AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

$50M Service-Disabled Veteran-Ow ned Small Business (SDVOSB) Multiple Environmental Government Acquisition (MEGA) Indefinite

Delivery Contract (IDC) for Environmental Remediation Services (ERS) Projects Assigned to the Regional Planning and Environmental Center

(RPEC) and as Assigned to the Southw estern Division (SWD) and South Pacif ic Division (SPD)

1. Amendment #0003 is being issued to replace Section B, Pricing Schedule; Section J, Example Project PWS; Attachment L-1, Milestone

Payment Schedule Without Cost; and Attachment L-2, Milestone Payment Schedule With Cost.

2. The point of contact for this action is Joshua Hope, 918-669-7460.

1. CONTRACT ID CODE PAGE OF PAGES

1 17

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-May-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV21R0025

X 9B. DATED (SEE ITEM 11)

25-Mar-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-May-2021

CODE

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E. 81ST STREET

TULSA OK 74137-4290

W912BV 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BV21R0025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Section B, Price Schedule 22 16-MAR-2021

Attachment 2 Section J, Example

Project Attach L-1 w/o

Cost

2 16-MAR-2021

Attachment 3 Section J, Example

Project Attach L-2 With

Cost

3 16-MAR-2021

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Amndmt 0003 Section B, Pricing Schedule

22 13-MAY-2021

Attachment 2 Amndmt 0003 Attach L-1

MPS wo Cost

2 13-MAY-2021

Attachment 3 Amndmt 0003 Attach L-2

MPS w/Cost

3 13-MAY-2021

The following have been added by full text:

AMDMT 0003 EXAMPLE PROJECT PWS

Section J

Solicitation #W912BV-21-R-0025

EXAMPLE PROJECT

PERFORMANCE WORK STATEMENT (PWS)

EXCAVATION AND DISPOSAL

TNT CONTAMINATED AREA

LSAAP, TEXARKANA, TEXAS

Amendment #0001

Amendment #0003

13 April 2021

23 April 2021

16 March 2021

**Note to Offerors: This is an Example Project, with no existing documentation (i.e. RI/FS, Decision Document, site figures, site address, etc.). This Example Project will not be awarded. Offerors will develop a technical approach and proposed price based on Section L requirements and the information contained therein.

1.0. INTRODUCTION

This an Example Project for a non-personal services contract to provide in excavation and disposal remediation actions at Lonestar Army Ammunition Plant (LSAAP) approximately 12 miles west of Texarkana, TX. The

Government shall not exercise any supervision or control over the Contractor and its subcontractors performing the services herein. Such contract service providers shall be accountable solely to the primary Contractor who, in turn is responsible to the Government.

1.1. Background

LSAAP was constructed during World War II. Immediately following the completion of initial construction, the

Lone Star Defense Corporation, a subsidiary of the B.F. Goodrich Company, Akron, Ohio, placed the plant into active production. Goodrich operated the plant during World War II and for several months thereafter in conjunction with closeout procedures. Effective November 4, 1945, Lone Star Ordnance Plant was incorporated with Red River

Ordnance Depot, and a few months later the name of the installation was changed to Red River Arsenal. In the early part of 1950, Lone Star was selected for reactivation and Day and Zimmermann, Inc. was selected as the architect and operating engineer. Effective November 1, 1951, the plant was designated Lone Star Ordnance Plant, a Class II industrial activity under the jurisdiction of the Chief of Ordnance. On July 1, 1963, the plant was re-designated

LSAAP. Early in 1969, ammunition production activities began to decline.

LSAAP was a government owned/Contractor operated (GOCO) facility that produced a variety of military munitions. LSAAP occupied over 15,000 acres of land on which the various functions necessary to load, assemble and pack (LAP) ammunition items for the Army were performed and maintained. The plant contained an administration area, thirteen (13) production lines, seven (7) storage areas, maintenance shops, a railroad classification yard, a sewage treatment plant, demolition areas, a high explosives (HE) burning ground, a munitions test area, landfills (active and closed) and a fire-fighting pumping station.

The site referenced in this PWS is a 100 ft x 135ft area that is easily accessed by paved roadways (the excavation site is approximately 50 feet from the roadway) and no overhead or underground utilities remain active or are abandoned in place. While electricity is the only utility available for the contractor’s use, at the contractor’s cost after coordination with the local utility company, from a pole approximately 25’ from the excavation site, a fire hydrant is located approximately 2 blocks away and can be used at no charge for dust control and other contract requirements. The contractor can also utilize the area near the power pole as their laydown area during field activities, but must provide their own security for all equipment. The excavation site area remains to be developed for use; therefore, the contractor can expect little to no traffic during field activities.

1.2. The contractor is ultimately responsible for meeting all performance objectives within the task order’s performance period specified in this PWS. Performance Objectives and Standards are presented in Table 1 below:

TABLE 1 – PERFORMANCE OBJECTIVES AND STANDARDS

DESCRIPTION Task Performance Objective Performance Standard

Project Management Task 1 Complete all Project

Management Plans and

Deliverables

USACE Accepted Final Documents

Optimized UFP-

QAPP/SWPPP

Task 2 Prepare an acceptable

Optimized UFP-QAPP

/SWPPP identifying all activities that will take place to achieve site closure.

USACE and TCEQ Approved Final

Optimized UFP-QAPP/SWPPP.

Explosive Safety

Submission (ESS)

Task 3 Prepare an acceptable ESS and approval through

DDESB

USACE and DDESB Approved Final

ESS.

Soil Excavation and

Disposal

Task 4 Implement the Proposed

Plan’s and Decision

Document’s Primary

Remediation Alternative

USACE Accepted Final Completion

Report with Photo Documentation, and

Waste Manifests and Landfill Receipts

Excavation Site

Sampling

Task 5 Laboratory validation that no residual contamination remains at excavated site

USACE Accepted Sampling Report

Excavation Site

Backfill

Task 6 Backfill excavated site in accordance with ASTM

D698

USACE Accepted Compaction Report

Excavation Site Re-vegetation

Task 7 Restore excavated site with native grass with at least 70% survival rate

USACE Verified Vegetation Survival

Rate

Response Action

Completion Report

(RACR), Request for

No Further Action

(NFA) and Site Closure

Task 8 Achieve Site Closure USACE and TCEQ approved Final

RACR

After Action Report

(AAR)

Task 9

Prepare an acceptable AAR that identifies all activities completed and closes out the

ESS

USACE and DDESB approved Final

AAR

2.0. SCOPE

A site-specific Remedial Investigation and Feasibility Assessment (RI/FS) was conducted in 2016, which identified

Trinitrotoluene (TNT) contamination in the area caused by previous demolition activities. A Feasibility Study was developed with various alternatives for remediation of this site. Based on this Feasibility Study, Excavation and

Disposal was selected as the primary remediation alternative in the proposed plan and decision document.

The overall objective of this task order is to excavate and dispose of TNT contaminated soil to reduce the concentration of TNT to meet the TCEQ Tier 1 Residential Total Soil Combined PCL of 3.3E+01 mg/kg.

The contractor shall provide all personnel, supervision, equipment, supplies, facilities, transportation, tools, materials, and any other items or services necessary to perform the environmental remediation services to meet the performance objectives of this PWS in accordance with all applicable federal, state and local laws and regulations, and relevant Department of Defense (DoD), Army and USACE policies for the duration of the contract.

3.0. PROJECT MILESTONES

Performance Milestones are identified in Table 2 – Performance Milestones. The Contractor shall propose pricing for the performance milestones utilizing Attachment L-2, Milestone Payment Schedule with Cost. (NOTE: The

Excel version of Attachment L-2 provided with the RFP shall be submitted with the Offeror’s Volume II, Factor 6.) The Contractor must utilize Attachment L-1, Milestone Payment Schedule without Cost to identify their anticipated scheduled start and completion dates for each milestone, based upon their overall project schedule. The

Contractor may NOT propose interim milestones to the Performance Milestones within Table 2. As noted in

Section 10, payments will be tied to the successful completion of a milestone, or an interim milestone, approved by the Contracting Officer, through the COR.

Table 2 – Performance Milestones

TABLE 2 – PERFORMANCE MILESTONES

CLIN Milestone Task

Performance Acceptance

Standards and Approval

Authority

Deliverable

TASK 1 – PROJECT MANAGEMENT

0001 Project Kick-Off Meeting via teleconference within 15 calendar days of contract award

Meeting minutes due within 7 calendar days

USACE

Project Kick-off

Meeting Minutes

0002 Project Management Plan (PMP)

Draft PMP due within 21 calendar days of contract award.

Government will provide comments to the Draft PMP within

15 calendar days.

Final PMP due within 21 calendar days after receipt of Government comments on Draft.

Draft PMP

Approved Final

PMP

Authority

Deliverable

0003 Quality Assurance/Quality Control

(QA/QC) Plan

Draft QA/QC Plan due within 15 calendar days of contract award.

Government will provide comments to the Draft QA/QC

Plan within 21 calendar days.

Final QA/QC Plan due within 10 calendar days after receipt of

Government comments on Draft.

Draft QA/QC Plan

Approved Final

QA/QC Plan

0004 Monthly Progress Reports

Submitted with the invoice not later than the 10th of each month via email

USACE Approved Monthly

Progress Report

0005 Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)

Due within 21 calendar days prior to site mobilization

USACE Approved

APP/SSHP

0006 Annual Contractor Manpower Reporting

Complete manpower reporting in accordance with PWS Section

4.1.6

Reporting period shall end 30

September of each year

Copy of submitted Contractor

Manpower Report shall be submitted to the USACE PM/TM no later than 31 October of each year

2 reports will be required for the following periods:

o Ending 30 Sept 2022 o Ending 30 Sept 2023

USACE Annual Contractor

Manpower Report

TASK 2 – UFP-QAPP

0007 Optimized UFP-QAPP

Draft UFP-QAPP due within 30 calendar days of kick-off meeting

Government will provide comments within 30 calendar days

Final due within 14 calendar days of receipt of comments on the

Draft

TCEQ

Draft UFP-QAPP

Optimized UFP-

QAPP approved by

Authority

Deliverable

0008 Stormwater Pollution Prevention Plan

(SWPPP)

Draft and Final SWPP due in accordance with the approved

UFP-QAPP

USACE and TCEQ Final SWPPP approved by TCEQ

TASK 3 - ESS

0009 Explosive Safety Submission (ESS)

Draft ESS due within 60 calendar days of kick-off meeting

Government will provide comments within 30 calendar days

Final due within 14 calendar days of receipt of comments on the

USACE, USATCES, and

DDESB

ESS approved by

TASK 4 – EXCAVATION AND DISPOSAL

0010 Excavation and Disposal

Excavate and dispose of 3,000 CY of contaminated soil from the TNT contaminated area

Excavation site boundary is clearly marked; dimensions are approximately 100’ x 135’ x 6’

USACE Excavated Soil

Waste Manifests and Landfill

Receipts

TASK 5 – EXCAVATION SITE SAMPLING

0011 Sampling

Sampling Report due within 14 calendar days after laboratory validation

USACE Sampling Report

TASK 6 – EXCAVATION SITE BACKFILL

0012 Backfill

Backfill placed in lifts no greater than 8-inches and compacted to

95% Proctor (IAW ASTM D698)

Upper compacted layer may be less than 95% to achieve the required re-vegetation rate

Compaction Test Report due within 7 calendar days of compaction test

USACE Compaction Test

Report

Authority

Deliverable

TASK 7 – EXCAVATION SITE RE-VEGATATION

0013 Re-vegetation

Shall be grass seed mixture native to the Texarkana area to completely re-vegetate the excavated area

Shall achieve a survival rate of at least 70% coverage of the excavation site

USACE Letter of

Completion and

Photo

Documentation

TASK 8 – RACR, NFA, SITE CLOSURE

0014 Final Response Action Completion Report

(RACR) & Site Closure

Draft RACR due within 60 calendar days of completion of all field activities

Government will provide comments within 21 calendar days

Final RACR due within 14 calendar days of receipt of comments on the Draft

Draft RACR

Final RACR approved by TCEQ

TASK 9 8 – AAR, ESS CLOSEOUT

0015 Final After Action Report (AAR)

Draft AAR due within 60 calendar days of completion of all field activities

Government will provide comments within 21 calendar days

Final AAR due within 14 calendar days of receipt of comments on the

Draft

USACE, EMCX,

USATCES, and DDESB

Final AAR approved by

4.0. TASK DESCRIPTIONS

4.1. Task 1 – Project Management:

The contractor shall provide Contract Management for performing the PWS requirements. The contractor shall provide Contract management including prime and subcontract support as required, internal project controls and

Quality Control (QC), status reports on work being performed under this contract, invoicing and pay requests, and other coordination and personnel support for the individuals assigned to this contract. A Project Manager will be designated by the Contractor as the single POC for all contract performance and administrative matters. A list of required submittals and their review times are identified in PWS Attachment 1 – Deliverables Schedule.

4.1.1. Project Kick-Off Meeting (DELIVERABLE)

The Contractor shall participate in a kick-off meeting via teleconference within 15 calendar days of task order award. The kick-off meeting will provide an introduction of both contractor and Government personnel, personnel roles and responsibilities, discuss the contractual requirements, and lay out the path forward for successful contract execution. The Contractor shall prepare meeting minutes and provide them to all meeting participants within 7 calendar days of the kick-off meeting. All contractor key personnel will attend this meeting. (See Section 5 of this

PWS for Key Personnel)

4.1.2. Project Management Plan (DELIVERABLE)

The Contractor shall prepare and maintain a Project Management Plan (PMP) that is based on the Contractor’s proposal that, at a minimum, includes technical approach, management organization and integration of the contractor’s project team, their responsibilities and authorities, schedule and schedule management, transitional activities (if any), risk management, quality management, health and safety management, project communications and stakeholders, and security management. The PMP must remain current throughout the performance period of the contract and be updated when any changes occur.

The PMP shall also present a detailed discussion of lines of communication. The contractor shall coordinate and receive approval from USACE prior to communicating with regulatory and external stakeholders with the exception of routine and necessary coordination with the landowners adjacent to the excavation site, if necessary, during the field efforts. All written correspondence (except for email) from USACE to any stakeholder will be signed by an

USACE representative unless otherwise directed. For other communications, the Contractor shall coordinate with the USACE COR or USACE Project Manager (PM). The USACE COR or PM will provide guidance to the

Contractor on communications with upper level management. If conference calls are required to adequately address concerns, issues, and/or questions, the Contractor shall be responsible for setting up conference call lines.

Contractual issues will be directed to the USACE COR or contracting officer (KO).

As part of the PMP, the Contractor shall, 1) develop and maintain a Work Breakdown Structure (WBS). The

Contractor shall submit a WBS in the PMP. The WBS shall be prepared in hard copy and electronic copy in

Microsoft Project version 2007 or 2010 (or compatible.) The WBS shall be provided to USACE monthly and upon request, and updated as required. The WBS shall include 100% of the work defined by this PWS and capture all field work elements and submittal development and deliverables. PMP shall describe the process by which the contractor will deliver weekly and monthly progress reports. Weekly and monthly progress reports shall be submitted during all fieldwork activities. During no fieldwork, or during demobilizations, the contractor shall submit only monthly progress reports.

The WBS shall fully support the technical approach and outline all activities and milestones defined at the appropriate level of detail, logically sequenced to support and manage completion of the performance objectives in the PWS and which allows for sufficient review time of deliverables. Additionally, the due dates for all payable deliverables shall be identified. Activities identified in the respective QASPs should be appropriately coded to allow for planning of QA inspections. USACE will make all payments after verification of milestone completion in accordance with the approved MPS. The Contractor will submit monthly invoices with appropriate back-up documentation no later than the 10th day of each month. Partial or bi-monthly invoicing is not allowed. All performance objectives must be completed within the allowable period of performance for the contract.

The draft PMP shall be submitted to the COR within 21 calendar days of Task Order award. USACE will provide comments within 15 calendar days. All comments shall be addressed by the Contractor and submit the Final PMP within 21 calendar days of receipt of USACE comments.

4.1.3. Quality Assurance/ Quality Control (QA/QC) Plan (DELIVERABLE) The Contractor shall prepare a separate QA/QC Plan that specifically addresses the work outlined in this PWS and what measures and techniques the contractor will be implementing to ensure the work performed is adequately monitored and verified for successful completion in accordance with the PWS requirements. The contractor’s quality control program is the means by which he/she is assured the work performed complies with the contract.

The Draft QA/QC Plan must be submitted to the PM and COR within 15 calendar days of task order award.

USACE will provide comments within 21 calendar days. All comments shall be addressed by the Contractor and submit the Final QA/QC Plan within 10 calendar days of receipt of USACE comments. The QA/QC Plan must be updated as necessary to remain current.

A list of required submittals and their review times are identified in PWS Attachment 1.

4.1.4. Progress Reports (DELIVERABLE)

The contractor shall submit to the COR and USACE PM a Monthly Progress Report by close of business the 10 th day of each month reporting the previous month’s activities. During all field work activities, the Contractor shall provide the COR and USACE PM a Weekly Progress Report in addition to the Monthly Progress Report, documenting the work in progress. The report for any week shall be provided by close of business on Monday of the following week. All reports must be as concise as possible, highlighting important progress, identifying potential issues (and a plan for their resolution) as well as key upcoming activities or events. When no fieldwork is in progress, or during demobilizations, the contractor shall submit only a Monthly Progress Report.

4.1.5. Accident Prevention Plan (APP) / Site Safety and Health Plan (SSHP) (DELIVERABLE) The contractor shall develop an Accident Prevention Plan (APP) / Site Safety and Health Plan (SSHP) for this contract as a standalone document and shall be submitted separately which will only be reviewed by USACE. Field activities shall not begin until the APP/SSHP has been reviewed and accepted by the COR. The AAP / SSHP shall be specific and shall address procedures to implement all of the activities described in the UFP-QAPP. The APP /

SSHP shall be submitted to the COR a minimum of 21 calendar days for review acceptance prior to starting field work; therefore, the contractor shall allow sufficient time for review and any revisions to the AAP/SSHP prior to mobilization. The contractor shall use the same APP / SSHP on all mobilizations, including corrective actions and update the Plan as area conditions warrant. In addition to the APP / SSHP, the contractor shall develop initial

Activity Hazards Analysis/Analyses (AHAs). The AHAs shall be posted in an area(s) available to all workers. The

AHAs shall be included in the APP. The APP / SSHP and AHAs shall be prepared in accordance with the most current edition of USACE Safety Manual, EM 385-1-1, as amended. A list of required submittals and their review times are listed in PWS Attachment 1.

Any changes to the risk assessment code (RAC) on an AHA must be submitted to USACE for approval before they are implemented by the field crew.

The Contractor shall ensure that its subcontractors, suppliers, and support personnel comply with the approved APP

/ SSHP. The USACE reserves the right to stop work under this contract for any violations of the APP / SSHP at no additional cost to the Government. Once the USACE verifies through the COR that a safety violation has been corrected, the Contractor will be authorized to continue work.

Engineering Manual 385-1-1, part 01.D "Accident Reporting and Recordkeeping" is required for the work identified in this PWS. The Contractor shall comply with all USACE guidance. The contractor shall report every accident, no matter how small or minor.

4.1.6. Contractor Manpower Reporting (CMR) (DELIVERABLE)

In accordance with FAR 4.1703, Section 743(a)(3) of Division C of Public Law 111-117, Office of Federal

Procurement Policy (OFPP) and the Revised Department of Defense Contractor Manpower Reporting Initiative, the contractor shall report required information for Services Contracts meeting specific thresholds and that are within four (4) prescribed Product Service Codes (PSCs). Contractors must log into their SAM profile accounts at www.SAM.gov to perform the contract reporting (also reference the SAM Quick Start Guide for Service Contract

Reporting).

SAM receives contract information from FPDS-NG and will enable reporting for entities with contracts that meet the required reporting thresholds and will auto-populate much of the required information for reporting. After logging into the SAM account, the Contractor will select ‘Entity Registration’ and then select ‘Service Contract

Reporting’. SAM will display the entities which have service contracts and meet the reporting criteria. Next, select

‘View by Entity’ to see the service contracts for each entity, then select ‘Add’ for the service contract against which a Service Contract Report is to be created. The Contractor will then be taken automatically to the Complete Service

Contract Report page. SAM automatically retrieves and displays the contract information.

http://www.sam.gov/

The required information to be entered is:

a. Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous Government fiscal year under the contract (this amount should include the prime and any subcontract amount).

b. Prime Contractor Hours Expended: Prime Contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 to calculate a

Full Time Employee (FTE) equivalent, displayed under the Prime Contractor Hours Expended as a Prime Contractor

FTEs.

c. Tier 1 Subcontractor Information: Report any required Tier 1 subcontractor information by selecting the ‘Add

Tier 1 Subcontract Information’ button.

Click ‘Submit’ once the report is completed. This saves the report and returns the user to the ‘Select Service

Contract’ page where another report can be created, or an existing report can be edited.

Any previously completed report can be edited as frequently as necessary until the end of the reporting period by selecting ‘View/Edit’ for the selected report.

Reporting must be completed annually by October 31 for each services performed under applicable services contracts during the preceding Government fiscal year (October 1-September 30).

4.2. Task 2 –Optimized UFP-QAPP (DELIVERABLE)

The Contractor shall prepare a draft and final Optimized UFP-QAPP and a Stormwater Pollution Prevention Plan

(SWPPP), in accordance with PWS Attachment 1 – Deliverables Schedule, to identify all the activities that will take place during the period of performance.

A draft Optimized UFP-QAPP shall be submitted to the USACE COR and the USACE PM for review and comments and the final Optimized UFP-QAPP shall be prepared based upon the resolution of the submitted comments and then submitted to the USACE COR and the USACE PM. Once final approval is given from the

USACE COR for the Optimized UFP-QAPP, the USACE shall submit it to the Texas Commission on

Environmental Quality (TCEQ) for review. The draft Optimized UFP-QAPP shall be submitted no later than 30 days from the date of kick off meeting. The Government will provide comments NLT 30 calendar days after submission of the Draft. The Final Optimized UFP-QAPP shall be submitted no later than 14 days from receipt of comments.

4.3. Task 3 – Explosive Safety Submission (DELIVERABLE)

The Contractor shall prepare a Draft Explosive Safety Submission (ESS) to be submitted to the USACE COR and

USACE PM within 60 calendar days of the kickoff meeting. USACE will review and provide comments to the

Draft within 30 calendar days. The Contractor shall address all comments and submit the Final ESS to the USACE

COR and USACE PM within 14 calendar days of receipt of comments. Once the Final ESS is approved by USACE, it will then be submitted to the DoD Explosive Safety Board (DDESB) for approval. The Contractor shall address any comments based on the DDESB review NLT 14 calendar days from receipt of comments.

Note: For purposes of this Example Project, assume no comments are received from USATCES and

DDESB on the Final ESS.

4.4. Task 4 – Excavation and Disposal (DELIVERABLE)

The Contractor shall perform excavation and disposal at the TNT contaminated site location in accordance with the proposed plan and decision document to remove 3,000 cubic yards of contaminated soil; for the purposes of this

Example Project, assume the excavation site dimension are approximately 100ft x 135ft x 6ft. The boundaries of the excavation site have been clearly marked; therefore, there are no survey requirements. The groundwater level is below the bottom of the excavation area.

The excavated soil shall be disposed of at a permitted facility authorized to handle the contaminated soil. The

Contractor will be required to submit to the USACE COR and USACE PM a copy of all associated waste manifests as well as a copy of all landfill receipts as evidence of proper soil disposal. For purposes of this project, the excavated contaminated soil shall be considered less than 10% contamination and therefore considered non-hazardous waste. No municipal solid waste (MSW) or any other contaminants are present at the site. The nearest licensed landfill is the New Boston Landfill, estimated to be 8 miles north of west of the site along U.S.

Highway 82, and approximately 12 miles west of Texarkana.

Note: For the purposes of this example, assume that the excavation site is grass covered with no trees, shrubs, utilities or other infrastructure. The boundaries of the excavation site have been clearly marked;

therefore, there are no survey requirements. The Contractor can assume the concentration of TNT is below

10% and can be disposed of at a landfill accepting non-hazardous waste. The Contractor can assume the landfill will accept the soil for use as top cover.

4.5. Task 5 – Sampling

The Contractor shall perform confirmatory sampling at the excavated site to ensure no residual contamination remains. Sampling shall occur prior to backfilling. A sampling report shall be prepared and submitted to the

USACE COR and USACE PM within 14 days after completion of the laboratory validation.

Note: For purposes of this Example Project, assume soil sampling resulted in no need for further excavation.

4.6. Task 6 – Backfill

The Contractor shall backfill the excavated area only with clean backfill soil that is available, at no cost to the contractor, within ¼ mile of the site. The backfill shall be placed in lifts no greater than 8” and shall be compacted to 95% Proctor (in accordance with ASTM D698) and the site graded to match the original condition. The upper compacted layer may be compacted to less than 95%, if necessary, to achieve the required re-vegetation rate identified in Task 6. All Proctor tests shall be in accordance with American Society for Testing and Materials

(ASTM) guidelines D698. The results of the compaction test shall be submitted to the USACE COR and the

USACE PM within 7 days of the completion of the test. This information will also be included in the final report.

The contractor shall invoice only for the actual quantity removed, based on a survey of the completed open excavation(s). The contractor shall provide evidence that the soil was disposed of at a landfill licensed to accept the contaminated soil. The contractor shall assume the soil is non-hazardous.

Note: For purposes of this Example Project, assume known clean soils exist within ¼ mile of the project and is suitable for re-vegetation purposes. Assume no sampling is required for borrow soils. The excavated waste is considered to be less than 10% TNT and therefore considered non-hazardous waste.

4.7. Task 7 – Re-Vegetation

The Contractor shall apply a grass seed mixture native to the Texarkana (can be found via an internet search) area to completely re-vegetate the excavated area to prevent future erosion. The Offeror must achieve a vegetation survival rate of at least 70% coverage of the excavation site. The vegetative cover must be established before payment for this task is approved. After establishment of the vegetation, the SWPPP will be terminated by the contractor.

4.8. Task 8 – Final Response Action Completion Report (RACR) & Site Closure

The Contractor shall prepare a Draft RACR to be submitted to the USACE COR and USACE PM within 60 calendar days of completion of field activities. USACE will review and provide comments to the Draft within 21 calendar days. The Contractor shall address all comments and submit the Final RACR to the USACE COR and

USACE PM within 14 calendar days of receipt of comments. Once the Final RACR is approved by USACE, the

Contractor shall then submit it to TCEQ for review.

Note: For purposes of this Example Project, assume no comments are received from TCEQ on the Final

RACR.

4.9. Task 9 – Final After-Action Report (AAR)

The Contractor shall prepare a Draft AAR to be submitted to the USACE COR and USACE PM within 60 calendar days of completion of field activities. USACE will review and provide comments to the Draft within 21 calendar days. The Contractor shall address all comments and submit the Final AAR to the USACE COR and USACE PM within 14 calendar days of receipt of comments; USACE will coordinate AAR review by EMCX and USATCES.

Once the Final AAR is approved by USACE, it will then be submitted to DDESB to be utilized in closing out the

ESS.

Note: For purposes of this Example Project, assume no comments are received from EMCX, USATCES or

DDESB on the Final AAR.

5.0. KEY PERSONNEL

In accordance with the Base IDC Section C SOW, Section 4, the contractor shall designate a Project Manager (PM) for this task order. The designated PM shall meet the qualifications identified in the Section C SOW and will be responsible for successfully achieving the performance objectives of this PWS. The name of this person and an alternate, who shall act for the contractor when the Project Manager is absent, shall be designated in writing to the

Contracting Officer. The Project Manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this task order.

6.0. PERIOD OF PERFORMANCE

The Period of Performance is 365 calendar days from the date of task order award.

7.0. GENERAL INFORAMTION

7.1. Quality Control

The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS (see also PWS Section 4.1.3). The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.

7.2. Quality Assurance

The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality

Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

7.3. Government Holidays

The following holidays will not be worked:

New Year’s Day Labor Day

Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day

Memorial Day Thanksgiving Day

Independence Day Christmas Day

7.4. Hours of Operation

The contractor may work onsite between the hours of 7:00am to 5:00pm Monday through Friday.

7.5. Place of Performance

The work to be performed under this contract will be performed at LSAAP, Texarkana, Texas.

7.6. Type of Contract

The government’s intent is to award a Firm-Fixed-Price, performance-based task order.

7.7. Protection of Property

The Contractor shall be responsible for any damage caused to Government property resulting from negligence or willful misconduct by its employees, sub-contractors, or suppliers. Any damage must be repaired promptly at no additional cost to the Government to the satisfaction of the Contracting Officer. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost the

Contractor in accordance with FAR clauses 52.236-9 and 52.237-2.

7.8. Contractor Travel

The contractor is responsible for travel associated with executing the PWS requirements. Contractor will be authorized travel expenses consistent with the Joint Travel Regulation (JTR).

7.9. Periodic Progress Meetings

The Contracting Officer or Contracting Officers Representative (COR) may require the Contractor to meet periodically to review the Contractor's performance. These meetings would be outside regular project status meeting conducted with the Project or Technical Manager. At these meetings the Contracting Officer or COR will apprise the contractor of how the Government views the contractor's performance and the contractor will apprise the

Government of any problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

7.10. Contracting Officer Representative (COR)

The COR will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor contractor's performance and notifies both the KO and contractor of any deficiencies;

coordinate availability of government furnished property (if applicable); and provides area entry of contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms or conditions of the contract.

7.11. Data Rights

The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the

Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

7.12. Public Affairs

The contractor shall not publicly disclose any data generated or reviewed under this contract unless specifically authorized. The contractor shall refer all requests for information concerning site conditions to the COR. All reports and other information generated under this PWS shall become the property of the Government, and distribution to any other source by the Contractor is prohibited unless authorized by the Contracting Officer.

8.0. SECURITY REQUIREMENTS

8.1. Physical Security

At the close of each work period, all contractor facilities, equipment, and materials shall be secured. Contractors, along with all subcontractors, shall display company signs on their vehicles at all times while on government property.

8.2. Identification of Contractor Employees

The Contractor and its sub-contractors shall provide each of its employees who will be involved in the performance of this contract an identification (ID) badge. The ID badge shall clearly display the Contractor’s name and the employee’s name and color photograph. It is the Contractor’s responsibility to ensure that all Contractor and sub-contractor personnel wear their ID badge at all times when performing work under this contract. Unless otherwise specified in the contract, each Contractor and sub-contractor employee shall wear the ID badge in a conspicuous place on the front of their clothing and above their waist, except when safety or health reasons prohibit such placement. This requirement is in addition to any Government facility security provisions that require that a

Government-issued security badge also be worn.

Contractor personnel shall clearly identify themselves to all attendees as a Contractor employee before the commencement of meetings with Government or other Contractor personnel. Contractor personnel shall clearly and immediately identify themselves as a Contractor employee when placing, answering or participating in telephone/VTC conversations with Government or other Contractor personnel.

When Contractor personnel send e-mail messages from or to a Government-owned computer, they shall include a signature block that includes their employer’s name and the employee’s full name and e-mail address.

Each of the requirements set forth above, must be included in all sub-contracts at any tier.

9.0. CERTIFICATION AND APPROVAL OF PROJECT MILESTONES AND DELIVERABLES

The COR will be responsible for contract management, inspection, oversight, review, and approval activities.

Certification and approval of project milestones by the COR is necessary before approval of invoices and distribution of payments.

10.0. PAYMENT REQUESTS (DELIVERABLE)

Monthly invoices must be submitted by the 10th of every month. Partial payment for established payment milestones is not permissible. Upon completion of one or more milestones, the contractor may submit payment requests no more frequently that monthly, with corresponding documentation attached, via email to the USACE

Regional Planning and Environmental Center (RPEC) – Tulsa:

USACE Regional Planning and Environmental Center - Tulsa

E-mail: Invoices-RPEC@usace.army.mil

11.0. GOVERNMENT POINT OF CONTACT (POC)

Contract Specialist: Joshua Hope

Tulsa District Corps of Engineers

CECT-SWT

2488 East 81st Street

Tulsa, OK 74137-4290

(918) 669-7460

Joshua.D.Hope@usace.army.mil

Additional government points of contact will be provided after task order award. All written correspondence pertaining to this Performance Work Statement should be addressed to the Contract Specialist unless otherwise directed by the KO. Written directions or clarifications to this Performance Work Statement may only be given to the contractor by the KO or contract specialist. A change in Government Points of Contact during the period of performance for Task Order execution does not constitute a change to the PWS.

12.0. SUSTAINABILITY

The contractor shall meet the recycled paper content requirements set forth by EPA for post-consumer recycled copy paper. For identifying Greener Paper and environmental attributes to consider when selecting copy paper and other items to comply with EPA-Designated Recovered Material Products, please visit https://www.epa.gov/greenerproducts/identify-greener-products-and-services .

The contractor shall also meet USDA-Designated Bio-preferred Program requirements for products such as fertilizers, mulch and erosion control. For minimum bio-based contents to meet USDA guidance for products please visit https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml and select the appropriate product category.

See contract clauses 52.204-4, 52.223-2, and 52.223-17.

mailto:Joshua.D.Hope@usace.army.mil https://www.epa.gov/greenerproducts/identify-greener-products-and-services https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml

13.0. ATTACHMENTS

Attachment 1– Deliverables Schedule

ATTACHMENT 1 – DELIVERABLES SCHEDULE

Deliverable

Number Deliverable Frequency

# of

Copies

Medium/Form at Submit To

1 Kick-off Meeting

Minutes

(PWS Section

4.1.1)

7 calendar days after kick-off meeting

1 Electronic

(Adobe.pdf)

All meeting participants

2 Project

Management Plan

(PMP)

(PWS Section

4.1.2)

Draft PMP-21 calendar days after award

Final PMP-21 calendar days after receipt of comments to the Draft

Electronic (MS

Word for Draft, MS Word and

.pdf for Final)

USACE COR,

USACE PM

3 Quality

Assurance/Quality

Control Plan

(QA/QC)

(PWS Section

4.1.3)

Draft QA/QC-15 calendar days of award

Final QA/QC-10 calendar days of receipt of comments to the Draft

Updates as necessary

Electronic (MS

Word for Draft, MS Word and

.pdf for Final, updates in MS

Word and .pdf)

USACE COR,

USACE PM

4 Accident

Prevention Plan

(APP)/Site Safety and Health Plan

(SSHP)

(PWS Section

4.1.5)

Minimum of 21 calendar days prior to site mobilization

1 Electronic (MS

Word for Draft, MS Word and

.pdf for Final)

USACE COR

5 Progress Reports

(PWS Section

4.1.4)

Monday of the following week during which field work was performed.

Otherwise, 10th day of every month

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM

6 Monthly Invoice

(PWS Section

10.0)

10th of every month 1 Electronic

(Adobe.pdf)

Identified

USACE POCs

7 Draft Optimized

UFP-QAPP

(PWS Section 4.2)

30 calendar days after kickoff meeting

Electronic

(Adobe .pdf)

8 Final Optimized

UFP-QAPP

(PWS Section 4.2)

14 calendar days after receipt of comments to the

6 (2

Copies to

TCEQ)

Hard Copy

USACE PM,

9 Draft SWPPP

(PWS Section 4.2)

Per the approved UFP-

QAPP

1 Electronic

(Adobe .pdf)

10 Final SWPPP

(PWS Section 4.2)

Per the Approved UFP-

QAPP

2 Hard Copy USACE PM, TCEQ

11 Draft ESS

(PWS Section 4.3)

60 calendar days after kickoff meeting

1 Electronic

(Adobe .pdf)

ATTACHMENT 1 – DELIVERABLES SCHEDULE

Deliverable

Number Deliverable Frequency

# of

Copies

Medium/Form at Submit To

12 Final ESS

(PWS Section 4.3)

14 calendar days after receipt of comments to the

Draft

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM

13 Excavated Soil

Waste Manifests, Landfill Receipts

(PWS Section 4.4)

Upon completion of excavation and disposal activities

1 Hard Copy USACE COR, USACE PM

14 Sampling Report

(PWS Section 4.5)

14 calendar days after laboratory validation

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM

15 Compaction Test

Report

(PWS Section 4.6)

7 calendar days after completion of the test

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM

16 Draft RACR

(PWS Section 4.8)

60 calendar days after completion of field activities

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM

17 Final RACR

(PWS Section 4.8)

14 calendar days after receipt of comments on the

Draft

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM,

TCEQ

17 Draft AAR

(PWS Section 4.9)

60 calendar days after completion of field activities

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM

18 Final AAR

(PWS Section 4.9)

14 calendar days after receipt of comments on the draft AAR

1 Electronic

(Adobe .pdf)

USACE COR,

USACE PM,

DDESB

19 Contractor

Manpower Report

(PWS Section

4.1.6)

By 31 October for each year in which any type of work was performed for the year ending 30 September

1 Electronic

(Adobe .pdf)

The following have been deleted:

AMDMT 0002 EXAMPLE PROJECT PWS

(End of Summary of Changes)