About this file
This document is an amendment to a Request for Information (RFI) for an Indefinite Delivery Indefinite Quantity (IDIQ) Architectural and Engineering Services contract for the U.S. Army Corps of Engineers (USACE) - Philadelphia District. The amendment provides responses to questions submitted by potential offerors, clarifying information about the contract requirements and evaluation criteria. Key details include:
The contract is a Small Business Set-Aside with a total maximum capacity of $24 million. The contract will be for general engineering and design services to support the Philadelphia District's Civil Works Program. The responses confirm that submissions will be evaluated based on the criteria in the solicitation synopsis, not the detailed Statement of Work. Relevant projects completed outside the 7-year window will be considered, but carry less weight. The agency plans to post additional amendments on July 10 and July 19 to provide further clarification and answers to questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Synopsis - CW Program AE IDC 18July24 Changes from RFIs.pdf | ||
| Synopsis - CW Program AE IDC 10July24 Changes from RFIs.pdf | ||
| Amendment 2_ CW IDC RFIs responses.xlsx | XLSX spreadsheet | |
| SOW CIV Pgm AE IDC _final.docx | DOCX document | |
| Attachment B_NAVFAC_USACE_PPQ.pdf | ||
| Synopsis - CW Program AE IDC.pdf | ||
| SF330.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFI # | Question | USACE Response |
| 1 | What was the award number of the previous Philadelphia A&E IDIQ | W912BU18D0007 |
| 2 | The Word document attachment, “SOW CIV Pgm AE IDC _final.docx,” mentions many additional services not included in the synopsis, such as electrical engineering, fire protection engineering, etc. Does our submission need to include qualifications for every service listed in this Word document or just the services listed in the synopsis? | Submission should address qualifications listed in the synopsis. |
| 3 | On page 7 of the synopsis under Submission Requirements Excluded from the SF330 70 Page Limitation, ISRs and Commitment to Small Business are listed. As this contract is a Small Business Set Aside and these items are not referenced anywhere else in the synopsis,. are these items still required to be submitted with the response? | That section will be revised to remove ISRs and commitment to small business since they are not required for this solicitation. |
| 4 | Is one 11 x 17 page acceptable for the organizational chart | Yes |
| 5 | Confirm that firms' submittals will be evaluated strictly against the scope listed in the Synopsis under III. Selection Criteria A and NOT the scope of work provided in the Word file titled, "SOW_CIV_Pgm_AE_IDC__final.docx". | SF330s will be evaluated against criteria in the Synopsis, not against the SOW |
| 6 | Confirm if Section II. Project Information in the synopsis will be part of the evaluation under Selection Criteria A. For example, Section II states that high voltage distribution may be included under this contract, yet there is no mention of electrical scope in Criteria A or an electrical engineer in Criteria B. | SF330s should be tailored to the criteria set forth in factors listed in the solicitation; in this example high voltage distribution and electrical engineer is not part of the evaluation criteria |
| 7 | Confirm that relevant Section F projects completed outside the 7-year window will still be evaluated (with less consideration). | Projects may be completed outside the 7 year window and will receive less consideration. |
| 8 | Since development of our submittal will rely heavily on your response to our questions, please consider publishing answers to questions as soon as possible. | Acknowledged |
| 9 | If you have specific date you will be releasing answers to questions, please publish the date in SAM.gov to allow firms to plan for adjustments that may be necessary. | Acknowledged, schedule for posting amendments is 10 July and 19 July |
| 10 | Confirm that a PPQ (using the NAVFAC/USACE form) completed for another pursuit may be submitted in this response. | That is correct |