W912BV18R0059-0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SIte_Visit_-_MEI_Sign-In_Sheet_at_RS_Kerr.pdf | ||
| WW912BV18R0059_0001_-_RS_Kerr_MEI_-_Complete.pdf | ||
| CORRECTION_to_Site_Visit_Information_for_W912BV19R0059_-_R.S._Kerr_MEI.pdf | ||
| Kerr_MEI_Specifications_3-20-19_Solicitation_Revisied.pdf | ||
| Contract_Drawings_RKP-1.004_MEI_022619.pdf | ||
| Kerr_MEI_Specifications_3-20-19_Solicitation_RFP_Final.pdf | ||
| COMBINED_REFERENCE_DRAWINGS_062918.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
ROBERT S. KERR LOCK AND DAM 15 MODERNIZATION OF ELECTRICAL INFRASTRUCTURE
Amendment 0002 is hereby issued to address supplemental bidders' inquiries and Government responses, provide PCB test results, and replace specifications and drawings as annotated on the continuation page.
The proposal due date is extended from 2:00PM CST on 10 June 2019 to 2:00PM CST on 18 June 2019. All other terms and conditions remain unchanged.
Contract Specialist: Julie S. Hill, 918-669-7699 or julie.s.hill@usace.army.mil.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Jun-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BV18R0059
X 9B. DATED (SEE ITEM 11)
18-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Jun-2019
CODE
CONTRACTING DIV
US ARMY CORPS OF ENGINEERS, TULSA DISTRICT
2488 E. 81ST STREET
TULSA OK 74137-4290
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SUMMARY OF CHANGES
AMENDMENT 0002
RFP NO. W912BV18R0059
MODERNIZATION OF ELECTRICAL INFRASTRUCTURE
ROBERT S. KERR LOCK AND DAM 15, OKLAHOMA
Standard Form (SF) 30, Block 14 (continuation):
The proposal documents shall be revised as follows:
Supplemental Bidders’ Inquiries and Government Responses dated June 5, 2019 are provided for clarification. The specifications and drawings have been amended when necessary to incorporate the supplemental responses.
PCB Test Results dated 2-6-2015 are provided for information only in response to a bidder’s inquiry. Results indicate all PCBs are below action levels.
SPECIFICATIONS
Delete previously issued section numbers as follows and replace with new sections of the same number attached hereto:
01 11 00.00 26 01 22 00.00 26 02 82 13 (with Asbestos Sampling Memorandum) 02 83 13 03 60 00.01 26 26 05 00.00 26 26 08 01.00 26 26 13 13.00 26 41 22 23.19
Paragraphs containing revisions are highlighted by bold text.
DRAWINGS
Delete previously issued Sheet IDs as follows and replace with new Sheet IDs attached hereto:
E-601 E-602 E-603 E-801 E-802 E-803 E-804
END OF SUMMARY OF CHANGES – AMENDMENT 0002
SUPPLEMENTAL BIDDERS INQUIRIES AND GOVERNMENT RESPONSES
JUNE 5, 2019
• Specification Section 02 42 00.00 26 Paragraph 3.2.1 states all insulating oil and piping in the powerhouse shall be removed up to the capping location in the Paint & Grease Room and Oil Purification Room as indicated in the plans and specifications. What is the total quantity of oil that is to be removed on the project, from the transformers, tanks, piping, etc.? Should the contractor assume this oil is above or below 50 ppm? This has a large impact on pricing and must be known prior to bid.
o The existing generator step up transformers each contain 6,350 gallons as shown on the transformer nameplates in the reference drawing package. Assume 1000 gallons in the tanks for a project total of 13,700 gallons. All oil is below 50 ppm as shown in the attached oil test reports. See updated section 01 22 00.00 26 item 0030.
• The existing units are very large in size and weight. Will the government allow the units to be partially disassembled onsite to allow for smaller over the road loads. This will greatly reduce overall project costs.
o Can remove bushings, surge arrestors, and coolers, and other misc. equipment. No salvage of transformers onsite. See updated section 26 05 00.00 26 paragraph 3.2.7, 3.2.8.
• The new cable schedule calls for 15kV #6 cable to be installed. #2 is the smallest 15kV cable that we can find. Should we #2 for this circuit?
o The cable and conduit schedule has been updated to use #2 15KV cable. See updated E- 801, 802
• Section 26 05 19.00 26 “Insulated Wire and Cable” paragraph 2.2.5.1 provides two jacket options. Neither of the options are stock items for cable manufacturers and must be ordered with minimum quantities. This contract requires 31 different conductor/size configuration cables that would require a minimum order. This would lead to thousands of feet of unneeded cable at additional unnecessary cost to the contract. We propose substituting a thermoplastic CPE jacket which is a common stock item for cable manufacturers that can be ordered in exact quantities required by the project.
o The cable and conduit schedule has been updated reduce the number of cables. See updated E-801- 804. Thermoplastic will not be allowed.
• Is a Seismic Certification, including shake table testing, required for the metal enclosed bus duct?
o The bus duct is required to have a seismic certification in accordance with section 13 48
00.00 26 paragraph 1.4.4 which allows testing or analysis.
• The drawings indicate that the fire pump controller is to be furnished under another contract. However, the new fire and jockey pumps supplied under this contract will require specific controllers. Should the contractor provide and install these controllers under this contract? If by another contract, they would need to be coordinated with the new pumps and installed prior to or at the same time as the pumps.
o The Fire pump is will be supplied and installed under another contract. This contract requires connecting to the controller.
• How is the contractor to get the new 6,000 gallon tanks into the existing Oil Purification Room. Drawing MD104 says to enlarge the doorway of the insulating oil room for the replacement of the six tanks in that room, but doesn’t address the two in the oil purification room. Should the contractor also plan on enlarging the door to the oil purification room?
o The contractor will need to construct the tanks in the oil storage room. Enlarging the door will not be allowed.
SUPPLEMENTAL BIDDERS INQUIRIES AND GOVERNMENT RESPONSES
JUNE 5, 2019
• Spec section 26 13 13.00 26 2.2.2 shows breaker ratings to be 2000A. Drawing E-602 shows generator breakers to be 3000A. Please clarify.
o All 15kV breakers are 2000A. See updated E-601, 602, 603
• Drawing E-603 does not indicate amp rating for breakers XJ01, 02, 03, 04, Please clarify required breaker rating.
o All 15kV breakers are 2000A. See updated E-601, 602, 603
• Spec section 26 13 13.00 26 2.2.2 states that all breakers shall be a generated rated breaker. Please clarify that this is required for the other breakers in SJ2 and SJ3 (Lock switchgear, SS transformer).
o All 15KV breakers are generator rated breakers so all breakers are interchangeable.
• If 3000A rated breakers are required, then it is not possible to have an auxiliary section (PT) above the breaker. The requirement for 80” high structure does not allow physical space for an aux compartment with a 3000 amp breaker in a single structure. The 3000A breaker is a taller breaker than a 2000A breaker. In order to keep the same footprint, SJ2 and SJ3 would require either the Lock Swgr or SS XFMR breaker to be 2000A or less. SJ1 and SJ4 would meet the width requirement with putting all PT’s in opposite structure from breaker.
o All 15KV breakers are 2000A. 80” is to upgrade operation and maintenance access to equipment from the original switchgear. The maximum depth is 92 inches. See updated section 26 13 13.00 26 paragraph 2.3.2.
• Specification Section 41 22 23.19 Paragraph 2.2 calls out a Harrington RH05U-52D4P-4-V model or equal. The Harrington unit and its equals are not available with 60-minute rated hoist or trolley motors as required in paragraph 2.6. In addition to this a Class C crane would typically have a 30-minute rated motor on both the hoist and trolley and be well within the customer’s usage unless it was a very long lift hoist with a slow lifting speed. If the USACE would like 60-min rated motors on both the hoist and the trolley we can provide them, albeit not with a Harrington model or equal. Please advise on how to proceed.
o Section 41 22 23.19 paragraph 2.6 has been updated to a 30 minute duty rating.
• Specification Section 41 22 23.19 Paragraph 2.8 requires provision of a 3 position spring return bypass key to lower the hoist once it reaches the weighted limit switch (last line of defense before a two blocking condition). This is not something you’d see with this duty hoist and it cannot be provided with the Harrington or equal unit. We can provide it, but it will be with a heavier duty, much more expensive hoist. Please advise on how to proceed.
o Section 41 22 23.19 paragraph 2.8 has updated the limit switch requirements. A 3 position spring return switch is not required.
• Please clarify the intent of the 30 day period in paragraph 3.4 of Section 26 08 01.00 26. How many days of assistance with the government require for commissioning assistance? Since paragraph 3.4 states the government will have 30 days to perform their commissioning, should we assume there will be a 30 day period after finishing the first unit before we can begin the second unit?"
o The 30 day period has been updated to 7 days in section 26 08 01.00 26 paragraph 3.4.
The Contractor has to finish the first unit before beginning the second unit.
0000001UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB CLEAN TANK CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
08/05/1991 45 0.026 32.0 0.5 0.870 0.010 0.039 45 0.00* Good Retest 1 YearClear
05/16/2013 56 0.030 28.2 1.0 0.880 21 Good Retest 1 YearClear
02/06/2015 51 0.020 30.9 1.0 0.880 0.028 1.426 49 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705098 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0.05 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
Nashville, TN 37210
615-255-3700 800-873-8774
0000002UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
2 CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
50,000
13,200
TRANS
Oil
7001432
WESTINGHOUSE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
OPERATING
TEMP
PEAK
TEMP
FLUID
LEVEL
PSI
VAC PAINT BUSHINGS ENVIR. LEAKS / COMMENTS
RECOMMENDED
SERVICE
ACTUAL
TEMP
VISUAL INSPECTION DATA
6308/30/2007
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
08/30/2007 56 0.016 31.3 1.0 0.880 31 Good Retest 1 YearClear
06/24/2009 28 0.024 37.3 1.0 0.879 16 Good Retest 1 YearClear
05/16/2013 42 0.016 30.8 1.0 0.880 0.026 0.630 30 Good Retest 1 YearClear
02/06/2015 48 0.022 35.0 1.0 0.878 0.025 1.321 23 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705099 <1
DATE
HYDROGEN
H2
METHANE
CH4
ETHYLENE
C2H4
ETHANE
C2H6
ACETYLENE
C2H2
CARBON
MONOXIDE
TOTAL
COMB. GAS
CARBON
DIOXIDE
OXYGEN
O2METHOD
DISSOLVED GAS ANALYSIS ASTM D3612 (PPM)
TOTAL
DISV. GAS%
NITROGEN
N2 C2H2/C2H4 CH4/H2 C2H4/C2H6
Rogers Ratio
08/30/2007 2 35 1 34 0 40 2302 105016 3006 112 11.0D3612A 0.0 17.5 0.0
06/24/2009 2 6 0 14 0 12 1451 179466 2876 34 18.4D3612A 0.0 3.0 0.0
05/16/2013 0 1 0 8 0 6 892 79781 5579 15 8.6D3612C 0.0 0.0 0.0
COMMENT: 02/15 Low level combustible gases indicate unit operating properly. Retest 1 year.
02/06/2015 0 0 0 4 0 3 381 68821 1481 7 7.1D3612C 0.0 0.0 0.0
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000002UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
2 CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
COMMENT:
0 0 0 0 0 0 0
05/13 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
05/16/2013
HMF FOL FAL ACF MEF TOTAL PPB CLASSIFICATIONDATE
FURAN ANALYSIS ASTM D5837 (PPB)
0 0 19 1 0 20 Acceptable08/30/2007
0 2 15 0 2 19 Acceptable06/24/2009
0 0 16 0 0 16 Acceptable05/16/2013
0 0 14 0 15 29 Acceptable02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000003UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
XFMR CLEAN TANK CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
OTHER
Oil
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
08/05/1991 32 0.018 36.2 0.5 0.875 0.015 0.080 41 0.00* Bad RT/DehydrateClear
05/16/2013 43 0.024 28.1 1.0 0.880 47 Bad DehydrateClear
02/06/2015 40 0.032 33.1 1.0 0.878 31 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705100 <1
DATE
HYDROGEN
H2
METHANE
CH4
ETHYLENE
C2H4
ETHANE
C2H6
ACETYLENE
C2H2
CARBON
MONOXIDE
TOTAL
COMB. GAS
CARBON
DIOXIDE
OXYGEN
O2METHOD
DISSOLVED GAS ANALYSIS ASTM D3612 (PPM)
TOTAL
DISV. GAS%
NITROGEN
N2 C2H2/C2H4 CH4/H2 C2H4/C2H6
Rogers Ratio
COMMENT: 08/91 Low level combustible gases indicate unit operating properly. Retest 1 yr.
08/05/1991 8 0 0 0 0 125 1005 91189 3195 133 9.6D3612A 0.0 0.0 0.0
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0.09 0 0 0 0 0.1105/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000004UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
1 CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
50,000
TRANS
Oil
7001433
WESTINGHOUSE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
OPERATING
TEMP
PEAK
TEMP
FLUID
LEVEL
PSI
VAC PAINT BUSHINGS ENVIR. LEAKS / COMMENTS
RECOMMENDED
SERVICE
ACTUAL
TEMP
VISUAL INSPECTION DATA
6308/30/2007
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
08/30/2007 52 0.014 32.0 0.5 0.879 31 Good Retest 1 YearClear
06/24/2009 31 0.024 31.4 0.5 0.878 10 Good Retest 1 YearClear
05/16/2013 48 0.012 34.6 0.5 0.880 0.014 0.322 21 Good Retest 1 YearClear
02/06/2015 52 0.018 36.1 0.5 0.876 11 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705101 <1
DATE
HYDROGEN
H2
METHANE
CH4
ETHYLENE
C2H4
ETHANE
C2H6
ACETYLENE
C2H2
CARBON
MONOXIDE
TOTAL
COMB. GAS
CARBON
DIOXIDE
OXYGEN
O2METHOD
DISSOLVED GAS ANALYSIS ASTM D3612 (PPM)
TOTAL
DISV. GAS%
NITROGEN
N2 C2H2/C2H4 CH4/H2 C2H4/C2H6
Rogers Ratio
08/30/2007 3 2 0 4 0 11 1868 101837 3888 20 10.8D3612A 0.0 0.7 0.0
06/24/2009 3 2 0 4 0 17 1748 235163 9983 26 24.7D3612A 0.0 0.7 0.0
05/16/2013 0 2 0 5 0 13 2112 82456 4854 20 8.9D3612C 0.0 0.0 0.0
COMMENT: 02/15 Low level combustible gases indicate unit operating properly. Retest 1 year.
02/06/2015 0 1 0 5 0 4 1338 72903 1085 10 7.5D3612C 0.0 0.0 0.0
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000004UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
1 CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
COMMENT:
0 0 0 0 0 0 0
05/13 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
05/16/2013
HMF FOL FAL ACF MEF TOTAL PPB CLASSIFICATIONDATE
FURAN ANALYSIS ASTM D5837 (PPB)
0 0 14 0 1 15 Acceptable08/30/2007
0 2 15 0 2 19 Acceptable06/24/2009
0 0 18 0 0 18 Acceptable05/16/2013
0 0 10 0 8 18 Acceptable02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000005UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 12 A PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
A/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 36 0.032 31.4 1.0 0.870 0.008 0.15 47 Good Retest 1 YearClear
08/11/1999 29 0.020 30.0 1.0 0.880 0.01 0.29 40 Good Retest 1 YearClear
05/16/2013 50 0.034 26.9 1.0 0.880 55 Bad RT/DehydrateClear
02/06/2015 51 0.040 26.7 1.0 0.876 33 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705102 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 0.0605/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000006UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 12 B PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
B/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 58 0.030 32.6 1.0 0.870 0.020 0.030 52 Bad DehydrateClear
08/11/1999 27 0.020 31.2 0.5 0.880 0.01 0.32 47 Good Retest 1 YearClear
05/16/2013 47 0.036 26.1 1.0 0.879 56 Bad RT/DehydrateClear
02/06/2015 40 0.036 27.8 1.0 0.876 39 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705103 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000007UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 12 C PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
C/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 54 0.030 29.5 1.0 0.880 0.012 0.024 55 Bad DehydrateClear
08/11/1999 25 0.016 29.3 0.5 0.880 0.01 0.45 39 Good Retest 1 YearClear
05/16/2013 52 0.032 27.5 1.0 0.880 55 Bad RT/DehydrateClear
02/06/2015 40 0.030 28.2 1.0 0.878 42 Good Retest 1 YearS/Cb
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705104 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000008UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 22 A PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
A/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 33 0.360 29.5 1.0 0.880 0.006 0.032 49 Good Retest 1 YearClear
08/11/1999 30 0.020 32.6 1.0 0.880 0.01 0.28 44 Good Retest 1 YearClear
05/16/2013 52 0.028 26.7 1.0 0.879 56 Bad RT/DehydrateClear
02/06/2015 51 0.028 28.1 1.0 0.877 38 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705105 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 0.0705/16/2013
COMMENT:
0 0 0 0 0.05 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000009UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 22 B PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
B/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 52 0.032 31.4 1.0 0.880 0.024 0.060 53 Bad RT/DehydrateClear
08/11/1999 35 0.020 32.7 1.0 0.880 0.01 0.25 46 Good Retest 1 YearS/Pt
05/16/2013 54 0.030 26.8 1.0 0.879 61 Bad RT/DehydrateClear
02/06/2015 40 0.028 28.2 1.0 0.877 23 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705106 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000010UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 22 C PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
C/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 47 0.020 28.2 1.0 0.880 0.008 0.030 53 Bad DehydrateClear
08/11/1999 36 0.010 31.4 1.0 0.880 0.01 0.29 44 Good Retest 1 YearS/Pt
05/16/2013 46 0.032 27.1 1.0 0.880 61 Bad RT/DehydrateClear
02/06/2015 46 0.038 27.0 1.0 0.876 37 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705107 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000011UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 32 A PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
A/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 44 0.030 30.1 1.0 0.880 0.018 0.050 48 Good Retest 1 YearClear
08/11/1999 28 0.020 34.4 1.0 0.880 0.03 0.33 45 Good Retest 1 YearS/Pt
05/16/2013 37 0.030 26.1 1.0 0.879 67 Bad RT/DehydrateClear
02/06/2015 53 0.044 25.2 1.0 0.876 28 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705108 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 0.0605/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000012UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 32 C PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
C/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 40 0.030 31.9 1.0 0.880 0.016 0.030 50 Good Retest 1 YearClear
08/11/1999 32 0.020 32.6 1.0 0.880 0.01 0.29 58 Bad RT/DehydrateS/Pt
05/16/2013 50 0.032 25.4 1.0 0.879 64 Bad DehydrateS/Cb
02/06/2015 40 0.024 26.2 1.0 0.876 31 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705109 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000013UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 42 A PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
A/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 52 0.030 30.3 0.5 0.880 0.010 0.038 49 Good Retest 1 YearS/Pt
08/11/1999 32 0.020 33.7 1.0 0.880 0.01 0.53 27 Good Retest 1 YearS/Pt
05/16/2013 34 0.032 25.8 1.0 0.880 48 Good Retest 1 YearClear
02/06/2015 50 0.028 29.0 1.0 0.880 71 Bad RT/DehydrateClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705110 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
Nashville, TN 37210
615-255-3700 800-873-8774
Jim Bagby Highlight
0000014UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 42 QB CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
B/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 52 0.020 33.3 0.5 0.880 0.004 0.020 47 Good Retest 1 YearClear
08/11/1999 36 0.010 34.5 1.0 0.880 0.03 0.48 30 Good Retest 1 YearS/Pt
05/16/2013 50 0.034 27.5 1.0 0.879 49 Good Retest 1 YearClear
02/06/2015 49 0.024 30.6 1.0 0.878 24 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705111 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 0.0505/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000015UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 32 B PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
B/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 52 0.028 30.5 1.0 0.880 0.006 0.034 49 Good Retest 1 YearClear
08/11/1999 46 0.030 26.0 1.0 0.880 0.03 0.70 41 Good Retest 1 YearClear
05/16/2013 52 0.030 25.7 1.0 0.880 49 Good Retest 1 YearClear
02/06/2015 41 0.036 27.1 1.0 0.877 23 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705112 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000016UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 42 C PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
C/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 49 0.028 31.9 0.5 0.880 0.014 0.040 53 Bad RT/DehydrateClear
08/11/1999 42 0.010 33.7 1.0 0.880 0.02 0.59 39 Good Retest 1 YearClear
05/16/2013 48 0.030 28.9 1.0 0.880 44 Good Retest 1 YearClear
02/06/2015 47 0.032 28.5 1.0 0.878 30 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705113 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000017UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 52 A PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
A/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 26 0.032 30.8 1.0 0.880 0.008 0.020 45 Good Retest 1 YearClear
08/11/1999 35 0.014 31.2 1.0 0.880 0.02 0.32 38 Good Retest 1 YearS/Cb
05/16/2013 47 0.024 28.7 1.0 0.880 59 Bad RT/DehydrateClear
02/06/2015 47 0.024 27.5 1.0 0.877 30 Good Retest 1 YearS/Cb
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705114 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000018UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 52 B PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
B/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 53 0.032 31.9 1.0 0.880 0.006 0.062 50 Good Retest 1 YearS/Cb
08/11/1999 27 0.020 32.0 1.0 0.880 0.02 0.41 45 Good Retest 1 YearS/Cb
05/16/2013 55 0.026 29.2 1.0 0.880 51 Bad RT/DehydrateClear
02/06/2015 40 0.030 29.7 1.0 0.878 30 Good Retest 1 YearS/Cb
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705115 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000019UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 52 C PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
C/
169,000
OCB
Oil
GE
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 28 0.030 31.5 1.0 0.880 0.010 0.038 43 Good Retest 1 YearClear
08/11/1999 42 0.020 33.5 1.0 0.880 0.02 0.44 41 Good Retest 1 YearS/Pt
05/16/2013 51 0.024 29.0 1.0 0.880 50 Good Retest 1 YearClear
02/06/2015 51 0.032 28.3 1.0 0.878 55 Bad RT/DehydrateClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705116 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
Nashville, TN 37210
615-255-3700 800-873-8774
Jim Bagby Highlight
0000020UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
RSKPH OCB 28 A PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
OCB
Oil
G.E.
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 40 0.040 30.5 0.5 0.880 0.030 0.050 48 Good Retest 1 YearClear
08/11/1999 28 0.014 33.2 1.0 0.880 0.01 0.33 47 Good Retest 1 YearClear
05/16/2013 49 0.028 26.5 1.0 0.880 47 Good Retest 1 YearClear
02/06/2015 52 0.032 28.0 1.0 0.878 27 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705117 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000021UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
RSKPH OCB 28 B PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
OCB
Oil
G.E.
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 54 0.028 30.4 0.5 0.880 0.018 0.062 49 Good Retest 1 YearClear
08/11/1999 32 0.020 33.7 0.5 0.880 0.01 0.22 49 Good Retest 1 YearS/Pt
05/16/2013 50 0.030 26.7 1.0 0.880 46 Good Retest 1 YearClear
02/06/2015 40 0.036 29.9 1.0 0.876 27 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705118 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
0000022UPSI #:LOCATION:CUSTOMER: OKKEOTAU. S. ARMY CORPS OF ENG.
OCB 28CRSKPH OCB 28 C PHASE CUST. ID:CO EQUIP #:SUB NAME: OK100131
Oil Test Report
United Power Services, Inc
MFG:
OCB
Oil
G.E.
S/N:
ACCESS:
ROOF:
POLE:
PLATFORM:
INSIDE:
OUTSIDE:
GROUND:
WEIGHT:
PHYSICAL DIM:
CONS. TANK:
BUSHINGS T/S:
WATER COOLED:
GAS HEADSPACE:
# FANS:
# RADS:
WELDED LID:
PHASE/CYCLE:
KVA:
IMPED:
LOW VOLT:
HIGH VOLT:
EQUIP TYPE:
DATE MFR:
VALVES:
LIQUID:
GAL:
DATE
D877
DIEL
D974
NN
D971
IFT
D1500
COLOR
D1524
VISUAL
D1298
SG
D924
PF25
D924
PF100
RECOMMENDED
SERVICE
D1533
H2O
D4768
DBPC CLASSIFICATION
D1816
1mm
D1816
2mm
LIQUID TEST DATA
07/28/1995 41 0.032 29.7 0.5 0.880 0.012 0.042 56 Bad DehydrateClear
08/11/1999 35 0.016 35.1 0.5 0.880 0.01 0.24 43 Good Retest 1 YearS/Pt
05/16/2013 53 0.030 26.7 1.0 0.879 38 Good Retest 1 YearS/Sd
02/06/2015 52 0.028 26.0 1.0 0.875 30 Good Retest 1 YearClear
PCB CONTENT ASTM D4059
CERTIFICATE
NUMBER
AROCLOR
AROCLOR
AROCLOR OTHER
TOTAL
CONTENT (PPM)DATE
02/06/2015 705119 <1
DATE ALUMINUM COPPER IRON LEAD SILVER TIN ZINC SILICON
ICP METAL IN OIL ANALYSIS (PPM)
0 0 0 0 0 0 005/16/2013
COMMENT:
0 0 0 0 0 0 0
02/15 All values fall within normal range for oils in service and do not indicate any specific problem with unit. Detection limit 0.050 ppm.
02/06/2015
Lab Navigator v. 1.7.1
817 Fesslers Parkway
Kerr Modernization of Electrical Infrastructure - FY19 KERRMEIFY19
SECTION 01 11 00.00 26
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY OF WORK
The work to be performed under this contract consists of providing the labor, equipment, and materials to remove the existing GSU transformers, the 15 kV switchgear for units 1, 2, 3, and 4, the non-segregated bus between the generator and the 15kV switchgear, the non-segregated bus between the transformers and the 15kV switchgear, the non-segregated bus between the station service transformers and the 480V station service switchgear, the 480V switchgear, the 13.8kV/480V transformers, 480 Volt switchgear feeders, make connections to the new GSU transformers, install new non-segregated phase bus between the transformer and 15 kV switchgear, install new non-segregated phase bus between the 15 kV switchgear and generators, install new 15 kV switchgear, install new 480V switchgear and
13.8 kV/480V transformers, provide new controls and relaying, furnishing new control room remote 480V switchgear panel, furnish and install new motor control center feeders, and all the necessary auxiliary and ancillary equipment and systems required to install the equipment at the R.S. Kerr Powerhouse to make it fully operational. The new GSU power transformers are to be furnished by others with the external connections and deluge system to be made under this contract as summarized below and as required in specifications and drawings.
The work includes, but not limited to, the following:
a. Remove and dispose of two (2) three-winding GSU transformers including oil, piping, cabling and conduit, equipment no longer to be used and the disconnection from the overhead transmission line.
b. Remove and dispose of the four 15 kV switchgear lineups (unit 1, 2, 3, and 4) including the cable and conduit no longer to be used.
c. Remove and dispose of the two (2) 13.8 kV/480 Volt station service transformers including the cable and conduit no longer to be used.
d. Remove and dispose of the 480V switchgear lineup including the cable and conduit no longer to be used.
e. Remove and dispose of the existing non-segregated bus for units 1, 2, 3, and, 4 to include the sections from the generator to the switchgear and from the switchgear to the two GSU transformers.
f. Remove and dispose of the existing non-segregated bus for the 480 Volt switchgear to include the sections from station service transformers to the 480 Volt switchgear.
g. Remove six (6) tanks, oil piping, and accessories from insulating oil room.
h. Remove the existing oil filled transformer nitrogen piping, fire suppression deluge piping, oil piping systems, and their support structures.
SECTION 01 11 00.00 26 Page 1 This Section Reissued by Amendment 0002
i. Design, manufacturer, test and deliver FOB R.S. Kerr Powerhouse four
(4) new 15 kV switchgear assemblies with all breakers and auxiliary equipment.
j. Design, manufacturer, test and deliver FOB R.S. Kerr Powerhouse new non-segregated bus for connection between the generator main leads and the new 15 kV switchgear and non-segregated bus for connection of the new switchgear to the new GSU transformers.
k. Design, manufacturer, test and deliver FOB R.S. Kerr Powerhouse new 480V switchgear assembly including two (2) 13.8 kV/480 Volt transformers with all breakers and auxiliary equipment.
l. Design, manufacturer, test and deliver FOB R.S. Kerr Powerhouse one
(1) 480 Volt switchgear Remote Panel.
m. Modify the existing transformer pedestal. Design and install new transformer foundation to allow the transformer supplier to place the transformers in the final location. The new foundation will include new deluge containment. After the transformer is placed in its final location, weld and provide touchup paint.
n. Connect the power and control cables and conduits to the new GSU Transformers T1 and T2 (furnished by others) on the R.S. Kerr Powerhouse tailrace deck. (transformers to furnished and placed in location by others). Connect the cable from the new high voltage transformer bushings to the overhead transmission lines.
o. Install, level, and test new 15 kV switchgear for units 1, 2, 3, and 4 including all cable and conduit connections to make the equipment fully operational both locally and remotely as well as connection of the 15 kV cable connections to the existing lock switchgear and the new station service transformers.
p. Install, adjust, level, and test new non-segregated phase bus from the new 15 kV switchgear to the existing generator main leads including the bus tap for the existing excitation system.
q. Install, adjust, level, and test new non-segregated phase bus from the new 15 kV switchgear to the new GSU transformers (provided by others) and connect to the low voltage bushings to make it fully operational.
r. Install, level, and test new 480V station service switchgear and two
(2) station service transformers including all cable and conduit connections to make the equipment fully operational both locally and remotely as well as connection of the 600V cable connections to the existing motor control centers. Cover holes in control room. Install new diesel generator HRG.
s. Install, level, and test new 480V station service remote panel including all cable and conduit connections to make the equipment fully operational.
t. Design and install new fire suppression deluge piping and their support structures.
u. Pr ovi de new t ank( s) f or oi l cont ai nment and st or age of del uge wat er i n t he I nsul at i ng & OCB Oi l Room. Tank( s) shal l be i nst al l ed wi t hout cut t i ng, al t er i ng, or ot her wi se damagi ng exi st i ng concr et e st r uct ur es
SECTION 01 11 00.00 26 Page 2
( wal l s, f l oor s, cei l i ngs, et c. ) . Tank( s) shal l be pr ovi ded by const r uct i ng t he t ank( s) on si t e f r om i t ems smal l enough t o pass t hr ough exi st i ng openi ngs.
v. Install two (2) new insulating oil storage tanks: "clean" and "dirty" tanks in the Oil Purification Room.
w. Furnish and install new grounding conductors to new equipment.
x. Install all new wire, cables and raceways including supports required to connect the new equipment and make it fully operational including remote operation, alarm and indication. Cables going to existing equipment to be installed by Contractor but terminated at the existing equipment by others.
y. Furnish as-constructed drawings.
z. Furnish the services of manufacturer erecting engineers to supervise, direct the installation, and test the 15kV switchgear, 480V switchgear, and bus.
aa. Perform field acceptance testing and commissioning in coordination with the GSU transformer field engineer for the new transformer. GSU transformer field engineer services to be furnished under GSU transformer supply contract.
bb. Replace the two (2) 4500 GPM unwatering pumps and motors, one (1) 500 GPM unwatering sump pump and motor, and two (2) 500 GPM station service sump pump and motor replacement.
cc. DELETED.
dd. Replace the 4 ton single hoist monorail system on El. 440 with a new 10 ton monorail hoist system comprised of two (2) new 5 ton hoists.
ee. Replace the 18 inch draft tube valves, stems, and actuators.
ff. Replace the spiral case valves.
gg. Upgrade and relocate the governor oil kidney loop filter systems.
hh. Per f or m asbest os r emedi at i on on al l exi st i ng asbest os cont ai ni ng mat er i al s di st ur bed by t he Cont r act or .
i i . Per f om l ead r emedi at i on on al l exi st i ng l ead cont ai ni ng mat er i al s di st ur bed by t he Cont r act or .
1.2 SPECIFICATIONS AND DRAWINGS
Technical specifications in Divisions 01-48 listed in the Table of Contents cover the detailed requirements for the equipment and services listed in the schedule. The drawings listed on INDEX OF DRAWINGS, SHEET G-002 accompany this specification and are part thereof.
1.3 CHANGES IN SPECIFICATIONS AND DRAWINGS
The Government reserves the right to revise or amend the specifications and/or drawings prior to the date set for opening bids. Copies of such amendments will be furnished to all prospective bidders. If the revisions
SECTION 01 11 00.00 26 Page 3 and amendments require material changes in quantities or prices bid, or both, the date set for bid opening may be extended to enable bidders the opportunity to revise their bids.