This document is a Request for Quotation (RFQ) from the Army Contracting Command - Detroit Arsenal (ACC-DTA) for the procurement of 108 Support Barrel units (NSN 1005-01-530-8726) with a 100% option for an additional 108 units. The solicitation is a Total Small Business Set-Aside (SBSA) for a one-time buy with a Firm-Fixed-Price (FFP) contract. The procurement includes a Distribution Code D Technical Data Package (TDP) with limited access to U.S. Government agencies and contractors, requiring potential bidders to have a current DD 2345 Militarily Critical Technical Data Agreement certification.
Key requirements include submitting a signed offer by the specified date, with all offers valid for 120 calendar days. Contractors must comply with export control regulations, destroy technical data after use, and follow specific guidelines for configuration management and technical data package access. The contract involves a Support Barrel for the Machine Gun, Caliber .50 M2 Series, with delivery scheduled at 20 units per month after contract award. Offerors must demonstrate capability to meet technical requirements, provide first article testing, and comply with various operational security and training obligations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912CH-25-Q-0022 (002).pdf | ||
| First-Article-Waiver-Worksheet.pdf | ||
| Attachment 0002 Attach A CUI 2023 (002).pdf | ||
| W912CH-25-Q-0022 (001).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION This RFQ is is not a small business set-aside Page Of
(This is NOT an Order)
1. Request No. 2. Date Issued 3. Requisition/Purchase Request No. 4. Cert For Nat Def. Under BDSA Rating
See Schedule Reg. 2 and/or DMS Reg. 1 5A. Issued By 6. Deliver by (Date)
See Schedule
7. Delivery
FOB Other Destination
5B. For Information Call: (Name and telephone no.) (No collect calls)
8. To: Name and Address, Including Zip Code 9. Destination (Consignee and address, including Zip Code)
See Schedule
10. Please Furnish Quotations to the Issuing Office in Block 5A On or Before Close of Business (Date)
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please indicate on this form and return it to the address in Block 5B. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services.
Supplies are of domestic origin unless otherwise indicated by quoter. Any interpretations and/or certifications attached to this Request for Quotation must be completed by the quoter.
11. Schedule (Include applicable Federal, State, and local taxes)
Item Number (a)
Supplies/Services (b)
Quantity (c)
Unit (d)
Unit Price (e)
Amount (f)
(See Schedule)
12. Discount For Prompt Payment a. 10 Calendar Days b. 20 Calendar Days c. 30 Calendar Days d. Calendar Days % % % Number Percentage
NOTE: Additional provisions and representations are are not attached.
13. Name and Address of Quoter (Street, City, County, State and 14. Signature of Person Authorized to Sign 15. Date of Quotation Zip Code) Quotation
16. Signer
a. Name (Type or Print) b. Telephone
Area Code
c. Title (Type or Print) Number
AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 18 (Rev. 8-95) PREVIOUS EDITIONS NOT USABLE 18-118 Prescribed by GSA-FAR (43 CFR) 53.215-1(a)
X
W912CH-25-Q-0022 DOA5
W912CHACC-DTA
6501 E. 11 MILE RD.
DETROIT ARSENAL, MI 48397-5000
ASHLEY YOUNG (571)588-8996
CCTA-APS-C
EMAIL: ASHLEY.A.YOUNG2.CIV@ARMY.MIL
X
1 59
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SUPPLEMENTAL INFORMATION
Buyer Name: ASHLEY YOUNG
Buyer Office Symbol/Telephone Number: CCTA-APS-C/(571)588-8996
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
Weapon System: Machine Gun, Caliber .50 M2 Series w/Tri
*** End of Narrative A0000 ***
A.1 DESCRIPTION OF THE ACTION
A.1.1 This solicitation is intended to result in the award of a ONE-TIME BUY with 100% OPTION, FIRM-FIXED PRICE (FFP) Contract for 108
EACH (EA) Support, Barrel, National Stock Number (NSN) 1005-01-530-8726.
A.1.2 This solicitation is a TOTAL SMALL BUSINESS SET-ASIDE (SBSA) in accordance with (IAW) Federal Acquisition Regulation (FAR) 19.502-
2.
A.1.3 There is a Technical Data Package (TDP) associated with this solicitation. The TDP is a distribution code D which limits access to the U.S. Government Agencies and its contractors. Please refer to Section C.3 and Section A.2 for additional information.
A.1.4 To be considered for award, please return one signed copy of your offer by the date/time indicated in the associated SAM.gov posting as well as the cover page of this solicitation. All offers submitted in response to this solicitation shall be valid for a minimum of 120 calendar days following the offer due date.
A.2 DISTRIBUTION AND DESTRUCTION OF EXPORT CONTROL TECHNICAL DATA PACKAGE
A.2.1 This solicitation and resulting contract contains technical data whose export is restricted by the Arms Export Control Act
(Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.
A.2.2 To be eligible to gain access to this export controlled TDP (via SAM.gov) an offeror must have a current DD 2345, Militarily
Critical Technical Data Agreement certification on file with the Defense Logistics Information Service (DLIS). To obtain certification, contractors must submit a DD Form 2345 to the United States (U.S.)/Canada Joint Certification Office (JCO), along with a copy of supporting documentation. DD Form 2345 and instructions can be found on the Joint Certification Program website at:
http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP.aspx Processing time is estimated at six (6) to ten (10) weeks after receipt. Upon receipt of certification, an offeror may request the TDP in accordance with the solicitation's
Section C Technical Data Package instructions.
A.2.3 Upon completion of the purposes for which Government Technical Data has been provided, the offeror, and all subcontractors, vendors, and sub-vendors of the offeror, are required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed.
A.2.4 Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the
TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.
A.3 ARMY CONTRACTING COMMAND DETROIT ARSENAL (DTA) OMBUDSPERSON
Information regarding the Ombudsperson for this contract is located at the following website: https://www.tacom.army.mil/ombudsperson
. (Best viewed using Google Chrome or Microsoft Edge)
A.4 ELECTRONIC CONTRACTING
A.4.1 All Army Contracting Command Detroit Arsenal solicitations will be publicized on the System for Award Management website
(https://www.sam.gov ). Any additional attachments, will be separate attachments or links embedded in the solicitation.
A.4.2 Interested offerors shall submit a proposal via email to the Contract Specialist (ashley.a.young2.civ@army.mil) and cc the corresponding Contracting Officer (elizabeth.l.levinewelhouse.civ@army.mil) with the subject header: Proposal Submission W912CH-25-Q-
0056 (Heckler & Koch Defense, Inc.). Once a proposal is received, the Contract Specialist/Contracting Officer will reply with the respective Offeror stating receipt of proposal submission.
A.4.3 Please pay close attention to the Issued By block location on the cover page of the solicitation for closing date and time. The closing date and time is based on the local time of the listed location of the Issued By office. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, to be received by the Government office
2 59
W912CH-25-Q-0022
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
designated in the solicitation by the time specified.
A.4.3.1 Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.
A.4.4 Solicitations may remain posted on www.SAM.gov after the solicitation closing date.
A.4.5 Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of the Governments intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If an Offeror objects to such release in the base contract or contract modifications, the
Offeror must notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for the objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.
A.4.6 Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the
Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.
A.5 ACKNOWLEDGEMENT OF AMENDMENTS
Acknowledge all the amendments received from the Government by identifying the amendment number and its issue date below:
Amendment Number: Date:
A.6 ALL OR NONE
A.6.1 Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.
A.6.1.1 ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.
A.6.1.2 OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION WILL BE DEEMED NONRESPONSIVE.
*** END OF NARRATIVE A0001 ***
3 59
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SUPPLIES OR SERVICES AND PRICES/COSTS
0001 SUPPORT, BARREL
NSN: 1005-01-530-8726
Mfr CAGE: 19200
Mfr Part Number: 13027972
0001AA PRODUCTION QUANTITY 108 EA $ $ ___________________ ______________ __________________
COMMODITY NAME: SUPPORT, BARREL
CLIN CONTRACT TYPE:
Firm Fixed Price
PRON: EH4C0632EH PRON AMD: 01
AMS CD: SM2B1100000
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE SECTION D PACKAGING AND MARKING
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 W52H094096024V W562RP J 2
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 20 0180
002 20 0210
003 20 0240
004 20 0270
005 28 0300
FOB POINT: Destination
SHIP TO:
(W562RP) SR W0LX ARMY GENERAL SUPPLY
DLA DISTRIBUTION ANNISTON
7 FRANKFORD AVE 362
ANNISTON,AL,36201-4199
4 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0001AB FIRST ARTICLE TEST 1 LO $ __________________ __________________
SERVICE REQUESTED: BARREL, SUPPORT
FIRST ARTICLE TEST, PURSUANT TO THE REQUIREMENTS
LISTED IN:
- SECTION E.6 NOTICE REGARDING FIRST ARTICLE;
- SECTION E.8 INSPECTION AND ACCEPTANCE (FIRST
ARTICLE APPROVAL);
- SECTION E.9: NOTICE REGARDING FIRST ARTICLE TEST
SAMPLE, and
- FAR CLAUSE 52.209-3: SUPPLEMENTAL REQUIREMENTS TO
FIRST ARTICLE APPROVAL - CONTRACTOR TESTING (SEE
SECTION I FOR ADDITIONAL INFORMATION)
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 1 0120
5 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0002 SUPPORT, BARREL
NSN: 1005-01-530-8726
Mfr CAGE: 19200
Mfr Part Number: 13027972
0002AA UNEXERCISED OPTION QUANTITY 108 EA $ $ ___________________________ ______________ __________________
COMMODITY NAME: SUPPORT, BARREL
CLIN CONTRACT TYPE:
Firm Fixed Price
OPTION QUANTITY, PURSUANT TO FAR CLAUSE 52.217-7:
OPTION FOR INCREASED QUANTITY -- SEPARATELY PRICED
LINE ITEM
The quantity stated for option CLIN 0002AA DOES NOT
FORM A PART OF THE BASIC CONTRACTUAL QUANTITY. Part or all of it may, however, be added to the contract at the discretion of the Government, by exercise of the Option clause.
Failure to the offeror to insert a unit price applicable to the option quantity shall mean the offeror will supply all or any part of the option, if exercised by the Government, AT THE BASIC UNIT PRICE, and the offer will be evaluated for award accordingly.
(End of narrative B001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE SECTION D PACKAGING AND MARKING
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 20 0180
002 20 0210
003 20 0240
004 20 0270
005 28 0300
6 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
FOB POINT: Destination
SHIP TO:
(W562RP) SR W0LX ARMY GENERAL SUPPLY
DLA DISTRIBUTION ANNISTON
7 FRANKFORD AVE 362
ANNISTON,AL,36201-4199
7 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
1000 EXHIBIT - CONTRACT DATA REQUIREMENTS LIST (CDRL) ________________________________________________
A001 ENGINEERING CHANGE PROPOSAL (ECP) 1 LO $ ** NSP ** _________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
CLIN CONTRACT TYPE:
Firm Fixed Price
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A001
Engineering Change Proposal (ECP).
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A002 REQUEST FOR VARIANCE (RFV) 1 LO $ ** NSP ** __________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
CLIN CONTRACT TYPE:
Firm Fixed Price
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A002 Request
For Variance (RFV).
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
8 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
A003 NOTICE OF REVISION (NOR) 1 LO $ ** NSP ** ________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
CLIN CONTRACT TYPE:
Firm Fixed Price
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A003 Notice of
Revision (NOR).
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A004 ACCEPTANCE INSPECTION EQUIPMENT (AIE) REPORT 1 LO $ ** NSP ** ____________________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
CLIN CONTRACT TYPE:
Firm Fixed Price
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A004
Acceptance Inspection Equipment (AIE) Report.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A005 TEST PROCEDURE - HEAVY PHOSPHATE COATING 1 LO $ ** NSP ** ________________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
CLIN CONTRACT TYPE:
Firm Fixed Price
9 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A005 Test
Procedure - Heavy Phosphate Coating.
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A006 FIRST ARTICLE TEST REPORT (FATR) 1 LO $ ** NSP ** ________________________________ __________________
SERVICE REQUESTED: SERVICE DATA NOT PRICED
CLIN CONTRACT TYPE:
Firm Fixed Price
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A006 First
Article Test Report (FATR).
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
A007 OPSEC AWARENESS (LEVEL 1) TRAINING REPORT 1 LO $ ** NSP ** _________________________________________ __________________
SERVICE REQUESTED: CERTIFICATE OF COMPLIANCE
The contractor shall prepare and deliver data submissions IAW Exhibit A, Contract Data Requirements
List.
See Section J, Exhibit A: DD Form 1423 A007 OPSEC
Awareness (Level 1) Training Report - Certificate of
Compliance.
10 59
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
(End of narrative B001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
DLVR SCH PERF COMPL
REL CD QUANTITY DATE ________ ______________ __________
001 1 SEE DD FORM 1423
11 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C.1 HEAVY PHOSPHATE COATING REQUIREMENT
The following requirements regarding heavy phosphate coatings are applicable to this solicitation and any resultant contract in addition to those requirements set forth in specification MIL-DTL-16232.
C.1.1 Paragraph 3.1 of MIL-DTL-16232 refers to "Preproduction Inspection." The procedure shall be submitted in accordance with the
Contract Data Requirements List (CDRL) contained in the contract. The contract number must be cited on all phosphate coating procedures submitted for review and approval. Procedures shall include product name and manufacturer of all chemicals/materials to be used. All processes, equipment, controls along with testing and test frequencies used for phosphating including application of supplemental finishes shall be described in detail.
C.1.2 Paragraph 3.2.5-c of MIL-DTL-16232 refers to the "Chromic acid rinse, (Classes 1, 2 and 3)." The final rinse shall be checked by a standard free and total acid titration along with a pH reading "prior to starting production and at least every 8 hours thereafter."
C.1.3 Paragraph 4.7.3 of MIL-DTL-16232 refers to "Weight per unit area of phosphate coatings." The frequency for testing coating weight is "per lot, at least every 8 hours."
C.1.4 Paragraph 4.7.5 of MIL-DTL-16232 refers to "Accelerated corrosion resistance." Accelerated corrosion resistance shall be determined in accordance with 4.7.5.1. The frequency for testing accelerated corrosion resistance per ASTM B117 is "per lot, at least every 8 hours."
C.1.5 The "product name" along with the manufacturer of the supplemental dry film lubricant or CARC paint (primer/topcoat) shall be stated in the procedure and shall be traceable to the applicable Qualified Products List (QPL) or Qualified Products Database (QPD) at
Assist Online. QPD products may be obtained at the quick search site, type the specification number (i.e., 3150) in the second block and click the "Submit" button. Then click on the specification (i.e., MIL-PRF-3150). In the next screen, click on the word "Qualification".
To obtain MIL Specs, MIL Standards, QPL and QPD products see <"https://assist.dla.mil/online/start / ">.
To obtain MIL Specs, MIL Standards, QPD products see <"https://assist.dla.mil/online/start/ ">.
C.1.6 A thickness range for the supplemental dry film lubricant or CARC paint (primer/topcoat) shall be stated in the procedure along with a frequency for testing. A daily frequency is required.
C.1.7 Heat cured dry film lubricant shall be air dried for 1.0 hour (until dry to touch) after dipping/spraying or flash dried at 155-
175 degrees F for 10-30 minutes and then heat cured at a temperature of 375-425 degrees F for 55-65 minutes per paragraph 4.4.2.2 of MIL-
PRF-46010.
C.1.8 Air cure dry film lubricant shall be air dried at room temperature for 24 hours minimum.
C.1.9 Adhesion testing shall be stated in the procedure for a supplemental coating of dry film lubricant per ASTM D2510 or CARC paint per ASTM D3359, method B along with the frequency for testing. A daily frequency is required.
C.1.10 Salt spray testing of parts with phosphate and supplemental dry film lubricant per ASTM B117 for 100 hours shall be stated in the procedure along with the frequency for testing. The frequency for testing is "per lot or weekly." Parts shall show no more than 3 rust spots per 3" x 6" area with none larger than 1.0mm in diameter. Salt spray testing of parts with phosphate and primer per ASTM B117 for
336 hours shall be included in the procedure for supplemental coatings of CARC paint along with a frequency for testing. The frequency for salt spray testing is "per lot or monthly." Parts shall show no visible rust exceeding rust grade no. 9 per ASTM D610, no more than
5 blisters per 4" x 6" area with none larger than 3/64 inch in diameter. Under film attack at the scribe shall not exceed 1/8 inch.
C.1.11 Topcoat color shall be visual/equipment checked against the specified chip no. of SAE AMS-STD-595 per paint batch. The procedure shall include the specified color chip number.
C.1.12 Cure of the paint shall be checked daily by solvent wipe per paragraph 4.2.3.2 of MIL-DTL-53072. The manufacturer of the MEK solvent shall be stated in the procedure.
C.2 CONFIGURATION MANAGEMENT DOCUMENTATION
The Contractor may submit Engineering Change Proposals (ECPs), Requests for Variance (RFVs), and Notices of Revision (NORs) for the requirements in the Government-provided Technical Data Package (TDP).
C.2.1 The Configuration Change Management section of SAE EIA-649-1(current revision) Configuration Management Requirement for Defense
Contracts, Paragraph 3.3, shall be used for configuration control of material with the following exclusions: paragraph 3.3(3); the second sentence of paragraph 3.3.1.8.1(1).
C.2.2 Furnished item(s) shall conform to the approved configuration requirements/revision, unless a Request for Variance (RFV) is processed and approved as provided by Paragraph E. below. The term "Request for Variance" includes Requests for Deviations and Waivers.
12 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
C.2.3 Value Engineering Change Proposals (VECPs) for cost saving improvements to the TDP should not be processed per SAE EIA-649-1 and should be referred to Section I FAR Clause 52.248-1 - Value Engineering.
C.2.4 All ECPs submitted will be deemed routine. If an ECP is considered as an emergency or urgent; that justification for the rationale shall be included in the ECP submittal with all applicable supporting documentation.
C.2.5 For ECPs, RFVs, or NORs, the Contractor must submit the documentation listed in sub-paragraphs e (i) through e (iii). Failure to submit a complete legible package may result in return of the ECP/RFV/SCN/NOR without processing.
C.2.5.1 for ECPs, the Contractor shall prepare and deliver the ECP in accordance with (IAW) CDRL A001.
C.2.5.2 for RFVs, the Contractor shall prepare and deliver the RFV IAW CDRL A002.
C.2.5.3 for NORs, the Contractor shall prepare and deliver the NOR IAW CDRL A003.
C.2.6 The Governments acceptance of the data deliverable required by CDRL/DD Form 1423 in e(i)-(iii) above signifies only that the data satisfies the requirements of the DID and is considered acceptable for Government processing. Acceptance of the data deliverable does not signify "technical approval" of the change proposed by the deliverable and should not be interpreted as authorizing the Contractor to proceed with the work proposed by the change. Disposition of the change (approval/disapproval) will follow acceptance of the CDRL at the Governments sole discretion. Incorporation of an approved RFV or ECP will require execution of a contract modification.
C.2.7 The Contractor should direct questions regarding the status of an ECP or RFV to the Procuring Contracting Officer (PCO) and copy the Administrative Contracting Officer (ACO).
C.2.8 The submission of an ECP/RFV/SCN/NOR does not affect the required delivery date of the contract.
C.3 TECHNICAL DATA PACKAGE INFORMATION
C.3.1 The following Xd item applies to this solicitation:
[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.
[ X ] 2. The TDP for this solicitation resides within the System for Award Management (SAM) (https://SAM.gov ) associated with this solicitation number:
W912CH-25-Q-0022
To access the data through SAM:
a. Log on to the SAM web site: https://SAM.gov .
b. Search for the solicitation number.
c. Click on the attachment you would like to view.
d. If the attachment is restricted, request access to the document.
C.3.2 TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et.seq.)
or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..
C.3.3 Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.
C.3.4 To obtain these TDPs, contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with Defense
Logistics Information Service (DLIS). To obtain certification, go to DD FORM 2345 Instructions and DD 2345.
C.3.5 Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor.
Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.
C.3.5.1 If technical data is otherwise restricted, select Request Explicit Access. This will generate an email to the Contract
Specialist and Contracting Officer at Army Contract Command - Warren (DTA) with all the information needed to grant contractor access to restricted documents. SAM will automatically generate an email stating when the requesting contractor has permission to view or download
TDP items.
13 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
C.3.5.2 If multiple individuals in the contractors organization need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP.
Those same individuals MUST be registered in SAM. Any individuals no longer with the company should be deleted. Questions related to registration in SAM should be directed to https://www.sam.gov/ The SAM helpdesk phone number is (866) 606-8220. Vendors are responsible for placing correct information in SAM.
C.3.5.3 It is strongly suggested that contractors submit the explicit access request and provide the buyer with the completed Use and
Non-Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.
C.4 DRAWING LIMITATIONS
C.4.1 The drawings supplied with this contract are not shop or process drawings. The drawings are engineering design drawings, are adequate to permit manufacture, and:
C.4.1.1 depict the completed (item(s), and
C.4.1.2 serve as the basis for inspection of the completed item(s).
C.4.2 These drawings DO NOT cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if all the dimensions and tolerances specified in the engineering design drawing for each individual part are met, a cumulative unacceptable fit for the contract item could result.
C.4.3 The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the manufacturing process.
C.4.4 The Contractor agrees that he has obtained all specifications and drawings necessary to manufacture the items being solicited in accordance with the TDP including all incorporated specifications and drawings. The contractor is responsible for having all drawings and specifications. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.
C.4.5 Failure to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, will result in the Contractor being responsible for correcting this condition at no additional cost to the
Government and no delivery schedule extension
C.5 REQUIREMENT FOR AN OPSEC STANDING OPERATION PROCEDURE/PLAN
C.5.1 The contractor is subject to provisions of the TACOM LCMC OPSEC Standing Operating Procedures (SOP/Plan), or other U.S. Government
OPSEC plan, per AR 530-1, Operations Security. This SOP/Plan specifies the governments critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it.
C.5.2 The contractor will receive a copy of the SOP/Plan at time of award. Local form STA Form 7114 (or similar) will be used to document and record security OPSEC reviews which are conducted by G2, TACOM LCMC or individual organizations supporting OPSEC Officers.
C.5.3 The contractor shall identify an individual who will be an OPSEC Coordinator. The contractor will ensure that this individual is certified OPSEC Level I.
C.6 OPSEC TRAINING REQUIREMENT
C.6.1 Per AR 530-1, Operations Security, new contractor employees must complete Level I OPSEC training within 30 calendar days of reporting for duty. All contractor employees must complete annual OPSEC awareness training. OPSEC awareness training is available at:
https://securityawareness.usalearning.gov/opsec/index.htm . Within 10 calendar days of completing the training, the Contractor shall provide certificates/proof of completion to the Contracting Officers Representative (COR), if assigned to the contract, or the Procuring
Contracting Officer (PCO).
C.7 THREAT AWARENESS REPORTING PROGRAM
C.7.1 All contractor employees with security clearances working on any Army contract must receive annual TARP training by a Counter
Intelligence (CI) agent, or other authorized designated training method, per Army Regulation 381-12, para. 2-4b, Threat Awareness and
Reporting Program (TARP). The in-person training is the preferred method and is available by contacting the local CI Office to arrange for the conduct of training.
C.7.2 The Contractor shall contact the CI Office within (30) calendar days of contract award to schedule TARP training. Once training is complete Contractor shall provide certificates/proof of completion of training to the Contracting Officer's Representative (COR), if
14 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
assigned to the contract, or to the Procurement Contracting Officer (PCO) within (10) calendar days of completion.
C.7.3 The Contractor shall contact the CI Office to schedule training for any new employee whose performance commences after award, and who did not attend the initial TARP training session. Upon completion of the TARP training, certification/proof of completion shall be provided as required in paragraph (b).In special circumstances (on deployments or in remote locations) when in-person training is not available, TARP computer based training (CBT), which has been approved by Deputy Chief of Staff (DCS), G-2, is the only authorized online training method permitted. This alternate CBT training is only authorized in special circumstances with written approval obtained from the PCO. Upon receipt of the necessary written approval, contractor employees possessing an Army Knowledge Online (AKO) account and password or a Common Access Card can register and complete the online TARP training course by utilizing the Army Learning Management
System (ALMS) at: www.lms.army.mil .
*** END OF NARRATIVE C0001 ***
PACKAGING AND MARKING
D.1 PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS)
D.1.1 Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1, and the Special Packaging Instruction, see below.
D.1.1.1 LEVEL OF PRESERVATION: Military
D.1.1.2 LEVEL OF PACKING: B
D.1.1.3 QUANTITY PER UNIT PACKAGE: 001
D.1.1.4 SPECIAL PACKAGING INSTRUCTION NUMBER: 13027972
D.1.1.4.1 REVISION B
D.1.1.4.2 DATE OF REVISION 10 MAY 2024
D.1.1.4.3 THE REQUIRED SPECIAL PACKAGING INSTRUCTION (SPI) IS AVAILABLE ON THE WEB AT THE FOLLOWING URL: N/A
(Note: You must have the Adobe Acrobat reader installed on your PC to view the SPI. See Adobes website (http://get.adobe.com/reader/ ) for information on obtaining the latest version of the reader. If you're experiencing problems opening the Special Packaging
Instructions in Adobe .PDF images using Internet Explorer, try the following: Go to "Tools," then "Internet Options." Click on the
"Advanced" tab. Scroll down to the "Security" section. Uncheck "Do not save encrypted pages to disk." Click "Apply." Click "OK.")
D.1.2 Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.
D.1.3 Marking:
D.1.3.1 In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and as applicable, unitized loads shall be marked in accordance with MIL-STD-129). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel.
D.1.3.2 When an item is assigned a Unique Item Identifier (UII) as indicated by the inclusion of contract clause DFARS 252.211-7003, refer to the DoD Guide to Uniquely Identifying Items (available at: https://www.acq.osd.mil/dpap/pdi/uid/guides.html ) for development of the UII and MIL-STD-129 for UII package marking requirements. Contractors must verify the RFID and UII clauses cited above are included in this solicitation/contract.
D.1.4 Heat Treatment and Marking of Wood Packaging Materials (WPM):
D.1.4.1 In accordance with DOD 4140.65-M and the requirements of the International Standards for Phytosanitary Measures 15 (ISPM), 15 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Regulation of Wood Packaging Material in International Trade, current edition, (hereinafter ISPM 15), the following commercial heat treatment and marking process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging
Material (WPM). Foreign manufacturers shall comply with ISPM 15, and have the WPM heat treatment and marking verified in accordance with their National Plant Protection Organizations compliance program.
D.1.4.2 Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM using a conventional steam or dry kiln heat chamber (treatment code for the mark: HT) shall be heat treated to a minimum core temperature of 56 degrees Celsius for a minimum of 30 minutes, and certified by an agency accredited by the ALSC in accordance with Wood Packaging
Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org ). WPM heat treated wood using dielectric heating (treatment code for the mark: DH) shall follow the requirements in ISPM 15, and shall be certified by an agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:
http://www.alsc.org ). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure the materials used in manufacture can be traced to the original source of heat treatment, and that the original source of the heat treatment obtained the necessary certifications.
D.1.4.3 Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard. The
ALS approved quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens. Pallet markings shall be applied to the side of the stringer or end of the block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp. Foreign manufacturers shall comply with ISPM -15 and shall have the marking of WPM verified in accordance with their National Plant Protection Organizations compliance program.
D.1.5 Hazardous Materials (As applicable):
D.1.5.1 Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.
(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)
D.1.5.2 Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:
- International Air Transport Association (IATA) Dangerous Goods Regulations
- International Maritime Dangerous Goods Code (IMDG)
- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49
- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO P4030.19(I)/DLAM 4145.3(I) (for military air shipments).
D.1.5.3 If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the
United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers. A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.
D.1.6 This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the
SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.
D.1.7 SUPPLEMENTAL INSTRUCTIONS: N/A
*** END OF NARRATIVE D0001 ***
INSPECTION AND ACCEPTANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
16 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
For FAR clauses: https://www.acquisition.gov/
For DFARS clauses: https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996
2 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984
3 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
ISO 9001:2015 (21 Oct 2015) or equivalent
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
E.1 INSPECTION AND ACCEPTANCE POINTS: ORIGIN
E.1.1 The Government's inspection of the supplies offered under this contract/purchase order shall take place at ORIGIN. Offeror must specify below the exact name, address, and CAGE of the facility, or his subcontractor's facility, where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.
INSPECTION POINT: ORIGIN
a. NAME
b. CAGE
c. ADDRESS, CITY, STATE, ZIP
ACCEPTANCE POINT: ORIGIN
a. NAME
b. CAGE
c. ADDRESS, CITY, STATE, ZIP
E.1.2 FIRST ARTICLE TEST REPORT (FATR) ACCEPTANCE: DESTINATION
The Government's acceptance of the First Article Test Report (if required) offered under this order shall take place at DESTINATION.
E.2 REWORK AND REPAIR OF NONCONFORMING MATERIAL
E.2.1 Rework and Repair are defined as follows:
E.2.1.1 Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
E.2.1.2 Repair - The reprocessing of nonconforming material in accordance with Government-approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
E.2.2 Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the
Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
E.2.3 Repair procedures shall be documented by the Contractor and submitted on a Request for Variance, DD Form 1694, to the Contracting
Officer for review and written approval prior to implementation.
E.2.4 Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
17 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
E.2.5 The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data
Package requirements and shall in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
E.3 ACCEPTANCE INSPECTION EQUIPMENT (AIE)
E.3.1 The contractor shall use a calibration system with traceability to a national or international standard for the AIE used on this contract.
E.3.2 The contractor shall provide all AIE (except for any AIE listed as available in Section H or Appendix I) necessary to assure conformance of material to the contract requirements.
E.3.3 AIE shall be available for use on the First Article (FA) submission, if FA is required, or prior to use for acceptance of production material on this contract.
E.3.4 Contractor furnished AIE shall be made (i) to the AIE designs specified in Section C, or (ii) to any other design provided the contractor's proposed AIE design is approved by the Government. Contractor's proposed AIE design for inspection of characteristics listed as "Critical, Special or Major" shall be submitted to the Government for review and approval as directed on the Contract Data
Requirements List, DD Form 1423. Government approval of AIE design shall not be considered to modify the contract requirements.
E.3.5 When the contractor submits its proposed AIE on commercial off the shelf equipment, the contractor shall include the manufacturer's name and model number, and sufficient information to show capability of the proposed AIE to perform the inspection required. When submitting proposed AIE design documentation on commercial computer controlled test and measuring equipment include information on (1) test program listing (2) flowcharts showing accept and reject limits and computer generated test stimuli (3) calibration program listing (4) sample of the printout of an actual test and calibration (5) test plan to verify accuracy of inspection and correctness of accept or reject decision (6) identification of the equipment by model name and number.
E.3.6 Resubmission of the contractor's proposed AIE design for Government approval on a follow on Government contract is not required, provided the inspection characteristic parameters specified in the technical data package and the previously Government approved AIE designs have not changed. In this situation, the contractor shall provide written correspondence in the place of the AIE designs that indicates the prior Government approval and states that no changes have occurred.
E.3.7 The Government reserves the right to disapprove, at any time during the performance of this contract, any AIE that is not accomplishing its intended use in verifying an inspection or test characteristic.
E.3.8 If the contractor changes the design after the initial approval, the modified design must be submitted for approval prior to use.
E.4 FIRST ARTICLE TEST (CONTRACTOR TESTING)
E.4.1 The first article shall be examined and tested in accordance with contract requirements, the item specification(s), Quality
Assurance Provisions (QAPs) and all drawings listed in the Technical Data Package.
E.4.2 The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production. All components, subassemblies, and assemblies in the first article sample shall have been produced by the Contractor (including subcontractors) using the technical data package applicable to this procurement.
E.4.3 The first article shall be inspected and tested by the contractor for all requirements of the drawing(s), the QAPs, and specification(s) referenced thereon, except for:
E.4.3.1 Inspections and tests contained in material specifications provided that the required inspection and tests have been performed previously and certificates of conformance are submitted with the First Article Test Report.
E.4.3.2 Inspections and tests for Military Standard (MS) components and parts provided that inspection and tests have been performed previously and certifications for the components and parts are submitted with the First Article Test Report.
E.4.3.3 Corrosion resistance tests over 10 calendar days in length provided that a test specimen or sample representing the same process has successfully passed the same test within 30 calendar days prior to processing the first article, and results of the tests are submitted with the First Article Test Report.
E.4.3.4 Life cycle tests over 10 calendar days in length provided that the same or similar items manufactured using the same processes have successfully passed the same test within 1 year prior to processing the first article and results of the tests are submitted with the First Article Test Report.
18 59
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
E.4.3.5 Onetime qualification tests, which are defined as a one-time on the drawing(s), provided that the same or similar item manufactured using the same processes has successfully passed the tests, and results of the test are on file at the contractor's facility and certifications are submitted with the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .