This document contains a Milestone Payment Schedule template and Statement of Work for a Multiple Award Task Order Contract solicitation for environmental remediation services. The U.S. Army Corps of Engineers, Tulsa District will issue solicitation number W912BV19R0022 to award up to five firm-fixed price IDCs with a maximum shared capacity of $45 million. The NAICS code is 562910 with a small business size standard of 750 employees. Services include preparation of work plans, field investigations, monitoring, data management, risk assessments, engineering support, remedial actions, construction support, and project programming. The solicitation will be issued on February 21, 2019 via FedBizOpps with proposals due March 26, 2019. The base period of performance is three years with a two-year option. The set-aside is for 100% small business.

Amendment No. 0002, Attachment L-1, Milestone Payment Schedule without Cost excel version.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

ATTACHMENT L-1
MILESTONE PAYMENT SCHEDULE WITHOUT COST

$45M ERS MEGA MATOC

EXAMPLE PROJECT

Solicitation #W912BV-19-R-0022
Contract #W912BV-19-D-TBD

Amendment #0002 27 March 2019 8 January 2019

NOTES: 1) Offerors shall complete and return this Attachment L-2 Excel version with their Volume II proposal; 2) Offerors MAY NOT propose alternate Milestones by supplementing, or adding to, the CLINs identified below; 3) DO NOT make any changes to the spreadsheet cells or formulas below; 4) enter information in the green cells only (Projected Start and Completion Dates)

CLINMILESTONE DESCRIPTIONExpiration Date to Exercise OptionProjected Schedule Start Date (MM/DD/YR)Projected Completion Date (MM/DD/YR)
TASK 1 - PROJECT MANAGEMENT
0001Kick-Off Meeting via teleconference within 15 calendar days of contract awardAt Award
0002Project Management Plan (PMP)At Award
0003Quality Assurance/Quality Control (QA/QC) PlanAt Award
0004Monthly Progress ReportsAt Award
0005Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)At Award
0006Annual Contractor Manpower ReportingAt Award
TASK 2
0007Optimized UFP-QAPPAt Award
0008Stormwater Pollution Prevention Plan (SWPPP)At Award
TASK 3
0009Excavation and Disposal of Contaminated SoilAt Award
TASK 4
0010SamplingAt Award
TASK 5
0011BackfillAt Award
TASK 6
0012Re-vegetationAt Award
TASK 7
0013Final RACRReport & Site ClosureAt Award