This document summarizes a two-step sealed bid solicitation for repair and renovation work at Sheppard Air Force Base in Texas. The U.S. Army Corps of Engineers seeks to award a firm-fixed price contract between $10-25 million to replace HVAC systems and repair interior elements in a 67,000 square foot facility. Work includes replacing mechanical, fire suppression, plumbing and electrical systems, and repairing surfaces and finishes. The solicitation uses a two-step process with initial submission of technical proposals only, followed by an amendment issuing final specifications and drawings to acceptably rated offerors for priced bids. Technical proposals are due by the date specified in block 13 of the SF1442 form. Only small businesses may compete, under NAICS code 236220. A site visit will be scheduled by amendment for interested contractors to have active SAM registration.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Building 1956 and Replace HVAC, newest first.
File Type Posted
W912BV23B0001 Bid Abstract 1419.pdf PDF
Step 2 Site Visit 022723.pdf PDF
Step 1 Site Visit 110122.pdf PDF
W912BV23B0001_Final.pdf PDF
W912BV23B0001_80 Percent_ Design_Plans.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0001 hereby makes changes section 00 22 11, adds attachment A and attachment b, updates site visit information in FAR clause 52.236-27, updates FAR clause 52.211-10, and updates sections 01 91 00 and 33 52 43.

All other terms and conditions remain unchanged.

Contract Specialist: Lindsey.M.Byfield@usace.army.mil.

1. CONTRACT ID CODE PAGE OF PAGES

1 15

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BV23B0001

X 9B. DATED (SEE ITEM 11)

21-Sep-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Nov-2022

CODE

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E. 81ST STREET

TULSA OK 74137-4290

W912BV 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BV23B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION 00 11 00 - SF 1442 AND CLIN SCHEDULE

SUMMARY OF CHANGES

SECTION 00 11 00 - SF 1442 AND CLIN SCHEDULE

The required response date/time has changed from 25-Oct-2022 02:00 PM to 15-Nov-2022 02:00 PM.

The performance period code has changed from Mandatory to Negotiable.

The contractor period of performance end 270 has been deleted.

SECTION 00 21 00 - INSTRUCTIONS, CONDITIONS & NOTICES TO OFFERORS

The following have been modified:

INSTRUCTIONS

INSTRUCTIONS FOR PROCUREMENT,

CONDITIONS,

AND

NOTICES TO OFFERORS

1. GENERAL DESCRIPTION OF WORK

This solicitation is utilizing the Two-Step Sealed Bidding procurement method as described in FAR Part 14.5 to award a firm fixed-price contract for the project titled “Repair B1956 and Replace HVAC” at Sheppard AFB, TX.

The general scope of the design-bid-build project requires the contractor to repair, replace and improve building systems of a 67,000 square foot facility, including fire suppression, plumbing, HVAC and electrical, and repair damage to interior elements, surfaces, and finishes. Maintain the existing HVAC ductwork and replace only wetted insulation. Add HVAC fault detection and diagnostics when replacing controls to include added temperature monitoring. Replace all wet piping and restore to a comparable system with freeze protection. Make only minor repairs to select features of the fire alarm and mass notification system as directed. Demolish 14 existing jet fuel pumps located in inside various classrooms and install a new fuel pump by existing outside fuel tank.

This solicitation is for Step One, which is a request for technical proposals only. The technical drawings and specifications for Step One are approximately 80% complete and not considered final or for construction.

Step One submissions will be reviewed for acceptability only. In Step One, a proposal must be rated as acceptable for all evaluation factors in order to receive an overall “acceptable” rating and to be able participate in the Step Two bid.

In Step Two, only offerors who submitted acceptable technical proposals in Step One will be allowed to submit bids.

The 100% final technical drawings, final bid schedule and other final bidding information will be provided to all technically acceptable firms during Step Two via a solicitation amendment.

2. GOVERNMENT SECURITY REQUIREMENTS

The Contractor shall submit all volumes of its proposal electronically via Procurement Integrated Enterprise Environment (PIEE) Solicitation Module (https://piee.eb.mil).

USACE Tulsa District Point of Contact is Ms. Lindsey Byfield:

Phone: 918-669-7070 Email: Lindsey.M.Byfield@usace.army.mil

3. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

Copies of the solicitation and any amendments will be posted electronically on SAM.gov, Contract Opportunities via the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/.

Solicitation Number: W912BV23B0001

It shall be the offeror’s responsibility to check the websites for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation. The opening of Step Two bids will follow the procedures set forth in FAR 14.402.

Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.

