MAINT DREDGING - DELAWARE RIVER - PHILADELPHIA PA TO TRENTON NJ_CONSTRUCTION SPECS_JUNE 2025.pdf
PDF 35 MB Posted
- Solicitation number
- W912BU25BA008
About this file
This is an Invitation for Bid (IFB) for maintenance dredging services issued by the U.S. Army Corps of Engineers Philadelphia District. The firm fixed-price construction contract requires hydraulic cutterhead dredging of approximately 470,000 cubic yards of sediment from the Delaware River navigation channel between Philadelphia and Trenton, including the Fairless Turning Basin. Dredging must be performed to a depth of 41 feet MLLW plus one foot overdepth, with all material placed in the Money Island Disposal Area in Falls Township, Pennsylvania.
The solicitation (W912BU25BA008) is classified under NAICS code 237990 with a $45 million size standard, with an estimated contract value between $10-25 million. The project has a 240-calendar day performance period, with all dredging operations required to be completed by March 15, 2026, due to environmental restrictions. A mandatory pre-bid site visit is scheduled for July 8, 2025, at 10:00 AM EDT, with bidders required to be registered in the System for Award Management (SAM) and submit bids through the PIEE Solicitation Module. The bid submission deadline is July 28, 2025, with work to be performed in Bristol, Pennsylvania.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB W912BU25BA0008
US Army Corps of Engineers
Philadelphia District
Maintenance Dredging
Delaware River
Philadelphia, Pennsylvania to
Trenton, New Jersey
Construction Specifications
June 2025
This page was intentionally left blank for duplex printing.
IFB W912BU25BA008
SECTION 00 50 05
PRE-AWARD SURVEY SUBMITTAL REQUIREMENTS
PART 1 GENERAL
1.1 DEFINITIVE RESPONSIBILITY CRITERIA
Award of this Contract will be made as a whole to the lowest responsive and responsible Bidder whose bid conforms to all requirements of the specifications. Subsequent to the bid opening, the apparent low Bidder shall submit Pre-Award Survey Information that demonstrates compliance with the requirements set forth in this section as a precondition to receiving award.
1.2 GENERAL PRE-AWARD SURVEY INFORMATION
Complete the pre-award survey information sheets attached to this section, and submit to the Contracting Officer within 5 calendar days after bid opening.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
Section 00 50 05 Page 1
US ARMY CORPS OF ENGINEERS
PHILADELPHIA DISTRICT
PRE-AWARD SURVEY
A. GENERAL INFORMATION
1) Name of Firm: ___________________________________________________________________
Address: __________________________________________________________________________
Phone: _____________________________________ Fax:__________________________________
Email: ____________________________________________________________________________
CAGE CODE:
If your company has more than one CAGE Code, please list all that apply.
2) Location where accounts are kept (if different than item 1 above): ____________________________
3) Type of Firm (Please check one):
Sole Proprietorship [ ] Partnership [ ] Corporation [ ] Joint Venture [ ] Other
Date Organized: ____________________________________
Date Incorporated: __________________________________
State of Incorporation: _______________________________
4) Attach list of Name of Officers.
Please check "Yes" or "No" for each of the following:
Have current officers of your firm ever been indicted? Yes [ ] No [ ]
Are any of your officers currently under indictment? Yes [ ] No [ ]
If you have answered "Yes" to either of the above, please attach an explanation.
5) Has your firm been terminated for default on any contracts in the past six years? Yes [ ] No [ ] (If yes, please attach an explanation)
00 50 05 Page 2
B. PROPOSED SCHEDULE
Submit a preliminary schedule depicting your project plan from start to final completion. The schedule you submit will be used to determine your ability to successfully perform the project within the time frame stated in the specifications.
IAW FAR 52.236-15, Schedules for Construction Contracts, you will be required to submit a fully loaded schedule within five days after work commences on the awarded contract.
