This is a solicitation for laboratory analysis services including asbestos and metals testing. The U.S. Army seeks fixed-price quotes by September 6, 2023 for analysis of bulk samples, air samples, and paint chip samples to identify asbestos, lead, arsenic, and other metals. Services include polarized light microscopy, phase contrast microscopy, transmission electron microscopy, and toxicity characteristic leaching procedure. The base period of performance is October 2023 through September 2024 with four one-year option periods. Quotes will be evaluated on certification compliance, work experience, and price. Award will be made to the responsible vendor providing the lowest price that meets requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912CN23Q0032 02-Aug-2023
b. TELEPHONE NUMBER
(808) 656-0933
8. OFFER DUE DATE/LOCAL TIME
10:00 AM 06 Sep 2023
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912CN9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
KARI AKAMINE
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
413 CSB
413TH CSB, RCO-HAWAII,
742 SANTOS DUMONT AVENUE
BLDG 108, 3RD FLOOR (WAAF)
SCHOFIELD BARRACKS HI 96857-5026
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE WX3JN3 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
US ARMY GARRISON HI DIR OF PUB WKS DPW
JACQUELINE ALVAREZ-MARTINEZ
BLDG 104 947 WRIGHT AVE WAAF SERVICE CO
SCHOFIELD BARRACKS HI 96857
TEL: (808) 656-3097 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$19,000,000
NAICS:
541380
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
X
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF154
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 1449 - CONTINUATION SHEET
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 750 Each Asbestos Bulk PLM, 10 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days.
Reference Performance Work Statement (PWS) Paragraph 8.1.5 FOB: Destination
PSC CD: F107
NET AMT
0002 250 Each Asbestos Bulk PLM, 5 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
0003 20 Each Asbestos Bulk Point Count PLM, 10 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
0004 15 Each Asbestos Bulk Point Count PLM, 5 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
0005 100 Each Asbestos Air PCM, 5 Day
FFP
Asbestos - Air Samples, PCM (Phase Contrast Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
0006 25 Each Asbestos Air TEM 7402
FFP
Asbestos - Air Samples, TEM 7402 (Transmission Electron Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
0007 52 Each Asbestos Air TEM AHERA
FFP
Asbestos - Air Samples, TEM (Transmission Electron Microscopy), AHERA Analysis Method. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
0008 340 Each Metals Bulk Total Lead, 10 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0009 120 Each Metals Bulk Total Lead, 5 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0010 15 Each Metals Bulk Total Arsenic, 10 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0011 15 Each Metals Bulk Total Arsenic, 5 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0012 25 Each Metals Bulk TCLP Lead
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) Lead.
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0013 25 Each Metals Bulk TCLP RCRA
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) RCRA 8 Metals (As, Pb, Se, BA, Cd, Cr, Ag, Hg). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0014 15 Each Metals Air Total Lead
FFP
Metals - Air Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0015 15 Each Metals Air Total Arsenic
FFP
Metals - Air Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
0016 300 Each PTA Asbestos Bulk PLM
FFP
PTA Asbestos, Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
0017 15 Each PTA Asbestos Bulk Point Count PLM
FFP
PTA Asbestos, Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
0018 150 Each PTA Metals Bulk Total Lead
FFP
PTA Metals, Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
0019 15 Each PTA Metals Bulk Total Arsenic
FFP
PTA Metals, Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
1001 750 Each OPTION Asbestos Bulk PLM, 10 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1002 250 Each OPTION Asbestos Bulk PLM, 5 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1003 20 Each OPTION Asbestos Bulk Point Count PLM, 10 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1004 15 Each OPTION Asbestos Bulk Point Count PLM, 5 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1005 100 Each OPTION Asbestos Air PCM, 5 Day
FFP
Asbestos - Air Samples, PCM (Phase Contrast Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1006 25 Each OPTION Asbestos Air TEM 7402
FFP
Asbestos - Air Samples, TEM 7402 (Transmission Electron Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1007 52 Each OPTION Asbestos Air TEM AHERA
FFP
Asbestos - Air Samples, TEM (Transmission Electron Microscopy), AHERA Analysis Method. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
1008 340 Each OPTION Metals Bulk Total Lead, 10 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1009 120 Each OPTION Metals Bulk Total Lead, 5 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1010 15 Each OPTION Metals Bulk Total Arsenic, 10 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1011 15 Each OPTION Metals Bulk Total Arsenic, 5 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1012 25 Each OPTION Metals Bulk TCLP Lead
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) Lead.
