About this file

This is a Solicitation for Proposals (RFP) issued by the Army Contracting Command - Detroit Arsenal for the procurement of a Tent Door, NSN 8340-01-440-8885. The solicitation (W912CH-25-R-0179) seeks 67 units with a 67-unit option, to be acquired through a Firm-Fixed Price contract. The requirement includes a First Article Test Report and involves an export-controlled Technical Data Package (TDP) with Distribution Statement C, limiting access to U.S. Government Agencies and their Contractors.

Key details include a proposal submission deadline of 28 August 2025 at 3:00 PM local Warren, MI time, with a 90-calendar day proposal validity period. The procurement uses NAICS code 314910 (Textile Bag and Canvas Mills) with a small business size standard of 500 employees. Contractors must be registered in the System for Award Management (SAM) and obtain Joint Certification Program (JCP) approval to access the Technical Data Package. The contract will be awarded on a full and open competition basis, with proposals to be submitted electronically to the Contract Specialist.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER AND AWARD 1. This Contract Is A Rated Order Under

DPAS (15 CFR 700)

Rating Page of Pages

2. Contract Number 3. Solicitation Number 4. Type of Solicitation 5. Date Issued 6. Requisition/Purchase Number Sealed Bid (IFB)

Negotiated (RFP)

7. Issued By Code 8. Address Offer To (If Other Than Item 7)

NOTE: In sealed bid solicitations ‘offer’ and ‘offeror’ mean ‘bid’ and ‘bidder’.

SOLICITATION

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in item 8, or if handcarried, in the depository located in until (hour) local time (Date).

Caution - Late Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. For Information A. Name B. Telephone (No Collect Calls) C. E-mail Address

Call: Area Code Number Ext.

11. Table Of Contents

(X) Sec. Description Page(s) (X) Sec. Description Page(s)

Part I - The Schedule Part II - Contract Clauses A Solicitation/Contract Form I Contract Clauses

B Supplies or Services and Prices/Costs Part III - List Of Documents, Exhibits, And Other Attach.

C Description/Specs./Work Statement J List of Attachments D Packaging and Marking Part IV - Representations And Instructions E Inspection and Acceptance K Representations, Certifications, and F Deliveries or Performance Other Statements of Offerors G Contract Administration Data L Instrs., Conds., and Notices to Offerors H Special Contract Requirements M Evaluation Factors for Award

OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

12. In compliance with the above, the undersigned agrees, if this offer is accepted within _____ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. Discount For Prompt Payment 10 Calendar Days (%) 20 Calendar Days (%) 30 Calendar Days (%) Calendar Days (%) (See Section I, Clause No. 52.232-8)

14. Acknowledgment of Amendments (The offeror acknowledges Amendment No. Date Amendment No. Date receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):

15A. Name and Code Facility 16. Name and Title of Person Authorized to Sign Offer Address of (Type or Print) Offeror

15B. Telephone Number 15C. Check if Remittance Address is 17. Signature 18. Offer Date Area Code Number Ext. Different From Above – Enter such

Address In Schedule

AWARD (To be completed by Government)

19. Accepted As To Items Numbered 20. Amount 21. Accounting And Appropriation

22. Authority For Using Other Than Full And Open Competition: 23. Submit Invoices To Address Shown In Item

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

24. Administered By (If other than Item 7) Code 25. Payment Will Be Made By Code

26. Name of Contracting Officer (Type or Print) 27. United States Of America 28. Award Date

(Signature of Contracting Officer)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 33 (Rev. 9-97) Previous edition is unusable Prescribed By GSA-FAR (48 CFR) 53.214(c)

W912CH-25-R-0179

X

2025JUL29

2025AUG2803:00pm

DOA4

2025JUL29 SEE SCHEDULE

W912CH

ACC-DTA

6501 E. 11 MILE RD.

DETROIT ARSENAL, MI 48397-5000

DANIELLE CAMPBELL

(571)588-1532

CCTA-APS-A

DANIELLE.R.CAMPBELL9.CIV@ARMY.MIL

1 70

X 1

X 4 X 11

X 14 X 16 X 22

X 28

X 30

X 49

X 50

X 62

X 69

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: DANIELLE CAMPBELL

Buyer Office Symbol/Telephone Number: CCTA-APS-A/(571)588-1532

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

Weapon System: Collective Protection Equipment

*** End of Narrative A0000 ***

A.1 DESCRIPTION OF THE ACTION

A.1.1 This solicitation is issued on a full and open competition basis and is intended to result in the award of a single, firm-fixed price (FFP) contract for the supply of the Door, Tent.

