AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Hospital Demolition Fort Riley, KS

The purpose of this amendment is to :

1. Delete Section 02 65 00 in the Specif ications.

2. Delete Draw ing Sheet CD004 in the Draw ings.

3. Clarify number of copies to be submitted for Bids.

Bids are due September 18, 2017 at 10:30 AM Central Time.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Sep-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DQ17B4010

X 9B. DATED (SEE ITEM 11)

18-Aug-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Sep-2017

CODE

USACE, KANSAS CITY +

FEDERAL BLDG. CT-M RM 647; 601 E 12TH ST

KANSAS CITY MO 64106-2896

W912DQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DQ17B4010

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

CHANGES

The Solicitation is amended as follows:

Deleted text is shown with a strikethrough. Added text is shown with underline.

1. SPECIFICATION CHANGES:

a. DELETE Section 02 65 00 “Underground Storage Tank Removal” in its entirety and replace with the revised section that accompanies this amendment.

2. DRAWINGS CHANGES:

a. Delete the following Drawing Sheet in its entirety and replace with the revised Drawings Sheet that accompanies this amendment.

CD004 Demolition Plan Sanitary Sewer

3. Offer shall submit (1) one original, and (1) CD of the Bid.

4. All other terms and conditions remain unchanged and in full force.

Demolish Hospital W912DQ-17-B-4010 Fort Riley, Kansas Amendment 0002

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 65 00

UNDERGROUND STORAGE TANK REMOVAL

PART 1 GENERAL

1.1 UNIT PRICES

1.2 REFERENCES

1.3 SYSTEM DESCRIPTION

1.4 SUBMITTALS

1.5 QUALITY ASSURANCE

1.5.1 Support Staff

1.5.2 Preconstruction Conference and Work Plan

1.5.2.1 Site Safety and Health Plan

1.5.2.2 Excavation and Material Handling Plan

1.5.2.3 Tank and Piping Removal and Disposal Plan

1.5.2.4 Spill and Discharge Control Plan

1.5.2.5 Site Safety And Health Officer

1.5.3 Permits and Licenses

1.5.4 Statutes and Regulations

1.6 PROJECT/SITE CONDITIONS

PART 2 PRODUCTS

2.1 BACKFILL MATERIAL

2.2 PLASTIC SHEETING

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Safety Guidelines

3.1.2 Exclusion Zone (EZ) And Contamination Reduction Zone (CRZ)

3.1.3 Onsite Training

3.1.4 Personnel Protection

3.1.5 Respiratory Protection Program

3.1.6 Decontamination

3.1.7 Emergency Response and First Aid Equipment

3.1.8 Burning and Explosives

3.1.9 Protection of Existing Structures and Utilities

3.2 TANK CONTENTS VERIFICATION

3.2.1 Sampling

3.2.2 Analysis

3.3 CLEARING, GRUBBING AND REMOVALS

3.4 TOPSOIL

3.5 PREPARATIONS FOR EXCAVATION

3.5.1 Removal of Product, Pumpable Liquids, and Sludge

3.5.2 Contaminated Water Disposal

3.5.2.1 Sampling, Analysis, and Containment

3.5.2.2 Treatment

3.6 PURGING AND INERTING

02 65 00 - 1

Demolish Hospital W912DQ-17-B-4010 Fort Riley, Kansas Amendment 0002

3.7 EXCAVATION

3.7.1 Exploratory Trenches

3.7.2 Tank Excavation

3.7.3 Temporary Containment of Excavated Soil

3.7.4 Piping Excavation

3.7.5 Open Excavations

3.7.6 Hidden Structures

3.7.7 Stockpiles

3.8 REMOVAL OF PIPING, ANCILLARY EQUIPMENT, AND TANK

3.8.1 Piping and Ancillary Equipment

3.8.2 Tank

3.8.3 Contaminated Soil, Tank and Piping Excavation Examination

3.8.4 Testing Along Piping

3.9 TANK CLEANING

3.9.1 Exterior

3.10 SOIL EXAMINATION, TESTING, AND ANALYSIS

3.10.1 Analysis

3.11 BACKFILLING

3.12 DISPOSAL REQUIREMENTS

3.12.1 Treatment, Disposal, and Recycling

3.12.2 Tank and Ancillary Equipment Disposal

3.12.3 Transportation of Wastes

3.12.4 Salvage Rights

3.12.5 Manifest Records

3.12.6 Hazardous/Special Waste Manifests

3.12.7 Documentation of Treatment or Disposal

3.13 SPILLS

3.14 INSPECTIONS

3.15 TANK CLOSURE REPORT

3.16 COMPACTION, FINISH GRADING, and SEEDING

-- End of Section Table of Contents --

02 65 00 - 2

02 65 00 - 1

SECTION 02 65 00

UNDERGROUND STORAGE TANK REMOVAL

02/10

PART 1 GENERAL

1.1 UNIT PRICES

Compensation for removal of contaminated soil and pumpable liquids will be paid as a unit cost. This unit cost includes testing, excavation, stockpiling, transportation and disposal of the contaminated soil and backfilling with non-contaminated soil. Payment for all other work is under the base bid for the tank removal and constitutes full payment for all work defined in the contract documents including testing of the contents, excavation and disposal of the tank, and testing of the underlying soil.

Assume, for bidding purposes, that soil, bituminous pavement, concrete slabs, and water encountered during the removal of the underground tanks are contaminated with fuel oil and to be handled as specified herein. Wash bituminous pavement and concrete slabs and dispose of as demolition debris. Collect and store wash water.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN PETROLEUM INSTITUTE (API)

API PUBL 1628 (1996) A Guide to the Assessment and

Remediation of Underground Petroleum Releases

API RP 1604 (1996; R 2010) Closure of Underground

Petroleum Storage Tanks

API RP 2003 (2015; 8th Ed) Protection Against Ignitions Arising out of Static, Lightning, and Stray Currents

API RP 2219 (2016) Safe Operation of Vacuum Trucks

Handling Flammable and Combustible Liquids in Petroleum Service

API STD 2217A (2009) Guidelines for Safe Work in Inert

Confined Spaces in the Petroleum and Petrochemical Industries

API Std 2015 (2014) Safe Entry and Cleaning of

Petroleum Storage Tanks

ASTM INTERNATIONAL (ASTM)

ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method

Demolish Hospital Fort Riley, Kansas

W912DQ-17-B-4010

Amendment 0002

02 65 00 - 2

ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D2167 (2015) Density and Unit Weight of Soil in

Place by the Rubber Balloon Method

ASTM D2487 (2011) Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D4397 (2016) Standard Specification for

Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications

ASTM D6938 (2015) Standard Test Method for In-Place

Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements

Manual

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 530-R-97-007 (1997) Best Management Practices (BMPs) for Soils Treatment Technologies;, Suggested Operational Guidelines to Prevent Cross-Media Transfer of Contaminants During Cleanup Activities

EPA 600/4-79/020 (1983) Methods for Chemical Analysis of

Water and Wastes

EPA SW-846 (Third Edition; Update IV) Test Methods for Evaluating Solid Waste:

Physical/Chemical Methods

CFR

U.S.

NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

Occupational Safety and Health Standards

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 266 Standards for the Management of Specific Hazardous Wastes and Specific Types of Hazardous Waste Management Facilities

Demolish Hospital Fort Riley, Kansas

02 65 00 - 3

40 CFR 268 Land Disposal Restrictions

40 CFR 279 Standards for the Management of Used Oil

40 CFR 280 Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks (UST)

1.3 SYSTEM DESCRIPTION

The work consists of removal, decontamination and disposal of two 20,000 gallon and 5,000 gallon underground storage tanks , one 20,000 gallon underground storage tank serving Building 615, one 5,000 gallon underground storage tank serving Building 600, associated piping and ancillary equipment, including but not limited to dewatering , disposal of contaminated soil, laboratory testing, providing reports which are required by regulatory agencies, and backfilling. The tanks are constructed of steel and fiberglass . The tank was used for storing fuel oil. The 20,000 gallon tank is constructed of steel and the 5,000 gallon tank is constructed of fiberglass. Both tanks were used for storing fuel oil.

Residue remaining in the tank is considered a special hazardous waste.

S. Existing native soils are predominantly unknown. The site is not a hazardous waste site, but due to the nature of the materials and hazards present, use specified procedures until closure activities are complete.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Work Plan;

Site Safety and Health Plan;

Excavation and Material Handling Plan;

Field Sampling and Laboratory Testing Plan;

Tank and Piping Removal And Disposal Plan;

Spill and Discharge Control Plan;

Qualifications;

Laboratory Services;

State Licensed Hazardous Waste Transporter

SD-06 Test Reports

Laboratory and Field Testing Reports Backfill Material Tank Contents Verification Contaminated Water Disposal Soil Examination, Testing, and Analysis Backfilling.

SD-11 Closeout Submittals

Salvage Rights;

Tank Closure Report

Demolish Hospital Fort Riley, Kansas

02 65 00 - 4

1.5 QUALITY ASSURANCE

Qualifications

Substantiate a minimum of 2 years of tank removal experience, including subcontractors and personnel employed on the project, and certification by the State authority having jurisdiction for tank removal work. Experience shall include removal, transportation, and disposal of underground tanks, associated piping, and soil exceeding State of Kansas Tier 2 RSK levels for TPH-LRH, TPH-MRH and TPH-HRH for the Residential Scenario, in conformance with the following:

a. API RP 1604

b. 40 CFR 280, State and local regulations and procedures.

c. Applicable safety rules and regulations.

1.5.1 Support Staff

Identify all staff involved for the various components, including personnel collecting and shipping samples, and detail staff member's qualifications.

1.5.2 Preconstruction Conference and Work Plan

Prior to the commencement of work, a preconstruction conference will be scheduled by the Contracting Officer's Representative. Prepare and submit a comprehensive Work Plan within 30 days of contract award. The work plan shall conform to the requirements of this specification, API RP 1604, API Std 2015, API RP 2003, API STD 2217A and API RP 2219. Allow 30 days in the schedule for the Government's review and approval. No adjustment for time or money will be made for re-submittals required as a result of noncompliance. No work at the site is allowed, with the exception of site inspections and mobilization, until the Work Plan is approved. As a minimum, include the following in the Work Plan:

1.5.2.1 Site Safety and Health Plan

Furnish detailed safety, health, and accident prevention provisions and develop a Site Safety and Health Plan (SSHP). Incorporate the requirements of 29 CFR 1910 and EM 385-1-1 into the SSHP. Include current training certification statement for personnel prior to entry into the work site.

Do not commence work until the SSHP is approved by the Contracting Officer's Representative. As a minimum, include the following:

a. Health and safety organization, including discussion of distribution of functions and responsibilities.

b. Organization and components of the SSHP.

c. Physical and chemical site hazard identification.

d. Basic toxicology and toxicity information.

e. Discussion of the EZ and CRZ.

f. Protective clothing.

Demolish Hospital Fort Riley, Kansas

02 65 00 - 5

g. Respiratory protection.

h. Air quality monitoring.

i. Personnel exposure guidelines.

j. Decontamination procedures.

k. Basic first aid review.

l. Emergency response and contingency plan.

m. Site entry and exit procedures.

n. Sampling procedures.

1.5.2.2 Excavation and Material Handling Plan

Describe methods, means, equipment, sequence of operations and schedule to be employed in excavation, transport, handling, borrowing source and stockpiling of soil during underground tank removal. Include shoring requirements. Fifteen days before beginning tank removal work, submit to the Contracting Officer's Representative, for approval, a material handling plan that describes phases of dealing with the contaminated soil and water as it relates to the proposed tank and piping removal, including methods of excavating, a material handling plan for the contaminated material, soil testing requirements, and water pumping and collection requirements.

1.5.2.3 Field Sampling and Laboratory Testing Plan

Describe field sampling methods and quality control procedures. Identify laboratory and laboratory methods to be used for contamination testing.

Include sample reports showing sample identification for location, date, time, sample method, contamination level, name of individual sampler, identification of laboratory, and quality control procedures for all laboratory services.

1.5.2.4.3 Tank and Piping Removal and Disposal Plan

Describe methods, means, sequence of operations, and schedule to be employed in the testing, pumping, cleaning, de-vaporizing, inspecting, cutting and removal, and disposal of underground storage tanks and piping.

Include methods to be employed for product, sludge, vapor, and pumpable liquid removal; purging and inerting; and storage methods proposed for control of surface water. Also address the following:

a. Treatment Options

b. Identification of waste, tank and contaminated soil transporters and means of transport.

c. Disposal or remediation.

d. Decontamination procedures and coordination with SSHP.

Coordinate decontamination procedures, shoring, and safety measures in accordance with Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS.

Demolish Hospital Fort Riley, Kansas

02 65 00 - 6

1.5.2.5.4 Spill and Discharge Control Plan

Develop a comprehensive spill and discharge control plan. Consider and provide contingency measures for potential spills and discharges from handling and transportation of contaminated soils and water. A possible source of guidance for assessment and remediation is API PUBL 1628.

1.5.2.6.5 Site Safety And Health Officer

Identify an individual to serve as the Certified Industrial Hygienist (CIH)Site Safety and Health Officer (SSHO) to report problems and concerns regarding health and safety to the Contracting Officer's Representative.

Provide documentation that the CIHSSHO possesses working knowledge of local and Federal occupational safety and health regulations, and provide training, in accordance with 29 CFR 1910 to Contractor employees in air monitoring practices and techniques. The CIHSSHO or an Industrial Hygiene Technician (IHT) who is under the direction of the CIHSSHO shall remain onsite to provide day to day industrial hygiene support, including air monitoring, training, and daily site safety inspections. The CIH may be assigned other duties, such as project foreman or quality control manager.

1.5.3 Permits and Licenses

As required or as directed by the Contracting Officer's Representative, obtain local, state, or federal permits and licenses that directly impact the Contractor's ability to perform the work prior to commencing removal operations.

1.5.4 Statutes and Regulations

Perform tank closures, removal, and disposal in accordance with 40 CFR 280, 40 CFR 262, 40 CFR 264, and 40 CFR 265 as well as the applicable local, State of Kansas, and Federal regulations. Transport hazardous material waste in accordance with Section 02 81 00 TRANSPORTATION AND DISPOSAL OF

HAZARDOUS MATERIALS.

1.6 PROJECT/SITE CONDITIONS

Notify the Installation Environmental Coordinator (IEC) and the Contracting Officer's Representative 5 days prior to tank removal. The Contractor is responsible for contacting the Implementation Agency (IA) in accordance with the applicable reporting requirements.

PART 2 PRODUCTS

2.1 BACKFILL MATERIAL

Obtain backfill material Ft. Riley borrow area, excavated soil, or from offsite. Backfill material from Ft. Riley borrow area does not need to be tested. Backfill material from excavated soil needs to be tested at a frequency of 1 sample per 100 cubic yards to reuse. Backfill obtained offsite will need to be tested to ensure it isn't contaminated. Baackfill should be tested for the following:

- SW-846 Method 8260B TCL VOCs

- SW-846 Method 8270C TCL SVOCs

- SW-846 Method 8081A/8082 TCL pesticides and PCBs

- SW-846 Method 6010B and 7000 series - TAL metals

The levels should be below the Kansas Tier 2 RSK values for the residential scenario. Classify backfill in accordance with ASTM D2487 as GW, GP, GM, GC, SW, SP, SM, SC, MH, CL, or CH and free from roots and other organic

Demolish Hospital Fort Riley, Kansas

02 65 00 - 7 matter, trash, debris, snow, ice or frozen materials. Secure and submit soil classification test results, including the chain-of-custody records, prior to bringing offsite materials onsite. The testing frequency for backfill material is 1 per 1000 cubic yards or a minimum of 1 test.