C. PERFORMANCE AND PAYMENT BOND INFORMATION
1) Performance & Payment Bonds will be furnished by:
Name of Company: _______________________________________________________________
Phone No: _____________________________________________________________________
2) Firm's bonding capacity as authorized by your Insurance Company:
Single Project: ___________________________________________________________________
Aggregate Basis: _________________________________________________________________
D. BANKING INFORMATION
Name of Bank: ___________________________________________________________________
Address: ________________________________________________________________________
Account Representative: ____________________________________________________________
Phone No: ________________________________ E-mail: _______________________________
Authorized Credit Line: ________________________________________________
If additional banks are utilized, please provide this information for each.
E. INSURANCE INFORMATION
Name of Insurance Company: ______________________________________________________
Type of Insurance Provided: _______________________________________________________
Insurance Agency: _______________________________________________________________
Address: _______________________________________________________________________
Agent: _________________________________________________________________________
Phone No: ______________________________ Email: _________________________________
If more than one insurance company is utilized, please provide this formation for each.
00 50 05 Page 3
F. FINANCIAL DATA
Please provide the last two certified public accountant's financial statements.
G. SAFETYDATA
Please check "Yes" or "No" for each of the following:
1. Does your firm have a Standard Operating Procedure for Safety?
Yes [ ] No [ ] If yes, please provide a copy.
Does your firm have a Policy Letter dealing with Safety?
Yes [ ] No [ ] If yes, please provide a copy.
2. What was your accident rate for last year? _____________________
3. What is your accident rate to date for this year? ____________________
H. QUALITY CONTROL DATA
Please check "Yes" or "No" for each of the following:
1. Does your firm have a Standard Operating Procedure for Quality Control?
Yes [ ] No [ ] If yes, please provide a copy.
2. Does your firm have a Policy Letter dealing with Quality Control?
Yes [ ] No [ ] If yes, please provide a copy.
I. EQUIPMENT DATA
Please provide the following data for each piece of construction equipment (including equipment you will rent or lease), intended to be used on the project. Do not include consumables.
Make Year Mfg.
Description Purchase Price (if equipment is owned) Size Book Value (if equipment is owned) Model Number Unpaid Balance (if equipment is owned)
J. EXPERIENCE DATA
1. Please provide the following data for all major projects in progress or completed with the past three years.
Also, provide the same data for Corps of Engineer projects completed within the last five years. Those projects containing work similar in nature to that involved under this solicitation are to marked with an asterisk (*).
Name and Address of Owner Point of Contact and Telephone Number Project Location Type of Work performed by your firm Indicate whether you performed as a prime or subcontractor Name of Architect/Engineer in charge for Owner Address of Architect/Engineer Contract or Subcontract Amount Approximate date completed or, if not completed provide percent complete
00 50 05 Page 4
Were time extensions necessary? Were penalties imposed? Were liens, claims or stop work orders filed?
2. How many years have you been in business as a contractor? ________________________________
3. How many years experience in the type of work involved in the subject solicitation do you have
a) as prime contractor? ___________________________________
b) as a subcontractor? ___________________________________
K. KEY PROJECT PERSONNEL
Please provide resumes for each of the following key personnel to be assigned to this project:
Project Engineer, Superintendent, Quality Control Manager/Technician, Safety Technician, Office Engineer
(Signature of Person Supplying Data)
(Print or Type Name and Title of Person Supplying Data)
(Phone No.)
(Email Address)
00 50 05 Page 5
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 DIVING SERVICES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 05 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING
35 20 23.33 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM PIPELINE
HYDRAULIC DREDGE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
33 CFR 88 ANNEX V: PILOT RULES
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification. Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Superintendent's Qualifications; G
Evidence Of Insurance
Notice To Mariners
Movement Of Navigation Aids
Placing Submerged Pipelines Across The Channel
SD-11 Closeout Submittals
Certified Labor Payrolls
1.3 SUPERVISION
1.3.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent
Section 01 30 00 Page 1 are the same as for the project superintendent. Submit superintendent's qualifications prior to mobilization to the work site..
1.3.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.3.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.3.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.4 PRECONSTRUCTION CONFERENCE
Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The conference must take place after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, and the processes for joint risk management between the Contractor and Government, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.4.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.5 U.S. COAST GUARD COORDINATION MEETING
Prior to any work, contact U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue, Philadelphia, PA 19147, to conduct a coordination
Section 01 30 00 Page 2 meeting with U.S. Coast Guard, the Contractor, and USACE to facilitate safe marine traffic scheme for navigation.
