The U.S. Army Corps of Engineers, Kansas City District, conducted the bid opening today for Turkey Creek Missouri Interceptor, attached is the opening results. 2:01 opening 15 SEP 2017 in room 254.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Turkey Creek – Missouri Interceptor 15‐Sep‐17
GOVT Bid Bid Bid Bid Bid Bid Bid
Item No. CLIN Description IGE
Radmacher Brother
Excavating Kolb Grading Kissick
Construction Co. Miles Excavating Bid not accepted
0001 PACKAGE B SANITARY SEWER LINE 1 & LINE 2 1,745,900.00$ 1,328,984.00$ 938,068.00$ 1,374,485.43$
0002 PACKAGE B CLEARING, GRUBBING & SITE DEMO 1,060,000.00$ 775,135.00$ 613,093.00$ 1,407,285.89$
0003 PACKAGE B EXCAVATION, BACKFILLING, SITE 3,356,400.00$ 1,756,073.00$ 7,188,936.00$ 5,715,091.53$
0004 PACKAGE B CULVERTS & UTILITIES 16,572,000.00$ 13,242,958.00$ 18,276,469.00$ 11,754,905.29$
0005 PACKAGE B PAVEMENT & TRAFFIC CONTROL 1,655,100.00$ 939,870.00$ 175,895.00$ 863,071.03$
0006 PACKAGE B REMOVING & DISPOSAL OF SOIL 404,000.00$ 537,600.00$ 763,360.00$ 1,059,200.00$
0007 PACKAGE B TREATING OF CONTAMINATED WATER 100,000.00$ 100,000.00$ 250,026.00$ 100,000.00$
0008 PACKAGE C ITEMS 219,000.00$ 276,800.00$ 665,900.00$ 199,106.86$
0009 PACKAGE C REMOVING & DISPOSAL OF SOIL 1,048,000.00$ 364,550.00$ 1,595,212.00$ 1,312,839.88$
0010 PACKAGE C CULVERTS & UTILITIES 2,707,500.00$ 2,912,731.00$ 2,597,925.00$ 2,029,658.71$
0011 PACKAGE C PAVEMENT & TRAFFIC CONTROL 451,400.00$ 783,610.00$ 621,840.00$ 442,109.73$
0012 PACKAGE C REMOVING & DISPOSAL OF PETROLE 404,000.00$ 536,800.00$ 763,360.00$ 870,000.00$
0013 PACKAGE C WATER MAIN REPLACEMENT 163,600.00$ 332,980.00$ 529,494.00$ 108,770.49$
0014 PACKAGE D CLEARING, GRUBBING & SITE DEMO 139,000.00$ 324,120.00$ 85,600.00$ 189,124.54$
0015 PACKAGE D EXCAVATION, BACKFILLING & SITE 872,400.00$ 274,675.00$ 550,148.00$ 815,473.46$
0016 PACKAGE D CULVERTS & UTILITIES 1,217,100.00$ 1,258,954.00$ 1,438,997.00$ 609,109.06$
0017 PACKAGE D PAVEMENT & TRAFFIC CONTROL 340,000.00$ 831,930.00$ 208,953.00$ 622,113.02$ Total Total 32,455,400.00$ 26,577,770.00$ 37,263,276.00$ ‐$ 29,472,344.92$ ‐$ ‐$ ‐$
17 17 0 17 0 0