A.1.2 There is a Technical Data Package (TDP) associated with this procurement. The TDP is Distribution Statement C, which limits access to U.S. Government Agencies and their Contractors. Please refer to Section C for additional information.

A.2 SOLICITATION STRUCTURE

The Government will utilize North American Industry Classification System (NAICS) code 314910 (Textile Bag and Canvas Mills).

A.3 SYSTEM FOR AWARD MANAGEMENT (SAM), SIZE STANDARDS, AND NAICS CODES

Failure to register in SAM for the corresponding NAICS code identified in paragraph A.2 prior to submitting a proposal against this solicitation may preclude an award being made to your company. Offerors should be aware of how U.S. Small Business (SB) concerns are defined in FAR Part 19, Defense Federal Acquisition Regulation Supplement (DFARS) Part 19, and 13 CFR 121, Small Business Size

Regulations. Offerors are advised to review 13 CFR 121.103, "How does SBA Determine Affiliation."

A.4 ELECTRONIC CONTRACTING

A.4.1 All Army Contracting Command Detroit Arsenal solicitations will be publicized on the System for Award Management website

(https://www.sam.gov). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.

A.4.2 Interested offerors shall submit a proposal via email to the Contract Specialist (danielle.r.campbell9.civ@army.mil) with the subject header: Proposal Submission W912CH-25-R-0179 (company name). Once a proposal is received, the Contract Specialist/Contracting

Officer will reply with the respective Offeror stating receipt of proposal submission.

A.4.3 Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, to be received by the Government office designated in the solicitation by the time specified.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

A.4.4 Solicitations may remain posted on www.SAM.gov after the solicitation closing date.

A.4.5 Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the Government's intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the

Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

A.4.6 For technical assistance in doing business with the Government, and doing business electronically, please visit the Procurement

Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.

A.4.7 All questions regarding the requirements of this solicitation and applicable attachments must be submitted by 12 August 2025, 12:00 PM Local Warren, MI time to danielle.r.campbell9.civ@army.mil. The Government shall review all questions received but is not obligated to answer questions submitted after the date noted above.

2 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

A.5 ACKNOWLEDGEMENT OF AMENDMENTS

Acknowledge all the amendments received from the Government by identifying the amendment number and its issue date below:

Amendment Number: Date:

A.6 ARMY CONTRACTING COMMAND DETROIT ARSENAL (DTA) OMBUDSPERSON

Information regarding the Ombudsperson for this contract is located at the following website: https://www.tacom.army.mil/ombudsperson.

(Best viewed using Google Chrome or Microsoft Edge)

A.7 DISTRIBUTION AND DESTRUCTION OF EXPORT CONTROL TECHNICAL DATA PACKAGE

A.7.1 This solicitation and resulting contract contains technical data whose export is restricted by the Arms Export Control Act (Title

22, U.S.C., Sec 2751, et. seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

A.7.2 To be eligible to gain access to this export controlled TDP (via SAM.gov) an offeror must have a current DD 2345, Militarily

Critical Technical Data Agreement certification on file with the Defense Logistics Information Service (DLIS). To obtain certification, contractors must submit a DD Form 2345 to the United States (U.S.)/Canada Joint Certification Office (JCO), along with a copy of supporting documentation. DD Form 2345 and instructions can be found on the Joint Certification Program website at:

http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplica ions/JCP.aspx

Processing time is estimated at six (6)to ten (10) weeks after receipt. Upon receipt of certification, an offeror may request the TDP in accordance with the solicitation's Section C Technical Data Package instructions.

A.7.3 Upon completion of the purposes for which Government Technical Data has been provided, the offeror, and all subcontractors, vendors, and sub-vendors of the offeror, are required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed.

A.7.4 Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the

TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

A.8 ALL OR NONE

A.8.1 Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

A.8.1.1 ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

A.8.1.2 OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION WILL BE DEEMED NONRESPONSIVE.

A.9

*** END OF NARRATIVE A0001 ***

3 70

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

0001 DOOR, TENT

NSN: 8340-01-440-8885

Mfr CAGE: 81337

Mfr Part Number: 5-4-3371-2

0001AA PRODUCTION QUANTITY 67 EA $ $ ___________________ ______________ __________________

COMMODITY NAME: DOOR, TENT

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH4C0137EH PRON AMD: 02

AMS CD: SM2B1100000

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS; SECTION D

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W58HZ13354V021 W41G27 J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 67 0150

FOB POINT: Destination

SHIP TO:

(W41G27) SR W0K4 USA OSC PINE BLUFF ARS

TRANS OFFICE BLDG 11 080

10020 KABRICH CIRCLE

PINE BLUFF,AR,71602-9500

0001AB FIRST ARTICLE TEST REPORT (FATR) 1 LO $ ________________________________ __________________

SERVICE REQUESTED: FIRST ARTICLE TEST AND REPORT

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH5C0484EH PRON AMD: 01

AMS CD: SM2B1100000

First Article Test Report (Contractor), pursuant to the requirements listed in:

4 70

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

Section E.5: Notice Regarding First Article;

Section E.6: Notice Regarding First Article Test

Sample;

Section E.7: Supplemental Requirements to First

Article Approval (Contractor Testing);

Section E.8: Inspection and Acceptance (First Article

Approval);

FAR 52.209-3 First Article Approval Contractor

Testing Alternate I and Alternate II (See Section I for additional information); and

Addenda

-Exhibit A: Contract Data Requirements List DD Form

1423, A004.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 1 0090

0002 DOOR, TENT

Mfr CAGE: 81337

Mfr Part Number: 8340014408885

0002AA UNEXERCISED OPTION QUANTITY 67 EA $ $ ___________________________ ______________ __________________

COMMODITY NAME: DOOR, TENT

CLIN CONTRACT TYPE:

Firm Fixed Price

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS; SECTION D

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

5 70

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 67 0120

FOB POINT: Destination

SHIP TO:

(W41G27) SR W0K4 USA OSC PINE BLUFF ARS

TRANS OFFICE BLDG 11 080

10020 KABRICH CIRCLE

PINE BLUFF,AR,71602-9500

9000 CONTRACT DATA REQUIREMENTS LIST _______________________________

The Exhibit Line Item Numbers (ELINs) below are associated with specific contract requirements.

Please refer to the citations listed within each ELIN for additional information.

(End of narrative A001)

A001 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: ENGINEERING CHANGE PROPOSAL

Engineering Change Proposal (ECP) for Door, Tent in accordance with:

- Section C.2 Configuration Management Documentation;

and

- Exhibit A: Contract Data Requirements List DD Form

1423, A001.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A002 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

6 70

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SERVICE REQUESTED: REQUEST FOR VARIANCE

Request for Variance (RFV) for Door, Tent in accordance with:

- Section C.2: Configuration Management

Documentation; and

- Exhibit A: Contract Data Requirements List DD Form

1423, A002.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A003 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: NOTICE OF REVISION

Notice of Revision (NOR) for Door, Tent in accordance with:

- Section C.2: Configuration Management

Documentation; and

- Exhibit A: Contract Data Requirements List DD Form

1423, A003.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A004 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: MEETING MINUTES

Report, Record of Meeting Minutes for Door, Tent in accordance with:

7 70

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

- Section C.3: Start of Work Meeting; and

- Exhibit A: Contract Data Requirements List Form DD

1423, A004.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A005 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: FIRST ARTICLE TEST REPORT

First Article Test Report (FATR) for Door, Tent in accordance with:

- Section E.2: Inspection and Acceptance (First

Article Approval);

- Section E.3: First Article Testing Contractor;

- Section E.4: Destructive Testing;

- Section E.5: Inclusion of Testing Costs;

- Section E.6: Lab Performance Certification

Requirements;

- Section E.7: First Article Testing (Contractor)

Utilization of ECBC Lab (TSA);

- FAR 52.209-3: First Article Approval; and

- Exhibit A: Contract Data Requirements List Form DD

1423, A005.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

8 70

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

A006 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: CERTIFICATE OF COMPLIANCE

Certificate of Compliance (Blocks 3 through 19 of

Form 010) for Door, Tent in accordance with:

- Exhibit A: Contract Data Requirements List Form DD

1423, A006.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A007 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: QUALITY PROGRAM PLAN

Quality Program Plan (QPP) for Door, Tent in accordance with:

- Exhibit A: Contract Data Requirements List Form DD

1423, A007.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A008 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: OPSEC TRAINING REPORT

Certificate of Compliance, OPSEC Awareness (Level 1)

Training Report for Door, Tent in accordance with:

- Section C.5: Controlled Unclassified Information

(CUI) Guidelines;

9 70

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

- Section C.6: Requirement for an OPSEC Standing

Operation Procedure/Plan;

- Section C.7: OPSEC Training Requirement; and

- Exhibit A: Contract Data Requirements List Form DD

1423, A008.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

A009 DATA ITEM - DD 250 NOT REQUIRED 1 LO $ ** NSP ** _______________________________ __________________

SERVICE REQUESTED: THREAT AWARENESS REPORTING

Certificate of Compliance, Threat Awareness Reporting

Program (TARP) for Door, Tent in accordance with:

- Section C.8: Threat Awareness Reporting Program;

and

- Exhibit A: Contract Data Requirements List Form DD

1423, A009.

(End of narrative B001)

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Destination

DLVR SCH PERF COMPL

REL CD QUANTITY DATE ________ ______________ __________

001 1 SEE DD FORM 1423

10 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1 TECHNICAL DATA PACKAGE INFORMATION

C.1.1 The TDP for this solicitation resides within the System for Award Management (SAM) (https://SAM.gov) associated with this solicitation number:

W912CH-25-R-0179

C.1.2 To access the data through SAM:

C.1.2.1 Log on to the SAM web site: https://SAM.gov.

C.1.2.2 Search for the solicitation number.

C.1.2.3 Click on the attachment you would like to view.

C.1.2.4 If the attachment is restricted, request access to the document.

C.1.2.5 If technical data is otherwise restricted, select "Request Explicit Access." This will generate an email to the Contract

Specialist and Contracting Officer at Army Contract Command - Warren (DTA) with all the information needed to grant contractor access to restricted documents. SAM will automatically generate an email stating when the requesting contractor has permission to view or download

TDP items.

C.1.2.6 If multiple individuals in the contractor's organization need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP.

Those same individuals MUST be registered in SAM. Any individuals no longer with the company should be deleted. Questions related to registration in SAM should be directed to https://www.sam.gov/ The SAM helpdesk phone number is (866) 606-8220. Vendors are responsible for placing correct information in SAM.

C.1.2.7 It is strongly suggested that contractors submit the explicit access request and provide the buyer with the completed "Use and

Non-Disclosure Agreement" at the same time if the solicitation requires both to gain access to view the TDP.

C.1.3 TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Section 2751 of Title 22, United

States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 48014852 of Title 50, United States Code).

C.1.3.1 Further dissemination of the TDP must be in accordance with provisions of DoD Directive 5230.25, DoDI 5230.24, its Distribution

Statement markings, and U.S. export control laws. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

C.1.3.2 To obtain these TDPs, contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with Defense

Logistics Information Service (DLIS). To obtain certification, go to DD FORM 2345 Instructions and DD 2345.

C.1.4 Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor.

Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

C.2 CONFIGURATION MANAGEMENT DOCUMENTATION

C.2.1 The Contractor may submit Engineering Change Proposals (ECPs), Requests for Variance (RFVs), and Notices of Revision (NORs) for the requirements in the Government-provided Technical Data Package (TDP).

C.2.1.1 The Configuration Change Management section of SAE EIA-649-1(current revision) Configuration Management Requirement for Defense

Contracts, Paragraph 3.3, shall be used for configuration control of material with the following exclusions: paragraph 3.3(3); the second sentence of paragraph 3.3.1.8.1(1).

C.2.1.2 Furnished item(s) shall conform to the approved configuration requirements/revision, unless a Request for Variance (RFV) is processed and approved as provided by Paragraph E. below. The term "Request for Variance" includes Requests for Deviations and Waivers.

C.2.1.3 Value Engineering Change Proposals (VECPs) for cost saving improvements to the TDP should not be processed per SAE EIA-649-1 and should be referred to Section I FAR Clause 52.248-1 - Value Engineering.

C.2.1.4 All ECPs submitted will be deemed routine. If an ECP is considered as an emergency or urgent; that justification for the rationale shall be included in the ECP submittal with all applicable supporting documentation.

C.2.1.5 For ECPs, RFVs, or NORs, the Contractor must submit the documentation listed in sub-paragraphs C.2.1.5.1 through C.2.1.5.3.

11 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Failure to submit a complete legible package may result in return of the ECP/RFV/SCN/NOR without processing.

C.2.1.5.1 for ECPs, the Contractor shall prepare and deliver the ECP in accordance with (IAW) CDRL A001.

C.2.1.5.2 for RFVs, the Contractor shall prepare and deliver the RFV IAW CDRL A002.

C.2.1.5.3 for NORs, the Contractor shall prepare and deliver the NOR IAW CDRL A003.

C.2.1.6 The Government's acceptance of the data deliverable required by CDRL/DD Form 1423 in C.2.1.5.1-C.2.1.5.3 above signifies only that the data satisfies the requirements of the DID and is considered acceptable for Government processing. Acceptance of the data deliverable does not signify "technical approval" of the change proposed by the deliverable and should not be interpreted as authorizing the Contractor to proceed with the work proposed by the change. Disposition of the change (approval/disapproval) will follow acceptance of the CDRL at the Government's sole discretion. Incorporation of an approved RFV or ECP will require execution of a contract modification.

C.2.1.7 The Contractor should direct questions regarding the status of an ECP or RFV to the Procuring Contracting Officer (PCO) and copy the Administrative Contracting Officer (ACO).

C.2.1.8 The submission of an ECP/RFV/SCN/NOR does not affect the required delivery date of the contract.

C.2.1.9 The contractor shall electronically transmit copies of all ECPs, NORs, RFVs, and VECPs to:

CCDC CBC Engineering Office

OFFICE: FCDD-CBE-M

EMAIL: usarmy.ria.ccdc-cbc.mbx.cmaction@mail.mil

FAX: 309-782-4537

C.3 START OF WORK MEETING

C.3.1 The contractor shall hold a start of work meeting at its facility, unless some other location is designated in the contract, within 30 calendar days after contract award. The Start of Work Meeting is to assure a clear and mutual understanding of the contract terms, conditions, line items, technical requirements and sequence of events needed for successful execution of the subject contract effort. The contractor shall participate with the Government to arrange a schedule and agenda for the meeting.

C.3.2 The contractor shall at a minimum invite Government contracting personnel (PCO/Contract Specialist). At the discretion of the PCO, other Government technical personnel may be invited to the meeting: Contracting Officer's Representative (COR) identified in Section G or in an appointment letter; Quality Assurance personnel; DCMA; etc. All Government invitees shall be given at least 14 days advance notice of the time, date, and location of the start of work meeting. The preferred method of notification is by email. The contractor shall provide the Government with minutes of the Start of Work Meeting within 14 calendar days after the meeting is held.

C.4 USE OF CLASS I AND CLASS II OZONE DEPLETING SUBSTANCES

C.4.1 Definitions.

C.4.1.1 Class I and Class II Ozone-Depleting Substances (CIODS) refers to the class of substances identified in Section 602(a) of the

Clean Air Act, (42 U.S.C. 7671a(a)), complete list provided at: https://www.govinfo.gov/content/pkg/USCODE-2013-title42/html/USCODE-2013-title42-chap85-subchapVI-sec7671a.htm

C.4.1.2 Directly requires the use of CIODS means that the Government's specification or technical data package, at any tier, explicitly requires the use of any Class I Ozone-Depleting Substance (CIODS) in performance of the contract.

C.4.1.3 Indirectly requires the use of CIODS means that the Government's specification or technical data package, while not explicitly requiring the use of any CIODS, does require a feature that the contractor can meet or produce only by the use of CIODS.

C.4.2 Per Section 326 of Public Law 102-484, the Army cannot award any contract that directly or indirectly requires the use of CIODS without the approval of the Senior Acquisition Official, per current Army Policy the approval authority is the Army Acquisition

Executive. Thus, no CIODS shall be used in meeting the requirements of this contract. If the use of CIODS is required in the performance of this contract, please notify the Contracting Officer immediately in writing.

C.4.3 No Class II Ozone Depleting Substances shall be required in the performance of this contract without government approval. If the use of Class II ODS is required in the performance of this contract, please notify the Contracting Officer immediately in writing.

C.5 CONTROLLED UNCLASSIFIED INFORMATION (CUI) GUIDELINES

C.5.1 The contractor shall comply with the requirements outlined in Attachment 0001, Controlled Unclassified Information

12 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(CUI) Guidelines, which provides detailed information on the handling, protection, and dissemination of CUI.

C.6 REQUIREMENT FOR AN OPSEC STANDING OPERATION PROCEDURE/PLAN

C.6.1 The contractor is subject to provisions of the TACOM LCMC OPSEC Standing Operating Procedures (SOP/Plan), or other U.S. Government

OPSEC plan, per AR 530-1, Operations Security. This SOP/Plan specifies the government's critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.

C.6.2 The contractor will receive a copy of the SOP/Plan at time of award. Local form STA Form 7114 (or similar) will be used to document and record security OPSEC reviews which are conducted by G2, TACOM LCMC or individual organizations supporting OPSEC Officers.

C.6.3 The contractor shall identify an individual who will be an OPSEC Coordinator. The contractor will ensure that this individual is

OPSEC Level I.

C.7 OPSEC TRAINING REQUIREMENT

C.7.1 Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of reporting for duty. All contractor employees must complete annual OPSEC awareness training. OPSEC awareness training is available at:

https://securityawareness.usalearning.gov/opsec/index.htm. Within 10 days of completing the training, the Contractor shall provide certificates/proof of completion to the Contract Specialist and the Procuring Contracting Officer (PCO).

C.8 THREAT AWARENESS REPORTING PROGRAM

C.8.1 All contractor employees must receive annual TARP training by a Counter Intelligence (CI) agent, or other authorized designated training method, per Army Regulation 381-12, para. 2-4b, Threat Awareness and Reporting Program (TARP). The in-person training is the preferred method and is available by contacting the local CI Office to arrange for the conduct of training.

C.8.2 The Contractor shall contact the CI Office within 30 calendar days of contract award to schedule TARP training. Once training is complete Contractor shall provide certificates/proof of completion of training to the Contract Specialist and Procurement Contracting

Officer (PCO) within 10 calendar days of completion.

C.8.3 The Contractor shall contact the CI Office to schedule training for any new employee whose performance commences after award, and who did not attend the initial TARP training session. Upon completion of the TARP training, certification/proof of completion shall be provided as required in paragraph C.8.2. In special circumstances (on deployments or in remote locations) when in-person training is not available, TARP computer based training (CBT), which has been approved by Deputy Chief of Staff (DCS), G-2, is the only authorized online training method permitted. This alternate CBT training is only authorized in special circumstances with written approval obtained from the PCO. Upon receipt of the necessary written approval, contractor employees possessing an Army Knowledge Online (AKO) account and password or a Common Access Card can register and complete the online TARP training course by utilizing the Army Learning Management

System (ALMS) at: www.lms.army.mil.

*** END OF NARRATIVE C0001 ***

13 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION D - PACKAGING AND MARKING

D.1 Packaging Requirements (Special Packaging Instructions)

D.1.1 Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1, and the Special Packaging Instruction, see below.

D.1.1.1 LEVEL OF PRESERVATION: Military

D.1.1.2 LEVEL OF PACKING: B

D.1.1.3 QUANTITY PER UNIT PACKAGE: 001

D.1.1.4 SPECIAL PACKAGING INSTRUCTION NUMBER: P5-4-3371-2

D.1.1.5 DATE OF REVISION: 28 FEB 2024

D.1.2 Note: You must have the Adobe Acrobat reader installed on your PC to view the SPI. See Adobe's website

(http://get.adobe.com/reader/) for information on obtaining the latest version of the reader. If you're experiencing problems opening the Special Packaging Instructions in Adobe .PDF images using Internet Explorer, try the following: Go to "Tools," then "Internet

Options." Click on the "Advanced" tab. Scroll down to the "Security" section. Uncheck "Do not save encrypted pages to disk." Click

"Apply." Click "OK.")

D.1.3 Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

D.1.4 Marking:

D.1.4.1 In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and as applicable, unitized loads shall be marked in accordance with MIL-STD-129). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel.

D.1.4.2 When an item is assigned a Unique Item Identifier (UII) as indicated by the inclusion of contract clause DFARS 252.211-7003, refer to the DoD Guide to Uniquely Identifying Items (available at: https://www.acq.osd.mil/dpap/pdi/uid/guides.html) for development of the UII and MIL-STD-129 for UII package marking requirements. Contractors must verify the RFID and UII clauses cited above are included in this solicitation/contract.

D.1.5 Heat Treatment and Marking of Wood Packaging Materials (WPM):

D.1.5.1 In accordance with DOD 4140.65-M and the requirements of the International Standards for Phytosanitary Measures 15 (ISPM), "Regulation of Wood Packaging Material in International Trade," current edition, (hereinafter "ISPM 15"), the following commercial heat treatment and marking process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging

Material (WPM). Foreign manufacturers shall comply with ISPM 15, and have the WPM heat treatment and marking verified in accordance with their National Plant Protection Organization's compliance program.

D.1.5.2 Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM using a conventional steam or dry kiln heat chamber (treatment code for the mark: HT) shall be heat treated to a minimum core temperature of 56 degrees Celsius for a minimum of 30 minutes, and certified by an agency accredited by the ALSC in accordance with Wood Packaging

Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). WPM heat treated wood using dielectric heating (treatment code for the mark: DH) shall follow the requirements in ISPM 15, and shall be certified by an agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:

http://www.alsc.org). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure the materials used in manufacture can be traced to the original source of heat treatment, and that the original source of the heat treatment obtained the necessary certifications.

D.1.5.3 Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard. The

ALS approved quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens. Pallet markings shall be applied to the side of the stringer or end of the block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp. Foreign manufacturers shall comply with ISPM -15 and shall have the marking of WPM verified in accordance with

14 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

their National Plant Protection Organization's compliance program.

D.1.6 Hazardous Materials (As applicable):

D.1.6.1 Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.

(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

D.1.6.2 Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:

- International Air Transport Association (IATA) Dangerous Goods Regulations

- International Maritime Dangerous Goods Code (IMDG)

- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO P4030.19(I)/DLAM 4145.3(I) (for military air shipments).

D.1.6.3 If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the

United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers. A Product Material Safety Data Sheet (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

D.1.7 This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the

SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

D.1.8 SUPPLEMENTAL INSTRUCTIONS: Place a red X and the words "SHORT BOX" on the front of any box that has a short quantity, then place that box/boxes with the markings showing on the top front of the pallet load.

*** END OF NARRATIVE D0001 ***

15 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION E - INSPECTION AND ACCEPTANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

For FAR clauses: https://www.acquisition.gov/

For DFARS clauses: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

E-1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

E-2 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984

E-3 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014

(a) The contractor shall comply with the higher-level quality standard(s) listed below.

Quality Management System ISO 9001:2015 Requirements, not including paragraph 8.3.

General Requirements for the competence of testing and calibration laboratories ISO/IEC17025, 3rd Edition, 11/1/2017 for agent testing requires compliance but not registration or accreditation (Limited to Government/Contractor Labs that do Agent Testing).

(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require--

(i) Control of such things as design, work operations, in-process control, testing and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of clause)

E.1 INSPECTION AND ACCEPTANCE POINTS: ORIGIN

E.1.1 The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.

Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.

INSPECTION POINT: __________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

ACCEPTANCE POINT: __________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

E.2 INSPECTION AND ACCEPTANCE (FIRST ARTICLE APPROVAL)

E.2.1 First Article Test Report acceptance shall take place at DESTINATION.

E.3 FIRST ARTICLE TESTING - CONTRACTOR

E.3.1 In accordance with FAR clause 52.209-3 (Section I), first article testing - contractor shall be performed in accordance with all the requirements of the specifications and drawings for each subcomponent. A Certificate of Conformance shall be required for all materials. Engineering exceptions are applicable to this procurement and shall be viewed by the contractor to ensure compliance with the requirements of this procurement.

E.3.2 The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of

16 70

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement.

E.3.3 The first article shall be inspected and tested by the contractor for all requirements of the drawing(s), the QAPs, and specification(s) referenced thereon, except for:

E.3.3.1 Inspections and tests contained in material specifications provided that the required inspection and tests have been performed within the last year and the results are submitted with the Certificates of Conformance are submitted with the First Article Test

Report.

E.3.3.2 Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.

E.3.3.3 Corrosion resistance tests over 10 days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 days prior to processing the first article, and results of the tests are submitted with the

First Article Test Report.

E.3.3.4 Life cycle tests over 10 days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the

First Article Test Report.

E.3.3.5 Onetime qualification tests, which are defined as a one-time on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the contractor's facility and certifications are submitted with the First Article Test Report.

E.3.4 Those inspections which are of a destructive nature shall be performed upon additional sample parts selected from the same lot(s) or batch(es) from which the first article was selected.

E.3.5 A First Article Test Report shall be compiled by the contractor documenting the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The First Article Test Report shall include actual inspection and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and QAP requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. Evidence of the QAR's verification will be provided. One copy of the First Article Test Report shall be submitted electronically through the QAR to the Contract Specialist, PCO and FCDD-CBE-SQI QA at usarmy.ria.devcom-cbc.mbx.labcerts@army.mil, in accordance with CDRL A004.

E.3.6 Notwithstanding the provisions for waiver of first article, an additional first article sample or portion thereof, may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of 90 days, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply. When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the

Contracting Officer so that a determination can be made concerning the need for the additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results. Costs of the additional first article testing resulting from any of the causes listed herein that were instituted by the contractor and not due to changes directed by the

Government shall be borne by the Contractor.

E.4 DESTRUCTIVE TESTING

E.4.1 All costs for destructive testing by the Contractor and items destroyed by the Government are considered as being included in the contract unit price.

E.4.2 Where destructive testing of items or components thereof is required by contract or specification, the number of items or components required to be destructively tested, whether destructively tested or not, shall be in addition to the quantity to be delivered to the Government as set forth in the Contract Schedule.

E.4.3 All pieces of the complete First Article shall be considered as destructively tested items unless specifically exempted by other provisions of this contract.

E.4.4 The Contractor shall not reuse any components from items used in a destructive test during First Article, lot acceptance or in process testing, unless specifically authorized by the Contracting Officer.

E.4.5 The Government reserves the right to take title to all or any items or components described above. The Government may take title to all or any items or components upon notice to the Contractor. The items or components of items to which the Government takes title shall be shipped in accordance with the Contracting Officer's instructions. Those items and components to which the Government does not obtain title shall be rendered inoperable and disposed of as scrap by the Contractor.

17 70

Name of Offeror or…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .