RFIs and Responses dtd 07 Nov 2024 W912BV24R0103.xlsx
XLSX spreadsheet 13 KB Posted
- Solicitation number
- W912BV24R0103
About this file
This document contains a set of Requests for Information (RFIs) and corresponding responses related to a federal contract opportunity for the Temporary Wall Replacement at Denison Powerhouse in Denison, TX (Solicitation Number: W912BV24R0103).
The key details are:
- The scope of work includes demolition and disposal of the existing temporary wall and related structures, and the design and construction of a new permanent wall system.
- The contract is a Firm-Fixed Price (FFP) to be awarded using the Lowest Price Technically Acceptable (LPTA) process.
- The contractor will be required to commence work within 10 days of Notice to Proceed (NTP) and complete the work within the proposed number of calendar days, not to exceed 730 days.
- The RFIs cover various technical and logistical aspects of the project, including commissioning requirements, design coordination meetings, on-site personnel, government-furnished materials, temporary facilities, and access to the project site. The responses provide clarifications and additional details on these topics.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFI | SPECIFICATION REFERENCE | QUESTION | ANSWERS |
| 1 | Specification 01 32 01.00 Project Schedule Hydro Power | Section 3.3.9.9 Commissioning Coding (MCOM) A Commissioning code (MCOM) shall be assign to every activity that part of the Commissioning Scope of Work whether it is a submittal, report, or construction. Each activity shall have only one Commissioning code. Manual inputting of Commissioning Codes into RMS is prohibited. As applicable and/or as a minimum, the Contractor shall provide in the schedule the following activities. Question: The primary scope of work includes wall replacement. Please advise is commissioning required? | All mechanical and electrical equipment shall be installed in accordance with the Contract Documents and manufacturer's instructions. Commissioning is not required per se, however any new mechanical equipment shall be installed and start-up operations shall be completed in accordance with manufacturer's written instructions. At a minimum, direction of fan rotation and CFMs shall be verified to comply with contract requirements and test results submitted for government acceptance. |
| 2 | Specification 01 33 16.00 Design Data ( After Award) | Section 1.6.2.1 Meetings. Please advise how many in-person design coordination meeting should be anticipated? | At a minimum the contractor should plan on at least (1) design meeting being conducted in-person. The initial design conference should be conducted at the project site. All other meetings should be conducted in conformance with the contract specifications. Virtual meeting options are acceptable for some of the required meetings. |
| 3 | Section 01 45 00 Quality Control | Section 1.2.1. Please advise if any on site full time staff members: SSHO, Quality Control and Superintendent maybe dual hatted, as long as they meet the individual qualification? | All on-site personnel shall meet the requirements outlined in the specifications. The SSHO, QC and Superintendent should all be independent. No dual-hatting is permitted. |
| 4 | Specification 01 33 16.00 Design Data ( After Award) | Section 1.4.2 Government Furnished Material. Government material that may be incorporated into, or attached to, an end item to be delivered under a contract or which may be consumed in the performance of a contract. It includes, but is not limited to, raw and processed material, parts, components, assemblies, and small tools and supplies. QUESTION. Please provide an itemized list of goverment furnished, Contractor Installed. | At this time, there is no specific GFM that is to be installed by the contractor. There are item(s) outlined in the contract documents that are to be salvaged for reinstallation by the contractor or turned over to the Government. |
| 5 | Specification 01 50 00 Temporay Construction Facilities and Controls | Section 3.4.1 and 3.4.2 Field Offices: QUESTION: Please advise if a separate QC and Superintindent on site project trailer are required as suggessted in these sections. Or one trailer is acceptable? | One job/office trailer is acceptable as long as separate dedicated space is provided for the QC. |
| 6 | 01 11 00 General Requirements Scope of Work | Section 3.4.1.1 Fire Protection in temporay Wall: The fire protection system in the area of the temporary wall is to protect the framing timbers only. Install a plug at the root valve for the branch run and demolish and dispose of the entire fire system within the temporary wall. QUESTION: Please provide more details of this requirements. | A record drawing of the fire protection system as currently installed in the temporary wall area is unavailable. Additional as-built drawings of the raw water and fire protection systems within the powerhouse are available. The work is to include removal of all fire protection piping, hangers, components, etc. downstream from the closest valve serving the temporary wall work area. If the valve is threaded, than it should be plugged, if it is flanged, then blind off. |
| 7 | To support the wall replacement project, contractor and subcontractors will need to move some materials and equipment through the powerhouse. Materials and equipment would be limited to scaffolding materials, temporary barrier wall materials (primarily plywood), materials to build the wainscotting tile wall, new door assembly, new exhaust units, and the new floor grates. Materials would be moved using manual push carts and panels carts. Equipment would include the abatement exhaust units and small tool carts. At this time, it is anticipated that forklifts or scissor/man lifts are not going to be required to perform the work, and if required, would NOT be moved through the Powerhouse. The contractor requires confirmation the acceptability of the intent to move the material and equipment that is anticipated through the Powerhouse. All abatement material will be removed through the exterior side of the existing temporary wall. | Moving new construction materials through the powerhouse as described using push carts and panel carts is acceptable. A pre-construction inspection should be preformed prior to commencing work to determine and inventory any existing damage to powerhouse floor. Any damage as a result of construction activities will be the responsibility of the contractor to correct. | |
| 8 | The contractor request clarification that the new wainscotting tiles wall is to be installed on the generator level of the new wall. This wainscotting wall will be approximately 10’-6” above the Powerhouse lower level bottom floor and start at the level of the new floor grating to be installed. The lover level of the new wall will not have any covering over the interior side of the steel frame (occupants would be looking at the steel structure and backside of the painted concrete panel if standing under the steel grate deck). | This assessment is correct. The wainscot only needs to be installed at the powerhouse finish floor level to 10’-6” above the floor, to align with the top of the existing tile wainscot. Tiles will be installed on the concrete panels between the steel structural supports. Visibility below the grating is not a concern. The tile wainscot is required for the concrete panel option and is optional in the hybrid concrete panel/metal panel option (depending on how tall the concrete base panels are.) The wainscot will not be required for the metal panel only option. | |
| 9 | Please confirm if the new door to be installed in the new wall at the lower level is to be considered an emergency exit. If an emergency exit, exit lighting will be provided. If required to be an emergency exit, is another door with proper stair assembly required to be installed at the generator floor level at 10’-6” above the Powerhouse bottom floor since the new floor grating will be providing a level surface to the new wall? | The new lower level door is not considered to be an emergency exit and will not require emergency exit lighting, nor is an additional exit stair from the lower level required. | |
| 10 | The contractor's technical approach will rely on access to the dirt road to the west of the Powerhouse for establishing a “pick site” for the crane. Please confirm the contractor will access to the North entry and the ability to utilize this road for material pick site for the crane operations. | Access to the west side of the powerhouse is available via the gravel road, approaching either from the north and through the security fence or from the south around the powerhouse. |