This notice provides details for a renovation project at Fort Buchanan Softball Field in Puerto Rico. The Mission and Installation Contracting Command at Fort Buchanan will issue an Invitation for Bid around August 5, 2021 for renovations to the Cabana Softball Field. The project magnitude is estimated between $250,000 to $500,000. The solicitation will be set aside 100% for HUBZone small businesses under NAICS code 236220 for commercial and institutional building construction with a size standard of $39.5 million. Interested parties should monitor the Contract Opportunities website at sam.gov for the IFB and any amendments. Bids must include any amendments issued. The contact for any request for information is Ray Santana and Maria Otero.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESTORATION OF CABANA
SOFTBALL FIELD
FORT BUCHANAN, PUERTO RICO
INDEX OF DRAWINGS
SHEET NO. TITLE
T101 TITLE SHEET, LOCATION SITE MAPS & DRAWING INDEX
D101 DEMOLITION PLAN
A101 NEW WORKS PLAN
P101 NEW DRAINAGE WORKS
P102 DRAINAGE DETAILS
E101 ELECTRICAL DEMOLITION PLAN
LIST OF ABBREVIATIONS NOTE: SOME ABBREVIATIONS LISTED ARE NOT CONTAINED IN THESE DRAWINGS
A A.B.I . ACOUSTICAL BATT INSULATION E EA EACH K p
NC AIR CONDITIONING EF EACH FACE
KV KILOVOLT PL PLATE
KVA KILOVOLT-AMPERE AFF ABOVE FINISH FLOOR EL, ELEV PRELIM PRELIMINARY ELEVATION
KW KILOWATT PSI POUNDS PER SQUARE INCH AL, ALUM ALUMINUM ELEC ELECTRIC, ELECTRICAL
ALT ALTERNATE EMB
PVC POINT OF VERTICAL CURVE,
EMBBEDED
L POLYVINYL CHLORIDE AMP,A AMPERE L LENGTH, LENGTH OF CURVE
EMT ELECTRICAL METALLIC TUBING
POUNDS PSF POUNDS PER SQUARE FOOT AP ACCESS PANEL LBS
APPROXIMATE
ETC ETCETERA LED LIGHTING EMITING DIODE APPROX
ARCH ARCHITECTURAL
EW EACH WAY
LT LIGHT
ARR ARRESTOR EXIST, EX, E EXISTING R R RADIUS, RISER, RUBBER SHEATH
AWG AMERICAN WIRE GAGE
M RR RETURN REGISTER
F MAX MAXIMUM RG RETURN GRILLE
F FAREN HEIT
MBH MEGA BRITISH HOUR RE.REF REFERENCE, REFER TO B B, BOT BOTTOM FDB FAREN HEIT DRY BULB
BD BOARD FD FLEXIBLE DUCT MECH MECHANICAL REINF REINFORCEMENT
BUILDING FFE FINISHED FLOOR ELEVATION MD MANUAL DAMPER REV REVISION
BLDG, B
FIN FINISH MIN MINIMUM RM ROOM
BW BOTH WAY
FL FLOOR, FLASHING MISC MISCELLANEOUS RLA RATED LOAD AMPERE
FT FOOT, FEET MTD MOUNTED RTU ROOF TOP UNIT
C7 CIRCUIT NUMBER FWB FAREN HEIT WET BULB
CC,CTC CENTER TO CENTER N N,NW NORTH, NEW
CFM CUBIC FEET PER MINUTE G NFPA NATIONAL FIRE PROTECTION
SCH, SCHED SCHEDULE
CKT CIRCUIT GA, G GAGE ASSOCIATION
