US Army Corps of Engineers Tulsa District

Rehabilitation and Painting Tainter Gates

Fort Gibson Dam Wagoner County, Oklahoma

May 2009

Solicitation Number W912BV-09-R-1014

TABLE OF CONTENTS

REHABILITATION AND PAINTING TAINTER GATES

FT. GIBSON LAKE, OKLAHOMA

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00010 SOLICITATION, OFFER, AND AWARD

00050 PROJECT DESCRIPTION - SCOPE OF WORK

00100 BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

00110 PROPOSAL PREPARATION

00120 PROPOSAL EVALUATION AND CONTRACT AWARD

00600 REPRESENTATIONS & CERTIFICATIONS

00700 CONTRACT CLAUSES

00800 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 04 00 COORDINATION, FIELD ENGINEERING, AND MEETINGS

01 10 00 SAFETY

01 27 00 MEASUREMENT AND PAYMENT

01 30 00 SUBMITTAL PROCEDURES

01 31 20 QUALITY CONTROL SYSTEM (QCS)

01 32 00 PROJECT SCHEDULE

01 44 00 CONTRACTOR QUALITY CONTROL

01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 56 10 ENVIRONMENTAL PROTECTION

01 58 00 BULLETIN BOARD, PROJECT SIGN, AND SAFETY SIGN

01 60 00 MATERIAL AND EQUIPMENT

01 70 00 CONTRACT CLOSEOUT

DIVISION 05 - METALS

05055 WELDING

05500 TAINTER GATE SIDE AND BOTTOM SEAL ASSEMBLIES

DIVISION 09 - FINISHES

09 96 50 PAINTING: HYDRAULIC STRUCTURES

ADDITIONAL SPECIFICATIONS/INFORMATION

11287 TAINTER GATE ROLLER CHAINS

35 01 41 TAINTER GATE HOIST CHAIN REPLACEMENT

MISCELLANEOUS BABBITT REPAIR PROCEEDURE

-- End of Project Table of Contents --

DEANNA S MALL 918-669-7273

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

20-May-2009

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, notice to proceed. This performance period is mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________5 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________19 Jun 2009 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIV

USAED, TULSA 1645 S 101 E AVE

TULSA OK 74128-4609

W912BV

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

04:00 PM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W912BV-09-R-1014

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

PROPOSAL SCHEDULE

REHABILITATION AND PAINTING TAINTER GATES

FT. GIBSON LAKE, OKLAHOMA

Item Unit No. Description Quantity Unit Price Amount

1. Sandblast and Paint Upstream and Downstream Sides of Tainter Gates 30 EA ____ _______

2. Seal Pier Landings 31 EA ____ _______

3. Replace Hoist Platform Anchor Bolts, Nuts, and Washers 6 HST ____ _______

4. Treat Pack Rust and Seal Hoist Platform Girders 6 HST ____ _______

5. Rehabilitate Babbitt Material 30 EA ____ _______

6. Inspect for and Repair Corrosion Pits on Surfaces to be Painted 6000 SI ____ _______

7. Fill Corrosion Pits with Weld Material 3000 SI ____ _______

8. Paint Hoist Machinery Platforms SUM JOB XXXX _______

9. Traffic Control SUM JOB XXXX _______

10. Mobilization/demobilization SUM JOB XXXX _______

11. Remove and Replace Side Seal Assemblies SUM JOB XXXX _______

12. Replace Hoist Chains SUM JOB XXXX _______

13. Rehabilitate/Paint Trunnion Anchorage and Assemblies

- Intermediate Piers 55 EA ____ _______

14. Rehabilitate/Paint Trunnion Anchorage and Assemblies

- End Piers 1 EA ____ _______

TOTAL PROPOSAL $________

00010-3

00010-4

EA = Each HST = Hoist SI = Square Inches

NOTES

1. All costs for items of work that are not listed separately in the Proposal

Schedule or specifically mentioned to be included in a particular item price shall be included in the listed item price most closely associated with the work involved.

2. This solicitation requires submission of a proposal on all items. Failure to do so will result in the proposal being rejected without further consideration.

3. All quantities are estimated except where the unit is given as job.

4. Only one contract for the entire schedule will be awarded under this soliciation.

00010 -

CAUTION TO OFFERORS

All information required by the terms of the Solicitation must be furnished. MISTAKES OR OMISSIONS CAN BE COSTLY. Important items for you to check are included in but not limited to, those listed below. This checklist is furnished only to assist you in submitting a proper offer.

Check as you read.

( ) Have you acknowledged all amendments?

( ) Have you completed the "Representations and Certifications?"

( ) Is your offer properly signed?

( ) If a bid guarantee is required, is it included with your offer?

(A late bid guarantee is treated the same as a late offer.)

( ) Is your bid guarantee in the proper amount? (Usually 20 percent of total price.)

( ) If your bid guarantee is in the form of a bid bond, is the bond properly signed by both the bidder and surety and are all required seals affixed?

( ) Is the name in which you submitted the offer the same on your offer as on bid bond?

( ) If required, have you entered a unit price in for each bid item?

(The Solicitation will specifically state when this is necessary.)

( ) Are decimals in unit prices in the proper places? Are your figures legible?

( ) Are the extensions of your unit prices, and your total price correct?

( ) Are all erasures or corrections initialed by the person signing the offer?

( ) Have you not restricted your offer by altering the provisions of the Solicitation?

( ) Is the envelope containing your offer properly identified that it is a sealed offer and does it contain the correct Solicitation number and bid opening time?

SECTION 00050 FORT GIBSON LAKE 1 OF 9

SECTION 00050

SCOPE OF WORK

This action is being procured as part of the American Recovery and Re- Investment Act (ARRA) of 2009.

PART 1 GENERAL

1.1 GENERAL PROJECT DESCRIPTION

The Contractor shall provide all materials, equipment, labor, instruments, tools, subcontractors, supervision, and management to complete all work required by this task order. The Scope of Work in general includes the following: sandblast and paint tainter gates, replace existing side seals and rehabilitate Babbitt on the weir sills, replace hoist chains, prepare and paint hoist machinery, machinery platforms and catwalks, and clean and paint trunnion anchorages and assemblies. The tainter gates are approximately 40 feet wide and 35 feet high. The entire gate including beams, girders, pockets behind cross braces, and strut arms shall be cleaned of all debris, including but not limited to: debris, sludge, water and biological formations.

Blast and paint equipment, equipment platforms, and the access walkways.

a. Tainter Gates – Clean all surfaces to SSPC SP5 (White Metal).

Each gate (to include tie back beam and trunnion arm) shall be painted with system no. 5-E-Z. Either pre-sandblast the corroded areas or sandblast to white metal and apply up to the first coat of paint in the 5-E-Z paint system on the gate. A combined inspection shall then be done with the Corps and Contractor to verify areas that get epoxy. Inspect the gate for corrosion damage 1/8 inch or deeper. Cleaning and painting shall be so programmed that dust or other contaminants from the cleaning process do not fall on wet, newly painted surfaces. Structural repairs shall be made to the gates to fix corrosion damage.

b. Provide and replace the side seal assemblies, including but not limited to seals, bolts, nuts, washers, screws, retainer and spacer for proper fit to minimize water leaks when gates are shut.

c. Repair Babbitt on the weir sill to provide smooth and level surface. Ensure the gate bottom is straight and even to provide a flush watertight seal between the Babbitt and the gate.

d. Replace all existing hoist chains and provide two complete spare chains.

e. Hoist Platforms - Work will include, but not necessarily be limited to, replacing hoist platform anchor bolts, nuts, and washers, and treating pack rust on hoist platform for gate numbers 8, 9, 13, 18, 22, and 29.

f. Hoist Machinery Platform – Work shall include, but not necessarily be limited to, cleaning, preparing for painting, and painting all of the hoist machinery for each of the thirty

SECTION 00050 FORT GIBSON LAKE 2 OF 9

platforms including the top surface of the beams supporting the platforms underneath. Paint shall be System No. 15.

g. Trunnion anchorages and assemblies – Work will include, but not necessarily be limited to, removing residual sealant, debris, laminated rust, and pack rust, unclogging drain holes, cleaning drain holes and pans of debris, removing Plexiglas covers over trunnion assemblies, cleaning trunnion yoke 6” access holes and drain holes, blasting, painting, and greasing the trunnion assemblies, and sealing the pier landings. Painting work consists of blasting to white metal, priming, and painting each trunnion anchorage and assembly in its entirety with System No.

5-E-Z.

h. Pier Landings – Work will include, but not necessarily be limited to, applying a protective finish coating to the concrete at the pier landings starting from where the tie back beams first jut into the concrete extending along the access hallway to the ladder. All of this work shall be done with the purpose in mind to help prevent future rusting of the tie back beam directly below the pier landing.

i. Clean all existing Government property including the gates, weirs, and bridge of all blast media and debris resulting from the Contractor’s construction activities.

Work shall be performed in accordance with the requirements of 29 CFR 1910, 29 CFR 1926, the most recent version of EM 385-1-1, and other references as listed herein. Matters of interpretation of the standards shall be submitted to the Contracting Officer for resolution before starting work. Where the regulations conflict, the most stringent requirements shall apply. The Government stresses the importance of safety on all US Army Corps of Engineers job sites.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 30 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Detailed Work Plan; G

A detailed work plan shall be submitted. The plan shall include details for the following:

a. Pre-sandblast repair of corrosion damage, correct deficiencies,

b. Sandblast, prepare for painting, and painting,

c. Water Control, SECTION 00050 FORT GIBSON LAKE 3 OF 9

d. Traffic Control,

e. Babbitt repair,

f. Side seal replacement,

g. Hoist chain replacement,

h. Rehabilitation of hoist anchor bolts, imbedded steel plate, and pack rust.

1.3 PROTECTION OF EQUIPMENT

Due to the enormous cost of possible repair, the importance of protecting the trunnion assemblies (bronze bushings, steel castings, trunnion pins, keys, keeper plates, etc.) during blasting and painting cannot be over emphasized. Proper protection shall rest solely on the Contractor. Any damage to the trunnion assemblies, as with all damage to Government property, shall be repaired by the Contractor entirely at the Contractor’s expense. Trunnion assembly protection methods shall be submitted to the Contracting Officer for approval before any work begins.

The Contractor shall ensure protection of the hoist equipment to include the controls and gear boxes during all work.

1.4 LEAD PAINT

The existing paint system on the Ft. Gibson tainter gates contains lead. Test results from December 2006 indicate a concentration of 943 mg/Kg on the downstream side, 617 mg/Kg on the upstream side, and 1,460 mg/Kg on the trunnion arm of the tainter gate tested.

1.5 SITE VISIT

An authorized contractor representative in conjunction with the USACE Contracting Officer and/or technical representative(s) shall conduct a site visit at the proposed construction sites. The purpose of this site visit will be to meet with project representative(s) and obtain a more detailed understanding of the work required in this Scope of Work.

This site visit will also allow the contractor the opportunity to examine the project site conditions.

1.6 PRICE PROPOSAL

The price proposal for the task order shall follow the guidance in section 00120 of this request for proposal. Proposals shall be submitted in accordance with the Bidding Schedule. The contractor shall use the information in this Scope of Work in conjunction with information obtained at the site visit as the basis of his proposal.

SECTION 00050 FORT GIBSON LAKE 4 OF 9

1.7 PRE-WORK CONFERENCE

The Contractor shall attend a pre-work conference with the Contracting Officer’s Representative prior to commencing work on the project.

1.8 WORK HOURS

Work hours shall be Monday through Friday, 7 a.m. to 5 p.m. unless otherwise requested in writing by the Contractor and approved in writing by the Contracting Officer. The Contractor shall not work on Federal holidays unless prior approval is granted in writing by the Administrative Contracting Officer. Request and approval shall be on a case-by-case basis.

1.9 GOVERNMENT FURNISHED UTILITIES

At Ft. Gibson Lake, 480V/3 phase/30 amp electric service is available at each tainter gate operating machinery platform (Elevation 584.75).

120V/15 amp single-phase service is available at each pier. Non-potable (raw lake) water is available at the spillway. Electricity and non-potable water are available at no additional cost to the Contractor if proper energy conservation methods are implemented. The Contractor shall be responsible for conditioning the power as necessary and providing conductors, hoses, etc. from existing service locations.

1.10 HISTORICAL DATA

Ft. Gibson Lake monthly charts of reservoir data since November 1994 may be viewed at http://www.swt-wc.usace.army.mil/FGIBcharts.html. Any conclusions drawn by the Contractor from this data are done so at the Contractor’s risk.

1.11 LIMITATION ON GATES OUT OF SERVICE

Only one tainter gate may be worked on or out of service at one time.

1.12 WATER RELEASES

Water releases may impact the Contractor’s operations. Two types of water releases may be made: low flow releases and flood releases. Low flow releases to maintain water quality for fish and wildlife habitat will be made from the outlet works year around as necessary to meet regulatory requirements. The Government will give 24 hours advance notice to the Contractor when water releases and/or gate changes are made for water quality purposes. Wind direction, the gates currently being worked on, and the amount of water to be released will be taken into consideration in an attempt to minimize impact on the Contractor’s work. Flood releases will be made as required for flood damage reduction. In flood release emergencies, every effort will be made to give the Contractor 24 hours notification of gate changes. The Contractor shall constantly monitor weather conditions and forecasts and be prepared for potential emergency conditions. The Contractor

SECTION 00050 FORT GIBSON LAKE 5 OF 9

shall be prepared to secure and protect current working areas and personnel from flood releases. The Contractor’s on-site superintendent will be notified of gate changes by the Government. Phone and/or voice mail notification will be made when Government personnel are unable to contact the superintendent in person.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 TRAFFIC CONTROL

Prior to starting work, the Contractor shall submit a traffic control plan for Government review. The traffic control plan shall cover all work and shall be in accordance with all requirements of this task order and the Manual on Uniform Traffic Control Devices (MUTCD), 2003 Edition. The Contracting Officer may take up to 14 days each to review the traffic control plan and any required revisions. The Contractor shall also submit the traffic control plan to the Oklahoma Department of Transportation (ODOT). The Contractor shall receive ODOT approval before road closure is allowed. All coordination with ODOT shall be the responsibility of the Contractor.

At Ft. Gibson Lake, the road/bridge is State Highway 251A and carries a considerable amount of traffic, especially during morning and afternoon commute periods. Closures shall take place only during work hours specified below and traffic control devices shall be removed after each day’s work. The Contractor shall remove position indicators. Two-lane bridge closure will only be allowed during use of a crane (setting scaffolding or equipment on the trunnion girders, removing position indicators, etc.) and shall take place only between the hours of 9 a.m.

and 3 p.m. Monday through Friday. The Contractor shall notify the Contracting Officer, ODOT, the public, and local, county, and state officials seven (7) calendar days before all partial or complete bridge/road closures. No complete bridge/road closures shall take place two calendar days before, during, or two calendar days after a Federal holiday unless prior approval is granted in writing by the Contracting Officer. Long-term one lane bridge/road closures may be allowed by the Government if proper traffic control in accordance with the MUTCD is provided at all times and the long-term closure is approved by ODOT.

3.2 CRANE PLACEMENT AND BRIDGE LOADING

The Contractor shall not exceed the load limits of the bridge. If the Contractor desires to use a crane on the bridge, he must first analyze the bridge for that crane lifting all proposed loads. The Contractor’s crane/bridge analysis shall be performed by a Licensed Professional Engineer with documented experience in crane dynamic load analyses.

The Contractor shall submit to the Contracting Officer for approval the load analysis and an operation plan showing the size and type of crane, where and how it will be operated, and how the outriggers will be placed. Government review of the plan and any required resubmittals may take up to 30 days for each review. Depending upon the weight, boom, and placement of the outriggers, the bridge may not support crane operations.

SECTION 00050 FORT GIBSON LAKE 6 OF 9

3.3 TAINTER GATE REHABILITATION

3.3.1 Lead Content

The existing paint at Ft. Gibson has a lead content of 943 mg/Kg on the downstream side, 617 mg/Kg on the upstream side, and 1,460 mg/Kg on the trunnion arm of the tainter gate tested. Containment and monitoring measures shall be as specified in Section 09 96 50.

3.3.2 Removal of Bird Screens and Debris on Tainter Gates

Before blasting, all bird screens and debris on the tainter gates shall be removed. All Plexiglas screens covering the trunnion yoke holes shall be removed and discarded.

3.3.3 Preparation

The extent of damage caused by corrosion cannot be fully determined until the corroded areas are blasted. To reveal the extent of damage, the Contractor shall either pre-blast the corroded areas or blast an entire gate to white metal and apply up to the first two coats of paint in the 5-E-Z paint system.

3.3.4 Structural Repair

All structural repairs shall be conducted with the tainter gate in an unloaded condition. An unloaded condition constitutes the gate resting on timbers with bulkhead in place upstream of the tainter gate. No water shall be touching the tainter gate during repair. Any required replacement of structural members shall be performed one at a time.

3.3.4.1 Corrosion Repair Greater Than 1/8 Inch Deep

For all corrosion damage, the Contractor shall document the corrosion damage by taking digital photographs of the damaged areas before and after the repair. The photographs shall have a legible scale/ruler in the picture and a means to indicate size and depth of corrosion.

Locations of corrosion-damaged areas shall be documented by sketches of the gates with measurements from a known point or feature and cross-referenced with the digital photographs. Repair these areas with weld build-up as specified Section 05055 WELDING. To insure no holes, pits, or low areas remain, the entire weld build up area shall extend completely above the original metal profile and be ground back to the original metal profile. Blast to white metal an area covering a minimum 1 foot beyond the weld and apply the first coat of the 5-E-Z paint system. For areas that require weld build-up opposite of a side that has already been painted, these areas shall be jointly inspected on the painted side after the weld is completed. If the paint has been damaged due to welding operations, the area on the painted side shall be repaired by a method to be approved by the Contracting Officer.

3.3.4.2 Corrosion Repair Less Than 1/8 Inch Deep

For all corrosion damage less than 1/8 inch deep, blast to white metal if the area was only pre-blasted then immediately fill the damaged area

SECTION 00050 FORT GIBSON LAKE 7 OF 9

with epoxy coating Belzona 1311, Devcon Plastic Steel Putty, or Thortex Metaltech E.G. Sand the epoxy smooth, clean with solvent, and apply the first coat of the 5-E-Z paint system.

3.6.5 Blasting and Painting

Blast and paint each gate in accordance with the Section 09965A Painting: Hydraulic Structures. The gates shall be blasted to a surface preparation standard of SSPC-SP 5 (white metal). Paint system shall be 5-E-Z. Each subsequent coat of paint shall completely hide previous coat.

3.6.5 Bulkhead Transportation and Placement

The Contractor shall transport and place the bulkhead at Ft. Gibson.

The Contractor shall submit a Bulkhead Transportation and Placement Plan before moving the bulkhead. The plan shall include the proposed method and equipment for bulkhead transportation and placement. Due to the effort required to move the bulkhead during high winds and inflows, a temporary storage location near the structure will be considered if proposed by the Contractor in the bulkhead transportation and placement plan.

3.3.7 Bird Droppings

The Contractor shall minimize exposure by controlling aerosolized dust by saturating built up debris piles. Personnel involved in the cleanup should wear respirators, rubber gloves and disposable coveralls.

Collect wetted bulk material and place in durable secure container and dispose. Not regulated as hazardous material.

3.4 HOIST PLATFORM REHABILITATION AT FT. GIBSON LAKE

3.4.1 Anchor beam bolts

The contractor shall replace all anchor bolts and washers to supporting beams on platforms 8, 9, 13, 18, 22, & 29.

3.4.2 Hoist Platform Girders

The contractor shall rehabilitate pack rust on all the beams at platforms 8, 9, 13, 18, 22, & 29.

3.5 PIER LANDING REHABILITATION AT FT. GIBSON

3.5.1 Seal pier landing

A protective finish coating shall be applied to the concrete at the pier landings starting from where the tie back beams first jut into the concrete extending along the access hallway to the ladder. The protective coating shall be Solarshield Bright White by Macklanburg- Ducan, Rev Cote by Revere, or any approved equal concrete sealant as determined by the Contracting Officer.

SECTION 00050 FORT GIBSON LAKE 8 OF 9

3.6 TRUNNION ANCHORAGE AND TRUNNION ASSEMBLY WORK

3.6.1 Lead Content

The existing paint at Ft. Gibson has a lead content of 943 mg/Kg on the downstream side, 617 mg/Kg on the upstream side, and 1,460 mg/Kg on the trunnion arm of the tainter gate tested. Containment and monitoring measures shall be as specified in Section 09 96 50.

3.6.2 Removal of Gate Position Indicators

Before blasting begins on each trunnion anchorage and assembly, the Contractor shall remove the gate position indicators from the trunnion.

The gate position indicators weigh approximately 200 pounds each. The Contractor shall transport the gate position indicators to a storage facility on Government property as designated by the Contracting Officer. Gate position indicators will not be replaced.

3.6.3 Removal of Plastic (Plexiglas) Covers on Trunnion Assemblies

Before blasting, the Plexiglas covers of the trunnion assemblies shall be removed. Screw holes shall be filled with epoxy material such as Devcon Plastic Steel Putty, Thortex Methal-Tech EG, or a similar material. Covers shall not be replaced.

3.6.4 Removal of Bird Screens and Debris on Trunnion Assemblies

Before blasting, all bird screens and debris inside the 6” access holes in between the strut arms shall be removed. All ¼” drain holes shall be completely cleaned of debris. After blasting and painting, bird screens shall be replaced in kind in all trunnion assemblies.

3.6.5 Removal of Rust and Debris Between Anchor Beams and Concrete Piers

Before blasting, all loose laminated rust, pack rust, scaled rust, debris, and sealant shall be removed from the anchor beams. Removal shall extend 6” inside the face of the concrete piers. The Contractor’s method and equipment for removal shall be submitted to the Contracting Officer for approval. The Contractor shall provide 24 hours notice before any painting beings to allow the Government to inspect the anchor beams after blasting and before painting.

3.6.6 Blasting and Painting

The Contractor shall blast and paint each trunnion anchorage and assembly in accordance with the specification Section 09 96 50 Painting of Hydraulic Steel and Cast Iron Structures, Including Removal of Lead- Based Paint. Paint for all structures shall be System No. 5-E-Z. Each subsequent coat of paint shall completely hide previous coat. Blasting and Painting of the trunnion assemblies shall extend from the extreme downstream end of the trunnion assembly, along the tainter gate strut arms to a point 3 feet past the centerline of the trunnion pin. Using specialized equipment, and/or nozzles, the Contractor shall blast and paint the anchor beams 6” inside the face of the concrete piers.

SECTION 00050 FORT GIBSON LAKE 9 OF 9

3.7 GREASING TRUNNION ASSEMBLIES

After sealing pier landings, the Contractor shall grease the trunnion assemblies. Grease shall be Texaco Starplex 2 or equal. Each assembly shall be greased before the Contractor is allowed to start work on another trunnion anchorage.

3.8 PROTECTION OF GOVERNMENT PROPERTY

In addition to all requirements to protect Government property in the Contract Clauses, and Special Contract Requirements, the Contractor shall take particular care to protect the tainter gate hoist operating machinery assemblies and trunnion assemblies, which are highly susceptible to damage by dust, blast media, and debris. The contractor shall not drill holes or otherwise alter or deface any existing structure including the bridge, bulkhead, trunnion anchorages, trunnion assemblies, tainter gates, piers, bullnoses, weirs, catwalks, or equipment decks unless requested in writing with proposed repair methods and approved in writing by the Contracting Officer.

Scaffolding, work platforms, hoists, chain falls, or other equipment shall not be attached to catwalks or equipment decks unless requested in writing with attachment details and calculations showing the catwalks or equipment decks are capable of supporting the proposed loads and approved in writing by the Contracting Officer.

3.9 CLEAN UP

After completion of construction, the Contractor shall clean all Contractor-generated blast media and construction debris from all gates, weirs, bridge, catwalk, machinery, decks, and assemblies, and all other Government property. The Contractor shall ensure that all drain holes are completely open.

3.10 SUBMITTALS

Certification and manufacturer’s data shall be submitted for the following items:

Welding equipment and operators Welding rods Paint system components Blast media Bird screens Anchor bolts, washers Rust inhibitor Concrete sealant

All submittals shall be in accordance with specification Section 01 30 00 SUBMITTAL PROCEDURES and Section 01 31 20 Quality Control System (QCS). Items shall be submitted and numbered under the technical specification section to which the materials and equipment apply and these numbers shall properly interface with WinRMS and QCS.

(END OF SECTION 00050)

00800-i W912BV-09-R-1014

SECTION 00100

INDEX OF CLAUSES

1. 52.204-6 Data Universal Numbering System (DUNS) Number APR 2008

2. 52.215-13 Subcontractor Cost or Pricing Data--Modifications OCT 1997

3. 52.225-10 Notice of Buy American Act Requirement--Construction Materials

4. 52.228-15 Performance and Payment Bonds--Construction NOV 2006

5. 52.236-28 Preparation of Proposals--Construction OCT 1997

6. 52.0000-4025 PERFORMANCE OF WORK BY CONTRACTOR

7. 52.214-5000 APPARENT CLERICAL MISTAKES (MAR 1995)--EFARS

8. 52.216-1 TYPE OF CONTRACT (APR 1984)

9. 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE

EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

10. 52.228-1 BID GUARANTEE (SEP 1996)

11. 52.233-2 SERVICE OF PROTEST (SEP 2006)

12. 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

13. 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

14. 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

00800-ii W912BV-09-R-1014

00800-1 W912BV-09-R-1014

SECTION 00100

BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

CLAUSES INCORPORATED BY REFERENCE

1. 52.204-6 Data Universal Numbering System (DUNS) Number APR 2008

2. 52.215-13 Subcontractor Cost or Pricing Data--Modifications OCT 1997

3. 52.225-10 Notice of Buy American Act Requirement--Construction Materials

FEB 2009

4. 52.228-15 Performance and Payment Bonds--Construction NOV 2006

5. 52.236-28 Preparation of Proposals--Construction OCT 1997

CLAUSES INCORPORATED BY FULL TEXT

6. 52.0000-4025 PERFORMANCE OF WORK BY CONTRACTOR

Unless he has submitted such description with his bid, the successful bidder must furnish the Contracting Officer within l4 calendar days after award a description of the work which he intends to perform with his own organization (e.g., earthwork, paving, brickwork, or roofing), the percentage of the total work this represents, and the estimated cost thereof. (See Section 00800 clause entitled "Performance of Work by Contractor.")

7. 52.214-5000 APPARENT CLERICAL MISTAKES (MAR 1995)--EFARS

(a) For the purpose of initial evaluations of bids, the following will be utilized in the resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

(b) For the purpose of bid evaluation, the government will proceed on the assumption that the bidder intends his bid to be evaluated on basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.

(c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

(End of statement)

8. 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm fixed price contract resulting from this solicitation.

(End of provision)

00800-2 W912BV-09-R-1014

9. 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

10.2 6.9

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Oklahoma, Wagoner County, Fort Gibson.

00800-3 W912BV-09-R-1014

10. 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be twenty (20) percent of the bid price or $3,000,000 whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of clause)

11. 52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Contracting Officer, Tulsa District, Corps of Engineers, 1645 S. 101st East Avenue, Tulsa, OK 74128.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

12. 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Date of organized site visit is to be determined and will be announced by Amendment.

(End of provision)

13. 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include

00800-4 W912BV-09-R-1014

blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://farsite.hill.af.mil

(End of provision)

14. 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

http://farsite.hill.af.mil

SECTION 00110 FORT GIBSON LAKE 1 OF 6

SECTION 00110

PROPOSAL PREPARATION

PART 1 - GENERAL

1.1 WHERE AND WHEN TO SUBMIT PROPOSAL

Proposals are due as indicated on the Solicitation, Offer and Award form

(Standard Form 1442) found in SECTION 00010 - SOLICITATION, OFFER, AND

AWARD.

1.2 INQUIRIES ABOUT THIS REQUEST FOR PROPOSALS (RFP)

Inquiries about this RFP shall be directed to:

U.S. Army Corps of Engineers, Tulsa District, Contracting Division ATTN: Susan Bruce or Susie Mall 1645 S. 101st East Ave Tulsa, OK 74128

The inquiry should include the solicitation number and section of the solicitation by paragraph, drawing number, or other reference pertinent to the question or inquiry. Oral explanations or instructions are not binding.

Any information given to an offeror which impacts the offer will be provided in the form of a written amendment to the solicitation.

The Tulsa District business hours are from 7:45 AM to 4:30 PM, Monday through Friday. Tulsa District offices are closed on Federal holidays.

1.3 PROPOSAL PREPARATION

Instructions for the preparation and organization of each proposal are included herein. The proposal shall be submitted as summarized below and as required by the specifications.

a. Volume I, Tab A – Past Performance/Experience

(1) Tainter Gate Rehabilitation

(2) Tainter Gate Painting

b. Volume I, Tab B – Management

(1) Financial Capacity

(2) Project organization and staff

(3) Management control systems

(4) Quality control systems

(5) Certifications

(6) Project schedule

(7) Work Plan

d. Volume II - Cost/Price Proposal

(1) Solicitation, Offer, and Award (Standard Form 1442)

(2) Proposal Schedule

(3) Representation & Certifications

(4) Bid Bond

The proposal submittal set shall include the original (paper) and compact disc (CD) formats. The format for each volume is described in the paragraphs below. Include five paper copies and three CD copies of Volume I (Past Performance/Experience and Management). Volume II (Cost/Price Proposal) shall be submitted in the original paper copy only. A separate breakout shall be included for the Cost/Price Proposal for each item listed on the Proposal Schedule. The Cost/Price Proposal shall be sealed in a single package separate from the other proposal volumes and clearly marked as indicated on Standard Form 1442. Do not include the Cost/Price Proposal on the CDs with the Past Performance/Experience and Management information.

1.4 PAST PERFORMANCE/EXPERIENCE (VOLUME I, TAB A)

1.4.1 Content

The past performance/experience area of the proposal shall include the information as described below and shall be presented in the sequence listed.

a. Tainter Gate Rehabilitation

Demonstrate the successful past performance of the team, including subcontractors, to successfully complete rehabilitation of the tainter gates. This section may be in any format but must include the following:

(a) A list of relevant projects, currently underway or completed in the last 5 years that demonstrates your successful past performance.

List no more than five projects. The list of projects shall include the following information:

Project Name and Location Nature of Firm’s Responsibility (design, construction, or both) Project Owner’s Name and Address and Project Manager’s/Point of Contact Name and Phone Number Project Completion Date Overall Size of project (in number and size of gates or other relevant measurement) Project Cost Duration of Construction List of change orders and circumstances on past projects Safety record

Note: Points of contact provided may be selectively contacted, and their comments will affect the evaluation of proposals. It is important to verify that the points of contact listed are still available at the phone number and address provided and that they are individuals who have sufficient knowledge of the project and your performance to be able to offer meaningful comments.

(b) Provide a brief statement (less than 100 words) how each project illustrates your performance capabilities.

b. Tainter Gate Painting

Submit the same information for painting as specified for rehabilitation above.

1.4.2 Format

The Past Performance/Experience proposal (original) shall be submitted in a loose-leaf binder. It shall be typed, the pages shall be numbered, and conform to the format specified. The Past Performance/Experience proposal length shall be limited to 20 single-sided or 10 double-sided pages, printed on 8-1/2" x 11" sheets. Do not use condensed print. A cover sheet identifying the Offeror, project, and RFP number shall be provided. The second sheet shall be a Table of Contents.

The Offeror shall provide the complete Past Performance/Experience proposal on CD. The CD shall contain the entire proposal, printed to .pdf format

SECTION 00110 FORT GIBSON LAKE 2 OF 6

using Adobe Acrobat software. Do not scan the proposal into a .pdf file.

Sections of the proposal shall be bookmarked (linked to the index) in logical order.

1.5 MANAGEMENT (VOLUME I, TAB B)

1.5.1 Content

The Management area of the proposal shall include the information described below and shall be presented in the sequence listed.

a. Financial Capacity

Demonstrate financial capability for providing all necessary activities and services for this project. As a minimum, provide the following:

(1) Current Balance Sheet and Profit/Loss Statement

(2) Summary of litigation, lawsuits, or outstanding judgments

(3) Bonding capacity (letter of current capacity from bonding company)

b. Project Organization and Staff

(1) Approach

(a) Provide an organizational chart which describes how the team shall be structured, i.e., how many firms are involved and the responsibility of each firm for this project.

(b) Discuss how the project team is structured. Demonstrate ability to staff properly the project for the scope of work required. Indicate the responsibilities of each member of the project team.

(c) Demonstrate your firm's ability to establish and maintain a schedule using a network analysis system in accordance with

SECTION 01 32 00 - PROJECT SCHEDULE.

(d) Demonstrate your firm's ability and experience to coordinate personnel and subcontractors in a team effort.

(e) Limit discussion to three pages.

(2) Subcontractors

Provide a potential list of subcontractors; provide their disciplines and to what extent they may be used in this contract. Subcontractors used for this contract must be selected from this list.

Subcontractors and all subcontractor personnel working on this project must be U. S. citizens or documented workers and must be able to provide proof of citizenship or other authorized documentation (See Contract Clause 52.0000-4515 Security Contract Language for All Corps of Engineers’ Unclassified Contracts). Proposed subcontractor replacements must be approved by the Contracting Officer.

c. Management Control Systems

(1) Quality Assurance

Demonstrate ability to control quality throughout the rehabilitation and painting process including testing, inspection, and safety.

(2) Controlling Schedule

SECTION 00110 FORT GIBSON LAKE 3 OF 6

Demonstrate management’s ability to control the schedule. Present the plan to control the schedule. Demonstrate ability to minimize time overruns due to changes, unforeseen circumstances, and delays.

Present the plan for maintaining the schedule. Describe the time control systems to be utilized and how time control savings shall be presented.

(3) Limiting Cost Growth

Demonstrate management’s ability to maintain a project budget during construction. Describe the cost control systems and procedures that shall be utilized. Describe a plan to minimize cost overruns caused by changes, unnecessary specification requirements, unforeseen circumstances, and delays.

(4) Past Success

Verify management control with examples of past successes. Limit discussion to two pages.

e. Quality Control Systems

Provide narrative of methods of field quality control, including corrosion repair, welding, raising and reinstallation of gates, placement of bulkhead, match Government specified finishes, and other quality standards specified in the specifications for this solicitation.

f. Certifications

Provide all certifications for personnel who will be participating on the project to include: welders, safety personnel, industrial hygienist, etc. Include certifications of subcontractor if known, otherwise provide a listing of certifications the subcontractor will be required to have.

g. Project Schedule

Submit a Gantt chart type schedule reflecting the activities from Notice to Proceed (NTP) through completion.