible for removing and disposal of the waste materials and preventing material from falling onto the spillway below.

D. The joint shall not be left exposed.

E. If during joint sealant removal, the concrete surrounding the joint begins spalling, the contractor shall immediately stop the sealant removal and shall provide safe access for the government inspector to inspect the exposed joint.

F. After the existing joint materials has been removed and prior to installing the new joint sealant, the contractor shall provide safe access for the government inspector to inspect the prepared joint.

18.3 Joint Sealant Replacement:

A. The joint shall be resealed within the working day that the existing joint sealant material is removed.

B. If conditions exist in which resealing the joint within the same working day is not possible, measures to protect the joint from moisture shall be implemented in accordance with the approved Quality Control Plan.

Kansas City District

18.4 Joint Sealant Replacement Material:

A. The joint sealant, bond breaker, primer and other materials required by the manufacturer for proper installation shall be furnished and installed by the contractor according to the manufacturer’s specifications.

B. The contractor shall furnish the manufacturer’s written product information, installation procedures and instructional information for the chosen product as required.

C. The contractor is responsible for care, handling and storage of the material in accordance with the manufacturer’s specifications until completion of the contract.

D. The new joint sealant shall consist of Sika Material, Sikasil – 728 NS a non-sag, one-component, ultra-low modulus, elastomeric, neutral cure silicone sealant or an approved equal.

E. Material properties for the joint sealant shall meet the minimum requirements stated in

Table 1.

F. The primer shall consist of Sika Material, Sikasil Primer-2100, or an approved equal, which promotes adhesion to a variety of construction materials such as stone and masonry. The primer and the sealant shall be compatible.

TABLE 1: JOINT SEALANT PROPERTIES

Property Value

Material 100% silicone

Tensile Strength 175 psi (ASTM D412)

Movement Capability + 100%, - 50%

Weathering Resistance Excellent

Kansas City District

19.0 Pictures of Trunnion Girders:

Please see drawings for additional details.

Photo 1: Trunnion Girders at Monoliths 9, 10, 11, 12, and 13 (Right to Left) respectively)

Photo 2: Trunnion Girders (captured from Monolith 13)

Kansas City District

Photo 4: Trunnion Girders (captured from left non-overflow section)

Photo 3: Trunnion Girders (captured from Monolith 9)

Kansas City District

Photo 5: Trunnion Girders (Entry to Monolith 13)

NOTE: Adjacent piers are accessed via catwalk shown below bridge deck.

Photo 6: Trunnion Girders

Kansas City District

Photo 7: Trunnion Girder #13 (see cap details in drawings)

Photo 8: Sealant at the top of Trunnion Girder

Kansas City District

Sealant

Photo 9: Sealant at the Bottom of the Trunnion Girder