2017-CG-Price_Schedule_-_Maintenance_Services_Contract.xls

XLS spreadsheet 159 KB Posted

Attached to
Mowing, Janitorial, Park Cleaning, Herbicide Application, Tree Maintenance and Buoy Maintenance;
Solicitation number
W912BV-17-R-0026
Issued by

View the file

Other files

File Type Posted
W912BV-17-R-0026.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2017-Base Year

BID SCHEDULE -- BASE YEAR - 1APR2017 - 31MAR2018PROJECT: COUNCIL GROVE LAKE
CONTRACTOR:Contract No.:TOTAL BY
ITEM NOSERVICESQUANTITYUNITUNIT PRICEAMOUNTAPPENDIX
APPENDIX A - MOWING
0001A*LAWN AREAS7MO00.0
TOTAL: MOWING-LAWN AREAS
*IMPROVED AREAS
0002ACanning Creek Cove7MO0.00
0003ANorth Richey Cove(Custer Park)7MO0.00
0004AKanza View7MO0.00
0005AOutlet Area7MO0.00
0006AKit Carson Cove7MO0.00
0007AMarina Cove7MO0.00
0008ANeosho Park7MO0.00
0009ARichey Cove7MO0.00
0010ASanta Fe Trail7MO0.00
TOTAL: MOWING-IMPROVED AREAS0.00
*NATURE/HIKING TRAILS
0011ACanning Creek Cove Trail7MO0.0
0012APioneer Nature Trail7MO0.0
0013ARichey Cove Trail7MO0.0
TOTAL: MOWING-NATURE/HIKING TRAILS0.00
0014A*DAM EMBANKMENT7MO
TOTAL: MOWING-DAM EMBANKMENT
0015A*SEMI-IMPROVED AREAS3AC
TOTAL: MOWING-SEMI-IMPROVED AREAS
TOTAL APPENDIX A - MOWING
APPENDIX B - JANITORIAL
0016B*Janitorial Work - Project Office12MO
TOTAL APPENDIX B - JANITORIAL
APPENDIX C - CLEANING OF PARKS
*SUMMER PERIOD
0017CCanning Creek Cove7MO
0018CNorth Richey Cove(Custer Park)5MO
0019CKanza View7MO
0020CKit Carson Cove5MO
0021CMarina Cove7MO
0022CNeosho Park5MO
0023COutlet Channel East & West7MO
0024COverlook7MO
0025CRichey Cove7MO
0026CSanta Fe Trail7MO
SUBTOTAL: SUMMER PERIOD
*WINTER PERIOD 1
0027CCanning Creek Cove2MO
0028CKanza View2MO
0029CMarina Cove2MO
0030COutlet Channel East & West2MO
0031COverlook2MO
0032CNeosho Park(Boat Ramp)2MO
0033CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 1
*WINTER PERIOD 2
0034CCanning Creek Cove2MO
0035CKanza View2MO
0036CMarina Cove2MO
0037COutlet Channel East & West2MO
0038COverlook2MO
0039CNeosho Park(Boat Ramp)2MO
0040CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 2
0041CCleaning of Toilets & Showers12EA
0042CCleaning of Refuse Containers130EA
* HIGH PRESSURE POWER WASHING
0043CPicnic Table Units200EA
0044CPedestal Cookers200EA
0045CFish Cleaning Station5EA
0046CToilet Floors or Shower Floors20EA
SUBTOTAL
TOTAL APPENDIX C - CLEANING OF PARKS
APPENDIX D - HERBICIDE
*SOIL STERILANT
0047DSoil Sterilant - Pads, Lots, Misc.6MO
0048DSoil Sterilant - Toe of Dam6MO
*RIPRAP AREAS
0049DConservation Corps Rock Wall6MO
0050DCanning Creek Cove6MO
0052DDiversion Channel6MO
0053DEmbankment6MO
0054DKit Carson Cove6MO
0055DMarina6MO
0056DOutlet Channel6MO
0057DRichey Cove6MO
0058DSanta Fe Trail6MO
0059DSpillway6MO
*GUARDRAIL AREAS
0060DNorth Richey Cove(Custer Park)6MO
0061DEmbankment6MO
0062DOutlet Channel6MO
0063DPaved Road & Parking Lot Shoulders6MO
0064DRoad/Parking Lot Cracks, Wheelstops6MO
0065DDiversion Channel-Woody Control6MO
0066DNoxious Weed Control50AC
TOTAL APPENDIX D - HERBICIDE
APPENDIX E - TREE MAINTENANCE
0067ETree Pruning (<10' from ground)30EA
0068ETree Pruning (>10' from ground)50EA
0069ETree Removal (<10" DBH)50EA
0070ETree Removal (10" up to <20" DBH)50EA
0071ETree Removal (20" and greater DBH)30EA
0072EStump Removal (up to 20" diameter)10EA
0073EStump Removal (21"-36" diameter)10EA
0074EStump Removal (>36" diameter)10EA
0075EEmergency Work40HR
TOTAL APPENDIX E - TREE MAINTENANCE
APPENDIX F - BUOY MAINTENANCE
0076FBuoy Inspection/Maintenance11MO
TOTAL APPENDIX F - BUOY MAINTENANCE
**Option**
0077AOpt. MOWING-SEMI-IMPROVED AREAS5AC
0078DOpt. HERB.-Noxious/Wood Control50AC
0079EOpt. Tree Pruning (>10' from ground)25EA
0080EOpt. Tree Removal (<10" DBH)25EA
0081EOpt. Tree Removal (10" up to <20" DBH)25EA
CONTRACT PERIOD TOTAL (ALL APPENDIX)
ACRONYMS: AC - Acre EA - Each MO - Month MW - Mowing HR - Hour

&C&"Arial"&10 B-&P

2018-Option Year-1

BID SCHEDULE -- OPTION YEAR-1 - 1APR2018 - 31MAR2019PROJECT: COUNCIL GROVE LAKE
CONTRACTOR:Contract No.:TOTAL BY
ITEM NOSERVICESQUANTITYUNITUNIT PRICEAMOUNTAPPENDIX
APPENDIX A - MOWING
1001A*LAWN AREAS7MO
TOTAL: MOWING-LAWN AREAS
*IMPROVED AREAS
1002ACanning Creek Cove7MO
1003ANorth Richey Cove(Custer Park)7MO
1004AKanza View7MO
1005AOutlet Area7MO
1006AKit Carson Cove7MO
1007AMarina Cove7MO
1008ANeosho Park7MO
1009ARichey Cove7MO
1010ASanta Fe Trail7MO
TOTAL: MOWING-IMPROVED AREAS
*NATURE/HIKING TRAILS
1011ACanning Creek Cove Trail7MO
1012APioneer Nature Trail7MO
1013ARichey Cove Trail7MO
TOTAL: MOWING-NATURE/HIKING TRAILS
1014A*DAM EMBANKMENT7MO
TOTAL: MOWING-DAM EMBANKMENT
1015A*SEMI-IMPROVED AREAS3AC
TOTAL: MOWING-SEMI-IMPROVED AREAS
TOTAL APPENDIX A - MOWING
APPENDIX B - JANITORIAL
1016B*Janitorial Work - Project Office12MO
TOTAL APPENDIX B - JANITORIAL
APPENDIX C - CLEANING OF PARKS
*SUMMER PERIOD
1017CCanning Creek Cove7MO
1018CNorth Richey Cove(Custer Park)5MO
1019CKanza View7MO
1020CKit Carson Cove5MO
1021CMarina Cove7MO
1022CNeosho Park5MO
1023COutlet Channel East & West7MO
1024COverlook7MO
1025CRichey Cove7MO
1026CSanta Fe Trail7MO
SUBTOTAL: SUMMER PERIOD
*WINTER PERIOD 1
1027CCanning Creek Cove2MO
1028CKanza View2MO
1029CMarina Cove2MO
1030COutlet Channel East & West2MO
1031COverlook2MO
1032CNeosho Park(Boat Ramp)2MO
1033CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 1
*WINTER PERIOD 2
1034CCanning Creek Cove2MO
1035CKanza View2MO
1036CMarina Cove2MO
1037COutlet Channel East & West2MO
1038COverlook2MO
1039CNeosho Park(Boat Ramp)2MO
1040CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 2
1041CCleaning of Toilets & Showers12EA
1042CCleaning of Refuse Containers130EA
* HIGH PRESSURE POWER WASHING
1043CPicnic Table Units200EA
1044CPedestal Cookers200EA
1045CFish Cleaning Station5EA
1046CToilet Floors or Shower Floors20EA
SUBTOTAL
TOTAL APPENDIX C - CLEANING OF PARKS
APPENDIX D - HERBICIDE
*SOIL STERILANT
1047DSoil Sterilant - Pads, Lots, Misc.6MO
1048DSoil Sterilant - Toe of Dam6MO
*RIPRAP AREAS
1049DConservation Corps Rock Wall6MO
1050DCanning Creek Cove6MO
1052DDiversion Channel6MO
1053DEmbankment6MO
1054DKit Carson Cove6MO
1055DMarina6MO
1056DOutlet Channel6MO
1057DRichey Cove6MO
1058DSanta Fe Trail6MO
1059DSpillway6MO
*GUARDRAIL AREAS
1060DNorth Richey Cove(Custer Park)6MO
1061DEmbankment6MO
1062DOutlet Channel6MO
1063DPaved Road & Parking Lot Shoulders6MO
1064DRoad/Parking Lot Cracks, Wheelstops6MO
1065DDiversion Channel-Woody Control6MO
1066DNoxious Weed Control50AC
TOTAL APPENDIX D - HERBICIDE
APPENDIX E - TREE MAINTENANCE
1067ETree Pruning (<10' from ground)30EA
1068ETree Pruning (>10' from ground)50EA
1069ETree Removal (<10" DBH)50EA
1070ETree Removal (10" up to <20" DBH)50EA
1071ETree Removal (20" and greater DBH)30EA
1072EStump Removal (up to 20" diameter)10EA
1073EStump Removal (21"-36" diameter)10EA
1074EStump Removal (>36" diameter)10EA
1075EEmergency Work40HR
TOTAL APPENDIX E - TREE MAINTENANCE
APPENDIX F - BUOY MAINTENANCE
1076FBuoy Inspection/Maintenance11MO
TOTAL APPENDIX F - BUOY MAINTENANCE
**Option**
1077AOpt. MOWING-SEMI-IMPROVED AREAS5AC
1078DOpt. HERB.-Noxious/Wood Control50AC
1079EOpt. Tree Pruning (>10' from ground)25EA
1080EOpt. Tree Removal (<10" DBH)25EA
1081EOpt. Tree Removal (10" up to <20" DBH)25EA
CONTRACT PERIOD TOTAL (ALL APPENDIX)
ACRONYMS: AC - Acre EA - Each MO - Month MW - Mowing HR - Hour

2019-Option Year-2

BID SCHEDULE -- OPTION YEAR-2 - 1APR2019 - 31MAR2020PROJECT: COUNCIL GROVE LAKE
CONTRACTOR:Contract No.:TOTAL BY
ITEM NOSERVICESQUANTITYUNITUNIT PRICEAMOUNTAPPENDIX
APPENDIX A - MOWING
2001A*LAWN AREAS7MO
TOTAL: MOWING-LAWN AREAS
*IMPROVED AREAS
2002ACanning Creek Cove7MO
2003ANorth Richey Cove(Custer Park)7MO
2004AKanza View7MO
2005AOutlet Area7MO
2006AKit Carson Cove7MO
2007AMarina Cove7MO
2008ANeosho Park7MO
2009ARichey Cove7MO
2010ASanta Fe Trail7MO
TOTAL: MOWING-IMPROVED AREAS
*NATURE/HIKING TRAILS
2011ACanning Creek Cove Trail7MO
2012APioneer Nature Trail7MO
2013ARichey Cove Trail7MO
TOTAL: MOWING-NATURE/HIKING TRAILS
2014A*DAM EMBANKMENT7MO
TOTAL: MOWING-DAM EMBANKMENT
2015A*SEMI-IMPROVED AREAS3AC
TOTAL: MOWING-SEMI-IMPROVED AREAS
TOTAL APPENDIX A - MOWING
APPENDIX B - JANITORIAL
2016B*Janitorial Work - Project Office12MO
TOTAL APPENDIX B - JANITORIAL
APPENDIX C - CLEANING OF PARKS
*SUMMER PERIOD
2017CCanning Creek Cove7MO
2018CNorth Richey Cove(Custer Park)5MO
2019CKanza View7MO
2020CKit Carson Cove5MO
2021CMarina Cove7MO
2022CNeosho Park5MO
2023COutlet Channel East & West7MO
2024COverlook7MO
2025CRichey Cove7MO
2026CSanta Fe Trail7MO
SUBTOTAL: SUMMER PERIOD
*WINTER PERIOD 1
2027CCanning Creek Cove2MO
2028CKanza View2MO
2029CMarina Cove2MO
2030COutlet Channel East & West2MO
2031COverlook2MO
2032CNeosho Park(Boat Ramp)2MO
2033CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 1
*WINTER PERIOD 2
2034CCanning Creek Cove2MO
2035CKanza View2MO
2036CMarina Cove2MO
2037COutlet Channel East & West2MO
2038COverlook2MO
2039CNeosho Park(Boat Ramp)2MO
2040CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 2
2041CCleaning of Toilets & Showers12EA
2042CCleaning of Refuse Containers130EA
* HIGH PRESSURE POWER WASHING
2043CPicnic Table Units200EA
2044CPedestal Cookers200EA
2045CFish Cleaning Station5EA
2046CToilet Floors or Shower Floors20EA
SUBTOTAL
TOTAL APPENDIX C - CLEANING OF PARKS
APPENDIX D - HERBICIDE
*SOIL STERILANT
2047DSoil Sterilant - Pads, Lots, Misc.6MO
2048DSoil Sterilant - Toe of Dam6MO
*RIPRAP AREAS
2049DConservation Corps Rock Wall6MO
2050DCanning Creek Cove6MO
2052DDiversion Channel6MO
2053DEmbankment6MO
2054DKit Carson Cove6MO
2055DMarina6MO
2056DOutlet Channel6MO
2057DRichey Cove6MO
2058DSanta Fe Trail6MO
2059DSpillway6MO
*GUARDRAIL AREAS
2060DNorth Richey Cove(Custer Park)6MO
2061DEmbankment6MO
2062DOutlet Channel6MO
2063DPaved Road & Parking Lot Shoulders6MO
2064DRoad/Parking Lot Cracks, Wheelstops6MO
2065DDiversion Channel-Woody Control6MO
2066DNoxious Weed Control50AC
TOTAL APPENDIX D - HERBICIDE
APPENDIX E - TREE MAINTENANCE
2067ETree Pruning (<10' from ground)30EA
2068ETree Pruning (>10' from ground)50EA
2069ETree Removal (<10" DBH)50EA
2070ETree Removal (10" up to <20" DBH)50EA
2071ETree Removal (20" and greater DBH)30EA
2072EStump Removal (up to 20" diameter)10EA
2073EStump Removal (21"-36" diameter)10EA
2074EStump Removal (>36" diameter)10EA
2075EEmergency Work40HR
TOTAL APPENDIX E - TREE MAINTENANCE
APPENDIX F - BUOY MAINTENANCE
2076FBuoy Inspection/Maintenance11MO
TOTAL APPENDIX F - BUOY MAINTENANCE
**Option**
2077AOpt. MOWING-SEMI-IMPROVED AREAS5AC
2078DOpt. HERB.-Noxious/Wood Control50AC
2079EOpt. Tree Pruning (>10' from ground)25EA
2080EOpt. Tree Removal (<10" DBH)25EA
2081EOpt. Tree Removal (10" up to <20" DBH)25EA
CONTRACT PERIOD TOTAL (ALL APPENDIX)
ACRONYMS: AC - Acre EA - Each MO - Month MW - Mowing HR - Hour

2020-Option Year-3

BID SCHEDULE -- OPTION YEAR-3 - 1APR2020 - 31MAR2021PROJECT: COUNCIL GROVE LAKE
CONTRACTOR:Contract No.:TOTAL BY
ITEM NOSERVICESQUANTITYUNITUNIT PRICEAMOUNTAPPENDIX
APPENDIX A - MOWING
3001A*LAWN AREAS7MO
TOTAL: MOWING-LAWN AREAS
*IMPROVED AREAS
3002ACanning Creek Cove7MO
3003ANorth Richey Cove(Custer Park)7MO
3004AKanza View7MO
3005AOutlet Area7MO
3006AKit Carson Cove7MO
3007AMarina Cove7MO
3008ANeosho Park7MO
3009ARichey Cove7MO
3010ASanta Fe Trail7MO
TOTAL: MOWING-IMPROVED AREAS
*NATURE/HIKING TRAILS
3011ACanning Creek Cove Trail7MO
3012APioneer Nature Trail7MO
3013ARichey Cove Trail7MO
TOTAL: MOWING-NATURE/HIKING TRAILS
3014A*DAM EMBANKMENT7MO
TOTAL: MOWING-DAM EMBANKMENT
3015A*SEMI-IMPROVED AREAS3AC
TOTAL: MOWING-SEMI-IMPROVED AREAS
TOTAL APPENDIX A - MOWING
APPENDIX B - JANITORIAL
3016B*Janitorial Work - Project Office12MO
TOTAL APPENDIX B - JANITORIAL
APPENDIX C - CLEANING OF PARKS
*SUMMER PERIOD
3017CCanning Creek Cove7MO
3018CNorth Richey Cove(Custer Park)5MO
3019CKanza View7MO
3020CKit Carson Cove5MO
3021CMarina Cove7MO
3022CNeosho Park5MO
3023COutlet Channel East & West7MO
3024COverlook7MO
3025CRichey Cove7MO
3026CSanta Fe Trail7MO
SUBTOTAL: SUMMER PERIOD
*WINTER PERIOD 1
3027CCanning Creek Cove2MO
3028CKanza View2MO
3029CMarina Cove2MO
3030COutlet Channel East & West2MO
3031COverlook2MO
3032CNeosho Park(Boat Ramp)2MO
3033CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 1
*WINTER PERIOD 2
3034CCanning Creek Cove2MO
3035CKanza View2MO
3036CMarina Cove2MO
3037COutlet Channel East & West2MO
3038COverlook2MO
3039CNeosho Park(Boat Ramp)2MO
3040CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 2
3041CCleaning of Toilets & Showers12EA
3042CCleaning of Refuse Containers130EA
* HIGH PRESSURE POWER WASHING
3043CPicnic Table Units200EA
3044CPedestal Cookers200EA
3045CFish Cleaning Station5EA
3046CToilet Floors or Shower Floors20EA
SUBTOTAL
TOTAL APPENDIX C - CLEANING OF PARKS
APPENDIX D - HERBICIDE
*SOIL STERILANT
3047DSoil Sterilant - Pads, Lots, Misc.6MO
3048DSoil Sterilant - Toe of Dam6MO
*RIPRAP AREAS
3049DConservation Corps Rock Wall6MO
3050DCanning Creek Cove6MO
3052DDiversion Channel6MO
3053DEmbankment6MO
3054DKit Carson Cove6MO
3055DMarina6MO
3056DOutlet Channel6MO
3057DRichey Cove6MO
3058DSanta Fe Trail6MO
3059DSpillway6MO
*GUARDRAIL AREAS
3060DNorth Richey Cove(Custer Park)6MO
3061DEmbankment6MO
3062DOutlet Channel6MO
3063DPaved Road & Parking Lot Shoulders6MO
3064DRoad/Parking Lot Cracks, Wheelstops6MO
3065DDiversion Channel-Woody Control6MO
3066DNoxious Weed Control50AC
TOTAL APPENDIX D - HERBICIDE
APPENDIX E - TREE MAINTENANCE
3067ETree Pruning (<10' from ground)30EA
3068ETree Pruning (>10' from ground)50EA
3069ETree Removal (<10" DBH)50EA
3070ETree Removal (10" up to <20" DBH)50EA
3071ETree Removal (20" and greater DBH)30EA
3072EStump Removal (up to 20" diameter)10EA
3073EStump Removal (21"-36" diameter)10EA
3074EStump Removal (>36" diameter)10EA
3075EEmergency Work40HR
TOTAL APPENDIX E - TREE MAINTENANCE
APPENDIX F - BUOY MAINTENANCE
3076FBuoy Inspection/Maintenance11MO
TOTAL APPENDIX F - BUOY MAINTENANCE
**Option**
3077AOpt. MOWING-SEMI-IMPROVED AREAS5AC
3078DOpt. HERB.-Noxious/Wood Control50AC
3079EOpt. Tree Pruning (>10' from ground)25EA
3080EOpt. Tree Removal (<10" DBH)25EA
3081EOpt. Tree Removal (10" up to <20" DBH)25EA
CONTRACT PERIOD TOTAL (ALL APPENDIX)
ACRONYMS: AC - Acre EA - Each MO - Month MW - Mowing HR - Hour

2021-Option Year-4

BID SCHEDULE -- OPTION YEAR-4 - 1APR2021 - 31MAR2022PROJECT: COUNCIL GROVE LAKE
CONTRACTOR:Contract No.:TOTAL BY
ITEM NOSERVICESQUANTITYUNITUNIT PRICEAMOUNTAPPENDIX
APPENDIX A - MOWING
4001A*LAWN AREAS7MO
TOTAL: MOWING-LAWN AREAS
*IMPROVED AREAS
4002ACanning Creek Cove7MO
4003ANorth Richey Cove(Custer Park)7MO
4004AKanza View7MO
4005AOutlet Area7MO
4006AKit Carson Cove7MO
4007AMarina Cove7MO
4008ANeosho Park7MO
4009ARichey Cove7MO
4010ASanta Fe Trail7MO
TOTAL: MOWING-IMPROVED AREAS
*NATURE/HIKING TRAILS
4011ACanning Creek Cove Trail7MO
4012APioneer Nature Trail7MO
4013ARichey Cove Trail7MO
TOTAL: MOWING-NATURE/HIKING TRAILS
4014A*DAM EMBANKMENT7MO
TOTAL: MOWING-DAM EMBANKMENT
4015A*SEMI-IMPROVED AREAS3AC
TOTAL: MOWING-SEMI-IMPROVED AREAS
TOTAL APPENDIX A - MOWING
APPENDIX B - JANITORIAL
4016B*Janitorial Work - Project Office12MO
TOTAL APPENDIX B - JANITORIAL
APPENDIX C - CLEANING OF PARKS
*SUMMER PERIOD
4017CCanning Creek Cove7MO
4018CNorth Richey Cove(Custer Park)5MO
4019CKanza View7MO
4020CKit Carson Cove5MO
4021CMarina Cove7MO
4022CNeosho Park5MO
4023COutlet Channel East & West7MO
4024COverlook7MO
4025CRichey Cove7MO
4026CSanta Fe Trail7MO
SUBTOTAL: SUMMER PERIOD
*WINTER PERIOD 1
4027CCanning Creek Cove2MO
4028CKanza View2MO
4029CMarina Cove2MO
4030COutlet Channel East & West2MO
4031COverlook2MO
4032CNeosho Park(Boat Ramp)2MO
4033CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 1
*WINTER PERIOD 2
4034CCanning Creek Cove2MO
4035CKanza View2MO
4036CMarina Cove2MO
4037COutlet Channel East & West2MO
4038COverlook2MO
4039CNeosho Park(Boat Ramp)2MO
4040CRichey Cove2MO
SUBTOTAL: WINTER PERIOD 2
4041CCleaning of Toilets & Showers12EA
4042CCleaning of Refuse Containers130EA
* HIGH PRESSURE POWER WASHING
4043CPicnic Table Units200EA
4044CPedestal Cookers200EA
4045CFish Cleaning Station5EA
4046CToilet Floors or Shower Floors20EA
SUBTOTAL
TOTAL APPENDIX C - CLEANING OF PARKS
APPENDIX D - HERBICIDE
*SOIL STERILANT
4047DSoil Sterilant - Pads, Lots, Misc.6MO
4048DSoil Sterilant - Toe of Dam6MO
*RIPRAP AREAS
4049DConservation Corps Rock Wall6MO
4050DCanning Creek Cove6MO
4052DDiversion Channel6MO
4053DEmbankment6MO
4054DKit Carson Cove6MO
4055DMarina6MO
4056DOutlet Channel6MO
4057DRichey Cove6MO
4058DSanta Fe Trail6MO
4059DSpillway6MO
*GUARDRAIL AREAS
4060DNorth Richey Cove(Custer Park)6MO
4061DEmbankment6MO
4062DOutlet Channel6MO
4063DPaved Road & Parking Lot Shoulders6MO
4064DRoad/Parking Lot Cracks, Wheelstops6MO
4065DDiversion Channel-Woody Control6MO
4066DNoxious Weed Control50AC
TOTAL APPENDIX D - HERBICIDE
APPENDIX E - TREE MAINTENANCE
4067ETree Pruning (<10' from ground)30EA
4068ETree Pruning (>10' from ground)50EA
4069ETree Removal (<10" DBH)50EA
4070ETree Removal (10" up to <20" DBH)50EA
4071ETree Removal (20" and greater DBH)30EA
4072EStump Removal (up to 20" diameter)10EA
4073EStump Removal (21"-36" diameter)10EA
4074EStump Removal (>36" diameter)10EA
4075EEmergency Work40HR
TOTAL APPENDIX E - TREE MAINTENANCE
APPENDIX F - BUOY MAINTENANCE
4076FBuoy Inspection/Maintenance11MO
TOTAL APPENDIX F - BUOY MAINTENANCE
**Option**
4077AOpt. MOWING-SEMI-IMPROVED AREAS5AC
4078DOpt. HERB.-Noxious/Wood Control50AC
4079EOpt. Tree Pruning (>10' from ground)25EA
4080EOpt. Tree Removal (<10" DBH)25EA
4081EOpt. Tree Removal (10" up to <20" DBH)25EA
CONTRACT PERIOD TOTAL (ALL APPENDIX)
ACRONYMS: AC - Acre EA - Each MO - Month MW - Mowing HR - Hour