Site Visit Q A's
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OH_Door_Site_Visit_Sign-in.pdf | ||
| PWS_outline_Final(2).pdf | ||
| Picture_6_East_End.jpg | JPG image | |
| Picture_2.jpg | JPG image | |
| Picture_1.jpeg | JPEG file | |
| Picture_3.jpg | JPG image | |
| Picture_5_West_End.jpg | JPG image | |
| Picture_4.jpg | JPG image | |
| NOTICE_TO_PROSPECTIVE_OFFERORS_OF_SITE_VISIT.pdf | ||
| Attachment_B_PWS_Overhead_Doors.pdf | ||
| Combined_Synopsis_Solicitation_Overhead_Doors_25_Apr_16.pdf | ||
| Attachment_A_Quote_Worksheet_Overhead_Doors.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overhead Door Site Visit – Question & Answers:
Main Gate/Gaffney Rd.
Q: Who will remove the security cameras and conduit?
A: Government will remove and reinstall security cameras. Conduit and cabling is contractor requirement.
Q: Who will reinstall the security cameras and conduit?
A: Government will remove and reinstall security cameras. Conduit and cabling is contractor requirement.
Q: Are the cameras being used?
A: Yes
Q: Is there any concern with not having a door in place at the end of a workday?
A: No, the Govt. will coordinate with the Contractor throughout the project.
Q: Does the cord on the outside of the building control all of the doors?
A: It supplies electricity to structure which supplies power to the door controls.
Q: What is the voltage for the outside cord?
A: Unknown.
Q: What is the voltage for each opener?
A: Unknown.
Q: Is the Government intending on adding heat to insulate the building this coming winter?
A: Not at this time.
Q: The thresholds under the door are not level and there will be a gap under the door. Is this gap acceptable?
A: Yes, the gap under the doors due to the slope of the asphalt is acceptable under this action.
Contractor should seek to minimize any gap during door installation.
Q: Please specify what you are looking for as far as controls. Do you want remotes?
A: Yes (please see PWS para 1.3.) 1 – hand remote per door and 1 wall mount per door and a manual override for each door for power outages.
Q: Do you want all doors controlled from one remote or separate remotes for each door?
A: One remote per door. Please (see PWS para 1.3.) 1 – hand remote per door and 1 wall mount per door and a manual override for each door for power outages.
Q: Do you want corresponding numbers on the doors to match remotes such as vinyl stickers?
A: Not required. Contractor will clearly delineate remotes and associated doors. Gov’t will mark the doors afterward.
Q: Do you want to keep one inspection bay operational?
A: Yes if possible one inspection needs to be operational at Main Gate. Badger gate will be closed to inspections during construction. The Govt. will coordinate with the scheduling needs of the contractor.
Badger Gate
Q: Can the tie downs be relocated?
A: Yes they can be removed for the installation of the doors and relocated to secure the structure to the ground as appropriate.
Q: Is the Contractor responsible to relocate and reinstall the tie downs?
A: Yes.
Q: What type of fuel is in the fuel line?
A: Diesel, JP-8 for heaters.
Q: Do you want the same plug-in as the main gate?
A: No the power box has a dedicated circuit breaker for each door located in the power panel in the east end of the structure.
Q: Can the bottom conduit be abandoned?
A: No. Conduit pathways may be relocated reinstalled with same cabling pulled back in new pathway.
Gov’t will remove cameras before and reinstall cameras once work is completed.