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1013 25 Each OPTION Metals Bulk TCLP RCRA
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) RCRA 8 Metals (As, Pb, Se, BA, Cd, Cr, Ag, Hg). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1014 15 Each OPTION Metals Air Total Lead
FFP
Metals - Air Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1015 15 Each OPTION Metals Air Total Arsenic
FFP
Metals - Air Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
1016 300 Each OPTION PTA Asbestos Bulk PLM
FFP
PTA Asbestos, Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
1017 15 Each OPTION PTA Asbestos Bulk Point Count PLM
FFP
PTA Asbestos, Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
1018 150 Each OPTION PTA Metals Bulk Total Lead
FFP
PTA Metals, Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
1019 15 Each OPTION PTA Metals Bulk Total Arsenic
FFP
PTA Metals, Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
2001 750 Each OPTION Asbestos Bulk PLM, 10 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2002 250 Each OPTION Asbestos Bulk PLM, 5 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2003 20 Each OPTION Asbestos Bulk Point Count PLM, 10 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2004 15 Each OPTION Asbestos Bulk Point Count PLM, 5 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2005 100 Each OPTION Asbestos Air PCM, 5 Day
FFP
Asbestos - Air Samples, PCM (Phase Contrast Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2006 25 Each OPTION Asbestos Air TEM 7402
FFP
Asbestos - Air Samples, TEM 7402 (Transmission Electron Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2007 52 Each OPTION Asbestos Air TEM AHERA
FFP
Asbestos - Air Samples, TEM (Transmission Electron Microscopy), AHERA Analysis Method. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
2008 340 Each OPTION Metals Bulk Total Lead, 10 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2009 120 Each OPTION Metals Bulk Total Lead, 5 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2010 15 Each OPTION Metals Bulk Total Arsenic, 10 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2011 15 Each OPTION Metals Bulk Total Arsenic, 5 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2012 25 Each OPTION Metals Bulk TCLP Lead
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) Lead.
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2013 25 Each OPTION Metals Bulk TCLP RCRA
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) RCRA 8 Metals (As, Pb, Se, BA, Cd, Cr, Ag, Hg). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2014 15 Each OPTION Metals Air Total Lead
FFP
Metals - Air Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2015 15 Each OPTION Metals Air Total Arsenic
FFP
Metals - Air Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
2016 300 Each OPTION PTA Asbestos Bulk PLM
FFP
PTA Asbestos, Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
2017 15 Each OPTION PTA Asbestos Bulk Point Count PLM
FFP
PTA Asbestos, Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
2018 150 Each OPTION PTA Metals Bulk Total Lead
FFP
PTA Metals, Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
2019 15 Each OPTION PTA Metals Bulk Total Arsenic
FFP
PTA Metals, Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
3001 750 Each OPTION Asbestos Bulk PLM, 10 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3002 250 Each OPTION Asbestos Bulk PLM, 5 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3003 20 Each OPTION Asbestos Bulk Point Count PLM, 10 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3004 15 Each OPTION Asbestos Bulk Point Count PLM, 5 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3005 100 Each OPTION Asbestos Air PCM, 5 Day
FFP
Asbestos - Air Samples, PCM (Phase Contrast Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3006 25 Each OPTION Asbestos Air TEM 7402
FFP
Asbestos - Air Samples, TEM 7402 (Transmission Electron Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3007 52 Each OPTION Asbestos Air TEM AHERA
FFP
Asbestos - Air Samples, TEM (Transmission Electron Microscopy), AHERA Analysis Method. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
3008 340 Each OPTION Metals Bulk Total Lead, 10 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3009 120 Each OPTION Metals Bulk Total Lead, 5 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3010 15 Each OPTION Metals Bulk Total Arsenic, 10 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3011 15 Each OPTION Metals Bulk Total Arsenic, 5 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3012 25 Each OPTION Metals Bulk TCLP Lead
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) Lead.
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3013 25 Each OPTION Metals Bulk TCLP RCRA
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) RCRA 8 Metals (As, Pb, Se, BA, Cd, Cr, Ag, Hg). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3014 15 Each OPTION Metals Air Total Lead
FFP
Metals - Air Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3015 15 Each OPTION Metals Air Total Arsenic
FFP
Metals - Air Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
3016 300 Each OPTION PTA Asbestos Bulk PLM
FFP
PTA Asbestos, Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
3017 15 Each OPTION PTA Asbestos Bulk Point Count PLM
FFP
PTA Asbestos, Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
3018 150 Each OPTION PTA Metals Bulk Total Lead
FFP
PTA Metals, Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
3019 15 Each OPTION PTA Metals Bulk Total Arsenic
FFP
PTA Metals, Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
4001 750 Each OPTION Asbestos Bulk PLM, 10 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4002 250 Each OPTION Asbestos Bulk PLM, 5 Day
FFP
Asbestos - Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4003 20 Each OPTION Asbestos Bulk Point Count PLM, 10 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4004 15 Each OPTION Asbestos Bulk Point Count PLM, 5 Day
FFP
Asbestos - Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4005 100 Each OPTION Asbestos Air PCM, 5 Day
FFP
Asbestos - Air Samples, PCM (Phase Contrast Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4006 25 Each OPTION Asbestos Air TEM 7402
FFP
Asbestos - Air Samples, TEM 7402 (Transmission Electron Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4007 52 Each OPTION Asbestos Air TEM AHERA
FFP
Asbestos - Air Samples, TEM (Transmission Electron Microscopy), AHERA Analysis Method. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.5
4008 340 Each OPTION Metals Bulk Total Lead, 10 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4009 120 Each OPTION Metals Bulk Total Lead, 5 Day
FFP
Metals - Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4010 15 Each OPTION Metals Bulk Total Arsenic, 10 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4011 15 Each OPTION Metals Bulk Total Arsenic, 5 Day
FFP
Metals - Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4012 25 Each OPTION Metals Bulk TCLP Lead
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) Lead.
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4013 25 Each OPTION Metals Bulk TCLP RCRA
FFP
Metals - Bulk Samples, TCLP (Toxicity Characteristic Leaching Procedure) RCRA 8 Metals (As, Pb, Se, BA, Cd, Cr, Ag, Hg). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 17 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4014 15 Each OPTION Metals Air Total Lead
FFP
Metals - Air Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4015 15 Each OPTION Metals Air Total Arsenic
FFP
Metals - Air Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 5 Days Reference Performance Work Statement (PWS) Paragraph 8.1.6
4016 300 Each OPTION PTA Asbestos Bulk PLM
FFP
PTA Asbestos, Bulk Samples, PLM (Polarized Light Microscopy). Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
4017 15 Each OPTION PTA Asbestos Bulk Point Count PLM
FFP
PTA Asbestos, Bulk Samples, Point Count PLM (Polarized Light Microscopy).
Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.5
4018 150 Each OPTION PTA Metals Bulk Total Lead
FFP
PTA Metals, Bulk Samples, Total Lead. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
4019 15 Each OPTION PTA Metals Bulk Total Arsenic
FFP
PTA Metals, Bulk Samples, Total Arsenic. Provide Laboratory Analysis Report.
Turn Around Time (TAT): 10 Days Reference Performance Work Statement (PWS) Paragraphs 1.1 and 8.1.6
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0010 Destination Government Destination Government 0011 Destination Government Destination Government 0012 Destination Government Destination Government 0013 Destination Government Destination Government 0014 Destination Government Destination Government 0015 Destination Government Destination Government 0016 Destination Government Destination Government 0017 Destination Government Destination Government 0018 Destination Government Destination Government 0019 Destination Government Destination Government 1001 Destination Government Destination Government 1002 Destination Government Destination Government 1003 Destination Government Destination Government 1004 Destination Government Destination Government 1005 Destination Government Destination Government 1006 Destination Government Destination Government 1007 Destination Government Destination Government 1008 Destination Government Destination Government
1009 Destination Government Destination Government 1010 Destination Government Destination Government 1011 Destination Government Destination Government 1012 Destination Government Destination Government 1013 Destination Government Destination Government 1014 Destination Government Destination Government 1015 Destination Government Destination Government 1016 Destination Government Destination Government 1017 Destination Government Destination Government 1018 Destination Government Destination Government 1019 Destination Government Destination Government 2001 Destination Government Destination Government 2002 Destination Government Destination Government 2003 Destination Government Destination Government 2004 Destination Government Destination Government 2005 Destination Government Destination Government 2006 Destination Government Destination Government 2007 Destination Government Destination Government 2008 Destination Government Destination Government 2009 Destination Government Destination Government 2010 Destination Government Destination Government 2011 Destination Government Destination Government 2012 Destination Government Destination Government 2013 Destination Government Destination Government 2014 Destination Government Destination Government 2015 Destination Government Destination Government 2016 Destination Government Destination Government 2017 Destination Government Destination Government 2018 Destination Government Destination Government 2019 Destination Government Destination Government 3001 Destination Government Destination Government 3002 Destination Government Destination Government 3003 Destination Government Destination Government 3004 Destination Government Destination Government 3005 Destination Government Destination Government 3006 Destination Government Destination Government 3007 Destination Government Destination Government 3008 Destination Government Destination Government 3009 Destination Government Destination Government 3010 Destination Government Destination Government 3011 Destination Government Destination Government 3012 Destination Government Destination Government 3013 Destination Government Destination Government 3014 Destination Government Destination Government 3015 Destination Government Destination Government 3016 Destination Government Destination Government 3017 Destination Government Destination Government 3018 Destination Government Destination Government 3019 Destination Government Destination Government 4001 Destination Government Destination Government 4002 Destination Government Destination Government 4003 Destination Government Destination Government 4004 Destination Government Destination Government 4005 Destination Government Destination Government 4006 Destination Government Destination Government 4007 Destination Government Destination Government
4008 Destination Government Destination Government 4009 Destination Government Destination Government 4010 Destination Government Destination Government 4011 Destination Government Destination Government 4012 Destination Government Destination Government 4013 Destination Government Destination Government 4014 Destination Government Destination Government 4015 Destination Government Destination Government 4016 Destination Government Destination Government 4017 Destination Government Destination Government 4018 Destination Government Destination Government 4019 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-OCT-2023 TO
30-SEP-2024
N/A US ARMY GARRISON HI DIR OF PUB
WKS DPW
JACQUELINE ALVAREZ-MARTINEZ
BLDG 104 947 WRIGHT AVE WAAF
SERVICE CO
SCHOFIELD BARRACKS HI 96857
(808) 656-3097
WX3JN3
0002 POP 01-OCT-2023 TO
30-SEP-2024
N/A (SAME AS PREVIOUS LOCATION)
0003 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0004 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0005 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0006 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0007 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0008 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0009 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0010 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0011 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0012 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0013 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0014 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0015 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0016 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0017 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0018 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
0019 POP 01-OCT-2023 TO
N/A (SAME AS PREVIOUS LOCATION)
1001 POP 01-OCT-2024 TO
30-SEP-2025
N/A (SAME AS PREVIOUS LOCATION)
1002 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1003 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1004 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1005 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1006 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1007 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1008 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1009 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1010 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1011 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1012 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1013 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1014 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1015 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1016 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1017 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1018 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
1019 POP 01-OCT-2024 TO
N/A (SAME AS PREVIOUS LOCATION)
2001 POP 01-OCT-2025 TO
30-SEP-2026
N/A (SAME AS PREVIOUS LOCATION)
2002 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2003 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2004 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2005 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2006 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2007 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2008 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2009 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2010 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2011 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2012 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2013 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2014 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2015 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2016 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2017 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2018 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
2019 POP 01-OCT-2025 TO
N/A (SAME AS PREVIOUS LOCATION)
3001 POP 01-OCT-2026 TO
30-SEP-2027
N/A (SAME AS PREVIOUS LOCATION)
3002 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3003 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3004 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3005 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3006 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3007 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3008 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3009 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3010 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3011 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3012 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3013 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3014 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3015 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3016 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3017 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3018 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
3019 POP 01-OCT-2026 TO
N/A (SAME AS PREVIOUS LOCATION)
4001 POP 01-OCT-2027 TO
30-SEP-2028
N/A (SAME AS PREVIOUS LOCATION)
4002 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4003 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4004 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4005 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4006 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4007 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4008 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4009 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4010 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4011 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4012 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4013 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4014 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4015 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4016 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4017 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4018 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
4019 POP 01-OCT-2027 TO
N/A (SAME AS PREVIOUS LOCATION)
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
JUN 2020
52.204-2 Security Requirements MAR 2021 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
NOV 2021
52.204-22 Alternative Line Item Proposal JAN 2017 52.212-4 Contract Terms and Conditions--Commercial Products and
Commercial Services
DEC 2022
52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.217-5 Evaluation Of Options JUL 1990 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-10 Waste Reduction Program MAY 2011 52.228-7 Insurance--Liability To Third Persons MAR 1996 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-8 Discounts For Prompt Payment FEB 2002 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-32 Performance-Based Payments APR 2012 52.232-37 Multiple Payment Arrangements MAY 1999 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014 52.237-1 Site Visit APR 1984 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.237-3 Continuity Of Services JAN 1991 52.242-13 Bankruptcy JUL 1995 52.242-17 Government Delay Of Work APR 1984 52.243-1 Alt I Changes--Fixed Price (Aug 1987) - Alternate I APR 1984 52.246-4 Inspection Of Services--Fixed Price AUG 1996 52.247-34 F.O.B. Destination NOV 1991 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors JAN 2023 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
JAN 2023
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
JAN 2023
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements MAR 2022 252.204-7020 NIST SP 800-171 DoD Assessment Requirements JAN 2023 252.204-7022 Expediting Contract Closeout MAY 2021 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
MAY 2019
252.215-7008 Only One Offer DEC 2022
252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors
JAN 2023
252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials
SEP 2014
252.225-7012 Preference For Certain Domestic Commodities APR 2022 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7004 (Dev) DoD Progress Payment Rates (DEVIATION 2020-O0010) MAR 2020 252.232-7007 Limitation Of Government's Obligation APR 2014 252.232-7009 Mandatory Payment by Governmentwide Commercial
Purchase Card
MAY 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JAN 2023
252.237-7024 Notice of Continuation of Essential Contractor Services. OCT 2010 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2022 252.244-7000 Subcontracts for Commercial Products or Commercial
Services
JAN 2023
CLAUSES INCORPORATED BY FULL TEXT
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Products and Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.
(a) Definitions. As used in this provision-
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."
(d) Representations. The Offeror represents that--
(1) It [ ___ ] will, [ ___ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and
(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--
It [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.
(e) Disclosures.
(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(End of provision)
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT
2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representations.
(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
52.212-1 INSTRUCTIONS TO OFFERORS--COMMERCIAL PRODUCTS AND COMMERCIAL…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .