Sheet1

ATTACHMENT L-1
MILESTONE PAYMENT SCHEDULE WITHOUT COST

$40M HubZone ERS MEGA MATOC

EXAMPLE PROJECT

EXCAVATION AND DISPOSAL AREA

FORMER FUEL STORAGE AREA

COLLEGE STATION, TEXAS

Solicitation #W912BV-21-R-0023
Contract #TBD

Amendment #0003 6 July 2021 2 March 2021

Offeror:

INSTRUCTIONS FOR COMPLETION OF ATTACHMENT L-1:

1) Ensure the Offeror's name is provided in the cell above.

2) DO NOT make any changes to this document.

3) Offerors MAY NOT propose alternate Milestones to the CLINs/sub-CLINs identified below;

4) Enter the Projected Start and Completion Dates for each CLIN/sub-CLIN ONLY (green cells in columns C and D).

5) Manually enter the dates, do not link the Unit Price to other spreadsheets.

**Non-compliance with the above instructions will result in the assignment of a 'Deficiency' and the Offeror's proposal being removed from further consideration for contract award.

IMPORTANT: Offerors MUST submit the Excel version of the Attachment L-1 provided with the RFP. Failure to do so will result in the assignment of a 'Deficiency' and, therefore, the Offeror's proposal being removed from further consideration for contract award.

CLINMILESTONE DESCRIPTIONProjected Start Date
(MM/DD/YY)Projected Completion Date

(MM/DD/YY)

TASK 1

PROJECT MANAGEMENT

0001Kick-Off Meeting via teleconference within 15 calendar days of contract award
0002Project Management Plan (PMP)
0002AADraft PMP
0002ABFinal PMP
0003Quality Assurance/Quality Control (QA/QC) Plan
0003AADraft QA/QC Plan
0003ABFinal QA/QC Plan
0004Monthly Progress Reports
0005Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)
0006Annual Contractor Manpower Reporting

-Period ending 30 Sep 2022 -Period ending 30 Sep 2023

TASK 2

OPTIMIZED UFP-QAPP & SWPP

0007Optimized UFP-QAPP
0007AADraft UFP-QAPP
0007ABFinal UFP-QAPP
0008Storm Water Pollution Prevention Plan (SWPPP)
0008AADraft SWPPP
0008ABFinal SWPPP

TASK 3

EXCAVATION AND DISPOSAL

0009 Excavation and Disposal of Contaminated Soil

TASK 4

SAMPLING

0010 Sampling

TASK 5

BACKFILL

0011 Backfill

TASK 6

RE-VEGETATION

0012 Re-Vegetation

TASK 7

FINAL RESPONSE ACTION COMPLETE REPORT (RACR)

0013Response Action Completion Report (RACR)
0013AADraft RACR
0013ABFinal RACR