ATTACHMENT L-1
MILESTONE PAYMENT SCHEDULE WITHOUT COST

$50M SDVOSB ERS MEGA MATOC

EXAMPLE PROJECT

EXCAVATION AND DISPOSAL AREA

TNT CONTAMINATED AREA

LSAAP, TEXARKANA, TEXAS

Solicitation #W912BV-21-R-0025
Contract #TBD

16 March 2021

Offeror:

INSTRUCTIONS FOR COMPLETION OF ATTACHMENT L-1:

1) Ensure the Offeror's name is provided in the cell above.

2) DO NOT make any changes to this document.

3) Offerors MAY NOT propose alternate Milestones to the CLINs/sub-CLINs identified below;

4) Enter the Projected Start and Completion Dates for each CLIN/sub-CLIN ONLY (green cells in columns C and D).

5) Manually enter the dates, do not link the Unit Price to other spreadsheets.

**Non-compliance with the above instructions will result in the assignment of a 'Deficiency' and the Offeror's proposal being removed from further consideration for contract award.

IMPORTANT: Offerors MUST submit the Excel version of the Attachment L-1 provided with the RFP. Failure to do so will result in the assignment of a 'Deficiency' and, therefore, the Offeror's proposal being removed from further consideration for contract award.

CLINMILESTONE DESCRIPTIONProjected Start Date
(MM/DD/YY)Projected Completion Date

(MM/DD/YY)

TASK 1 - PROJECT MANAGEMENT
0001Kick-Off Meeting via teleconference within 15 calendar days of contract award
0002Project Management Plan (PMP)
0002AADraft PMP
0002ABFinal PMP
0003Quality Assurance/Quality Control (QA/QC) Plan
0003AADraft QA/QC Plan
0003ABFinal QA/QC Plan
0004Monthly Progress Reports
0005Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)
0006Annual Contractor Manpower Reporting
TASK 2 - UFP-QAPP
0007Optimized UFP-QAPP
0007AADraft UFP-QAPP
0007ABFinal UFP-QAPP
0008Storm Water Pollution Prevention Plan (SWPPP)
0008AADraft SWPPP
0008ABFinal SWPPP
TASK 3 - FINAL ESS
0009Explosive Safety Submission (ESS)
0010Draft ESS
0011Final ESS
TASK 4 - EXCAVATION AND DISPOSAL
0010Excavation and Disposal of Contaminated Soil
TASK 5 - EXCAVATION SITE SAMPLING
0011Sampling
TASK 6 - EXCAVATION SITE BACKFILL
0012Backfill
TASK 7 - EXCAVATION SITE RE-VEGETATION
0013Re-Vegetation
TASK 8 - RACR, NFA, SITE CLOSURE
0014Response Action Completion Report (RACR)
0014AADraft RACR
0014ABFinal RACR
TASK 9 - AAR
0015After Action Report (AAR)
0015AADraft AAR
0015ABFinal AAR