4. OFFEROR'S QUESTIONS AND COMMENTS

All contractual matters, questions and or comments relative to these documents should be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=HomePagePublic no later than 10 calendar days prior to the proposal due date, in order that they may be given consideration or actions taken prior to receipt of offers.

The bidder inquiry key for this project is: P44F24-CJRRHF.

Instructions for registering in the ProjNet Bidder Inquiry system are available on the above website.

5. SMALL BUSINESS SIZE STANDARD/NAICS CODE

The NAICS Code selected for this project is 236220, Commercial and Institutional Building Construction, and the size standard is $39,500,000.00. Also see FAR 52.204-8.2

6. PROPOSAL/BID EXPENSES AND PRE-CONTRACT COSTS

This invitation for bid (IFB) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.

7. SITE VISIT

The Government intends to hold a site visit during Step One of the solicitation. The date, location, and time will be announced by amendment to the solicitation. All interested offerors are highly encouraged to attend in person.

The site visit information will be provided by amendment.

All interested offerors are urged to attend. During this conference, the requirements set forth in the solicitation will be reviewed and discussed, with part of the conference to include a question-and-answer period.

8. ACCURACY IN PROPOSALS/BIDS

Proposals must set forth full, accurate, and complete information as required by this IFB, (including attachments).

The penalty for making false statements is prescribed in 18 U.S.C. 1001.

9. PROPOSAL/BID SUBMITTAL

9.1 The submittal method for proposals is electronically through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/ using the applicable solicitation number.

Proposals submitted by email, mail or hand-carried will not be evaluated. Proposals sent through proprietary or third-party File Transfer Protocol (FTP) sites or DoD SAFE will not be retrieved. It is the responsibility of the offeror to confirm receipt of proposals.

9.2 Proposals/bids will be received until the date and time and specified in this Invitation for Bid.

9.3 The packaging shall be marked Solicitation Number: W912BV23B0001.

9.4 Submitted technical proposals in response to this solicitation shall not include prices or pricing information.

Bid bonds are not required to be submitted with the Step One technical proposal. Bid bonds will be required to be submitted with the Step Two bid submission.

10. PROPOSALS/BID DUE DATES

The Step One request for technical proposal is due no later than the date and time listed on the Standard Form 1442, Block 13A.

The Step Two bid due date will be issued by amendment.

For further information, refer to Section 00 22 11.

11. JOINT VENTURE PROPOSAL REQUIREMENTS

When proposing as a joint venture, all members of the joint venture shall sign the SF 1442 and the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration. If this is an 8(a) or HubZone joint venture, the offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 and 13 CFR Part 126, respectively. Regardless of any agreement, all members of the JV shall sign the contract and the performance and payment bonds.

12. DEVIATIONS AND EXCEPTIONS

Deviations and exceptions to the terms and conditions of the solicitation in either the technical or price proposal will not be accepted. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer will be determined “unacceptable” and, thus, ineligible for award.

Should the Offeror have any questions related to specific terms and conditions, these must be resolved prior to submission of the offer. Notwithstanding the above, if deviations and exceptions are included with the offer, the offer will be determined “unacceptable” and, thus, ineligible for award.

SECTION 00 22 11 - PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA, BASIS OF

AWARD ONE-STEP-BEST VALUE, DESIGN-BUILD (SINGLE AWARD)

SECTION 00 22 11

TWO-STEP SEALED BID

OVERVIEW, GENERAL SUBMISSION REQUIREMENTS, AND

INSTRUCTIONS, EVALUATIONS, AND CONTRACT AWARD

1. OVERVIEW

a. This is a “Two-Step Sealed Bid” Invitation for Bid for the Repair B1956 and Replace HVAC project located at Sheppard AFB, Texas. The Contracting Officer will award one (1) firm fixed-price construction contract to the responsive and responsible bidder whom the Government determines to have an acceptable Step One technical proposal, conforms to the solicitation requirements, is fair and reasonable, and bids the lowest overall price in Step Two.

b. The Step One Request for Technical Proposals is issued with approximately 80% complete sufficiently descriptive technical specifications and construction drawings. The information contained in Step One is not binding on the Government, and the actual delivery or performance requirements will be contained in the invitation issued under Step Two. The 80% specifications and drawings are not final or to be used for construction. Only those firms determined to be technically acceptable during Step One will be issued the 100% final technical specifications during Step Two.

c. The Two-Step Sealed Bidding procedure is a combination of competitive procedures designed to obtain the benefits of sealed bidding while ensuring only technically acceptable firms participate in the priced sealed bid. The process allows for the Step One technical proposal submission and evaluation to be performed concurrent with the development of the final 100% technical specifications and construction drawings. Step One ensures that only technically acceptable firms participate in the Step Two, the sealed bid process.