1.6 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (FAR 52.236-4)
a. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys. Samples of material to be dredged and dated as shown were obtained by using vibracore and grab sampling.
b. Tide Data. The mean ranges of tides in the Delaware River are approximately 6.4 feet at Burlington, NJ and 6.0 feet at Pier 11 North in Philadelphia.
c. Weather Conditions. The site of the work is sheltered from storms. It is believed that work can be performed during all seasons of the year except during winter months when ice conditions may interfere with dredging operations. Complete weather records and reports may be obtained from the local U.S. Weather Bureau Office nearest to the work site. The Contractor shall satisfy himself as to the hazards likely to arise from weather conditions during the construction period.
d. Channel Traffic. Traffic in the work area consists of ocean going and coastwise vessels, tugs and barges, and pleasure craft. Passing vessels may interfere with dredging operations.
e. Conditions of Channel and Turning Basin. The channel and basin conditions shown on the drawings represent the results of surveys made on the dates indicated and can only be considered as indicating the general conditions at that time.
f. Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor is required to conduct the work in such a manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. The Contractor shall request the U.S.
Coast Guard to issue a Notice to Mariners for each work assignment advising navigation interests that the Contractor's dredging plant will be operating in the work assignment waterway. The Contractor shall submit each such request to the U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue, Philadelphia, PA, 19106 for Delaware River work assignments. The Contractor shall furnish a copy of each request to the Contracting Officer not less than five days prior to the start of dredging. Each request shall contain the approximate time required for completion of dredging. The Contractor shall also notify the U.S. Coast Guard prior to the movement of his dredge plant from one acceptance section to another on the opposite side of the channel. Upon completion of dredging in a work assignment area, the Contractor shall promptly remove his plant, including ranges, buoys, piles and other marks placed by
Section 01 30 00 Page 3 him under the contract in navigable waters and on shore.
g. Navigation Aids. Do not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete dredging operations under this contract, notify the Fifth Coast Guard District (dpw) at least 45 days prior to the desired date for movement of the aid. To request a relocation, contact Waterways Management Section, Assistant Section Chief/NJ, DE, PA: LTJG Julie Delesandri at (757)398-6516; e-mail cgd5waterways@uscg.mil or FAX (757)398-6303 at least 45 days before the desired date for movement of the aid. When making a request by telephone, speak to the designated points of contact. The leaving of voicemail messages will not be acceptable. The Fifth CG District (dpw) will coordinate all temporary relocations or discontinuances. A copy of each request to the USCG for Movement of Navigation Aids (including records of telephone conversations) shall be furnished to the Contracting Officer.
h. Location. The location of the work is in the Delaware River between Philadelphia, PA and Trenton, NJ, near Newbold Island.he Contracting Officer reserves the right to issue additional work assignments in the Delaware River project channel. Should additional work assignments be issued, the Government will make available appropriate disposal area locations.
i. Laying of Submerged Pipelines and Obstruction of Channel. All discharge pipelines crossing the navigation channel shall be submerged. Should it become necessary in the performance of this contract to use a submerged pipeline, the Contractor shall notify the Contracting Officer in advance of the schedule for placement of the pipeline. If the submerged line is to be placed across a navigable channel, the Contractor shall submit a request for approval, at least 3 working days (Sundays and holidays excluded) prior to the desired closure date, to the U.S. Coast Guard, MSO/Group Philadelphia, 1 Washington Avenue Philadelphia, PA 19147. A copy of each request to the USCG for placing submerged pipelines across the channel shall be furnished to the Contracting Officer. This request shall contain the following information:
(1) Location (Channel Centerline Stationing) and depth (over the top ofthe pipeline) at which the submerged line will be placed;
(2) The desired length of time the channel is to be closed;
(3) The date and hour placement or removal will commence;
(4) The date and hour of anticipated completion; and
(5) The name and telephone number of the person to be contacted for information and response to any emergency condition.
The Coast Guard has indicated that the requirements of navigation may make it necessary to establish times other than those requested. Coordinate plans with the Coast Guard sufficiently in advance of the planned closing to prevent delay to the dredging operations and comply with the Coast Guard requirements. The minimum depth to the top of any submerged pipe in the Delaware River shall not be less than that shown as the required dredging depth.
j. Bridge and Utility Crossings:
Section 01 30 00 Page 4
(1) Bridges: The following bridges cross the project waterway. The vertical clearances stated are above mean high water.
Horizontal Vertical Miles Bridge Type Clearance Clearance above Mouth
Penn Central RR Co. Vert. Lift 500 ft.(down) 49 ft. 104.6 Philadelphia, PA to 135 ft.(up) Delair, NJ
Betsy Ross Bridge Fixed Hwy. 620 ft. 135 ft. 104.8 Philadelphia, PA to Pennsauken, NJ
Tacony-Palmyra Bascule Hwy. 240 ft. 53 ft. 107.2 Bridge Philadelphia, PA to Palmyra, NJ
Burlington-Bristol Vert. Lift 500 ft.(down) 62 ft. 117.8 Bridge 135 ft.(up) Burlington, NJ to Bristol, PA
PA - NJ Turnpike Fixed Hwy. 620 ft. 135 ft. 121.2 Bridge
(2) Utility Lines: The locations and elevations of all known utility lines crossing the river are presented in the following table:
Location Description Elevation
Upstream side of Penn 11 submarine cables 48 ft below MLW Central Railroad (1 communication, across draw opening Bridge 2 signal, 4 bridge operating, and 4 emergency)
300 ft upstream from (2) 12-inch 65 ft below MLW Penn Central Railroad submarine gas Bridge pipelines
Tacony-Palmyra Bridge (2) control cables natural bottom
(2) power cables and
(1) telephone cable (all submarine)
0.5 miles downstream aerial electric power 140 ft above MLW from Burlington- lines Bristol Bridge
Burlington Island to telephone cables unknown Bristol, PA
The Contractor shall take all necessary precautions to prevent damage to these utilities. The Contractor shall cause timely notice of the dredging
Section 01 30 00 Page 5 to be given to the owners and, when in the opinion of the Contractor such action is necessary, he shall request the Government require said owner or owners to mark the pipelines or move the cables so as to avoid interference with the dredging operations. Any request made by the Contractor shall be within 30 days following his receipt of the Notice to Proceed.
Disclaimer: The above information may not be complete and it is the Contractor's responsibility to investigate all utility crossings.
k. Current Meter: The Contractor shall be aware of the NOAA current meter at Newbold (vicinity of Kinder Morgaan Facility). The meter is located on the south side of Newbold range approximately 200 ft. east of buoy "R78".
Coordinates are 40 deg 08.0660' N, 074 deg 45.0059'W. The data cable to shore (1/2" diameter steel) runs along the bottom, NNW directly to the white NOAA tide house on the corner of the Kinder Morgan (Fairless) pier (40 deg. 08.234'N, 074 deg. 45.118'W).
l. Bridge to Bridge Radio Telephone Equipment. In order that radio telephone communication may be made with passing vessels, all dredges engaged in work under the contract shall be equipped with and operate bridge-to-bridge radio telephone equipment. The radio telephone equipment shall operate on VHF Channel 13 (156.65 MHZ) with low power output having a communication range of approximately ten miles. The frequency has been approved by the Federal Communication Commission.
m. The most recent contract maintenance dredging within the Delaware River upper portion of DPT project and the Fairless Turning Basin was accomplished under Contract No. W912BU23C0016 by Seaward Marine Corporation.
n. Disposal Area: The Government-furnished disposal area available for this contract is:
Money Island Cell B
Coordinate the dredge discharge pipeline location, limits, and all other disposal area issues with Mr. Dan Kelly, 215-656-6889, CENAP-OP.
o. "Abstract of Bottom Samples" are included as APPENDIX B40 of this contract.
p. "Sediment Core Logs" are included as APPENDIX B41 of this contract.
q. Survey Controls. Survey control description sheets are included in
APPENDIX A30.
r. Magnitude of the Contract Work. The estimated value of the contract is between $5,000,000 and $10,000,000.
1.7 LAYOUT OF WORK (DEC 1996)
The Contractor shall lay out its work from Government-provided channel coordinates and survey control points, furnished as part of each work assignment. The Contractor shall furnish, at its own expense, such stakes, templates, platforms, equipment, range markers and labor as may be required in laying out any part of the work, from the channel coordinates and surveying benchmarks furnished by the Government and shall be responsible for all measurements in connection therewith. If any Government control is found disturbed or destroyed, this must be
Section 01 30 00 Page 6 communicated to the Philadelphia District Surveys Branch through the COR before any control is re-established. The Contractor shall be responsible for executing the work to such lines and grades as may be established or indicated by the Contracting Officer. (CENAP)
1.8 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING WAGE
RATE REQUIREMENTS STATUTE CERTIFIED LABOR PAYROLLS (APRIL 2011)
a. The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.
b. If the contractor elects to use an electronic payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with the Wage Rate Requirements statute. When the contractor uses an electronic payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of this construction contract.
The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
c. The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the Federal Acquisition Regulation (FAR);
(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government's RMS;
(5) demonstrated security of data and data entry rights;
(6) ability to produce contractor-certified electronic versions of weekly payroll data;
(7) ability to identify erroneous entries and track the date/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;
Section 01 30 00 Page 7
(8) capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.
d. All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract. (UAI 5152.222-9000)
1.9 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 1995)
a. This clause does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and Federal Acquisition Regulation (FAR) part 49.
b. Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region I. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
c. Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
d. When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate.
The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet. (UAI 5152.231-9000)
1.10 SIGNAL LIGHTS (FEB 1983)
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and
Section 01 30 00 Page 8 vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working navigable channels, as approved by the Commandant, U.S. Coast Guard with respect to vessels in inland waters ( 33 CFR 88 ), as applicable. (CENAP)
1.11 CONTINUITY OF WORK (APR 1965 OCE)
No payment will be made for work done in any area designated by the Contracting Officer until the full depth required under the contract is secured in the whole of such area, unless prevented by ledge rock, nor will payment be made for excavation in any area not adjacent to and in prolongation of areas where full depth has been secured except by decision of the Contracting Officer. Should any such nonadjacent area be excavated to full depth during the operations carried on under the contract, payment for all work therein may be deferred until the required depth has been made in the area intervening. The Contractor may be required to suspend dredging at any time when for any reason the gages or ranges cannot be seen or properly followed. (CENAP)
1.12 SHOALING (1965 APR OCE)
If before the contract is completed, shoaling occurs in any section previously accepted, including shoaling in the finished channel, because of the natural lowering of the side slopes, redredging at contract price, within the limits of available funds, may be done if agreeable to both the Contractor and the Contracting Officer. (CENAP)
1.13 INSPECTION (DEC 1996)
The presence of the inspector shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor will be required:
a. To furnish, on the request of the Contracting Officer or any inspector, the use of such boats, boatmen, laborers, a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary in inspecting and supervising the work.
b. To furnish, on the request of the Contracting Officer or any inspector, suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant and to and from the disposal areas.
Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor. (CENAP)
1.14 PERFORMANCE EVALUATION OF CONTRACTOR (MAR 2014)
a. As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work for contracts less than one year in duration.
Contracts in excess of one year will receive at a minimum, an annual interim evaluation in addition to the final evaluation. However, interim evaluation may be prepared at any time during contract performance when determined to be in the best interest of the Government. The evaluation
Section 01 30 00 Page 9 will be entered into the Contractor Performance Assessment Reporting System (CPARS).
b. CPARS is a web-enabled application that supports the completion, distribution, and retrieval of construction contract performance evaluations. CPARS is for UNCLASSIFIED use only. An evaluation assesses Contractor performance and provides a record, both positive and negative, on a given contract. Each evaluation is based on objective facts and supported by contract management data, such as contract performance elements that evaluate quality, timely performance, effectiveness of management, and compliance with contract terms, labor standards, and safety requirements. The Contractor will be rated either outstanding, above average, satisfactory, marginal, or unsatisfactory in the areas of Contractor Quality Control, Timely Performance, Effectiveness of Management, Compliance with Labor Standards, and Compliance with Safety Standards. The Contractor will be advised of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all Contractor comments will be made a part of the official record. Performance Evaluation Reports will be available to all DOD Contracting offices for their future use in determining Contractor responsibility, in compliance with ER 415-1-17.
c. Upon successful award of the contract, the Contractor will be notified by CPARS via email that access has been granted to a contract within the system. The email will contain instructions of how to log into the system. (CENAP)
1.15 ACCOMMODATIONS AND MEALS FOR GOVERNMENT INSPECTORS (1965 APR OCE)
a. The Contractor shall furnish regularly to Government inspectors on board the dredge a suitable separate area for an office. A separate trailer on the dredge may be supplied in lieu of a room. The trailer must be securely lashed to the dredge and enclosed by railings. The room or trailer shall be fully equipped and maintained to the satisfaction of the Contracting Officer; it shall be properly heated, ventilated, lighted and insulated from noise, and shall have a desk which can be locked, a chair for each inspector, and washing conveniences. The entire cost to the Contractor for furnishing, equipping and maintaining the foregoing accommodations shall be included in the cost of all bid items. If the Contractor fails to meet these requirements, the facilities referred to above will be secured by the Contracting Officer, and the cost thereof will be deducted from payments to the Contractor.
b. If the Contractor maintains on this work an establishment for the subsistence of his own employees, he shall, when requested, furnish to inspectors employed on the work, and to all Government agents who may visit the work on official business, meals of a quality satisfactory to the Contracting Officer. The meals furnished will be paid for by the Government at a rate of $5.00 per person for each meal. (CENAP)
1.16 REQUIREMENT TO NOTIFY COAST GUARD OF RELEASE OF OBJECTS INTO THE
NAVIGABLE WATERS OF THE UNITED STATES
a. Requirement: As soon as a person has knowledge of any release from a vessel or facility into the navigable waters of the United States of any object that creates an obstruction prohibited under section 403 of this title, such person shall notify the Secretary and the Secretary of the Army, and the COR of such release.
Section 01 30 00 Page 10
b. Restriction on use of notification: Any notification provided by an individual in accordance with subsection (a) of this section may not be used against such individual in any criminal case, except a prosecution for perjury or for giving a false statement.
(Pub. L. 92–340, §15, as added Pub. L. 109–241, title VI, §602, July 11, 2006, 120 Stat. 553.)
1.17 INSURANCE REQUIREMENTS
Evidence of Insurance: Evidence of the following insurance shall be submitted to the Contracting Officer prior to commencement of work.
Insurance shall be maintained throughout the period of performance:
a. General Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $500,000 per occurrence.
b. Automobile Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $200,000 per person and $500,000 per accident. Property Damage Liability - $20,000 per accident.
c. Workmen's Compensation and Employer's Liability Insurance: Compliance with applicable workmen's compensation and occupational disease statutes is required. Employer's liability coverage in the minimum amount of $100,000 is also required."
d. Applicable Marine Casualty and Marine Workmen's Compensation Insurance: As appropriate for this contract.
1.18 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project that includes joint risk management, without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.18.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
Section 01 30 00 Page 11
d. The Partners will determine the frequency of the follow-on sessions.
e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
1.19 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 MEASUREMENT AND PAYMENT
The work specified in this section will not be measured for payment and all costs in connection therewith shall be included in the costs of all the bid items.
Section 01 30 00 Page 12
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Section 01 33 00 Page 1
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Baseline Network Analysis Schedule (NAS)
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan (APP)
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Section 01 33 00 Page 2
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submittal Register; G
Section 01 33 00 Page 3
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.2 For Information Only (FIO)
Submittals not requiring Government approval will be for information only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.5 PREPARATION
1.5.1 Transmittal Form
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.2.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Submit an electronic copy of drawings in PDF format.
Section 01 33 00 Page 4
1.5.2.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
Reserve a blank space, no smaller than 3 x 4 inches on the right-hand side of each sheet for the Government disposition stamp.
1.5.2.3 Format of SD-03 Product Data
Present product data submittals for each section as a complete, bound volume . Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.2.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.2.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance.