2024.02.06 Prado Dam Spillway Modifications - Pre Bid Conference SAMS Version.pdf
PDF 14 MB Posted
- Attached to
- Prado Dam Spillway Modification Project
- Solicitation number
- W912BV23R0032
About this file
This document provides details for a federal contract solicitation for the Prado Dam Spillway Modification Project. The solicitation will use best value tradeoff source selection and an integrated design and construction acquisition method. The project's NAICS code is 237990 for other heavy and civil engineering construction, with a size standard of $45,000,000. As the project's magnitude exceeds $500,000,000, DFARS 236.204 applies. The solicitation utilizes full and open competition. The Department of the Army Corps of Engineers Engineering District Tulsa is the contracting agency, with Ryan Kelly listed as the point of contact. Interested offerors should review the details provided in solicitation number W912BV23R0032.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Prado Site Visit 2.6.24.pptx | PPTX presentation | |
| Business Cards.pdf | ||
| Sign In Sheets.pdf | ||
| For Information Only - Example IDaC Graphing Tool.xlsx | XLSX spreadsheet | |
| IDaC preproposal conference 1.31.24.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
.59
For Official Use Only (FOUO) // Unclassified This document is FOR OFFICIAL USE ONLY (FOUO). It contains information that may be exempt from public release under the Freedom of Information Act (5 USC 552). It is to be controlled, stored, handled, transmitted, distributed, and disposed of in accordance with USACE policy relating to FOUO information and it is not to be released to the public or other personnel who do not have a valid “need to know” without prior written approval of an authorized USACE official.
For Official Use Only (FOUO) // Unclassified This document is FOR OFFICIAL USE ONLY (FOUO). It contains information that may be exempt from public release under the Freedom of Information Act (5 USC 552). It is to be controlled, stored, handled, transmitted, distributed, and disposed of in accordance with USACE policy relating to FOUO information and it is not to be released to the public or other personnel who do not have a valid “need to know” without prior written approval of an authorized USACE official.
06 February 2024
PRADO DAM
SPILLWAY MODIFICATIONS
PRE-BID CONFERENCE AND
SITE VISIT
AGENDA
Project Design Team Project Site Visit Logistics Project Background Project Objectives Design Challenges Design Overview Life Safety Risks During Construction Preconstruction Services and Early Work Items RFI’s and IDaC
DRIVING DIRECTIONS TO PRADO VISITOR’S CENTER
• While traveling East on I-91 from Orange County, exit at Exit 47 at Serfas Club / Auto Center Drive.
• At the light, turn left (North) onto Auto Center Drive.
• Then proceed straight through the next two traffic lights.
• After the crest of the bridge (beyond the West Corona Train station), turn left on Pomona- Rincon Drive (there is not an accurate street sign). Once you turn left, the business Duralum will be on your right.
• Follow this road straight past the guard shack to the Prado Office Trailer complex. Park in the visitor parking on the right, which is the parking lot outside of the fenced complex.
Address:
Prado Dam Visitor’s Center 2493 Pomona-Rincon Rd Corona, CA 92878
Do not put Prado Dam into your phone!!
PARKING FOR PRADO PRE-BID SITE VISIT STOP #1
POC: MAJ Sean Hutchison
USACE: 951-455-6523
N
SITE TOUR
Spillway
Outlet Works
SR-91
SR71
Dike
Main Embankment
Auxiliary DikeNN
PROJECT BACKGROUND
Project History
Original Prado Dam constructed from 1938 to 1941 Flooding in 1938 resulted in 115 deaths and $1.6B
(2022 dollars) Primary purpose is flood control Reservoir generally dry
Project History
1980’s studies concluded that the dam would only provide a 70-year level of flood protection and could not safely pass the PMF
Part of ongoing Santa Ana River Mainstem (SARM) Project to improve flood protection and infrastructure along 75 miles of the Santa Ana River – authorized in 1986
Spillway Raise Project to increase the spillway crest 20 feet originally authorization in 1986
Embankment was raised 28.4 feet and a new outlet works was constructed from 2004 to
Outlet Works
Main Embankment
SR-71 DikeSR-71
OW
Discharge Channel
Spillway
Ogee Crest Structure
SR-91
Auxiliary Dike Embankment
NN
EXISTING SPILLWAY
PROJECT OBJECTIVES
Elevated risks associated with the spillway chute were identified in 2019 and a DSMS was subsequently initiated in February of 2020 Missing critical spillway defensive measures
No foundation anchors No waterstops No continuous reinforcement across joints Undersized slab with single mat of reinforcement Erosion resistant foundation Joint offsets into flow
Individual Risk = probability of loading x probability of failure
Societal Risk = probability of loading x probability of failure x consequence
This is a consequence driven project with a significant downstream PAR
Prado TTX – Spillway Modifications Project Update
Prado Dam
SARM Spillway Raise
Dam Safety
Prado Spillway Modifications
DESIGN CHALLENGES
Challenging foundation conditions Mudstone and poorly cemented sandstone Vertical jointing Foundation defects consisting of faults and shears Low strength Expected settlement Swell pressures
DESIGN CHALLENGES
Significant seismic hazard OBE = 0.32g MCE = 1.14g
DESIGN OVERVIEW
Left Embankment Connection
Right Embankment Connection
Arced Labyrinth Control
Structure
New Spillway Flat Chute
50’x50’ Slabs
New Spillway Chute Walls –
40’ Tall
New Steep Chute Slab and Walls
RCC
Foundation
Access Roads and SART not shown
Crest El.
576.0
Crest El.
565.5 Crest El.
575.5
Crest El.
563.0
Crest El.
563.0
Crest El.
573.5
Crest El.
574.0
Invert El.
535.0
12’x15’ Gated Access Portals
Composite Embankment Connection
Composite Embankment Connection
Borrow Areas (primary)
Staging and Stockpile
Areas
Fill Areas
Batch Plant Exclusion
AreasBorrow Areas (if needed)
Site Access
N
Foundation Preparation Shaping and treatment Slaking bedrock Removal of swelling materials below chute slabs Mud mat, dental concrete, slush grout
Fine grained materials and shears in chute
Shears and faults beneath the control structure
Dewatering Contractor design Dewatering specialist GDR and GBR High on left drops off to the right Alluvium groundwater sensitive to reservoir pool but always subject to nuisance groundwater at depth
Wells and well points in alluvium is required
Regional Groundwater
Flows
Monoliths separated by control joints in slab and contraction joints in
RCC
Slabs discretized by construction joints
Wall heights ranging from 28 feet to 41 feet tall
Change in elevation at downstream nose walls
Labyrinth reinforcement drawings included in solicitation package
Remaining features reinforcement drawings still under development
Pounds of reinforcement per cubic yard was included in Amendment 4
Nose wall reinforcement is very congested
Slotted 8” C900 PVC Pipe Solid 8” C900 PVC Pipe Slotted 18” C900 PVC Pipe Solid 18” C900 PVC Pipe Slotted 12” C900 PVC Pipe Solid 12” C900 PVC Pipe
Left embankment toe drain right embankment toe drain
Groundwater collection pipe
Left chute collection pipe
Right chute collection pipe
DESIGN
OVERVIEW
RCC embankment connection monoliths (right and left side) Reinforced grout enriched vibrated RCC for exterior faces Embankment placement in conjunction with RCC placement
RCC Corner monoliths Reinforced concrete walls buttressed with RCC Anchored at interface
Embankment connections Zoned earthfill Zone I is Zone II and vice versa Zone II interface with RCC Filters and drains are continuous Toe drains for each side Built concurrent with RCC
– RCC to lead embankment placement by no greater than 5 feet
Structural connection and joint types Flat chute slab control joint Longitudinal and transverse Centered over underdrains Keyed Waterstop Lap splice bars Bond breaker
Structural connection and joint types (cont.)
Steep chute slab control joint Generally same as flat chute No underdrains Leveling concrete instead of
RCC
Foundation key pedestal and reinforcement joint types (cont.)
Slab to wall footing contraction joint Plain dowel Double waterstop Bond breaker No key Longitudinal drain joint types (cont.)
Wall footing to wall footing control joint Keyed Waterstop Lap splice bars Bond breaker joint types (cont.)
Wall stem to wall stem contraction joint Plain dowel Single waterstop Bond breaker No key
New Access Roads and SART Recreational trail O&M access roads for underdrain collection and conveyance system
Surface drainage features currently under design
EVALUATION OF CONSTRUCTION SEQUENCES
Eight alternatives evaluated in total Discretized by construction seasons
Dry Season – April 16 to Nov 14 Wet Season – Nov 15 to April 15
Hydrologic loading for each sequence step Independent evaluations of four alternatives Design Team Evaluation Risk Team Evaluation
Part A
1. Control structure to El.
2. Cycles 1 and 7 to El. 567
3. Demo chute slabs and place RCC
4. Corner monoliths RC walls to El.
CURRENT PREFERRED CONSTRUCTION SEQUENCE
Wier wall (Cycles 1) to El 567
Wier wall (Cycle 7) to El
Corner monolith
Corner monolith
Left cofferdam Temporary RCC Abutment El 567
Control structure weir walls (Cycles 2‐6) to El 543
Demo and place RCC
CURRENT PREFERRED CONSTRUCTION SEQUENCE
Right cofferdam El 567
Ogee demo to El. 535.0
Embankment connection to El. 567
Embankment connection to El. 567
Left cofferdam 567 Slab and Wall construction
Part B
1. Cofferdams to
El. 567 connected to Cycles 1 and 7
2. Corner monoliths to El.
3. Embankment connections to El. 567
4. Continue chute slab and wall construction
Embankment connection to El. 594.4
Control Structure to final crest elevations
Remove cofferdams
Slab and Wall construction
Embankment connection to El. 594
1. Cofferdam removal
2. Embankment connections to El. 594.4
3. Continue chute slab and walls
4. Control structure to final crest elevations
PRECONSTRUCTION SERVICES
Collaboration Workshop
Contractor Deliverables
• Construction Sequencing
Plan
• Constructability Report
• Design Conflicts Analysis
Report
• Construction Schedule
• Construction Cost Estimate
Government Deliverables
• Life Safety Risk Analysis
Report
• Least Risky Construction Sequence
• Vested Construction Plan Ready for Execution
• Prepared Site Ready for Construction Production
EARLY WORK ITEMS
EARLY WORKING ITEMS
Clearing and Grubbing Must be completed outside the nesting season – September 16 through February 14
Once completed must be maintained Environmental requirement
Soundwall Installation Must be completed outside the nesting season – September 16 through February 14
Once completed must be maintained Environmental requirement
EARLY WORK ITEMS
SCG Gas Removal Abandoned gas line beneath footprint of right embankment connection
Backfilled with grout Differing information regarding exact location – three potholes
BID SCHEDULE
BID SCHEDULE
CONSIDERATIONS AND RESTRICTIONS
Working hours Monday through Friday – 7:00am to 6:00pm Excludes federal holidays Exceptions for concrete placements subject to municipal noise restrictions Site security Transient population resides in reservoir limits Security program submittal Security manager
Construction work limits
Wildlife Corridor
Wildlife corridor Provide and maintain a minimum of 12 feet of walkable space through the wildlife corridor at night and during all non‐work hours for wildlife to use.
If the wildlife corridor requires temporary blocking for construction purposes, the total blocking time may not exceed 24 hours or two consecutive nights without prior coordination and approval by Contracting Officer
Haul roads All haul roads withing CWL are available for use Improvements subject to approval by the Contracting Officer Pre and post construction survey required
Water for construction Reservoir water may not be used for construction
IDAC AND RFI’S
Drawing package 310 total drawings 192 drawings issued as part of solicitation 26 drawings issued “for construction” as part of early work items 118 additional drawings will be available to successful offeror
Majority of reinforcement drawings Additional excavation sections and details Additional sections and details for access roads and SART Surface drainage plans, sections, and details Swing gate sections and details Miscellaneous details
IDAC AND RFI’S
Consider uniqueness of early contractor involvement for this project
Non-IDaC drawings will not be made available for proposal phase Electronic files will not be made available Utilize all available information Bid quantities provided in the bid schedule Thermal restrictions for mass concrete placements