2.2 PLASTIC SHEETING

Provide plastic sheeting conforming to ASTM D4397.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Furnish labor, materials, necessary permits, laboratory tests, and reports and equipment to remove and dispose of products remaining in the underground tanks; clean and vapor free the underground tanks and connecting piping; excavate, remove underground tanks and associated piping, and backfill to the level of the adjacent ground; sample soil and water to determine if contaminated; dispose of tanks and associated piping, and petroleum contaminated soil.

3.1.1 Safety Guidelines

Comply with personnel safety guidelines specified in Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS, and conform to the guidelines as stipulated in the approved SSHP.

3.1.2 Exclusion Zone (EZ) And Contamination Reduction Zone (CRZ)

Do not permit personnel, not directly involved with the project, to enter work zones, called the EZ and CRZ. The EZ is an area around the tank a minimum of 10 feet from the limits of the tank excavation. At the perimeter of the EZ, establish a CRZ. Clean equipment and personnel within the CRZ, as stated in the paragraph titled "Personnel and Equipment Decontamination." Locate the Contractor's site office, parking area, and other support facilities outside the EZ and CRZ. Clearly mark and post boundaries of the EZ and CRZ. Include a site map, outlining the extent of work zones and location of support facilities, in the SSHP.

3.1.3 Onsite Training

Prior to starting onsite work, conduct a health and safety training class directed by the CIH to discuss the implementation of the SSHP. Notify the Contracting Officer's Representative 24 hours prior to beginning the training class.

3.1.4 Personnel Protection

Furnish appropriate personal safety equipment and protective clothing to personnel and ensure that safety equipment and protective clothing is kept clean and well maintained. Furnish three clean sets of personal protective equipment and clothing for use by the Contracting Officer's Representative or official visitors as required for entry into the EZ.

3.1.5 Respiratory Protection Program

Fully employ respiratory protection program, addressing respirator usage and training, in accordance with 29 CFR 1910 and EM 385-1-1.

Demolish Hospital Fort Riley, Kansas

02 65 00 - 8

3.1.6 Decontamination

Decontaminate or properly dispose of personal protective equipment and clothing worn in contaminated areas at the end of the work day. The CIH is responsible for ensuring that personal protective clothing and equipment are decontaminated before being reissued.

3.1.7 Emergency Response and First Aid Equipment

a. Prior to commencement of work, thoroughly review emergency response and contingency plan in accordance with 29 CFR 1910. In an emergency, take action to remove or minimize the cause of the emergency, alert the Contracting Officer's Representative, and institute necessary measures to prevent repetition of the emergency. Equip site-support vehicles with route maps providing directions to the medical treatment facility.

b. Provide appropriate emergency first aid equipment for treatment of exposure to site physical and chemical hazards. Provide and post a list of emergency phone numbers and points of contact for fire, hospital, police, ambulance, and other necessary contacts. Provide and post a route map detailing the directions to the nearest medical facility.

c. Notify the Contracting Officer's Representative of any unforeseen hazard or condition which becomes evident during work.

3.1.8 Burning and Explosives

Use of explosives or burning debris is not allowed. Do not permit ignition sources in the EZ and CRZ.

3.1.9 Protection of Existing Structures and Utilities

Take all necessary precautions to avoid damage to existing structures, their appurtenances, monitoring wells, or utilities that may be affected by work activities. Repair any damage to utilities and monitoring wells resulting from the Contractor's operations at no expense to the Government. Coordinate with the installation to locate underground utilities prior to beginning construction. Do not disturb utilities encountered which were not previously shown or otherwise located without approval from the Contracting Officer's Representative.

3.2 TANK CONTENTS VERIFICATION

Conduct sampling and analysis in accordance with the approved Sampling and Analysis Plan. Submit reports, including the chain-of-custody records.

3.2.1 Sampling

Sample tank product, pumpable liquids, tank coatings and sludge. If the data is not adequate, additional sampling and analysis to the extent required by the approved offsite facility receiving the material is the responsibility of the Contractor. Meeting all regulatory requirements, including the preparation of hazardous materials and waste for transportation, is the responsibility of the Contractor.

3.2.2 Analysis

Test tank contents for the parameters listed herein. Include total

Fort Riley, Kansas

02 65 00 - 9 petroleum hydrocarbons (TPH) benzene, ethylbenzene, toluene and xylene (BETX) lead in the analysis.

3.3 CLEARING, GRUBBING AND REMOVALS

Perform clearing and grubbing in accordance with Section 31 11 00 CLEARING AND GRUBBING. Clear areas designated for clearing and grubbing as required and directed by the Contracting Officer's Representative of all trees, stumps, downed timber, brush, rubbish, roots larger than 3 inches in diameter, and matted roots prior to commencing operations. Saw cut concrete or asphalt pavement at the limits of removal and break, remove and dispose of the the resulting debris off Government Property. Chain link fence shall be disposed of offsite.

3.4 TOPSOIL

Topsoil shall meet the requirements in Section 31 00 00 EARTHWORK. Strip and stockpile uncontaminated topsoil separately for reuse at the location shown at a location approved by the Contracting Officer's Representative if it meets the requirements of clean fill given in Paragraph BACKFILLING.

Obtain additional topsoil in excess of that produced by excavation offsite from designated location onsite. Cover with topsoil all areas disturbed by tank removal operations, other than areas to receive pavement or similar surface under this contract. Topsoil shall be used wherever shown or stated on the drawings.

3.5 PREPARATIONS FOR EXCAVATION

Before excavating, drain product piping back to the tank remove residual liquids trapped in the product lines and remove all product from the tank.

Purge and vent the tank in accordance with API RP 1604, and as specified herein.

3.5.1 Removal of Product, Pumpable Liquids, and Sludge

Remove and dispose of tank product, pumpable liquids, and sludge. Use of Government facilities for permanent storage or disposal of the wastes is prohibited. Temporary storage on Government facilities will be allowed only until testing is complete, manifests (if necessary) are complete, and transportation is arranged. The Contractor is responsible for obtaining all required permits. Usable product shall be the property of the Contractor. Provide approved containers, vehicles, equipment, labor, signs, labels, placards and manifests and associated land disposal restriction notices and notifications, necessary for accomplishment of the work, including materials necessary for cleaning up spills that could occur from tank removal operations.

3.5.2 Contaminated Water Disposal

3.5.2.1 Sampling, Analysis, and Containment

Sample and analyze contaminated water both prior to and after treatment.

Analyze contaminated water produced from excavation operations and tank pumping treated onsite, for pH; benzene, ethylbenzene, toluene, and xylene (BETX); total lead; oil and grease; and total petroleum hydrocarbons (TPH).

Perform sampling and analysis prior to discharge to the installation sanitary sewer and disposal for every 50,000 gallons of contaminated water treated. Conform analysis of contaminated water to be taken to an offsite treatment facility to the requirements of the treatment facility, with

Demolish Hospital Fort Riley, Kansas

02 65 00 - 10

Irwin Army Hospital Demolition Ft. Riley, Kansas documentation of all analyses performed furnished to the Contracting Officer's Representative in accordance with paragraph RECORDS. Contain, store onsite, and analyze contaminated water prior to transport to the approved treatment, storage and disposal facility and dispose of in accordance with applicable Federal and state disposal regulations. Provide approved containers, vehicles, equipment, labor, signs, labels, placards and manifests and associated land disposal notices and notifications, necessary for accomplishment of the work.

3.5.2.2 Treatment

Treat contaminated water offsite at a permitted facility.

3.6 PURGING AND INERTING

After the tank and piping contents have been removed, but prior to excavation beyond the top of the tank, disconnect all the piping (except the piping needed to purge or inert the tank). Purge flammable and toxic vapors from the tank or make the tank inert in accordance with API RP 1604, with the exception that filling with water is not permitted and, if dry ice is employed, use a minimum of 3 pounds per 100 gallons of tank volume.

Continuously monitor the tank atmosphere for combustible vapors if the tank is purged, or continuously monitor for oxygen, if the tank is inerted.

3.7 EXCAVATION

Mark all excavation areas, as well as work near roadways.

3.7.1 Exploratory Trenches

a. Excavate exploratory trenches as necessary to determine the tank location, limits and the location of ancillary equipment. Upon commencing exploratory excavation, utilize organic vapor analyzer/flame ionization device (OVA/FID) equipment to obtain readings for total petroleum hydrocarbons (TPH), and benzene, tolulene, ethylbenzene, and xylene (BTX), and toxicity characteristic leaching procedure (TCLP).

If BTEX indicates gasoline, then provide TCLP.

3.7.2 Tank Excavation

a. Provide Contracting Officer's Representative with written documentation, no later than 30 days before work begins, that proper State or local authorities have been notified. Notify the Contracting Officer's Representative at least 48 hours prior to start of tank removal work. Stage operations to minimize the time that tank excavation is open and the time that contaminated soil is exposed to the weather. Provide protection measures around the excavation area to prevent water runoff and to contain the soil within the excavation area.

b. Perform excavation around the perimeter of the tank to limit the amount of potentially petroleum contaminated soil that could be mixed with previously uncontaminated soil. Segregate petroleum contaminated soil in separate stockpiles.

c. Maintain an excavation around the tank of sufficient size to allow workers ample room to complete the work, but also protect the workers from sliding or cave-ins. Install sheeting, bracing, or shoring in the

Demolish Hospital Fort Riley, Kansas

02 65 00 - 11 absence of adequate side slopes if there is a need for workers to enter the excavated area. Divert surface water to prevent direct entry into the excavation.

d. Dewatering of the excavation may require a discharge permit by the

State and shall be limited to allow adequate access to the tank and piping, to assure a safe excavation, and to ensure that compaction and moisture requirements are met during backfilling. Dewatering may result in the production of petroleum contaminated water and/or free product. Recover free product from the groundwater only as part of necessary dewatering.

e. Collect and test water generated by dewatering during excavation required for removal of tanks or piping, surface water collected in open excavation, or water used for washing equipment or existing concrete or bituminous surfaces, in accordance with EPA 530-R-97-007, EPA 600/4-79/020, EPA SW-846 and state or locally required analyses.

3.7.3 Temporary Containment of Excavated Soil

Provide temporary containment area near the excavated area. Cover containment area with three layers of 6 mil polyethylene sheeting. Place excavated soil on the impervious barrier and cover with 6 mil polyethylene sheeting. Provide straw bale berm around the outer limits of the containment area and cover with polyethylene sheets. Secure edges of sheets to keep the polyethylene sheeting in place.

3.7.4 Piping Excavation

Perform excavation as necessary to remove tank piping and ancillary equipment in accordance with paragraphs: Shoring, Tank Excavation, and Open Excavations.

3.7.5 Open Excavations

Secure open excavations and stockpile areas while awaiting confirmation test results from the soil beneath the tank. Backfill the excavation as soon as possible after tank and contaminated soil removals have been completed and confirmation samples have been taken. Divert surface water around excavations to prevent water from directly entering into the excavation.

3.7.6 Hidden Structures

During excavation activities, if asphalt pavement, concrete slabs, or other hidden structures are encountered, remove and wash with high pressure water cleaning equipment. Remove and dispose of the pavement, concrete, and other structures as specified in Section 02 41 00 DEMOLITION.

3.7.7 Stockpiles

Uncontaminated excavated soil and petroleum contaminated soil, that is not a state-regulated hazardous waste, that is below residential levels for TPH shall be stockpiled and used for backfill in the tank excavation prior to using borrow material and disposed of in the area designated on the drawings. Prior to reuse, soil must be tested at a rate of on sample per 100 CY and results shall be below the residential levels for TPH. Excavated material that is regulated by the state as a hazardousspecial waste which

Demolish Hospital Fort Riley, Kansas

02 65 00 - 12 is visibly stained for which real time vapor monitoring instrument readings exceed for volatile and possibly semi-volatile hydrocarbons depending on the performance criteria for the field screening method and which has an obvious petroleum odor or as required by the State of Kansas or implementing agency is considered contaminated. Place in containers such as drums, roll-offs or dumpsters for sampling in accordance with paragraph Stockpiled Material Sampling. Separately stockpile uncontaminated soil from the contaminated soil, a safe distance away from, but adjacent to, the excavation. Place allowable stockpiles of contaminated soil on an impermeable geomembrane plastic sheeting a minimum of 3 layers, each 6 mils thick, covered with a 6 mils sheet of geomembrane plastic sheeting as specified. Place the geomembrane plastic sheeting to prevent the stockpiled soil from coming into contact with surface water run-off. Locate the geomembrane plastic sheeting cover to prevent rain or surface water from coming into contact with the contaminated soil, as well as limit the escape of the volatile constituents in the stockpile.

3.8 REMOVAL OF PIPING, ANCILLARY EQUIPMENT, AND TANK

3.8.1 Piping and Ancillary Equipment

Disconnect all piping and ancillary equipment from the tank. Remove the piping completely (interior and exterior of the tank) from the exterior surface of the tank, cap and abandon in place. Cap all tank ancillary equipment and piping connections, except those connections necessary to inert the tank within the excavation zone. Clean the piping exterior and ancillary equipment to remove all soil and inspect for signs of corrosion and leakage. Ensure no spillage of the piping contents occurs, as specified in the Work Plan, and as required in paragraph SPILLS. If the soil under and around the tank pad is contaminated, remove the tank pad and dispose of offsite at an approved hazardous waste facility.

3.8.2 Tank

Remove the tank from the excavation and clean the exterior to remove all soil and inspect for signs of corrosion, structural damage, or leakage.

Use only non-sparking type materials or equipment which comes into contact with the tank, or in the vicinity of the excavation such as shovels, slings and tools. After removal from the excavation, place the tank on a level surface adjacent to the tank excavation at an approved location and secure it with wood blocks to prevent movement.

3.8.3 Contaminated Soil, Tank and Piping Excavation Examination

a. After the tank has been removed from the ground, examine and test the adjacent and underlying soil for any evidence of leakage. Visually inspect the soil for staining after removal of all obviously contaminated soil, then screen for the presence of volatile and/or semi-volatile contamination using a real time vapor monitoring instrument and or immunoassay field kits.

b. If tank is 20 feet or less in length, take two samples. Take each sample 2 feet from each end of the tank and 2 feet below the bottom of the excavation.

c. If the tank is greater than 20 feet, take three samples. Take two samples 2 feet from each end of the tank and 2 feet below the bottom of the excavation. Take a third sample from the middle of the tank area and 2 feet below the bottom of the excavation.

Demolish Hospital Fort Riley, Kansas

02 65 00 - 13

d. Analyze samples for TPH-LRH, TPH-MRH, and TPH-HRH. It is recommended that residential clean up values be used. If results exceed residential cleanup values, additional contaminated soil shall be excavated and additional confirmatory sampling shall be performed until residential cleanup values are achieved. Furnish results to the Contracting Officer's Representative within 24 hours after the results are obtained. Along with the results furnish a sketch showing underground tank, sampling location, and extent of excavations.

e. Transport offsite for disposal. Petroleum contaminated soil not regulated by the state as hazardous waste. Stockpile contaminated soil or suspected contaminated soil, or, if the site is a RCRA-designated CAMU, containerized until further disposition. Transport petroleum contaminated soil and dispose of as special waste at a facility permitted to accept the waste.

f. The State of Kansas inspector will determine the extent of the contaminated soil to be removed from each site. Report any evidence indicating that the amount of contaminated soil may exceed the individual site limit specifiedestimated contract quantity, to the Installation's Environmental Coordinator Contracting Officer’s Representative the same day it is discovered. If minimal additional excavation is required, the Contracting Officer's Representative may allow the Contractor to proceed. If extensive contamination is encountered, sample the excavation and backfill in accordance with paragraph BACKFILLING.

g. After the known contaminated soil is removed, sample and analyze the

3.8.4 Testing Along Piping

For every 25 linear feet of product delivery piping, for every change in direction, and at every mechanical joint take one soil sample and analyze for TPH. Conform sampling and analysis of soil materials to EPA standards specified above.

3.9 TANK CLEANING

3.9.1 Exterior

Remove soil from the exterior of the tank, piping, and associated equipment to eliminate soil deposition on roadways during transportation to a temporary storage area, ensure markings will adhere to the surfaces, and simplify tank cutting. Use non-sparking tools to remove soil. Remove soil believed to be contaminated, collect it on 3 layers of 6 mil impermeable polyethylene and stockpile it with other contaminated soil removed from the

3.10 SOIL EXAMINATION, TESTING, AND ANALYSIS

3.10.1 Analysis

Test soil samples from the excavation and stockpiled material in accordance with the approved Sampling and Analysis Plan for the following parameters:

total petroleum hydrocarbon (TPH) benzene, ethylbenzene, toluene,and xylene (BETX) 1,2-dichloroethane, and any other analysis required by the off-site

Demolish Hospital Fort Riley, Kansas

02 65 00 - 14 disposal facility. Submit copies of all laboratory and field testing reports results, including the chain-of-custody records, to the Contracting Officer's Representative.

3.11 BACKFILLING

a. Backfill the tank area and any other excavations only after the soil test results have been approved. Complete contaminated soil removal after approval by the state inspector.

b. Dewater the excavation if necessary. Use stockpiled material, subjected to chemical confirmation testing as backfill, if it is found to conform to the requirements of clean fill in accordance with appropriate state local regulations. Place clean backfill in layers with a maximum loose thickness of 8 inches, compacted to 90 percent maximum density for cohesive soils and 95 percent maximum density for cohesionless soils. Perform density tests using an approved commercial testing laboratory or by facilities furnished by the Contractor.

Attach test results to Contractor's Quality Control Report; submit 3 copies of the report for each UST site opened, prepared in a standard 3-ring binder, within 14 days of completing work at each site. Label each binder with contract number, project name, location and tank number; each binder shall be indexed. Furnish a copy of the report to the Installation Environmental Coordinator. Perform a minimum of 1 density test on each lift. Determine laboratory tests for moisture density relations in accordance with ASTM D1557, Method B, C, or D, or ASTM D6938. A mechanical tamper may be used, provided that the results are correlated with those obtained by the hand tamper. Determine field in-place density shall be in accordance with ASTM D1556/D1556M, ASTM D6938, or ASTM D2167.

3.12 DISPOSAL REQUIREMENTS

3.12.1 Treatment, Disposal, and Recycling

Perform disposal of hazardous or special wastes in accordance with all local, State, and Federal solid and hazardous waste laws and regulations;

the RCRA; Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS; and conditions specified herein. This work includes all necessary personnel, labor, transportation, packaging, detailed analyses (if required for disposal, manifesting or completing waste profile sheets), equipment, and reports. Recycle product and pumpable liquids removed from the tank to the greatest extent practicable. Dispose of the tanks removed at one of the following state approved facilities: Kansas. Provide manifest for each tank disposed of in this manner as required by the State of Kansas to document delivery and acceptance at the disposal facility.Dispose of tanks removed in accordance with Kansas State requirements.

3.12.2 Tank and Ancillary Equipment Disposal

After the tank, piping, and ancillary equipment have been removed from the excavation and the tank cleaned, cut the tank into sections with no dimension greater than 5 feet. Dispose of tank and piping sections in a State approved offsite disposal facility at the Defense Reutilization and Marketing Office (DRMO) . Dispose of tank and piping sections in a State approved offsite disposal facility. Perform tank cutting prior to being taken from the tank removal site. Do not sell the tank intact. Dispose of

Demolish Hospital Fort Riley, Kansas

02 65 00 - 15 ancillary equipment at an approved offsite disposal facility Piping shall be disconnected from the tank and removed unless otherwise indicated.

3.12.3 Transportation of Wastes

Provide transportation in accordance with Department of Transportation (DOT) Hazardous Material Regulations and State and local requirements, including obtaining all necessary permits, licenses, and approvals. Submit evidence that a State licensed hazardous waste transporter is being used.

3.12.4 Salvage Rights

The Contractor retains the rights to salvage value of recycled or reclaimed product and metal not turned in to the DRMO or otherwise identified, so long as the requirements of 40 CFR 266 and 40 CFR 279, or the applicable State requirements are met. At the end of the contract, provide documentation on the disposition of salvaged materials.

3.12.5 Manifest Records

Maintain records of all waste determinations, including appropriate results of analyses performed, substances and sample location, the time of collection, and other pertinent data as required by 40 CFR 280, Section 74 and 40 CFR 262 Subpart D. Also record transportation, treatment, disposal methods and dates, the quantities of waste, the names and addresses of each transporter and the disposal or reclamation facility, shall and available for inspection, as well as copies of the following documents:

a. Manifests are not required for transportation and disposal of special waste in the state of Kansas. There is a required special waste disposal authorization. The form and requirements can be found at the following link: www.kdheks.gov/waste/forms/solidwaste/sw600-specwaste.pdf.

b. Waste analyses or waste profile sheets.

c. Certifications of final treatment/disposal signed by the responsible disposal facility official.

d. Land disposal notification records required under 40 CFR 268 for hazardous wastes. The state of Kansas has special waste notification requirements. Link to these requirements can be found at:http://www.kdheks.gov/waste/proposed_regs/28-29- 109amendedpropregs.pdf

Provide records in accordance with Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS. Upon contract close out, the records will become the property of the Government.

3.12.6 Hazardous/Special Waste Manifests

Provide manifesting conforming to the requirements specified in Section

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS.

3.12.7 Documentation of Treatment or Disposal

Take wastes, other than recyclable or reclaimable product or metal, to a treatment, storage, or disposal facility which has EPA or appropriate state permits and hazardous or special waste identification numbers and complies

Demolish Hospital Fort Riley, Kansas

02 65 00 - 16 with the provisions of the disposal regulations. Furnish documentation of acceptance of special waste by the original return copy of the hazardous waste manifest, signed by the owner or operator of a facility legally permitted to treat or dispose of those materials shall be furnished to the Contracting Officer's Representative not later than 5 working days following the delivery of those materials to the facility; and include a copy in the Tank Closure Report. Furnish a statement of agreement from the proposed treatment, storage or disposal facility and certified transporters to accept hazardous or special wastes in the Work Plan. If the Contractor selects a different facility than is identified in the Work Plan, provide documentation for approval to certify that the facility is authorized and meets the standards specified in 40 CFR 264.

3.13 SPILLS

Use appropriate vehicles and operating practices to prevent spillage or leakage of contaminated materials from occurring during operations.

Inspect vehicles leaving the area of contamination to ensure that no contaminated materials adhere to the wheels or undercarriage. Take immediate containment actions as necessary to minimize effect of any spill or leak. Cleanup in accordance with applicable Federal, State, local laws and regulations, and district policy at no additional cost to the Government. Refer to Section 02 81 00 TRANSPORTATION AND DISPOSAL OF

HAZARDOUS MATERIALS for spill response and reporting requirements.

3.14 INSPECTIONS

Arrange for and perform required inspections. Provide copies of inspections to Contracting Officer's Representative.

3.15 TANK CLOSURE REPORT

Include in Tank Closure Reports the following information as a minimum:

a. A cover letter signed by a responsible company official certifying that all services involved have been performed in accordance with the terms and conditions of this specification.

b. A narrative report describing what was encountered at each site, including:

(1) condition of the UST.

(2) any visible evidence of leaks or stained soils.

(3) results of vapor monitoring readings.

(4) actions taken including quantities of materials treated or removed.

(5) reasons for selecting sample locations.

(6) sample locations.

(7) collection data such as time of collection and method of preservation.

Demolish Hospital Fort Riley, Kansas

02 65 00 - 17

(8) reasons for backfilling site.

(9) whether or not groundwater was encountered.

c. Copies of all analyses performed for disposal.

d. Copies of all waste analyses or waste profile sheets.

e. Copies of all certifications of final disposal signed by the responsible disposal installation official.

f. Information on who sampled, analyzed, transported, and accepted all wastes encountered, including copies of manifests, waste profile sheets, land disposal restriction, notification and certification forms, certificates of disposal, and other pertinent documentation.

g. Copies of all analyses performed for confirmation that underlying soil is not contaminated, with copies of chain-of-custody for each sample.

Analyses shall give the identification number of the sample used.

Sample identification numbers shall correspond to those provided on the one-line drawings.

h. Scaled one-line drawings showing tank locations, limits of excavation, limits of contamination, underground utilities within 50 feet, sample locations, and sample identification numbers.

i. Progress Photographs. Take a minimum of 4 views of the site showing such things as the location of each tank, entrance/exit road, and any other notable site condition before work begins. After work has been started at the site, photographically record activities at each work location daily. Photographs shall be 3-1/2 x 5 inches and shall include:

(1) Soil removal, handling, and sampling.

(2) Unanticipated events such as discovery of additional contaminated areas.

(3) Soil stockpile area.

(4) Tank.

(5) Site or task-specific employee respiratory and personal protection.

(6) Fill placement and grading.

(7) Post-construction photographs. After completion of work at each site, take a minimum of four (4) views of the site. Prints shall illustrate the condition and location of work and the state of progress. The photographs shall be mounted and enclosed back-to-back in a double face plastic sleeve punched to fit standard three ring binders.