d. Step One under this process consists of the request for, submission of, evaluation and (if necessary) discussion of a technical proposal. Only one technical proposal may be submitted by each offeror. The proposals are evaluated for technical acceptability. The Step One technical proposal must not include prices or pricing information.

e. In Step One, offerors must submit technical proposals that are complete and acceptable without the need for additional explanation or information. The Government may make a final determination regarding a proposal’s acceptability solely on the basis of the proposal as submitted. The Government may proceed with Step Two without requesting further information from any offeror; however, the Government may request additional information from, or enter into discussions with, the offerors of proposals that are determined to be reasonably susceptible of being made acceptable. Discussions will only be held if necessary, and if determined to be in the best interest of the Government.

f. A notice of “acceptable” or “unacceptable” will be forwarded to each Step One offeror upon completion of the technical proposal evaluation and final determination. The names of the offerors that submitted acceptable technical proposals will be listed on the Government’s https://sam.gov website for the benefit of prospective subcontractors.

g. In Step Two, an amendment with the final 100% technical specifications and construction drawings will be issued to only those offerors whose technical proposals are determined to be acceptable in Step One. The normal sealed bidding process in FAR Part 14 will be followed. In Step Two, only bids based upon technical proposals determined to be acceptable, either initially or as a result of discussions, will be considered for award. Each bid submitted in Step Two must be based on the bidder's own technical proposal that was submitted, evaluated and determined to be acceptable in Step One. Bidders must comply with the 100% technical specifications and construction drawings and the bidder’s acceptable technical proposal.

h. Contractor Team Arrangements are considered an arrangement in which (1) two or more companies form a partnership or joint venture to act as a potential prime contractor; or (2) a potential prime contractor agrees with one (1) or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program.

The Government will recognize the integrity and validity of contractor team arrangements; provided, the arrangements are identified and company relationships are fully disclosed in an offer or, for arrangements entered into after submission of an offer, before the arrangement becomes effective. The Government will not normally require or encourage the dissolution of contractor team arrangements.

The Offeror must identify the major or critical aspects of the requirement to be performed by those identified in the Contractor Team Arrangement.

i. Any Offeror submitting an offer in the name of a Joint Venture must include a fully executed copy of the Joint Venture Agreement with the offer. Joint Venture Agreements which require SBA approval may be submitted absent the requisite SBA Servicing Agency approving authorities’ signature;

however, the Offeror shall submit evidence from the Offeror’s SBA Servicing Agency that the Offeror has notified and discussed the proposed Joint Venture for this project with the appropriate SBA personnel.

2. STEP ONE TECHNICAL PROPOSAL SUBMISSION INSTRUCTIONS

All offerors are required to submit a technical proposal with the minimum content as specified herein. Proposals without the minimum content may be rated other than “acceptable”. Step One Technical Proposals shall be submitted electronically via Procurement Integrated Enterprise Environment (PIEE) Solicitation Module (https://piee.eb.mil), no later than the date and time established in Block 13 of the Standard Form (SF) 1442, or Block 14 of the most recent SF 30, as applicable:

Contracting Officer: Julie S. Hill at Julie.S.Hill@usace.army.mil Contract Specialist: Lindsey M. Byfield at Lindsey.M.Byfield@usace.army.mil

Each submission shall contain the following information:

a. Solicitation No: W912BV23B0001

b. Bid Due Date and Time: [Block 13 of the SF 1442 or Block 14 of the most recent SF 30, as applicable]

c. Bid Validity Date: 90 Days

Proposals received after the date and time stated within Block 13 of the SF 1442 or Block 14 of the most recent SF 30, as applicable, will be considered late and will not be considered for award. To avoid rejection of a proposal, the offeror must ensure the e-mail submission is virus-free. The Government will follow FAR 14.406 if an e-mail bid is unreadable.

Offerors must be registered in the System for Award Management (SAM) when sending the submission to comply with the annual representations and certifications requirements. The offeror certifies with its offer that the representations and certifications included in SAM are current, accurate, and complete.

3. STEP ONE TECHNICAL PROPOSAL FORMAT REQUIREMENTS

Submit the Step One technical proposal via email in PDF format and Optical Character Recognition (OCR)* compatible and word searchable. Each section must be clearly labeled by solicitation number, project name, and Offeror’s name.

*OCR is a common method of digitizing printed texts so that they can be electronically searched, stored more compactly, displayed on-line, and used in machine processes such as machine translation, text-to-speech, key data extraction and text mining.

Bidders shall enter a description for every file submitted. Bidders shall ensure all files are submitted in accordance with the submission requirements identified in PIEE.

Technical proposals will be organized with a table of contents as follows:

COVER LETTER: Solicitation number; Name, address, email, and telephone number of the offeror;

Names, titles, emails, and telephone numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this RFP. Name, title and signature of the person authorized to sign the proposal.

A statement specifying agreement with all terms, conditions and provisions included in the RFP; CAGE Code and UEI number for the offeror, and all teaming partners and / or joint ventures.

Note: The inclusion of any exceptions to the terms and conditions of the solicitation in the technical proposal, or the inclusion of any other terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the proposal is unacceptable and thus ineligible for award. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the proposal.

TAB A: Standard Form 1442, completed and signed by authorized individual(s) of the Offeror, include the offeror’s UEI number in Block 14.

Acknowledgement of all amendments to the RFP in accordance with the instructions on the Standard Form 30 (amendment form).

TAB B: Section 00 45 00 – Representations and Certifications, Printed Entity Record from the online System for Award Management (SAM) database.

TAB C: Teaming & Joint Venture Arrangements: Offers submitting proposals using a teaming arrangement shall submit a fully executed copy of the teaming arrangement signed both by the subcontractor/teaming partner and the offeror and the narrative described in Section 00 21 00 Paragraph 11.

Offers submitted in the name of a joint venture must be signed in accordance with the terms and conditions specified in the joint venture agreement as evidenced in the proposal, including letters of commitment from the joint venture firms. See Section 00 21 00 Paragraph 11.

TAB D: Deviations and Exceptions

TAB E: All submission requirements for Factor 1: Bond Surety Letter & Bank Letter

TAB F: All submission requirements for Factor 2: Specialized Experience

TAB G: All submission requirements for Factor 3: Technical Approach

TAB H: All submission requirements for Factor 4: Past Performance

4. STEP ONE TECHNICAL PROPOSAL INQUIRIES AND QUESTIONS

See Section 00 21 00 Instructions for Procurement, Conditions, and Notices to Offerors.

5. ELIGIBILITY FOR CONTRACT AWARD

In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award will be made unless the Contracting Officer makes an affirmative determination of responsibility. To be determined responsible, a prospective prime contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.

6. STEP ONE REQUEST FOR TECHNICAL PROPOSALS EVALUATION

The Government will evaluate each offeror’s technical proposal based on how well the proposal addresses each of the evaluation factors listed below. Factors 1, Bond Surety Letter and Bank Letter, and 4, Past Performance, will be evaluated by the Government and either an “acceptable” or “unacceptable” rating will be determined by consensus of the Government evaluation board. Factors 2, Specialized Experience, and 3, Technical Approach, will be evaluated by the Government and either an “acceptable”, “unacceptable” or “reasonably susceptible of being made acceptable” rating will be determined by consensus of the Government evaluation board. There are no relative weights assigned to the factors. A Step One acceptable technical proposal must be rated “acceptable” for all evaluation factors in order to receive an overall “acceptable” technical proposal rating.

6.1 General Technical Proposal and Evaluation Information:

6.1.1 The evaluation will be conducted in accordance with FAR Subpart 14.5, Two-Step Sealed Bidding. For this procurement, only one (1) technical proposal may be submitted by each offeror. The proposal must be complete without the need of additional explanation or information. The Government may proceed with Step Two without requesting further information from any offeror; however, the Government may request additional information from offerors of proposals that it considers “reasonably susceptible of being made acceptable.”

6.1.2 Technical Proposals will be rated at the factor level. If any factor is determined to be “unacceptable”, the entire proposal will be determined “unacceptable”. A technical proposal may be determined to be “reasonably susceptible of being made acceptable” and therefore eligible for discussions; however, a proposal with a factor that is determined to be “unacceptable” will be eliminated from further consideration.

6.1.3 Technical proposals which do not provide the specified information in the specified location in accordance with the submission instructions may be rated other than “acceptable”. The Government is under no obligation to search for information that is not in the specified locations. If an offeror submits alternates that are not requested, the information will not be evaluated.

6.1.4 In general, example projects or experience that the Government does not consider relevant for the purposes of evaluating experience will not be considered as a part of the minimum project requirement.

6.1.5 The degree of acceptability to the Government inherent in the content of the offeror’s technical proposal will be a consideration under every evaluation factor.

6.1.6 If discussions are held with offerors whose proposals are considered “reasonably susceptible of being made acceptable” and a request for proposal revisions are requested, the revised proposal will be reevaluated in accordance with the criteria in the solicitation. After completion of discussions and evaluation of any revised proposals, the proposal will be determined as “acceptable” or “unacceptable”.

If determined “unacceptable”, a notice of unacceptability will be forwarded to the offeror upon completion of the proposal’s evaluation.

6.1.7 Any proposal which modifies or fails to conform to the essential requirements or specifications of the request for technical proposals will be considered nonresponsive and categorized as “unacceptable”.

6.1.8 The offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. Failure to comply with the formatting and/or submission requirements may be seen as indicative of the type of problems that could be expected during contract performance.

Lack of conformance and material omission(s) may cause the technical proposal to be rejected as “unacceptable”.

6.1.9 The proposal submission instructions are written to give prospective offerors, where feasible, an indication of the level of detail desired by the Government. The offeror’s failure to include information that the Government has indicated must be included will result in the proposal being found other than “acceptable” if inadequate detail is provided.

6.1.10 Do not include exceptions to the terms and conditions of the solicitation in the technical proposal submissions. The inclusion of any terms and conditions in the proposals that conflict with the terms and conditions of the solicitation may result in a determination that the proposal/bid is “unacceptable” and thus, ineligible to bid in Step Two. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the proposal/bid; see “Proposal Inquiries and Questions”, located above in Section 00 21 00.

6.1.11 Factor and Overall Technical Proposal Ratings. Each factor and the overall technical proposal as a whole will be given one of the ratings identified and defined as follows:

Factors 1 & 4 Ratings Definition

Acceptable Proposal meets the requirements of the RFP, and based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.

Unacceptable Proposal does not meet the requirements of the RFP, and / or based on the offeror’s performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

Factors 2 & 3 Ratings Definition

Acceptable The proposal meets the requirements of the RFP and indicates an adequate approach and understanding of the requirements.

Reasonably Susceptible of Being Made Acceptable*

The proposal, as proposed, cannot be rated as acceptable because of error(s), omissions(s) or deficiency(ies) which are capable of being corrected without a major rewrite or revision of the proposal.

Unacceptable The proposal does not meet the requirements of the RFP.

*The rating of Reasonable Susceptible of Being Made Acceptable will not be used for the overall technical proposal rating.

6.1.12 Submission Requirements and Evaluation Criteria for the Technical Proposal

The information provided in this section will be used in evaluating the offeror’s specialized technical experience and proposed technical approach, specific to this solicitation.

6.2 Factor 1: Bond Surety Letter and Bank Letter

6.2.1 Submission Requirements:

6.2.1.1 Proposing firm must provide a letter from a surety appearing on the Department of Treasury Circular 570 (list of approved sureties at https://www.fiscal.treasury.gov/surety-bonds/list-certified-companies.html) stating:

a. The bidder is able to provide a project bid bond in Step Two for an individual project valued at a minimum of $20M.

b. The bidder is able to obtain performance and payment bonds for an individual project valued at a minimum of $20M should it be awarded the contract.

6.2.1.2 Financial statement and bank letter that verify that sufficient funds will be available to perform the work on an individual construction project valued at a minimum of $20M.

6.2.2 Evaluation Criteria:

The Government will evaluate all the proposing firm’s submission documents and categorize the proposal with one

(1) combined technical evaluation for this factor.

6.2.3 Minimum Acceptability Criteria:

6.2.3.1 The bidder provides a letter from a surety appearing on the Department of Treasury Circular 570 stating it is able to provide a project bid bond in Step Two for an individual project valued at a minimum of $20M.

6.2.3.2 The bidder provides a letter or other documentation from a surety appearing on the Department of Treasury Circular 570 stating it is able to obtain performance and payment bonds for an individual project valued at a minimum of $20M should it be awarded the contract.

6.2.3.3 The bidder provides financial statements and a bank letter verifying that sufficient funds will be available to perform the work on an individual construction project valued at a minimum of $20M.

Note: If a firm is found acceptable and qualified to participate in Step Two, a bid bond is required with its Step Two bid in accordance with FAR 52.228-1, Bid Guarantee. If a firm is selected for award, it must provide payment and performance bonding in accordance with FAR 52.228-15, Performance and Payment Bonds – Construction.

6.3 Factor 2: Specialized Experience

6.3.1 Submission Requirements:

Submit a minimum of three (3) example projects and a maximum of five (5) example projects completed within the last 6 years demonstrating the proposing firm’s recent, relevant experience. If more than five projects are submitted, only the first five will be evaluated. The projects submitted shall be limited to no more than five pages for each project submission. Additional pages above the limit may not be evaluated.

Multiple Award Task Order Contracts (MATOCs) or any other type of task-order contracts that provide for the issuance of task orders for the performance of tasks will not be considered projects for the purposes of this evaluation. Only individual task orders issued under such contracts will be evaluated as projects; however, a phased project using phased task orders for a single customer with multiple inter-dependent facilities on a single site may be considered a project for the purposes of this evaluation. Project descriptions that do not clearly describe the proposing firm’s or team member’s experience, the scope of the project, or the periods of project performance will not be considered.

The information that is required for Factor 2, below, is provided in the template Attachment A, Experience in Relevant Projects, which can be extended as necessary. Offerors are not required to use the form itself as part of their proposal, but the information requested for Factor 2 must be in the offeror’s proposal and should be in the same format as the template.

The following information is required for each submitted project experience:

a. Project Title

b. Location

c. Contract Number

d. Type of Contract: Indicate Firm Fixed Price; Cost Plus Fixed Fee; etc.

e. Total Dollar Amount at Award and Completion: Total amount of the proposing firm’s contract or subcontract (if a key subcontractor)

f. Project Delivery Method: Indicate Design/Bid/Build; Design/Build; Integrated Design; Design Only;

etc.

g. Role of Proposing Firm: Prime contractor or key subcontractor. If a subcontractor, state who is the prime contractor. State if the example project represents a Joint Venture. If a Joint Venture, name the Joint Venture’s parties. Indicate type of work and percentage of work performed by the parties.

h. Brief Description of Project: Provide a narrative with details about the proposing firm’s role and the relevancy to this project

i. Project Relevancy: Address any relevancy of the submitted project using, at a minimum, the relevancy criteria (a) through (f) below

j. Construction Start and Completion Dates: Project construction must be identified as complete or substantially complete. If a proposing firm presents a project that is substantially complete, the proposal must include an explanation of why that project should be considered.

k. Customer / End User’s Primary Point of Contact: Name, relationship to project, agency/firm, phone number, and e-mail address. The Government may contact and interview project references. Reference information will not be revealed to other parties.

l. Procuring Activity Point of Contact: Name, relationship to project, agency/firm, phone number, and e-mail address. The Government may contact and interview project references. Reference information will not be revealed to other parties.

6.3.2 Evaluation Criteria:

The Government will evaluate each submitted project’s extent of recent and relevant experience compared to this project’s size, scope of work, and performance requirements. The Government will categorize the proposal with one

(1) combined technical evaluation for this factor.

A recent project is a project that is complete, or substantially complete within six (6) years of this request for technical proposal issue date. If a proposing firm submits a project as substantially complete within the 6-year period, the proposal must include an explanation why that project should be considered substantially complete.

The relevancy of a submitted projects must be substantiated by the proposing firm’s role, work, size, scope, and complexity similar to the requirements in this project. In making this determination, the Government will use the following criteria to establish the acceptable relevancy of a submitted project (this is not an exclusive list and each relevant project does not need to meet all of the criteria) for experience with:

a. Full replacement of building systems, to include mechanical systems, fire suppression, plumbing, electrical and lighting

b. Commissioning of building mechanical systems

c. Repair of building interior surfaces and finishes

d. Large (>50,000 square foot) building facility project

e. Constructing a project on a military installation

f. Phasing construction operations in occupied facilities

6.3.3 Minimum Acceptability Criteria:

A firm’s acceptable proposal for this factor must include:

a. At least two of the submitted projects must have similar scope criteria as listed above in item a & b.

b. At least one submitted project must have similar scope criteria as listed in item a, c, & d.

c. One of the submitted projects must comply with item a and have a contract value of at least $10M.

d. Determined to meet the recency requirements above.

e. Determined to meet the relevancy requirements above.

The project descriptions and relevancy narratives must clearly articulate the relevancy in sufficient detail to determine technical capability. The more similarities an example project has with the prospective contract, the greater the degree of relevancy.

6.4 Factor 3: Technical Approach

6.4.1 Submission Requirements:

The proposing firm must clearly communicate its proposed technical approach for the solicited project which meets the attached 80% technical specifications and construction drawings. The TAB G technical approach, including all narrative and charts and other grahics, is limited to twenty-five (25) pages. The proposal must include, as a minimum, the following elements:

6.4.1.1 Construction Approach to include:

a. Demolition and disposal of existing, and installation of new building systems as specified in the contract documents

b. Commissioning of the new building HVAC controls

c. Description of your QC system and Safety Plan

d. Coordination between subcontractors

e. Construction data management and reporting requirements.

6.4.1.2 Conceptual Schedule Management to include:

a. Sequencing and managing important construction activities and milestones that demonstrates a firm understanding of how to schedule and manage the project’s construction and data management.

b. The schedule must include durations in calendar days that meets the contract requirements. (Note: this is a concept schedule used to assure the contractor understands the scope and sequencing of the project and is not considered a post award construction submittal).

c. Coordination between features of construction/sequencing work/staging.

6.4.1.3 Staffing and Management Plan to include:

a. Management organization chart of proposing firm (prime contractor) and Key Staff including Construction Project Manager, Quality Control Manager (CQC System Manager), Site Superintendent, and Site Safety & Health Officer

b. Key subcontractors

c. Work assignments of specialized skills and trades.

6.4.2 Evaluation Criteria:

6.4.2.1 The Government will evaluate the technical approach in its entirety and categorize the proposal with one

(1) combined technical evaluation for this factor.

6.4.2.2 The proposing firm’s technical approach narrative must be in an organized manner that acceptably addresses the elements and sub-elements listed in the submission requirements. The proposed technical approach must meet all the attached draft plans, specifications, and contract requirements, and be commensurate with this project’s size, scope, and complexity.

6.4.3 Minimum Acceptability Criteria:

6.4.3.1 The proposing firm’s technical approach must, at a minimum, include and address all the elements and elements listed in the submission requirements.

6.4.3.2 A proposing firm demonstrates an acceptable technical approach by meeting the minimum submission requirements for this factor and providing the Government with a technical approach that meets all of the attached plans, specifications, and contract requirements, commensurate with this project’s size, scope, and complexity.

6.5 Factor 4: Past Performance

6.5.1 Submission Requirements:

Submit past performance information on each project submitted for Factor 2. DO NOT provide Past Performance references for projects other than those project examples provided for Factor 2. The quantity of projects submitted for this factor is the same as the quantity of projects submitted for the Factor 2 submission requirements, a minimum of three (3) and a maximum of five (5).

The Past Performance Questionnaire (PPQ) (Attachment B) is provided for the offering firms to submit to the client of each project the offering firm includes in its submission requirements for Factor 2. Ensure correct phone numbers and email addresses are provided for the client’s point of contact. The completed PPQs should be submitted with the Step One technical proposals. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, lindsey.m.byfield@usace.army.mil via email prior to the Step One technical proposal closing date and time.

Note: If any of the projects are Government contracts with a completed CPARS, please only complete Blocks 1 through 5 of the PPQ form (Attachment B) and attach it to the front of the CPARS rating. Be sure to include the POC’s information of the client and the contract number of the project.

6.5.2 Evaluation Criteria:

The past performance evaluation is an assessment of the offeror’s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. The Government will at a minimum, evaluate the successful performance of all project examples submitted for Factor 2 and categorize the proposal with one (1) combined evaluation for this factor.

The burden of providing detailed, current, accurate and complete past performance information rests with the proposing firm. If any firm has multiple functions or divisions, the Government will only evaluate past performance of the division or unit submitting the offer or of the team member. The prime contractor will be rated on its own performance. A prime contractor may not establish past performance based on the past performance of its proposed key personnel, apart from that of the entity.

In accordance with FAR 15.305 and DFARS 215.305, the currency and relevance of the information, source of the information, context of the data, and general trends in contractor’s performance will be considered. However, the comparative assessment in FAR 15.305(a)(2)(i) does not apply. Therefore, past performance will be rated on an “acceptable” or “unacceptable” basis only.

In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)). Therefore, the offeror will be determined to have unknown (or “neutral”) past performance. In the context of acceptability/unacceptability, a neutral rating will be considered “acceptable.”

The Government may also review past performance information from any sources available to the Government, to include, but not limited to, the Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Assessment Reporting System (CPARS) or other databases using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal; interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction. The evaluation may take into account the number and severity of problems, the demonstrated effectiveness of corrective actions taken, and the overall work record.

6.5.3 Minimum Acceptability Criteria:

Past performance information must be submitted for each project submitted for Factor 2. This amounts to the same Factor 2 minimum of three (3) example projects and a maximum of five (5) example projects completed within the last 6 years from the date of the Step One solicitation issuance date demonstrating the proposing firm’s recent, relevant experience.

The recency and relevancy of each submitted project’s past performance evaluation will use the same determination made during the Factor 2 evaluation. Any additional recency and relevancy determinations of past performance information from other sources available to the Government will follow the same criteria used during the Factor 2 evaluation.

A proposing firm demonstrates acceptable past performance by meeting the minimum submission and past performance solicitation requirements and based on the offeror’s satisfactory or higher performance record, the Government has a reasonable expectation that the offeror will successfully perform the required efforts in the requirements. The Government will have confidence in the firm’s probability to successfully supply products and services that meet all the contract’s plans, specifications requirements.

7. STEP TWO INVITATION FOR BID, EVALUATION, AND AWARD

Step Two in the process involves the submission of sealed priced bids by those offerors who submitted acceptable technical proposals in Step One.

The Step-Two Invitation for Bid (IFB) will be issued to the acceptable firms as an amendment to the solicitation and include the final 100% technical specifications and construction drawings, final bid schedule, and other final bidding information. The priced bids will be due no later than the date and time listed in the amendment. The bids submitted in Step Two will be evaluated and the award made in accordance with Subparts 14.3 and 14.4.

In Step Two, only bids based upon technical proposals determined to be “acceptable”, either initially or as a result of discussions, will be considered for award. Each bid in Step Two must be based on the bidder's own technical proposal that was submitted, evaluated, and determined to be acceptable in Step One.

Bidders must comply with the final technical specifications and construction drawings and the bidder’s acceptable technical proposal. Do not include exceptions to the terms and conditions of the solicitation in the bid submissions.

The inclusion of any terms and conditions in the bid that conflicts with the terms and conditions of the solicitation may result in a determination that the proposal/bid is unacceptable and thus ineligible for Step Two and award.

Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the proposal/bid; see “Proposal Inquiries and Questions”, located in Section 00 21 00.

SECTION 00 72 00 - CONTRACT CLAUSES

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the proposed calendar days for completion.

The contractor shall propose a contract duration in number of calendar days on the schedule in Tab G Technical

Approach. If accepted, the proposed duration shall become the required contract duration. Offerors shall propose a contract duration that reflects value engineering, as well as maximum efficiency and cost savings to the Government. Offerors shall clearly indicate the key activities impacting the critical path in which time has been extended to reduce risk and annotate the nature and perceived severity of risk. During the subsequent comparison between proposals, differences between proposed contract durations of at least three (3) weeks (differences of 21 calendar days between proposals) will be considered an advantage to the Government, with greater differences also considered, accordingly. No advantage will be considered between proposals for differences less than 21 calendar days.The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) The site visit to review the ‘Repair Building 1956 and Replace HVAC’ project has been scheduled for Tuesday, 1 NOV 2022 from 0900-1100 CDT. Offerors must submit in writing, via e-mail, the firm’s name, address, point of contact, telephone number, and number of personnel planning to attend to Ms. Lindsey Byfield (lindsey.m.byfield@usace.army.mil) no later than five (5) working days prior to the site visit. A Government issued ID (i.e., driver’s license) is required to gain access to the installation. Each attendee who needs a Visitor Pass will need to provide their name, date of birth, and a valid driver's license or state ID number with state of issue. USACE will need to submit an entry access list to the Sheppard AFB Visitor Center before the visit for prior approval.

Offerors are reminded to allow sufficient time to pass through security to gain entrance to the installation.

(End of provision)

(End of Summary of Changes)

Repair B1956 and Replace HVAC Sheppard AFB, TX W912BV23B0001

00 22 11 - ##

SECTION 00 22 11 - ATTACHMENT A

COMPANY SPECIALIZED EXPERIENCE - CONSTRUTION OR PRIME CONTRACTOR

Provide the following information to show examples of construction projects your company completed within the last six (6) years indicating experience with projects of similar type and scope. Use one form per project.

a. Type of Facility Represented

b. Your Firm’s Name

c. Name of Project and Contract Number

d. Location of Project

e. Project Contract Type

f. Owner

g. General Scope of Project (address how this relates to this solicitation)

h. Your Role (Prime, Joint Venture, or Subcontractor) and Work Your Company Self-Performed (also include any proposed team members that were directly involved in this project, including work performed, roles and responsibilities) :

i. Provide a list of the management team and their responsibility at a minimum include Project Manager, Quality Control Representative, and Construction Superintendent.

j. Construction Cost

k. Extent and Type of Work You Subcontracted Out

l. Dates Construction: Began Completed

m. Your Performance Evaluation by Owner, if known

n. Were You Terminated or Assessed Liquidated Damages?

(If either is “Yes”, attach an Explanation)

o. Owner’s Point of Contact for Reference (Name and Company)

p. Current Telephone Number of Reference POC

00 22 11 - ##

COMPANY SPECIALIZED EXPERIENCE - DESIGN FIRM OR IN-HOUSE DESIGN CAPABILITY

Provide the following information to show examples of projects your company constructed within the last six (6) years indicating experience with projects of similar type and scope. Use one form per project.

a. Type of Facility Represented

b. Your Firm’s Name

c. Name of Project and…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .