AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
JOB ORDER CONTRACT (JOC), McAlester Army Ammunition Plant, Oklahoma
This amendment is issued to add the w age rates, include the clause 52.228-1 "Bid Guarantee" and clarify the follow ing items: The Government intends to aw ard only one contract from this solicitation. As noted in Section 00 11 00 "Guarantee Minimum" the amount per year is listed as $9,900,000. For Performance and Payment Bonds requirements after aw ard the amount to bond w ould be $9,900,000.
THE RECEIPT DATE HAS BEEN EXTENDED TO 16 JULY 2009 AT 11:00 AM, LOCAL TIME.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 24
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Jun-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BV-09-R-2033
X 9B. DATED (SEE ITEM 11)
12-Jun-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Jun-2009
CODE
CONTRACTING DIV
USAED, TULSA 1645 S 101 E AVE
TULSA OK 74128-4609
W912BV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912BV-09-R-2033
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
General Decision Number: OK080025 02/08/2008 OK25
Superseded General Decision Number: OK20070025
State: Oklahoma
Construction Types: Heavy Water Well Drilling
Counties: Oklahoma Statewide.
Modification Number Publication Date
0 02/08/2008
SUOK1992-006 05/12/1992
Rates Fringes Water Well Driller.............$ 8.00
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
W912BV-09-R-2033, JOB ORDER CONTRACT, MCALESTER ARMY AMMUNITION PLANT,
MCALESTER, PITTSBURG COUNTY, OKLAHOMA
SUMMARY
ALL AGENCY MEMORANDUM NO. 130
U.S. DEPARTMENT OF LABOR
WAGE AND HOUR DIVISION
The purpose of this summary is to set forth present policies of the Wage and Hour Division, Department of Labor (DOL), with regard to the determination of "projects of a character similar to the contract work" for wage determination purposes. The guidelines contained in the memorandum are to be used by the contracting agencies in selecting the proper schedule(s) of wage rates.
The Davis-Bacon and related Acts (DBA) require the Secretary of Labor to determine the prevailing wage rates for corresponding classes of laborers and mechanics on projects in the area which are of a "character similar" to the proposed contract work to which the determination will be applied.
Generally construction projects are classified as either Building, Heavy, Highway or Residential.
Generally, for wage determination purposes, a project consists of all construction necessary to complete a facility regardless of the number of contracts involved so long as all contracts awarded are closely related in purpose, time and place. Below are descriptions of these classifications with an illustrative listing of the kinds of projects that are generally included within the classification.
BUILDING CONSTRUCTION
Building construction generally is the construction of sheltered enclosures with walk-in access for the purpose of housing persons, machinery, equipment, or supplies. It includes all construction of such structures, the installation of utilities and the installation of equipment, both above and below grade level, as well as incidental grading, utilities and paving. Additionally, such structures need not be "habitable" to be building construction. The installation of heavy machinery and/or equipment does not generally change the project's character as a building.
Examples
Alterations and additions to buildings Apartment buildings (5 stories and above) Arenas (enclosed) Auditoriums Automobile parking garages Banks and financial buildings Barracks Churches City Halls Civic Centers Commercial buildings Court houses Detention facilities Dormitories Farm buildings Fire stations Hospitals Hotels Industrial buildings Institutional buildings
Summary, AAM #130
Libraries Mausoleums Motels Museums Nursing and convalescent facilities Office buildings Out-patient clinics Passenger and freight terminal buildings Police-stations Post Offices Power Plants Prefabricated buildings Remodeling buildings Renovating buildings Repairing buildings Restaurants Schools Service Stations Shopping Centers Stores Subway Stations Theaters Warehouses Water and sewage treatment plants (buildings only)
RESIDENTIAL CONSTRUCTION
Residential projects for Davis-Bacon purposes are those involving the construction, alteration, or repair of single family houses or apartment buildings of no more than four (4) stories in height. This includes all incidental items such as site work, parking areas, utilities, streets and sidewalks.
Examples
Town or row houses Apartment buildings (4 stories or less) Single family houses While home developments Multi-family houses Married student housing
HEAVY CONSTRUCTION
Heavy projects are those projects that are not properly classified as either "building", "highway", or "residential". Unlike these classifications, heavy construction is not a homogeneous classification. Because of this catch-all nature, projects within the heavy classification may sometimes be distinguished on the basis of their particular project characteristics, and separate schedules issued. For example, separate schedules may be issued for dredging projects, water and sewer line projects, dams, major bridges, and flood control projects.
Examples
Antenna towers Bridges (major bridges designed for commercial navigation) Breakwaters Caissons (other than building or highway) Canals Channels Channel cut-offs Chemical complexes or facilities (other than buildings) Cofferdams Coke ovens Dams Demolition (not incidental to construction) Dikes Docks Drainage projects Dredging projects Electrification projects (outdoors) Flood control projects Industrial incinerators (other than building) Irrigation projects Jetties Kilns Land drainage (not incidental to other construction) Land leveling (not incidental to other construction) Land reclamation Levees Locks, waterways Oil refineries (other than buildings) Pipe lines Ponds Pumping stations (prefabricated drop-in units - not buildings) Railroad construction Reservoirs Revetments Sewage collection and disposal lines Sewers (sanitary, storm, etc) Shoreline maintenance Ski tows Storage tanks Swimming pools (outdoors) Subways (other than buildings) Tipples Tunnels Unsheltered piers and wharves Viaducts (other than highway) Water mains Waterway construction Water supply lines (not incidental to building) Wells
HIGHWAY CONSTRUCTION
Highway projects include the construction, alteration or repair of roads, streets, highways, runways, taxiways, alleys, trails, paths, parking areas, and other similar projects not incidental to building or heavy construction.
Examples
Alleys Base courses Bituminous treatments Bridle paths Concrete pavement Curbs Excavation and embankment (for road construction) Fencing (highway) Grade crossing elimination (overpasses or underpasses) Guard rails on highway Highway Signs Highway bridges (overpasses; underpasses; grade separation) Medians Parking lots Parkways Resurfacing streets and highways Roadbeds Roadways Runways Shoulders Stabilizing courses Storm sewers incidental to road construction Street Paving Surface courses Taxiways Trails
CONTRACT NUMBER W912BV-09-R-2033
JOB ORDER CONTRACT
MCALESTER ARMY AMMUNITION PLANT
APPLICABILITY OF WAGE RATES
Wage Decision No. OK080017, Building Construction, with twelve modifications, dated 06/26/2009, will be applicable to construction, alteration, or repair of buildings, installations within buildings, exterior electrical work, and utilities within 5 feet of buildings in Pittsburg County.
Wage Decision No. OK080004, Residential Construction, with one modification, dated 07/25/2008, will be applicable to projects consisting of single family homes and apartments up to and including four stories. This includes incidental items such as site work, parking areas, utilities, streets, and sidewalks in Pittsburg County.
Wage Decision No. OK080002, Highway, Sewer and Water Line Construction, with one modification, dated 07/25/2008, will be applicable to construction, alteration, and/or repair of streets, highways, runways, erosion control structures, and water and sewer utilities in Pittsburg County.
Wage Decision No. OK080021, Heavy Construction, with one modification, dated 07/25/2008, will be applicable to any other construction requirements not shown in the paragraphs above in Pittsburg County.
Wage Decision No. OK080025, Heavy Water Well Drilling Construction, dated 02/08/2008, is applicable for water well drilling only in Pittsburg County.
All proposed work is unknown at this time, and Department of Labor's All Agency Memorandum No. 130 (summary attached) shall be used as a guideline for proper application of multiple schedules.
NOTE: The wage decision and schedule applicable to the work performed are to be noted on the payment records and payrolls.
General Decision Number: OK080002 07/25/2008 OK2
Superseded General Decision Number: OK20070002
State: Oklahoma
Construction Types: Heavy Sewer and Water Line and Highway
Counties: Adair, Alfalfa, Atoka, Beaver, Beckham, Blaine, Bryan, Caddo, Carter, Cherokee, Choctaw, Cimarron, Coal, Cotton, Craig, Custer, Delaware, Dewey, Ellis, Garvin, Grady, Grant, Greer, Harmon, Harper, Haskell, Hughes, Jackson, Jefferson, Johnston, Kay, Kingfisher, Kiowa, Latimer, Le Flore, Lincoln, Love, Major, Marshall, Mayes, McCurtain, McIntosh, Murray, Muskogee, Noble, Nowata, Okfuskee, Okmulgee, Ottawa, Pawnee, Payne, Pittsburg, Pontotoc, Pushmataha, Roger Mills, Seminole, Stephens, Texas, Tillman, Washington, Washita, Woods and Woodward Counties in Oklahoma.
Construction, alteration, and/or repair of streets, highways, runways, erosion control structures and water and sewer utilities (but does not include building structures on highway rest areas) also excludes heavy construction within the city limits of Muskogee.
Modification Number Publication Date 0 02/08/2008 1 07/25/2008
* SUOK1991-001 12/12/1991
Rates Fringes Air Tool Operator................$ 6.55 Asphalt Raker....................$ 6.75
BLASTER..........................$ 8.75
CARPENTER........................$ 8.50
Concrete Finisher-Paving.........$ 8.60 Concrete Finisher-Structures.....$ 8.00 Concrete Rubber..................$ 6.55 Flag Person......................$ 6.55 Form Builder-Structures..........$ 7.50 Form Setter-Paving & Curb........$ 7.50 Form Setter-Structures...........$ 7.50 Labor Common.....................$ 6.55 Manhole Inlet Builder............$ 7.25
MECHANIC.........................$ 9.00
Painter-Structures...............$ 7.00 Pile Driver......................$ 7.50 Pipelayer........................$ 7.50 Power equipment operators:
ASPAHLT PAVING MACHINE
SCREED......................$ 8.55
ASPHALT DISTIBUTOR..........$ 7.55
ASPHALT HOT-MIX PLANT.......$ 8.50
ASPHALT PAVING MACHINE......$ 8.55
BACKHOE-LOADER..............$ 8.30
BOX BLADE-LOADER............$ 7.55
BROOM/SWEEPER...............$ 7.00
BULLDOZER (150 H.P. & LESS).$ 8.40
BULLDOZER (OVER 150 H.P.)...$ 8.75
CONCRETE MIXING PLANT.......$ 8.50
CONCRETE PAVING
CURING/TEXTURE/FLOAT........$ 8.50
CONCRETE PAVING FINISHING
MACHINE.....................$ 8.55
CONCRETE PAVING FORM GRADER.$ 8.20
CONCRETE PAVING GRINDER.....$ 7.60
CONCRETE PAVING JOINT
SEALER......................$ 7.75
CONCRETE PAVING SPREADER....$ 8.50
CONCRETE SAW OPERATOR.......$ 7.40
CONCRETE SCREED MACHINE.....$ 7.75
CRANE, CLAMSHELL, DERRICK,
DRAGLINE, SHOVEL (1
1/2 C.Y. & LESS)........$ 7.95
CRANE, CLAMSHELL, DERRICK,
DRAGLINE, SHOVEL (OVER 1
1/2 C.Y.)..................$ 8.50
CRUSHER & SCREENING PLANT...$ 8.25
CURB MACHINE (SLIPFORM).....$ 8.30
FOUNDATION DRILL, TRUCK
MOUNTED.....................$ 11.85
FRONT END LOADER (2-1/2
C.Y. & LESS)................$ 7.75
FRONT END LOADER (OVER 2-
1/2 C.Y.)...................$ 8.45
HYDRAULIC EXCAVATOR.........$ 8.65
MOTOR GRADER (FINE GRADE)...$ 9.05
MOTOR GRADER (ROUGH)........$ 8.00
PAVEMENT MAKING MACHINE.....$ 8.00
PLANER, MILLING MACHINE.....$ 8.25
PUGMILL MIXING PLANT........$ 7.15
PUMP CRETE..................$ 7.15
REINFORCING STEEL MACHINE...$ 7.40
ROLLER PNEUMATIC (SELF-
PROPELLED)..................$ 7.45
ROLLER STEEL-WHEEL (OTHER)..$ 7.45
ROLLER STEEL-WHEEL (PLANT-
MIX)........................$ 7.85
SCRAPER (17 C.Y. & LESS)....$ 8.30
SCRAPER (OVER 17 C.Y.)......$ 8.55
SELF-PROPELLED HAMMER.......$ 7.20
SIDE-BOOM...................$ 7.65
TRACTOR: CRAWLER (150 H.P.
& LESS).....................$ 7.15
TRACTOR: CRAWLER (OVER 150
H.P.).......................$ 7.50
TRACTOR: PNEUMATIC (80
H.P. OR LESS)...............$ 7.45
TRACTOR: PNEUMATIC (OVER
80 H.P.)....................$ 7.65
TRAVELING MIXER.............$ 7.25
TRENCHING MACHINE...........$ 8.25
WAGON DRILL, BORING
MACHINE OR POST HOLE........$ 6.60
Reinforcing Steel Setter Paving...........................$ 7.50 Reinforcing Steel Setter Structures.......................$ 7.50 Servicer.........................$ 7.75
SIGN ERECTOR.....................$ 8.00
Spreader Box Person..............$ 7.00 Steelworker Structural...........$ 7.50 Traffic Control Device Monitor...$ 7.00
TRAFFIC SIGNALIZATION:
Traffic Signal Installation......$ 11.50
TRUCK DRIVER
LOWBOY, FLOAT...............$ 8.60
SINGLE AXLE, 2 TONS & UNDER.$ 6.85
SINGLE AXLE, OVER 2 TONS....$ 7.05
TANDEM AXLE & SEMITRAILOR...$ 7.30
Vibrator Operator - Hand Type....$ 6.55 WELDERS - Receive rate prescribed for craft performing operation to which welding is incidential.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
General Decision Number: OK080004 07/25/2008 OK4
Superseded General Decision Number: OK20070004
State: Oklahoma
Construction Type: Residential
Counties: Atoka, Bryan, Choctaw, Haskell, Latimer, Le Flore, McCurtain, Pittsburg and Pushmataha Counties in Oklahoma.
RESIDENTIAL CONSTRUCTION PROJECTS (consisting of single family homes and apartments up to and including 4 stories)
Modification Number Publication Date
1 07/25/2008
* SUOK1997-008 09/01/1997
Rates Fringes Air Conditioning Mechanic........$ 8.00
BRICKLAYER.......................$ 10.00
CARPENTER........................$ 7.57
CEMENT MASON/CONCRETE FINISHER...$ 7.29
Drywall Installer................$ 10.00
ELECTRICIAN......................$ 8.00
ELEVATOR MECHANIC................$ 13.74
FLOOR LAYER: CARPET (SOFT)
FLOOR............................$ 8.00
Insulation Installer.............$ 6.55 Ironworker.......................$ 6.85
LABORER..........................$ 6.55
PAINTER..........................$ 8.00
PLUMBER/PIPEFITTER...............$ 7.81
Power equipment operators:
Backhoe Operator............$ 6.68 Box blade Operator..........$ 6.68 Bulldozer Operator..........$ 6.69 Crane Operator..............$ 9.50 Motor Grader................$ 6.85 Roller......................$ 6.85 Scraper.....................$ 6.85 Tractor.....................$ 6.85 Trenching Machine...........$ 6.55 ROOFER, Including Built Up, Composition and Single Ply Roofs............................$ 6.55 Sheet metal worker...............$ 6.55
TILE SETTER......................$ 8.00
TRUCK DRIVER.....................$ 6.55
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
General Decision Number: OK080017 06/26/2009 OK17
Superseded General Decision Number: OK20070017
State: Oklahoma
Construction Type: Building
Counties: Hughes, Lincoln, McIntosh, Okfuskee, Okmulgee, Pittsburg and Seminole Counties in Oklahoma.
BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)
1 02/15/2008 2 05/30/2008 3 06/06/2008 4 06/27/2008 5 08/29/2008 6 10/10/2008 7 10/31/2008 8 11/28/2008 9 12/05/2008 10 02/06/2009 11 04/10/2009 12 06/26/2009
BROK0005-015 06/01/2008
HUGHES, LINCOLN AND SEMINOLE COUNTIES
Rates Fringes
Bricklayer, Stonemason...........$ 23.76 8.40
BROK0005-016 06/01/2008
MCINTOSH, OKFUSKEE, OKMULGEE AND PITTSBURG COUNTIES
Rates Fringes
Bricklayer, Stonemason...........$ 23.76 8.40
CARP0329-001 06/01/1997
Rates Fringes
Carpenters: (LINCOLN CO.
(S-1/2):)........................$ 15.50 2.80
CARP0943-002 06/01/1997
MCINTOSH, OKFUSKEE, OKMULGEE, PITTSBURG COS.;
Rates Fringes
Carpenters:......................$ 14.64 3.07
CARP1362-001 01/01/1995
HUGHES AND SEMINOLE COS.:
Rates Fringes
Carpenters:
CARPENTERS..................$ 13.40 2.85
CARP1686-002 06/11/1994
LINCOLN CO. (N-1/2):
Rates Fringes
Carpenters:......................$ 14.40 .80
* ELEC0584-003 05/27/2009
HUGHES, MCINTOSH, OKFUSKEE, OKMULGEE AND PITTSBURG COS.
Rates Fringes
Electricians:....................$ 25.03 9.05
* ELEC1141-002 05/27/2009
LINCOLN AND SEMINOLE COS.:
Rates Fringes
Electricians:....................$ 26.00 17.25%+4.70
ELEC1141-003 09/01/2000
Rates Fringes
Sound & Communication Technician.......................$ 17.86 3%+1.35
ENGI0627-003 06/01/2008
Rates Fringes
Power Equipment Operator
GROUP 1.....................$ 23.95 10.54
GROUP 2.....................$ 23.10 10.54
GROUP 3.....................$ 21.95 10.54
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
CRANES:
GROUP 1 - All crane type equipment with at least 300' of boom and over (including jib)
GROUP 2 - All crane type equipment with at least 200' and less than 300' of boom (including jib)
GROUP 3 - All crane type equipment with at least 100' and less than 200' of boom (including jib) all tower cranes -crane type equipment (3 cu. yds. and over)
ROOF0143-001 06/01/2008
Rates Fringes
ROOFER, Including Built Up, Composition and Single Ply Roofs............................$ 19.32 5.03
SHEE0124-002 07/01/2008
HUGHES, LINCOLN & SEMINOLE COUNTIES:
Rates Fringes
Sheet Metal Worker...............$ 25.85 11.35
SHEE0270-002 06/01/2000
MCINTOSH, OKFUSKEE, OKMULGEE PITTSBURG COS.:
Rates Fringes
Sheet Metal Worker...............$ 21.04 4.79
SUOK1992-001 11/02/1992
Rates Fringes
Heating & A/C Mechanic...........$ 9.81 .74
Ironworker.......................$ 13.30 3.27
Laborers:
Common......................$ 8.00 1.31 Pipelayers..................$ 9.31
PAINTER..........................$ 15.00
PLUMBER..........................$ 13.07
Power equipment operator -backhoe..........................$ 11.28
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
General Decision Number: OK080021 07/25/2008 OK21
Superseded General Decision Number: OK20070021
State: Oklahoma
Construction Type: Heavy
Counties: Adair, Alfalfa, Atoka, Beaver, Beckham, Blaine, Bryan, Caddo, Carter, Cherokee, Choctaw, Cimarron, Coal, Comanche, Cotton, Craig, Custer, Delaware, Dewey, Ellis, Garfield, Garvin, Grady, Grant, Greer, Harmon, Harper, Haskell, Hughes, Jackson, Jefferson, Johnston, Kay, Kingfisher, Kiowa, Latimer, Le Flore, Lincoln, Love, Major, Marshall, Mayes, McCurtain, McIntosh, Murray, Muskogee, Noble, Nowata, Okfuskee, Okmulgee, Ottawa, Pawnee, Payne, Pittsburg, Pontotoc, Pushmataha, Roger Mills, Seminole, Sequoyah, Stephens, Texas, Tillman, Washington, Washita, Woods and Woodward Counties in Oklahoma.
HEAVY CONSTRUCTION (does not include Sewer and Water Line Construction Projects); Excluding The City of Muskogee.
1 07/25/2008
* SUOK1992-003 05/11/1992
Rates Fringes
CARPENTER........................$ 8.85
Concrete Finisher................$ 8.35 Form Builder.....................$ 7.00 Form Setter......................$ 7.60 Laborers:
Air tool man................$ 6.55 Asphalt raker...............$ 6.55 Asphalt shoveler............$ 6.55 Common laborers.............$ 6.55 Pipelayers..................$ 6.95
MECHANIC.........................$ 9.90
PAINTER..........................$ 7.50
Power equipment operators:
Asphalt distributor.........$ 7.05 Asphalt paving machine......$ 8.30 Asphalt Plant operator......$ 8.60 Bulldozer operator..........$ 9.10 Concrete paving machine.....$ 9.85 Concrete saw operator.......$ 8.75 Crane, Clamshell, Backhoe...$ 8.40 Crusher and screening plant op....................$ 8.25
FLAGPERSON..................$ 6.55
Front End Loaders...........$ 8.50
Mixer.......................$ 8.20 Motor grader operator.......$ 9.05 Oiler.......................$ 8.75 Power broom operator........$ 6.55 Pug mill operator...........$ 6.55 Roller Pneumatic............$ 6.70 Roller steel wheel..........$ 7.25 Scrapers....................$ 8.60 Screed operator.............$ 8.70 Traveling plant operator....$ 8.35 Reinforcing Steel Setter.........$ 7.90 Tractor operator Crawler.....................$ 6.55 Pneumatic...................$ 7.10
TRAFFIC SIGNALIZATION:
Traffic Signal Installation......$ 10.25
TRUCK DRIVER.....................$ 7.25
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be ____20____ percent of the bid price or $3,000,000, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)