SD SPLITTER DAMPER
CENTERLINE GALV GALVANIZED NIC NOT IN CONTRACT SECT SECTION
CLG CEILING
GB GYPSUM BOARD NO NUMBER SHT SHEET GI GALVANIZED IRON NTS NOT TO SCALE CMU CONCRETE MASONRY UNITS GPM SPEC SPECIFICATION
CND,C CONDUIT
GALLONS PER MINUTE
GR GRADE SQ SQUARE
COL COLUMN GRD GROUND 0
ss STAINLESS STEEL
CONG CONCRETE GW GROUND WATER OD OUTSIDE DIAMETER STD STANDARD
COND CONDUCTOR OPNG OPENING STL STEEL
CONN CONNECTION OUTSIDE BLADE DAMPER STO STORAGE H H, HGT, HT HEIGHT OBD
CONST CONSTRUCTION
HEX HEXAGONAL STRUCT STRUCTURE.STRUCTURAL
HP HORSEPOWER SW SWITCH
D D DEPTH, DEEP, DEGREE OF CURVATURE ID INSIDE DIAMETER, INSIDE DIMENSION
DET, DTL DETAIL IN INCH
D, DIAM. DIAMETER IN C.W. INCH COLD WATER
DIM DIMENSION
DWG DRAWING
J D PNL DISTRIBUTION PANEL JB JUNCTION BOX
DN DOWN
T T TOP. TANGENT
3/P THREE POLE
TS TUBULAR STEEL
TON TONELATE
TYP TYPICAL
u UG UNDERGROUND
V V VENT, VOLT, VALVE
VCP VITRIFIED CLAY PIPE
VERT VERTICAL
w w WIDTH, WASTE, WATER, WATT, WEST
WI WITH
WP WATERPROOF, WEATHERPROOF
WT WEIGHT
X XFMR TRANSFORMER
4 ANGULAR
AT
& AND
goo ANGLE DEGREE
# NUMBER, POUND
0 DIAMETER
3W THREE WAYS
LOCATION MAP
ATLANTIC OCEAN
PUNTA BORINQUEN
(FOR MER RAMEY U.S. A IR FORCE BASE)
PUERTO RICO
O
SALINAS
TRAINGAREA
C A R I B B E A N S E A
D
FORT BUCHANAN SITE MAP
PROJECT SITE LOCATION
_j � ::c (C
11/' UII
ROOSEVEL TROADS
U.S. NAVAL STA TION
�z
Picnic Area a'�---------�
ACTIVITY
ENVIRONMENTAL DIVISION (DPW)
0&M DIVISION (DPW)
MASTER PLANNING
(DPW)
ENERGY MANAGER (DPW)
PHYSICAL SECURITY (DES)
MILITARY POLICE (DES)
FIRE DEPARTMENT (DES)
SAFETY OFFICE (DES)
FORCE PROTECTION (DPTMS)
NETWORK ENTERPRISE CENTER
(NEC)
TENANT
139� SITE
PRINT NAME
RT 039
70 , l
X X
INITIALS DATE
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
PROJECT MANAGER:
R.REYES
CIVIL I ARCH./ DESIGN DEVELOPMENT:
R.REYES
MECHANICAL DESIGN:
J. ROMAN
ELECTRICAL DESIGN:
A. MOJICA/ C. IRIZARRY
DRAFTER:
G. VILLARONGA
REVISED BY:
R.REYES
REVISIONS
REV. NO. DATE APPD.BY
RESTORATION
OF CABANA
SOFTBALL FIELD
CONSTITUTION AVE.
FT. BUCHANAN, PUERTO RICO
SHEET TITLE NAME
DRAWING#:
PROJECT#:
X
IJO:
DATE: MAY/2021
SCALE: N.T.S.
T101
E102 ELECTRICAL INSTALLATION WORKS
4 ..--�
DEMOLITION WORKS
SCALE: 1 /16" = 1 '-0"
r ilro··••········· kj"
, r '1 . . l·
•• •• I . . . . . . . " . .
l·· .. ·.·.
I
1 •• l
••••• I••
.·.•1· l l . . l
OUTFIELD AREA··
l l l l l
I l l
DEMOLITION WORKS:
© REMOVE AND DISPOSE 4" OF EXISTING SOIL
AND UNDERGROUND MATERIALS WITHIN IT.
REMOVE AND DISPOSE 3" OF EXISTING SOIL ON
GRASS AREA AND UNDERGROUND MATERIALS
WITHIN IT.
REMOVE AND STORE LIGHTING POLES .
LIGHTING FIXTURES TO BE DISPOSED
INCLUDING JUNCTION BOXES, CONDUITS,
CABLES AND ASSOCIATED ELEMENTS.
REMOVE AND STORE CHAIN LINK WIRE FENCE
AND CORRUGATED PLASTIC FENCE TOPPER.
® REMOVE CABLES AND CONDUITS.
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
PROJECT MANAGER:
R.REYES
CIVIL I ARCH./ DESIGN DEVELOPMENT:
R.REYES
MECHANICAL DESIGN:
J. ROMAN
ELECTRICAL DESIGN:
A. MOJICA/ C. IRIZARRY
DRAFTER:
G. VILLARONGA
REVISED BY:
R.REYES
REVISIONS
REV. NO. DATE APPD.BY
RESTORATION
OF CABANA
SOFTBALL FIELD
CONSTITUTION AVE.
FT. BUCHANAN, PUERTO RICO
DEMOLITION WORKS
DRAWING#:
PROJECT#:
X
IJO:
DATE: MAY/2021
SCALE: 1/16" = 1'- O"
D101
® REMOVE AND DISPOSE EXISTING FOUL POLE.6
®6 raymon.m.reyesnegron Line
NEW FIELD LAYOUT
SCALE: 1 /16" = 1'-0"
OUTFIELD AREA
- I
INFIELD AREA
5'-0''
-q"
I
I
I
I
NEW20'
FOUL POLE�
J
- J
HOME AREA DETAIL
SCALE: 1/4" = 1'-0"
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
PROJECT MANAGER:
R.REYES
CIVIL I ARCH./ DESIGN DEVELOPMENT:
R.REYES
MECHANICAL DESIGN:
J. ROMAN
ELECTRICAL DESIGN:
A. MOJICA/ C. IRIZARRY
DRAFTER:
G. VILLARONGA
REVISED BY:
R.REYES
REVISIONS
REV. NO. DATE APPD.BY
RESTORATION
OF CABANA
SOFTBALL FIELD
CONSTITUTION AVE.
FT. BUCHANAN, PUERTO RICO
NEW FIELD LAYOUT
WORKS PLAN
DRAWING#:
PROJECT#:
X
IJO:
DATE: MAY/2021
SCALE: VARIES
A101
NEW20'
FOUL
POLE�
NEW 10"0
PVC PIP�---..
CONSTRUCTION
BOUNDARY----
I
I
I
I
I
I
I
I
I
I
I
A/ / "" t;
" 0 .0.
NEW 10"0 (' PVC Pl P�
I �,...._
NEW 8"0
PVC PIP c--------..
'-rca�I
�-n2-90 I ii
I ci1 I 4" 0 C. 0 .:------�, �)-�12;:-MMi3iP:,-
J
�=----=� ,-------l"l2-90 �-12-90 -
NEW
MULTIPURPOSE
COLLECTOR
LINE 12" HIGH
I
(TYPICAL) ----1-----</..
I
�-12-C
--12-90
\ --12-90
--12-90
�---fl2-90
_ _,.12-90
_--,12-90
"0 C.O.
12-C
--12-90
\ --'.1'2-90
--12-90
NEW
MUL Tl PURPOSE
COLLECTOR
LINE 12" HIGH
TYPICAL)
NEW 8"0
PVC PIPE
--12-90
\ --12-90
--12-DP
--12-90
\ 12-90
\ --12-90
�-n2-DP \
12-90
\ 12-90
12-9
CONSTRUCTION
,,-BOUNDARY
I
I
I 1f-EC r+---1 2tE C
�12-¢
,--------±--1 2-E d
--12-EC I
--1 -EC
12-EC
12-EC
I
I I
I
I
I
I
_ _,12-90 12-EC
I
L
I
I
I
I
I
I
NEW8"0
PVC PIPH---V
CONSTRUl""lelr\
BOUNDARY-"
NEW DRAINAGE WORKS
SCALE: 1 /16" = 1'-0"
12-90
2-DP
12-90
12-90
\ 12-90
--12-DP
12-90
12-90
12-90 0
12-90
--12-90
12-9 �
�"0C.O.
MAIN DRAINAGE 1
12-90 �-<12-90
12-EC
12-90
I
I
--<12-90 2-EC I
�---112-90 '�"0C.O. I
MAIN DRAINA E 2
I
�-<12-90 NEW
MULTIPURPOSE
COLLECTOR
v-7��===1::::__/ -�----L
LINE 12" HIGH
r , T>-1-- (TYPICAL)
�--112-90
I
<-=.-C�
�---fl2-90
I I
9 I I I
A-+--!112-90
12-90 I
I
I
I
I
I
LEGEND:
12-DP
12-MPO
12-90
12-C
12-EC
4" 0 c.o.
----10>-----<0
12" MULTI-FLOW DRAINAGE PIPE
125' STANDARD ROLL LENGTH
MUL Tl-PURPOSE 12" OUTLET
(12-RT - 3" RIGI TAP REQUIRED)
MUL Tl-PURPOSE 12" 90 DEGREE OUTLET
(12-RT - 3" RIGI TAP REQUIRED)
12" COUPLER
12" END CAP
4" DIAMETER CLEAN OUT
FENCE LINE
GENERAL NOTES:
1. CONTRACTO SHALL SUBMIT FOR APPROVAL
THE FINAL LAYOUT PATTERN FOR THE NEW
WATER COLLECTION SYSTEM, SURFACE GRADING
WITH ELEVATIONS, DIMENSIONS AND RELATED
INFORMATION.
2. CONTRACTOR IS RESPONSIBLE TO VERYFY
NEW UNDERGROUND DRAINAGE LAYOUT
PATTERN IN ACCORDANCE TO FIELD DIMENSIONS.
3. CLEAN OUTS LOCATED INSIDE FENCED
PLAYING FIELD SHALL BE INSTALLED BELOW
GRADE LEVEL.
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
PROJECT MANAGER:
R.REYES
CIVIL I ARCH./ DESIGN DEVELOPMENT:
R.REYES
MECHANICAL DESIGN:
J. ROMAN
ELECTRICAL DESIGN:
A. MOJICA/ C. IRIZARRY
DRAFTER:
G. VILLARONGA
REVISED BY:
R.REYES
REVISIONS
REV. NO. DATE APPD.BY
RESTORATION
OF CABANA
SOFTBALL FIELD
CONSTITUTION AVE.
FT. BUCHANAN, PUERTO RICO
NEW DRAINAGE WORKS
DRAWING#:
PROJECT#:
X
IJO:
DATE: MAY/2021
SCALE: 1/16" = 1'- O"
P101
GEOTEXTILE
MEMBRANE
24" WIDE
o.c.
MIX FILL---� �-GEOTEXTILE
MEMBRANE
VARI�
OUTLET
e+==-�=-�=�-=�-=�-=�-=
- _3" 0 DIA PVC
SCH 40 PIPE
i0��� ����/.»> /21//>1/,}-----',,_»>:»»7&
12" HIGH COLLECTOR 12-RT - 3"
LINE "RIGI-TAP"
FLOW � 8"0 DIA PVC
SCH 40 PIPE
24" WIDE
o.c.
TRENCH
CLEAN COARSE SAND
NEW DRAINAGE DETAILS O' 5'
SCALE: 1-1 /2" = 1 '-0"
01.2-" Standard Profiles.80 -, •triaonoo-8 ► I
I I
----12.38----
1.20
11111111111111
I I I I �I �I I �I �I I I I
Isometric Views Standard Profiles
01.20---..
-T
I I
12.86 I
□-.2.50 _L
12-DP - 12" DRAINAGE PIPE - 125' STANDARD ROLL LENGHT 12-EC - 12" END CAP
SCALE: N.T.S.
Standard Profiles
1--
I I
I 14.29
I
I I l __ .....,____.
1.2 _ _/
7- 1 ----1
I I
12.86 I I
I I
J __
�- 3.50
I I
3.50 -, -, Isometric Views
SCALE: N.T.S.
Standard Profiles
3.50 .J
I I 3.5O--r-
Isometric Views
Isometric Views
12-MPO - MULTI-PURPOSE 12" OUTLET 12-90 - MULTI-PURPOSE 12" 90 DEGREE OUTLET
SCALE: N.T.S. SCALE: N.T.S.
Standard Profiles
-r a,
1.2 _ _/ I
I a, 1- I
I 7.74
I I
J_
I
I 12.86
I I
I I
_i a, a, a, a, a, a, a, I I 1 -7.74- 1
12-C - 12" COUPLER
SCALE: N.T.S.
12-RT - 3" "RIGI-TAP"
SCALE: N.T.S.
Isometric Views
IJ
OUTLET+ "RIGI-TAP"
INSTALLATION TO PVC PIPE
SCALE: N.T.S.
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
PROJECT MANAGER:
R.REYES
CIVIL I ARCH./ DESIGN DEVELOPMENT:
R.REYES
MECHANICAL DESIGN:
J. ROMAN
ELECTRICAL DESIGN:
A. MOJICA/ C. IRIZARRY
DRAFTER:
G. VILLARONGA
REVISED BY:
R.REYES
REVISIONS
REV. NO. DATE APPD.BY
RESTORATION
OF CABANA
SOFTBALL FIELD
CONSTITUTION AVE.
FT. BUCHANAN, PUERTO RICO
DRAINAGE DETAILS &
NEW DUGOUT WORKS
DRAWING#:
PROJECT#:
X
IJO:
DATE: MAY/2021
SCALE: VARIES
P102
5 7
L106
.\DPW logo.bmp
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
REVISIONS
REV. NO. DATE APPD. BY
SCALE: 1/32" = 1'-0"
E101
DRAWING #:
PROJECT #:
X
IJO:
DATE: MAY/2021
ELECTRICAL DEMOLITION
PROJECT NAME
FT. BUCHANAN, PUERTO RICO
CONSTITUTION AVE.
RESTORATION
OF CABAÑA
SOFTBALL FIELD
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
PROJECT MANAGER:
CIVIL / ARCH. / DESIGN DEVELOPMENT:
MECHANICAL DESIGN:
ELECTRICAL DESIGN:
REVISED BY:
DRAFTER:
ELECTRICAL DEMOLITION WORKS:
REMOVE AND DISPOSE CONCRETE LIGHTING POLE, H4 TYPE,
45 FT, INCLUDING FOUR METAL HALIDE (MH) LIGHTING
FIXTURES , MOUNTING KIT, BALLAST TRANSFORMERS, 100
AMP LOAD CENTERS, TRIPLEX WIRE AWG #2 POWER
CIRCUITS ATTACHED, AWG #10 LIGHTING CIRCUITS AND
CONDUITS AND ALL ITEMS MOUNTED ON LIGHTING POLES.
TEMPORARY REMOVE, RETAIN AND ENROLL THE AERIAL
MAIN FEEDER FROM MAIN BREAKER IN ORDER TO BEGIN
WITH REQUIRED WORKS.
REMOVE AND DISPOSE CONTACTOR BOX CONTROLLING
THE LIGHTING SYSTEM, INCLUDING THE ENCLOSURE AND
THE 200 AMPS CONTACTOR. REMOVE AND DISPOSE AS
WELL, THE MAIN BREAKER PANEL 200 AMPS, 120/208 VOLTS
AND AN ATTACHED 120 / 208 V, 60 AMPS LOAD CENTER
INCLUDING TWO DUPLEX RECEPTACLES AND TWO 20 AMPS
ONE POLE BREAKERS INSIDE OF IT.
REMOVE AND DISPOSE TWO (2) AERIAL CIRCUITS THAT
CONSIST OF CABLES THHN, 600 VOLTS AWG#10, CIRCUIT
GOES FROM MAIN PANELBOARD TO DUGOUT. REMOVE AS
WELL 120V DUGOUT RECEPTACLE.
REMOVE AND DISPOSE AERIAL CIRCUITS THAT CONSIST OF
THHN, 600 VOLTS AWG#2, TRIPLEX CABLES, AND WHICH
GOES FROM CONTRACTOR BOX AT POLE #2 ALL THE WAY
TO THE SUPPORT POLE.
REMOVE AND DISPOSE CABLES FROM EXISTING TELEPHONE
LINE FROM P#6 TO THE NEAREST DUGOUT. DO NOT REMOVE
TELEPHONE FIXTURE. COORDINATION WITH THE NETWORK
ENTERPRISE CENTER (NEC) IS REQUIRED BEFORE
DISCONNECTION.
1 8-18-21 Alex A. Mojica Medina
R. Reyes
R. Reyes
J. Roman
G. Villaronga
A. Mojica/ C. Irizarry
A. Mojica
AutoCAD SHX Text
L106 H4 POLE
AutoCAD SHX Text
L105 - H4 POLE
AutoCAD SHX Text
L104 H4 POLE ( LIGHTING POWER ENTRANCE)
AutoCAD SHX Text
L109 H4 POLE
AutoCAD SHX Text
P6 CABLE SUPPORT POLE. NOT A LIGHTING POLE
AutoCAD SHX Text
L108 H6 POLE
AutoCAD SHX Text
L109 H6 POLE
AutoCAD SHX Text
(NO WORK REQUIRED)
AutoCAD SHX Text
(NO WORK REQUIRED)
AutoCAD SHX Text
EXISTING TELEPHONE
AutoCAD SHX Text P3
AutoCAD SHX Text P1
AutoCAD SHX Text P2
AutoCAD SHX Text P4
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
ELECTRICAL DEMOLITION PLAN
AutoCAD SHX Text
P5 CABLE SUPPORT POLE. NOT A LIGHTING POLE
AutoCAD SHX Text
MAIN FEEDER FROM 3 AERIAL TRANSFORMERS 120/208V SYST
AutoCAD SHX Text
LEGEND:
AutoCAD SHX Text
TRIPLEX AERIAL CABLE AWG #2 FOR LIGHTING POWER. ITEM #5 IN NOTES
AutoCAD SHX Text
DUGOUTS AERIAL POWER CABLES AWG #10 ITEM #4 IN NOTES
AutoCAD SHX Text
AERIAL MAIN FEEDER (DO NOT REMOVE)
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
EXISITNG PANELBOARD
.\DPW logo.bmp
DPW ENGINEERING DIVISION
RECOMMENDED APPROVAL
MARIA LOPEZ
DIRECTOR OF PUBLIC WORKS
PROJECT TEAM
REVISIONS
REV. NO. DATE APPD. BY
SCALE: 1/32" = 1'-0"
E102
DRAWING #:
PROJECT #:
X
IJO:
DATE: MAY/2021
PROJECT NAME
FT. BUCHANAN, PUERTO RICO
CONSTITUTION
LUIS E. TORRES
ENGINEERING DIVISION CHIEF
APPROVED BY:
PROJECT MANAGER:
CIVIL / ARCH. / DESIGN DEVELOPMENT:
MECHANICAL DESIGN:
ELECTRICAL DESIGN:
REVISED BY:
DRAFTER:
ELECTRICAL INSTALLATION WORKS:
1 FURNISH AND INSTALL NEW CONCRETE POLES H-6 TYPE,
65FT HIGH, TO INSTALL NEW LIGHTING FIXTURE.
FURNISH AND INSTALL NEW METAL HALIDE (MH)
1000WATTS'S FIXTURES, 120/208 VOLTS, 5 LIGHTS IN POLE,
INCLUDING THEIR MOUNTING KIT, HOUSING, BULB AND
BALLAST/TRANSFORMERS AND CROSS ARMS BRACKETS. A
NEW 3 PHASE 120/208, 100 AMPS LOAD CENTER, NEMA 3R,
ONE TO BE USED FOR POWER DISTRIBUTING OF LIGHTING.
FURNISH AND INSTALL SURGE PROTECTOR 120/208 VOLTS
FOR EACH PANEL BOARD. TWO (2) NEW 20 AMPS, 2 POLES,
240 VOLTS BREAKERS FOR POLE LIGHTING CIRCUITS AND
ONE (1) NEW 20 AMPS, 2 POLES, 240 VOLTS BREAKERS FOR
SPARE. FURNISH AND INSTALL NEW RIGID GALVANIZED STEEL
(RGS) 3/4" CONDUIT FOR CIRCUITS ABOVE GROUND AND FOR
LIGHT FIXTURES POWER CONNECTION FROM EACH POLE PANEL
BOARD TO LIGHTS TRANSFORMERS. FURNISH AND
INSTALL NEW AWG# 10 COOPER CABLE STRANDED,
600V, THHN/THWN FOR ABOVEGROUND
INSTALLATION LIGHT FIXTURES POWER FROM
PANEL TO LIGHTS TRANSFORMERS.
FURNISH AND INSTALL 2-1/2” PVC, SHC 40, CONDUITS FOR
NEW UNDERGROUND CIRCUIT SYSTEM. TRENCH SHALL BE
36” DEEP AS PER PREPA SECONDARY URD-8 UNDERGROUND
DISTRIBUTION PATTERN WITH NEW UNDERGROUND
CIRCUITS FEEDERS AWG #2, 600 VOLTS, RHW/RHH FOR
120/208VOLTS LIGHTHING SYSTEM. POWER FROM
CONTACTOR BOX (ONE CIRCUIT GOING TO RIGHTFIELD AND
OTHER TO LEFT FIELD). DO NOT SPLICE THIS FEEDERS.
FURNISH AND INSTALL A ¾” PVC CONDUIT, SHC 40, TO BE
INSTALLED UNDERGROUND AS SPARE FOR BOTH EXCAVATIONS.
SHALL ATTACH ALL NEW PEDESTALS AND FROM EACH PEDESTAL
TO THEIR RESPECTIVE POLE JUNCTION BOXES.
FURNISH AND INSTALL A ¾” PVC CONDUIT, SHC 40,
UNDERGROUND FOR COMMUNICATION. THIS CONDUITS
SHALL GO UNDERGROUND FROM POLE #6 TO THE CLOSEST
DUGOUT. INSTALL NEW PVC BOX 4”X4” AT DUGOUT WALL
AND ANOTHER AT POLE #6 APPROXIMATE 20FT HIGH.
CREATE A CONCRETE BASE WITH SLOPE AS PER PREPA
URD-4 FOR CONDUIT PROTECTION.
FURNISH AND INSTALL NEW LOAD CENTER 225 AMPS WITH A
NEW 200 AMPS MAIN CIRCUIT BREAKER, 120/208V, RAIN
TIGHT/ WEATHER PROOF NEMA 4X, 30 SLOTS. THIS NEW
LOAD CENTER WILL POWER THE LIGHTING CONTACTOR BOX.
FURNISH AND INSTALL TWO (2) NEW 20 AMPS SPARE
BREAKERS. PROVIDE NEW SINGLE POLE, 120 VOLTS, 20 AMPS
BREAKERS AT MAIN PANEL BOARD, ONE FOR EACH DUGOUT
POWER. FURNISH AND INSTALL NEW LIGHTING
CONTACTOR BOX NEMA 4X, WITH A 208V, 200
AMPS CONTACTOR AND CONNECT FOR MAIN
PANELBOARD. FURNISH AND INSTALL NEW RAIN
TIGHT/WEATHER PROOF NEMA 4X LIGHT CONTROL
BOX POSITION SWITCH- ON/OFF AND LOCATE IT AT
THE EXTERIOR OF CONTACTOR ENCLOSURE TO TURN
ON/OFF ALL SOFTBALL LIGHTS. PROVIDE A NEW RAIN
PROOF/WHEATEAR PROOF 20 AMPS, 120V, DUPLEX
RECEPTACLE NEXT TO THE CONTACTOR BOX AND POWER IT
FROM MAIN BREAKER.
PROVIDE AND INSTALL CIRCUIT AND A NEW RAIN
PROOF/WHEATEAR PROOF 20 AMPS, 120V, DUPLEX
RECEPTACLE INSIDE THE TOWER STATION. POWER
RECEPTACLE DIRECTLY FROM MAIN PANELBOARD.
RECONNECT MAIN FEEDER AFTER COMPLETION OF WORKS.
FURNISH AND INSTALL NEW UNDERGROUND CIRCUIT FOR
DUGOUT RECEPTACLES. INSTALL AS PER SOW.
RESTORATION
OF CABAÑA
SOFTBALL FIELD
1 8-18-21 Alex A. Mojica Medina
R. Reyes
R. Reyes
J. Roman
G. Villaronga
A. Mojica/ C. Irizarry
A. Mojica
ELECTRICAL INSTALLATION
AutoCAD SHX Text
L106 H6 POLE
AutoCAD SHX Text
L105 - H4 POLE
AutoCAD SHX Text
L104 H4 POLE (LIGHTING POWER ENTRANCE)
AutoCAD SHX Text
P6 CABLE SUPPORT POLE. NOT A LIGHTING POLE.
AutoCAD SHX Text
L108 H6 POLE
AutoCAD SHX Text
L109 H6 POLE
AutoCAD SHX Text
(NO WORK REQUIRED)
AutoCAD SHX Text
(NO WORK REQUIRED)
AutoCAD SHX Text P3
AutoCAD SHX Text P1
AutoCAD SHX Text P2
AutoCAD SHX Text P6
AutoCAD SHX Text P5
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
ELECTICAL INSTALLATION PLAN
AutoCAD SHX Text
URD-26
AutoCAD SHX Text
URD-26
AutoCAD SHX Text
JB
AutoCAD SHX Text
JB
AutoCAD SHX Text
JB
AutoCAD SHX Text
URD-26
AutoCAD SHX Text
JB
AutoCAD SHX Text
P5 CABLE SUPPORT POLE. NOT A LIGHTING POLE.
AutoCAD SHX Text
JB FOR COMMUNICATION
AutoCAD SHX Text
JB FOR COMMUNICATION
AutoCAD SHX Text
LEGEND:
AutoCAD SHX Text
POLES
AutoCAD SHX Text
NEW MAIN PANELBOARD 225 AMPS
AutoCAD SHX Text
UNDERGROUND CONDUITS AND FEEDERS
AutoCAD SHX Text
4"X"4 JUNCTION BOXES, RAIN TIGHT
AutoCAD SHX Text
L109 H6 POLE
AutoCAD SHX Text P4
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
EXISTING TOWER STATION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
| E101 - RESTORATION OF CABANA SOFTBALL FIELD REV-1.pdf |
| Sheets and Views |
| 8. X01 |
| E102 - RESTORATION OF CABANA SOFTBALL FIELD REV-1.pdf |
| Sheets and Views |
| 9. X01 |
File details come from the government source that posted it. Updated .