Questions Government Response
Is Roppe stair nosing and trimmed down cove base an acceptable finish for you to be used at the transition to the break room on the west side of the building?
Roppe stair nosing and trimmed down cove base are acceptable finishes.
For the SDT that needs to be pulled up to fix the grounding wire....it states that you have replacement tile on hand but will we need to supply the adhesive?
The contractor will need to provide the adhesive.
SOW paragraph 3c, what are the user requirements for grounding in room 109?
The ground in room 109 will be a 2” wide copper strap extending 2’ horizontally under the tile with sufficient strapping exposed to allow the user to connect to a grounding point.