AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SATOC, IDIQ, For Design-Build and Construction Services in Support of Various Military and Civil Works Construction Projects within Boundaries of the Tulsa District with Emphasis on Tinker, AFB, Oklahoma.
1. This amendment is to update/revise section 00 21 00. Revised appendices/pages can be located in the specifications by searching for an asterisk and amendment number (i.e. *AM2).
2. The due date is extended to Monday, 4 Jan 2015, 2 PM CST.
3. All potential offerors must acknowledge this amendment by completing blocks 15A, 15B and 15C of this page.
Return the completed first page of this amendment with your proposal.
4. POC for this amendment is Pun Chittchang, punnie.chittchang@usace.army.mil, 918-669-7544.
5. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED BY THIS AMENDMENT.
1. CONTRACT ID CODE PAGE OF PAGES
1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV-15-R-0042
X 9B. DATED (SEE ITEM 11)
18 November 2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Dec-2015
CODE
CONTRACTING DIV
USACE, TULSA 1645 S 101 E AVE
TULSA OK 74128-4609
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
X
X 1
W912BV-15-R-0042
Section 00 21 00 - Instructions, Conditions & Notices to Offerors
00 21 00
INSTRUCTIONS TO OFFERORS
SECTION 00 21 00
INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
1.0 GENERAL INFORMATION
1.1 GENERAL DESCRIPTION OF WORK
1.2 GOVERNMENT SECURITY REQUIREMENTS
1.3 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS
1.4 OFFEROR'S QUESTIONS AND COMMENTS
1.5 SMALL BUSINESS SIZE STANDARD/NAICS CODE
1.6 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
1.7 PRE-PROPOSAL CONFERENCE
1.8 ACCURACY IN PROPOSALS
1.9 PROPOSAL SUBMITTALS
1.10 JOINT VENTURE PROPOSAL REQUIREMENTS
1.0 GENERAL INFORMATION
1.1. GENERAL DESCRIPTION OF WORK
The SATOC is for design-build construction services to meet the requirements and time constraints for military, civil, and Interagency and International Services (IIS) customers within Southwestern Division (SWD) Boundaries, and mainly for Tulsa District customers.
1.2. GOVERNMENT SECURITY REQUIREMENTS
The Offeror(s) must ensure that ALL mail sent to the Tulsa District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc. ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to bids, modifications to bids, proposals, revised proposals, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located at 1645 S. 101 E. Ave, Tulsa, OK 74128, if it does not contain a return mailing address. There will be no exceptions.
USACE Tulsa District Point of Contact is Punnie Chittchang:
Phone: 918-669-7544 Email: punnie.chittchang@usace.army.mil
1.3. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS
Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted through the Army’s Single Face to Industry (AFSI) to the Federal Business Opportunities (FBO) website at:
http://www.fbo.gov
Solicitation number: W912BV-15-R-0042
It shall be the contractor’s responsibility to check the websites for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.
1.4. OFFEROR'S QUESTIONS AND COMMENTS
Questions and/or comments relative to the document should be submitted via Bidders Inquiry at:
https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=HomePagePublic.
Instructions for registering in the ProjNet Bidder Inquiry system are available on the above web site.
The Bidder Inquiry Key for this project is: 3Q7IYB-WDGGCK (Bidder’s Key will be issued by amendment)
Any information given to an offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.
*AM1 -----------------------
Note: All questions and/or comments should be entered in Bidder’s Inquiry no later than 20 calendar days prior to the proposal deadline, so they may be given consideration or action taken prior to receipt of offers.
1.5. SMALL BUSINESS SIZE STANDARD/NAICS CODE
The small business size standard for NAICS Code 236220 is $36.5 Million.
1.6. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
This Request for Proposal (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.
1.7. PRE-PROPOSAL CONFERENCE
The Government intends to hold the pre-proposal conference. The date, location, and time will be announced by Amendment. The offeror must submit, via e-mail, the firm’s name, address, point of contact, telephone number, and number of personnel planning to attend to the following no later than two (2) working days prior to the conference:
U.S. Army Corps of Engineers, Tulsa District ATTN: Punnie Chittchang 1645 S. 101 E. Ave.
Tulsa, OK 74128 Phone: 918-669-7657 Fax: 918-669-7495 Email: punnie.chittchang@usace.army.mil
During this conference, the requirements set forth in the solicitation will be reviewed and discussed, with part of the conference to include a question and answer period.
1.8. ACCURACY IN PROPOSALS
Proposals must set forth full, accurate, and complete information as required by this RFP, (including attachments). The penalty for making false statements is prescribed in 18 U.S.C.
1001.
1.9. PROPOSAL SUBMITTALS
The submittal method for proposals is electronic via AMRDEC SAFE web site or email:
https://safe.amrdec.army.mil/safe/.
The following email addresses must be entered for notification of proposal receipt and download availability:
punnie.chittchang@usace.army.mil nathan.r.kloeckler@usace.army.mil
Also submit four (4) electronic copies on CD-ROM to the address below. Detailed description on the electronic format can be found in section 00 22 00, 2.0 General Instructions.
Proposals will be received until the time and date shown on Standard Form SF 1442 or as amended on SF30. Mail proposals to:
U.S. Army Corps of Engineers, Tulsa District ATTN: Punnie Chittchang, CESWT-CT 1645 S. 101 E. Ave.
Tulsa, OK 74128
The Packaging Proposals shall be marked:
”Proposal for Solicitation Number: “W912BV-15-R-0042”
1.10. JOINT VENTURE PROPOSAL REQUIREMENTS
When proposing as a joint venture, all members of the joint venture shall sign the SF 1442 and the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration.
If this is an 8(a) or HubZone joint venture, the offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 and 13 CFR Part 126, respectively
CLAUSES INCORPORATED BY REFERENCE
52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2004 52.215-16 Facilities Capital Cost of Money JUN 2003 52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.215-22 Limitations on Pass-Through Charges--Identification of Subcontract Effort
OCT 2009
52.232-14 Notice Of Availability Of Progress Payments Exclusively For Small Business Concerns
APR 1984
52.236-28 Preparation of Proposals--Construction OCT 1997
*AM2
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm fixed-price contract resulting from this solicitation.
(End of provision)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
14.8 6.9
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is [Contracting Officer shall insert description of the geographical areas where the contract is to be performed, giving the State, county, and city].
(End of provision)
52.232-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER—OTHER THAN SYSTEM FOR AWARD
MANAGEMENT (JULY 2013)
(a) Method of payment. (1) All payments by the Government under this contract shall be made by electronic funds transfer (EFT) except as provided in paragraph (a)(2) of this clause. As used in this clause, the term “EFT” refers to the funds transfer and may also include the payment information transfer.
(2) In the event the Government is unable to release one or more payments by EFT, the Contractor agrees to either--
(i) Accept payment by check or some other mutually agreeable method of payment; or
(ii) Request the Government to extend payment due dates until such time as the Government makes payment by EFT (but see paragraph (d) of this clause).
(b) Mandatory submission of Contractor's EFT information. (1) The Contractor is required to provide the Government with the information required to make payment by EFT (see paragraph (j) of this clause). The Contractor shall provide this information directly to the office designated in this contract to receive that information (hereafter: “designated office”') by (the Contracting Officer shall insert date, days after award, days before first request, the date specified for receipt of offers if the provision at 52.232-38 is utilized, or “concurrent with first request” as prescribed by the head of the agency; if not prescribed, insert “no later than 15 days prior to submission of the first request for payment”). If not otherwise specified in this contract, the payment office is the designated office for receipt of the Contractor's EFT information. If more than one designated office is named for the contract, the Contractor shall provide a separate notice to each office. In the event that the EFT information changes, the Contractor shall be responsible for providing the updated information to the designated office(s).
(2) If the Contractor provides EFT information applicable to multiple contracts, the Contractor shall specifically state the applicability of this EFT information in terms acceptable to the designated office. However, EFT information supplied to a designated office shall be applicable only to contracts that identify that designated office as the office to receive EFT information for that contract.
(c) Mechanisms for EFT payment. The Government may make payment by EFT through either the Automated Clearing House (ACH) network, subject to the rules of the National Automated Clearing House Association, or the Fedwire Transfer System. The rules governing Federal payments through the ACH are contained in 31 CFR part 210.
(d) Suspension of payment. (1) The Government is not required to make any payment under this contract until after receipt, by the designated office, of the correct EFT payment information from the Contractor. Until receipt of the correct EFT information, any invoice or contract financing request shall be deemed not to be a proper invoice for the purpose of prompt payment under this contract. The prompt payment terms of the contract regarding notice of an improper invoice and delays in accrual of interest penalties apply.
(2) If the EFT information changes after submission of correct EFT information, the Government shall begin using the changed EFT information no later than 30 days after its receipt by the designated office to the extent payment is made by EFT. However, the Contractor may request that no further payments be made until the updated EFT information is implemented by the payment office. If such suspension would result in a late payment under the prompt payment terms of this contract, the Contractor's request for suspension shall extend the due date for payment by the number of days of the suspension.
(e) Liability for uncompleted or erroneous transfers. (1) If an uncompleted or erroneous transfer occurs because the Government used the Contractor's EFT information incorrectly, the Government remains responsible for--
(i) Making a correct payment;
(ii) Paying any prompt payment penalty due; and
(iii) Recovering any erroneously directed funds.
(2) If an uncompleted or erroneous transfer occurs because the Contractor's EFT information was incorrect, or was revised within 30 days of Government release of the EFT payment transaction instruction to the Federal Reserve System, and--
(i) If the funds are no longer under the control of the payment office, the Government is deemed to have made payment and the Contractor is responsible for recovery of any erroneously directed funds; or
(ii) If the funds remain under the control of the payment office, the Government shall not make payment and the provisions of paragraph (d) shall apply.
(f) EFT and prompt payment. A payment shall be deemed to have been made in a timely manner in accordance with the prompt payment terms of this contract if, in the EFT payment transaction instruction released to the Federal Reserve System, the date specified for settlement of the payment is on or before the prompt payment due date, provided the specified payment date is a valid date under the rules of the Federal Reserve System.
(g) EFT and assignment of claims. If the Contractor assigns the proceeds of this contract as provided for in the assignment of claims terms of this contract, the Contractor shall require as a condition of any such assignment, that the assignee shall provide the EFT information required by paragraph (j) of this clause to the designated office, and shall be paid by EFT in accordance with the terms of this clause. In all respects, the requirements of this clause shall apply to the assignee as if it were the Contractor. EFT information that shows the ultimate recipient of the transfer to be other than the Contractor, in the absence of a proper assignment of claims acceptable to the Government, is incorrect EFT information within the meaning of paragraph (d) of this clause.
(h) Liability for change of EFT information by financial agent. The Government is not liable for errors resulting from changes to EFT information provided by the Contractor's financial agent.
(i) Payment information. The payment or disbursing office shall forward to the Contractor available payment information that is suitable for transmission as of the date of release of the EFT instruction to the Federal Reserve System. The Government may request the Contractor to designate a desired format and method(s) for delivery of payment information from a list of formats and methods the payment office is capable of executing. However, the Government does not guarantee that any particular format or method of delivery is available at any particular payment office and retains the latitude to use the format and delivery method most convenient to the Government. If the Government makes payment by check in accordance with paragraph (a) of this clause, the Government shall mail the payment information to the remittance address in the contract.
(j) EFT information. The Contractor shall provide the following information to the designated office. The Contractor may supply this data for this or multiple contracts (see paragraph (b) of this clause). The Contractor shall designate a single financial agent per contract capable of receiving and processing the EFT information using the EFT methods described in paragraph (c) of this clause.
(1) The contract number (or other procurement identification number).
(2) The Contractor's name and remittance address, as stated in the contract(s).
(3) The signature (manual or electronic, as appropriate), title, and telephone number of the Contractor official authorized to provide this information.
(4) The name, address, and 9-digit Routing Transit Number of the Contractor's financial agent.
(5) The Contractor's account number and the type of account (checking, saving, or lockbox).
(6) If applicable, the Fedwire Transfer System telegraphic abbreviation of the Contractor's financial agent.
(7) If applicable, the Contractor shall also provide the name, address, telegraphic abbreviation, and 9-digit Routing Transit Number of the correspondent financial institution receiving the wire transfer payment if the Contractor's financial agent is not directly on-line to the Fedwire Transfer System; and, therefore, not the receiver of the wire transfer payment.
(End of clause)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Charles Peterson, 1645 S. 101st E. Ave, Tulsa, OK 74128.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- TBD- Any updated information will be issued by amendment.
(c) Participants will meet at--
TBD
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/
(End of provision)
252.209-7992 REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID DELINQUENT TAX
LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW—FISCAL YEAR 2015
APPROPRIATIONS (DEVIATION 2015-OO0005) (DEC 2014)
(a) In accordance with sections 744 and 745 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235), none of the funds made available by this or any other Act may be used to enter into a contract with any corporation that—
(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless the agency has considered suspension or debarment of the corporation and made a determination that this further action is not necessary to protect the interests of the Government; or
(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless the agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.
(b) The Offeror represents that—
(1) It is [ ] is not [ ] a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability,
(2) It is [ ] is not [ ] a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.
(End of provision)
| SF30 |