Amendment 0003-Specs.pdf

PDF 3 MB Posted

Attached to
Periodic Nourishment - Beachfill, Long Beach Island, NJ
Solicitation number
W912BU24B0009
Issued by

About this file

This document appears to be an Amendment to a federal solicitation, specifically Amendment 0003 to Solicitation W912BU24B0009 for the Beach Nourishment project on Long Beach Island, New Jersey. The amendment provides responses to Requests for Information (RFIs) and revises several specifications and contract documents, including the Bid Schedule, Option Table, and technical sections such as Construction Photography, Survey Requirements, and Dune Crossovers. The key changes include extending the bid opening date, revising the maximum dredging depth for the borrow area, clarifying survey and photo documentation requirements, and making minor technical specification updates. The solicitation is for a firm-fixed-price construction contract with a base bid quantity of approximately 1,750,000 cubic yards of beachfill, plus multiple options to place additional quantities. The contract period of performance is 270 calendar days.

View the file

Other files

File Type Posted
Bid Abstract-W912BU24B0009-Long Beach Island-Final.pdf PDF
Amendment 0003-Dwgs.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
SOLICITATION W912BU24B0009-XYZ File.txt TXT text file
SOLICITATION W912BU24B0009-Dwgs.pdf PDF
SOLICITATION W912BU24B0009-Specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. CONTRACT ID CODE PAGE OF PAGES

J 1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU24B0009

X 9B. DATED (SEE ITEM 11)

28-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 0003 is hereby issued for the following:

To provide RFIs responses.

To provide a revised option bid schedule, specifications revision and drawings.

Extend the Bid Opening Due Date from 08 May 2024 at 1:00 pm EST to 15 May 2024 at 1:00 pm EST.

Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER AND AWARD) as Amendment No. 0003. Failure to acknowledge all amendments may be cause for rejection of the bid.

****************THE BID OPENING DATE HAS EXTENDED TO MAY 15, 2024, AT 1:00 PM EST*******************

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION

NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE

DATE

01 May 2024

-2024CODE

U.S. ARMY CORPS AND ENGINEERS - PHILA

1650 ARCH STREET

PHILADELPHIA PA 19103

W912BU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

This page was intentionally left blank for duplex printing.

Amendment No. 0003

IFB W921BU24B0009

Requests for Information and Responses

1) Can you please provide the latest survey data of the borrow area?

ANSWER: The latest survey we have is provided. The survey was performed in November

2020.

2) Can you please provide the anticipated date of NTP?

ANSWER: A specific date for the NTP cannot be forecasted at this time. NTP is dependent on the successful low bidder timely submission of pre-award survey documentations and timely submission of required post award documents. If all documents are approved, then NTP may be issued at that time.

3) In reference to section 01 32 33, Part 3, Section 3.1, is the pre-construction photo requirement a minimum of 25 images total for the entire project or 25 of each town/option area?

ANSWER: A minimum of 10 pre-construction photos are required for each town.

Specification section 01 32 33 has been revised to reflect this change.

4) In reference to section 01 32 33, Part 3, Section 3.1, are the weekly construction photos to be taken only of what is currently under construction?

ANSWER: Monthly construction photos are to be taken only of what is currently under construction. Specification section 01 32 33 has been revised to reflect this change.

5) In reference to section 01 32 33, Part 3, Section 3.1, can you confirm that the weekly construction photos required are 10 photos total and not 10 photos of each definable feature of work?

ANSWER: Monthly construction photos are 10 photos total, but request these photos consist as much definable features practical. Specification section 01 32 33 has been revised to reflect this change.

6) In reference to section 01 32 33, Part 3, Section 3.1.1, are hard copies of the construction photograph images required or just the digital images?

ANSWER: Only digital images are required.

7) In reference to section 01 32 33, Part 3, Section 3.2, do you want aerial obliques of the entire project each month or just the area under active construction?

ANSWER: Aerial obliques are to be provided for the entire project each month.

8) In reference to section 01 32 33, Part 3, Section 3.2.1, are hard copies of the aerial obliques required or just the digital images?

ANSWER: Only digital images of aerial obliques are required.

9) In reference to section 01 32 33, Part 3, Section 3.3.1, is there a required time frame for the aerial obliques to be taken in similar to the time frame for the geo-referenced aerial imagery?

ANSWER: Refer to the time frames specified in paragraphs 3.2 and 3.2.1 of specification section 01 32 33.

10) In reference to section 01 32 33, Part 3, Section 3.3.3, are hard copies of the geo-referenced aerial images required?

ANSWER: Only Digital images of the geo-referenced aerial images are required.

11) In reference to section 01 57 19, Part 3, Section 3.4.2, “Prior to the nesting season(s), ENSP will delineate the portions of the project area that contain highly suitable nesting habitat.

These are the areas, as well as existing nesting areas, that require monitoring during the nesting season. Monitoring of these areas shall begin a minimum of 2 weeks prior to construction activities within the suitable nesting habitat.” Is the two weeks prior to project construction as a whole or 2 weeks prior to construction activities in those particular areas?

ANSWER: This applies to construction as whole.

12) In reference to section 01 71 23, Section 3.6.1, is there a required time frame for the Pre-

Project and Post-Project surveys?

ANSWER: Refer to paragraph 3.2.4.1 of the revised specification section 01 71 23 included in this amendment.

13) In reference to section 01 71 23, Section 3.7.1, are the pre-placement condition surveys to be ran for the entire project at once or just the specific work areas 21 days prior to commencing work there?

ANSWER: Pre-condition surveys are to be collected for specific works areas 21 days prior to commencing work in that area. Specification section 01 71 23 has been revised for clarity.

14) Is planting to be conducted all at once, as the project progress after fencing has been installed in a particular location, or per town/option area as it is completed?

ANSWER: See Order of Work required in Section 32 92 00. Plantings can be installed at contractor’s discretion during the appropriate planting windows outlined in the specifications.

15) Can you please confirm if the contract time stated includes completion of all planting since planting is only allowed during a certain period of the year?

ANSWER: Dune grass planting and fertilizer may be completed outside of the 270 days due to seasonal planting and fertilizer time restrictions, but not later than one planting and fertilizer season after dune construction per specification section 32 92 00 Sand Fence and

Dune Grass.

16) We kindly request a two-week extension to the bid date.

ANSWER: Bid due date will be extended 14 days.

17) Could you please provide the most recent borrow area survey data for IFB W912BU24B0009

Beach Nourishment Barnegat Inlet to Little Egg Inlet Long Beach Island?

ANSWER: The latest survey we have is provided. The survey was performed in November

2020.

18) Appendix B41, Vibracore Logs on page 493 of 674 within the Contract Specifications. After reviewing the geotechnical data it is noted that there would not be a sufficient quantity of material in the borrow area if the base and all option items were awarded.

Paragraph 1.6.2 Restrictions on Borrow Area D-1 on page 443 of 674, states, “if during the progress of the work it is determined that the borrow area does not contain a sufficient quantity of material for completion of the project, the Contracting Officer may adjust the maximum allowable depth of the borrow area.”

a) Upon review of vibracore borings issued within Appendix B41 it is evident that many of the logs do not go deep enough to cover any additional depths added to the borrow area.

Will the Owner please provide additional geotechnical information on the material that may be encountered should the borrow area depths be extended for dredging?

b) If material encountered is not suitable for beach placement, will an additional/alternate borrow area be provided?

c) If an additional/alternate source is provided will the Owner please provide additional geotechnical information of this source?

ANSWER: Part A. The elevations on select vibracore logs were inaccurate and have been corrected. See AM0003.

Part B. A deeper maximum dredging depth is provided in AM0003. No additional borrow area will be provided.

Part C. No additional source will be provided.

19) On the projects Sam.Gov site, under description paragraph 2, it is stated that all work under this contract shall be completed no later than January 15ᵗʰ, 2025. While clause 52.211-10

Commencement, Prosecution and Completion, on page 36 of 674 of the contract specifications it states that the work must be completed NLT 270 days from receipt of NTP.

a) The Contractor is requesting clarification as to which will apply.

ANSWER: Work must be completed NLT 270 days from receipt of NTP.

20) Clause 52.211-10 Commencement, Prosecution and Completion, on page 36 of 674 of the contract specifications it is stated that the Contracting Officer can exercise any or all of the options within the durations listed on the optional table.

a) Due to the potential of additional cost for movement of pipelines the Contractor is requesting clarification on the award of the options, is it the Governments intent to award option items in a manner that would make them discontinuous with other adjacent beachfill reaches? For instance, the award of CLINs 50-52 “Surf City” without award of CLINS 47-49

“North Beach”, thus making the Surf City work potentially discontinuous.

b) If discontinuous reaches are encountered would the Contractor be allowed to place pipeline on the existing native non-filled beach in an effort to reach the awarded optional item section?

ANSWER: Part A. There may be an instance that no contiguous reaches may be issued.

Part B. This will be on case-by-case basis, with COR approval prior to entering an area.

21) In an effort to allow the best pricing and most flexibility for suitable equipment within the market the Contractor is requesting the Government change the work window from a must complete day format to a must complete date of March 1ˢᵗ, 2026.

ANSWER: Work must be completed NLT 270 days from receipt of NTP.

22) The Contractor is requesting the Government extend the bid due date by an additional 30 days.

23) Paragraph b. of Section 3.8.1 Completion Time Requirements on page 365 of 674 within the

Contract specifications states; the Contractor must complete after-beachfill surveys of a particular location no more than 14 calendar days after the commencement of the before-beachfill surveys. (14-day max performance period).

a) Due to the sail distances from the borrow area to the southern fill reaches, the potential of extreme weather events, sea state and atmospheric, it is not unheard of for particular locations taking more than 14 days to fill along this stretch of shoreline. The Contractor is requesting the Government alter/remove this statement from the specifications, thus allowing more time between before and after beachfill surveys.

ANSWER: Bid as shown

24) Section 11 of the Standard 1442 form issued with the Contract specifications states that the

Contractor shall begin performance within 10 calendar days and complete within 270 calendar days after receiving NTP.

a) The Contractor is requesting the Government specify when to expect NTP?

ANSWER: Notice to Proceed cannot be provided. See Answer 2 above.

25) Option 1 Brant Beach as listed on the table in clause 52.211-10 Commencement, Prosecution and Completion of Work, states that the Government would have up to 90 days after pre project survey approval to award this option. Due to the advancement of the national dredging fleet it would not be unheard of for a Contractor to complete the base bid items prior to that 90 day award window, thus allowing the potential of demobilization commencement prior to the end of the 90 day award window.

a) The Contractor is requesting the Government waive or change the award window for this work to a more suitable timeline.

b) The same question above applies for Options 11, 14, 20, & 23 as included on that table, all of which have a 120 award day window from the pre project survey approval.

ANSWER: Bid as shown.

26) The Contractor is having difficulty opening the XYZ data file issued with the contract documents for the borrow area.

a) The Contractor is requesting the Government verify the data format and re issue.

ANSWER: The XYZ data provided is the raw data that can be opened in notepad and turn into a text, or CSV file. The data must be manipulated to input into software such as AutoCAD.

27) This contract has many options with varying windows for possible award. Can the USACE confirm the following?

a) If a contractor shows up & completes all awarded work prior to the days allowed for awarding the options can the USACE confirm that the options will not be awarded once demobilization has begun?

b) For options that are widening or lengthening the beach can the USACE confirm that those options will be awarded by the time the contractor starts work within those sections and will not be awarded at a later time that the contractor would have to repump an area or lay additional pipe outside the ordinary advancement of beachfill activities on the beach?

ANSWER: Part A: Options may be awarded once demobilization has begun.

Part B: Bid as shown.

28) Can the USACE confirm what the intent is of having so many options vs quantity in the base bid

(i.e. is it funding or is it based on a need for sand in those areas)?

ANSWER: Potential need for sand based on Pre-Project condition surveys of areas outside of base.

29) This project is subject to the Project Labor Agreement (PLA) requirements of Executive Order 14063. Due to the time required to properly prepare an agreement between the contractor and all parties, please extend the bid date by 30 days.

30) We would like to submit a proposal for the photogrammetry and aerial photography scope.

Can you provide us with a list of bidding General Contractors? Or should we be submitting our proposal directly to you?

ANSWER: There are no bidding general contractor listings. All contractors interested in submitting a BID are encouraged to do so. BID submission instructions are in the solicitation.

31) I understand that this BID is due today. I have attached your BID page that shows the specifications on the Accessible Mats. These specs as they are written are for a specific product manufactured by our competitor. We see these specs repeated in most Beach

Replenishment Bids. The specs in our opinion, are too restrictive which does not allow us to compete. This to us appears to be a Brand Name Sole Source Opportunity yet that is not stated within the BID.

ANSWER: Specification section 32 15 00, paragraph 2.6.2 has been revised to reflect changes in anchoring requirements.

32) We also feel that this restricts the end user from receiving the best solution, whether it be mats or an alternative compliant product. I have attached the specs on our AccessMat and our AccessDeck USA for comparison and review.

ANSWER: Bid as shown.

33) Our company has a standing collective bargaining agreements with the Seafarers

International Union (SIU) and the International Union of Operating Engineers Local 25 Marine

Division. For the International Union of Operating Engineers, Local 825 in New Jersey, our company pays their members prevailing wages and benefits based on the local jurisdiction and trades involved in the project from that local. These existing agreements will be in effect for the duration of the contract. The existing agreements provide the most efficient and comprehensive solutions for labor disputes, labor management, productivity, health and safety, and prevention of strikes, lockouts, and similar job disruptions. Therefore, these standing agreements meet the basic requirements for a PLA under Executive Order 14063/

FAR 52.222-33-34 without disrupting the existing agreements with negotiations. The existing agreements also measure up to public policy concerns of the requirement by guaranteeing efficient and timely completion of the project. Please confirm these agreements will meet the requirements of Executive Order 14063/ FAR 52.222-33-34.

ANSWER: Responded under AM0001

34) The structure of this contract, a small base bid scope of work with multiple options totaling significantly more than the base, plus the extended timing regarding the award of options does not provide a clear picture of the project to be bid. At the time of award the contractor will not know if the scope of work is 1,750,000 cubic yards or 4,937,250 cubic yards. This is a significant scope of work without a clear completion contract date. These unknowns result in increased costs due to the contractor not being able to define the appropriate equipment, resources or work window. For contractors to prepare cost efficient estimates and provide competitive pricing we request the options be issued within 30 days of the award.

ANSWER: Options cannot be issued until after the pre-project condition surveys are reviewed and approved and for the base area options, until the pre-placement surveys are reviewed and approved. For the Base area, Options to be issued cannot be determined until the Pre-

Placement surveys are reviewed and approved.

35) In the Option Award Table, The Days to Exercise Option for Options 8-10 states 21 days after

Pre-Placement survey approval for station 780+00 to 967+00. The base beachfill stationing in the bid schedule is from 770+00 to 967+00. Is the option area meant to be 1,000’ less than the base area? Please clarify which stationing is correct.

ANSWER: Correct stationing is 770+00 to 967+00 for Options 8-10. The Option Table has been revised to resolve this discrepancy.

36) In the Option Award Table, The Days to Exercise Option for Options 14-16 states 120 days after Pre-Placement survey approval for station 373+00 to 447+00. The base beachfill stationing in the bid schedule is from 337+00 to 447+50. Is the option area meant to be different than the base area? Please clarify which stationing is correct.

ANSWER: Correct stationing is 337+00 to 447+50 for Options 14-16. The Option Table has been revised to resolve this discrepancy.

37) In the Option Award Table, The Days to Exercise Option for Options 17-19 states 120 days after Pre-Placement survey approval for station 447+00 to 520+00. The base beachfill stationing in the bid schedule is from 447+50 to 520+00. Is the option area meant to be different than the base area? Please clarify which stationing is correct.

ANSWER: Correct stationing is 447+50 to 520+00 for Options 17-19. The Option Table has been revised to resolve this discrepancy.

38) In each beachfill option area, does the USACE intend to award the large quantity (first option under each option beach section) before awarding the smaller quantity within that section? If the larger quantity is not awarded, will no other options be awarded in that beach section? If so, please add a note in the bid schedule that Options 2, 8, 11, 14, 17, 20 and 23 will be awarded first before any other option in that stretch of beach.

ANSWER: The First option for each of region outside of the base will be exercised prior to the other smaller sand only options for that region.

Example: Option 1 Brant Beach (Sta 520+00 to 570+00) will be exercised before any other option for Brant beach (Options 5, 6, or 7) can be exercised. The mobilization cost to move from base to Brant Beach goes into unit cost of Beachfill Item #31 of Option 1. It follows

North Beach (Sta. 310+00 to 373+00) Option 11 before Options 12 or 13; Surf City (Sta

373+00 to Sta 447+50) Option 14 before Options 15 or 16; Ship Bottom (Sta 447+50 to Sta

520+00) Option 17 before Options 18 or 19; LBT (Sta. 570+00 to Sta. 675+00) Option 20 before Options 21 or 22; LBT (Sta. 675+00 to Sta. 770+00) Option 23 before Options 24 or 25.

39) For Brant Beach, does the USACE intend to award Option 1 and/or Option 5 before they award Option 6 and 7? If so, please add a note in the bid schedule regarding this.

ANSWER: It is USACE intent that Option 1 will be awarded prior to either or all Options 5 or 6 or 7 being exercised.

40) On Page C-113 of the drawings, station 570+00 says it is the Base Contract Fill Limit, while the notation from STA 570+00 to 520+00 states this area is for Option 1 and Options 5 through 7.

STA 520+00 also states Base Contract Fill Limit stops at 520+00. The bid schedule states that

STA 520+00 to 570+00 is an area with options and not base work. A beachfill template is provided for Brant Beach, just like the base beaches. Please clarify whether this stretch of beach is base or option area.

ANSWER: Station 520+00 to 570+00 (Brant Beach) is Option Work only.

41) Both base beaches (Sta 120+00 to 310+00 and Sta 770+00 to 967+00) have areas within their stationing limits with significant gaps in the beachfill template. Should the contractor expect, if options are awarded, the quantity could be within these gaps (potentially less than 10 cy/lf) or within the beachfill template provided (making the fill density larger)?

ANSWER: Yes.

42) The bid schedule states the base work is in North Beach Haven, Beach Haven, and Holgate

(STA 770+967+00) while in Section 01 71 23 Page 8, states the base work areas is in North

Beach Haven, Beach Haven and Holgate (Sta. 770+00 to 962+33). Please clarify which beach stationing is correct so the contractor will know where the beachfill material will be placed.

ANSWER: Station 770+00 to Station 962+33 is correct. The Bid Schedule has been revised to resolve this discrepancy.

43) Will the contractor be allowed to transit the full length of Long Beach Island to move between base and option reaches?

ANSWER: Will be on a case by case basis with prior approval of COR and in accordance to restricted areas described in section 01 57 19.

44) The borrow area provided in the contract documents does not contain sufficient material to meet the contract pay quantity. The deficit is even more significant when allowing for reasonable buffer zones and the unavoidable losses associated with beach fill operations.

Please include an additional borrow area to the contract documents so that the full contract pay quantity can be met and contractors can accurately estimate beach fill costs based on the borrow source. Section 01 57 19 3.4 Biological Resources, b. "Record observation data of threatened and endangered animal and plant species on the attached Endangered Species

Observer Forms and submit with the Quality Control report to the COR on a daily basis." is the contractor required to have NFWS approved ESOs on board of the hopper dredge.

ANSWER: A deeper maximum dredging depth is provided in AM0003 to meet the contract pay quantity. No additional borrow area will be provided.

45) Section 01 57 19 3.4 Biological Resources, b. "Record observation data of threatened and endangered animal and plant species on the attached Endangered Species Observer Forms and submit with the Quality Control report to the COR on a daily basis." is the contractor required to have NFWS approved ESOs on board the hopper dredge?

ANSWER: No observer needs to be on board the dredge, but Endangered Species Form need to be completed per specifications. Munitions screens also need to be inspected according to the specifications.

46) Is there any timing restrictions on the Pre-Project Surveys? Will the contractor be allowed to conduct the Pre-Project Surveys once NTP is received?

ANSWER: Refer to paragraph 3.2.4.1 of the revised specification section 01 71 23 included in this amendment. (See specification section 01 71 23. paragraph 3.2.4.1). Additional applicable timing restrictions would apply. (See section 01 57 19 in the specifications).

47) Due to the multiple option locations throughout Long Beach Island, the contractor will be required to include in the main mobilization/demobilization line item, the cost to have multiple subline landings throughout Long Beach Island. Please consider having separate mobilizations for each option area not wholly contained within the footprint of the 2 distinct

Base Beachfill Areas.

ANSWER: Mobilization and Demobilization Estimated Amount Item#1 shall include only costs for mobilization for the BASE BID Items. The cost to move from Base Areas to Option Areas out side of base should be included in the unit costs for the first Beachfill item within each region. Item #’s 31, 47, 50, 53, 56, & 59, respectively.

48) Are dune repairs required only in areas shown on the drawings? Will there be dune repairs in areas where no beachfill is being paced? If so, where would the material be sourced from to fill the template?

ANSWER: Material will be sourced from Borrow Area D-1. Pre-conditional surveys will determine if additional dune repair is required.

49) Due to the complexity of the project and outstanding questions, the contractor requests that the bid date be postponed by 2 weeks.

ANSWER: Bid due date is extended 14 days.

BARNEGAT INLET to LITTLE EGG INLET BEACHFILL

Solicitation W912BU-24-B-0009

BASE BID - Period of Performance = 270 days from NTP

Option Table

OPTION

# Description Days to Exercise Option Additional Days

(If Awarded)

1 Brant Beach Beachfill (Station 520+00 to 570+00) 90 days after Pre-Project Survey Approval. 20

2 Additional Beachfill – Loveladies & Harvey Cedars (Station 120+00 to 310+00)

21 Days after Pre-Placement condition survey Approval for Station 120+00 to 310+00

3 Additional Beachfill – Loveladies & Harvey Cedars (Station 120+00 to 310+00)

21 Days after Pre-Placement condition survey Approval for Station 120+00 to 310+00

4 Additional Beachfill – Loveladies & Harvey Cedars (Station 120+00 to 310+00)

21 Days after Pre-Placement condition survey Approval for Station 120+00 to 310+00

5 Additional Beachfill – Brant Beach (Station 520+00 to 570+00)

21 Days after Pre-Placement condition survey Approval for Station 520+00 to 570+00

6 Additional Beachfill – Brant Beach (Station 520+00 to 570+00)

21 Days after Pre-Placement condition survey Approval for Station 520+00 to 570+00

7 Additional Beachfill – Brant Beach (Station 520+00 to 570+00)

21 Days after Pre-Placement condition survey Approval for Station 520+00 to 570+00

8 Additional Beachfill – No. Beach Haven to Holgate (Station 770+00 to 967+00)

21 Days after Pre-Placement condition survey Approval for Station 770+00 to 967+00

9 Additional Beachfill – No. Beach Haven to Holgate (Station 770+00 to 967+00)

21 Days after Pre-Placement condition survey Approval for Station 770+00 to 967+00

10 Additional Beachfill – No. Beach Haven to Holgate (Station 770+00 to 967+00)

21 Days after Pre-Placement condition survey Approval for Station 770+00 to 967+00

11 Additional Beachfill – No. Beach, Long Beach Twp. (Station 310+00 to 373+00)

120 days after Pre-Project Survey Approval. 12

12 Additional Beachfill – No. Beach, Long Beach Twp. (Station 310+00 to 373+00)

21 Days after Pre-Placement condition survey Approval for Station 310+00 to 373+00

13 Additional Beachfill – No. Beach, Long Beach Twp. (Station 310+00 to 373+00)

21 Days after Pre-Placement condition survey Approval for Station 310+00 to 373+00

14 Additional Beachfill -Surf City (Station 373+00 to 447+50)

120 days after Pre-Project Survey Approval. 15

15 Additional Beachfill -Surf City (Station 373+00 to 447+50)

21 Days after Pre-Placement condition survey Approval for Station 373+00 to 447+50.

16 Additional Beachfill -Surf City (Station 373+00 to 447+50)

21 Days after Pre-Placement condition survey Approval for Station 373+00 to 447+50.

17 Additional Beachfill – Ship Bottom (Station 447+50 to 520+00)

120 days after Pre-Project Survey Approval. 15

18 Additional Beachfill – Ship Bottom (Station 447+50 to 520+00)

21 Days after Pre-Placement condition survey Approval for Station 447+50 to 520+00.

19 Additional Beachfill – Ship Bottom (Station 447+50 to 520+00)

21 Days after Pre-Placement condition survey Approval for Station 447+50 to 520+00.

20 Additional Beachfill – Long Beach Twp.

(Station 570+00 to 675+00)

120 days after Pre-Project Survey Approval. 21

21 Additional Beachfill – Long Beach Twp.

(Station 570+00 to 675+00)

21 Days after Pre-Placement condition survey Approval for Station 570+00 to 675+00.

22 Additional Beachfill – Long Beach Twp.

(Station 570+00 to 675+00)

21 Days after Pre-Placement condition survey Approval for Station 570+00 to 675+00.

23 Additional Beachfill – Long Beach Twp.

(Station 675+00 to 780+00)

120 days after Pre-Project Survey Approval. 21

24 Additional Beachfill – Long Beach Twp.

(Station 675+00 to 780+00)

21 Days after Pre-Placement condition survey Approval for Station 675+00 to 780+00.

25 Additional Beachfill – Long Beach Twp.

(Station 675+00 to 780+00)

21 Days after Pre-Placement condition survey Approval for Station 675+00 to 780+00.

26 Harvey Cedars - Additional Dune Crossovers 21 Days after Pre-Placement condition survey Approval for Station 120+00 to 310+00

27 Harvey Cedars - Dowel Rail Fence 21 Days after Pre-Placement condition survey Approval for Station 120+00 to 310+00

(End of Summary of Changes)

IFB W912BU24B0009

14. DESCRIPTION OF AMENDMENT (continued)

a. REQUESTS FOR INFORMATION (RFI) WITH RESPONSES: RFI’s with responses, annotated Amendment No. 0003, attached hereto.

b. OPTION TABLE: Please delete the OPTION TABLE in its entirety and substitute the revised OPTION TABLE, annotated Amendment No. 0003, attached hereto.

c. TECHNICAL SPECIFICATIONS:

(1) BID SCHEDULE: Please delete the BID SCHEDULE in its entirety and substitute the revised BID SCHEDULE, annotated Amendment No. 0003, attached hereto.

(2) SECTION 01 30 00 – ADMINISTRATIVE REQUIREMENTS: Please delete pages 1 and 2 of this section in its entirety and substitute the revised pages

1 and 2, annotated Amendment No. 0003, attached hereto.

(3) SECTION 01 32 33 – CONSTRUCTION PHOTOGRAPHY: Please delete pages 1-7 of this section in their entirety and substitute the revised pages 1-7, annotated as Amendment No. 0003, attached hereto.

(4) SECTION 01 33 00 – SUBMITTAL PROCEDURES: Please delete pages 17-25 of this section in their entirety and substitute the revised pages 17-25, annotated Amendment No. 0003, attached hereto.

(5) SECTION 01 35 26 – GOVERNMENTAL SAFETY REQUIREMENTS: Please delete this section in its entirety and substitute the revised Section 01 35 26, annotated Amendment No. 0003, attached hereto.

(6) SECTION 01 35 50 – DIVING SERVICES: Please delete pages 1-6 of this section in their entirety and substitute the revised pages 1-6, annotated Amendment No. 0003, attached hereto.

(7) SECTION 01 50 00 – TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS:

Please delete pages 1-10 of this section in their entirety and substitute the revised pages 1-10, annotated Amendment No. 0003, attached hereto.

(8) SECTION 01 57 19 – TEMPORARY ENVIRONMENTAL CONTROLS: Please delete pages 1 and 2 of this section in its entirety and substitute the revised pages 1 and 2, annotated Amendment No. 0003, attached hereto.

(9) SECTION 01 71 23 – SURVEY REQUIREMENTS: Please delete this section in its entirety and substitute the revised Section 01 71 23, annotated

Amendment No. 0003, attached hereto.

(10) SECTION 32 15 00 – DUNE CROSSOVERS: Please delete this section in its entirety and substitute the revised Section 32 15 00, annotated

Amendment No. 0003, attached hereto.

(11) APPENDIX B41: Please delete APPENDIX B41 in its entirety and substitute the revised APPENDIX B41, annotated Amendment No. 0003, attached hereto.

d. CONTRACT DRAWINGS:

(1) Please delete drawing sheet C-401 in its entirety and substitute the revised drawing sheet C-401, with the latest revision date of 26 April

2024, attached hereto.

14. DESCRIPTION OF AMENDMENT (continued)

e. Please indicate receipt of this amendment on Standard Form 1442

(SOLICITATION, OFFER, AND AWARD) as Amendment No. 0003. Failure to acknowledge all amendments may be cause for rejection of the bid.

00010-3

BIDDING SCHEDULE

(To be attached to SF 1442)

Item Estimated Unit Estimated No. Description Quantity Unit Price Amount

BASE BID:

1. Mobilization and Demobilization 1 JOB LS $____________

2. Name the State of New Jersey, Long Beach Township, Harvey

Cedars Borough, Beach Haven Borough, Surf City Borough, and Ship Bottom Borough as additional insured under General Liability Insurance. 1 JOB LS $____________

LOVELADIES BEACH AND HARVEY CEDARS (Sta. 120+00 to 310+00)

3. Beachfill 1,100,000 CY $______ $____________

4. Pedestrian Dune Crossover 1,035 SF $______ $____________

5. Vehicular Dune Crossover 6,910 SF $______ $____________

6. ADA Accessible Dune Crossover 3,340 SF $______ $____________

7. Graded Sand Pedestrian Dune Crossover 10,890 SF $______ $____________

8. Dune Crossover Stabilization Mat 7,250 SF $______ $____________

9. Post and Rail Fence 655 LF $______ $____________

10. Split Rail Fence 415 LF $______ $____________

11. Dowel Rail Fence 2,745 LF $______ $____________

12. Sand Fence 10,070 LF $______ $____________

13. Dune Grass 18” O.C. 43,260 SY $______ $____________

14. Structures Monitoring 1 JOB LS $____________

15. MEC Modifications and Monitoring 1 JOB LS $____________

00010-4

NORTH BEACH HAVEN, BEACH HAVEN, AND HOLGATE (Sta. 770+00 to 962+33)

16. Beachfill 650,000 CY $______ $____________

17. Pedestrian Dune Crossover 23,510 SF $______ $____________

18. Vehicular Dune Crossover 8,570 SF $______ $____________

19. ADA Accessible Dune Crossover 1,000 SF $______ $____________

20. Post and Rail Fence 210 LF $______ $____________

21. Split Rail Fence 3,305 LF $______ $____________

22. Sand Fence 9,270 LF $______ $____________

23. Dune Grass 18” O.C. 53,870 SY $______ $____________

24. Dune Grass 24” O.C. 6,250 SY $______ $____________

25. Dune Grass Seeding 4,000 SY $______ $____________

26. Demo and Remove Post and Rail Fence 60 LF $______ $____________

27. Demo and Remove Wood Decking 210 SF $______ $____________

28. Demo and Remove Sand Fence 300 LF $______ $____________

29. Structures Monitoring 1 JOB LS $____________

30. MEC Modifications and Monitoring 1 JOB LS $____________

TOTAL BASE BID AMOUNT $_________________

OPTIONS:

OPTION 1 - BRANT BEACH OPTION (Sta. 520+00 to 570+00)

31. Beachfill 130,000 CY $______ $____________

32. Vehicular Dune Crossover 1,420 SF $______ $____________

00010-5

33. ADA Accessible Dune Crossover 880 SF $______ $____________

34. Post and Rail Fence 180 LF $______ $____________

35. Split Rail Fence 240 LF $______ $____________

36. Sand Fence 305 LF $______ $____________

37. Dune Grass 18” O.C. 860 SY $______ $____________

TOTAL OPTION 1 AMOUNT $________________

LOVELADIES BEACH AND HARVEY CEDARS OPTIONS (Sta. 120+00 to 310+00)

38. OPTION 2 – Beachfill 500,000 CY $______ $____________

39. OPTION 3 - Beachfill 250,000 CY $______ $____________

40. OPTION 4 - Beachfill 100,000 CY $______ $____________

BRANT BEACH OPTIONS (Sta. 520+00 to 570+00)

41. OPTION 5 - Beachfill 120,000 CY $______ $____________

42. OPTION 6 – Beachfill 60,000 CY $______ $____________

43. OPTION 7 - Beachfill 24,000 CY $______ $____________

NORTH BEACH HAVEN, BEACH HAVEN, AND HOLGATE OPTIONS (Sta. 770+00 to 962+33)

44. OPTION 8 - Beachfill 340,000 CY $______ $____________

45. OPTION 9 - Beachfill 170,000 CY $______ $____________

46. OPTION 10 - Beachfill 68,000 CY $______ $____________

NORTH BEACH, LONG BEACH TOWNSHIP OPTIONS (Sta. 310+00 to 373+00)

47. OPTION 11 - Beachfill 157,500 CY $______ $____________

48. OPTION 12 - Beachfill 50,000 CY $______ $____________

49. OPTION 13 - Beachfill 25,000 CY $______ $____________

00010-6

SURF CITY OPTIONS (Sta. 373+00 to 447+50)

50. OPTION 14 - Beachfill 186,500 CY $______ $____________

51. OPTION 15 - Beachfill 50,000 CY $______ $____________

52. OPTION 16 - Beachfill 25,000 CY $______ $____________

SHIP BOTTOM OPTIONS (Sta. 447+50 to 520+00)

53. OPTION 17 - Beachfill 181,250 CY $______ $____________

54. OPTION 18 - Beachfill 50,000 CY $______ $____________

55. OPTION 19 - Beachfill 25,000 CY $______ $____________

LONG BEACH TOWNSHIP OPTIONS (Sta. 570+00 to 675+00)

56. OPTION 20 - Beachfill 262,500 CY $______ $____________

57. OPTION 21 - Beachfill 50,000 CY $______ $____________

58. OPTION 22 - Beachfill 25,000 CY $______ $____________

LONG BEACH TOWNSHIP OPTIONS (Sta. 675+00 to 770+00)

59. OPTION 23 - Beachfill 262,500 CY $______ $____________

60. OPTION 24 - Beachfill 50,000 CY $______ $____________

61. OPTION 25 - Beachfill 25,000 CY $______ $____________

LOVELADIES BEACH AND HARVEY CEDARS OPTIONS (Sta. 120+00 to 310+00)

62. OPTION 26 - Private Pedestrian Dune Crossover 2,300 SF $______ $____________

63. OPTION 27 - Dowel Rail Fence 580 LF $______ $____________

TOTAL BASE BID AND OPTIONS AMOUNT $_________________

NOTES:

1. Bidders must bid on all items.

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements

EM 1110-2-1003 (30 Nov. 2013) Hydrographic Surveying Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 88 Pilot Rules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Evidence Of Insurance

SD-11 Closeout Submittals

Certified Payrolls

1.3 SUPERVISION

1.3.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.3.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard

SECTION 01 30 00 Page 1 identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.

1.3.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.3.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.4 PRECONSTRUCTION CONFERENCE

Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference. The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.

Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.4.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.5 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (FAR 52.236-4)

SECTION 01 30 00 Page 2

SECTION 01 32 33

CONSTRUCTION PHOTOGRAPHY

PART 1 GENERAL

1.1 SCOPE OF SECTION

The work specified in this section includes: 1) construction photographs,

2) aerial obliques; and 3) geo-referenced aerial imagery. All items required to be submitted by this section shall be provided for unrestricted use by the Government.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

American Society for Photogrammetry and Remote Sensing (ASPRS)

ASPRS-PAS (Ed. 1, Ver 1.0 Nov 2014) Positional Accuracy Standards for Digital Geospatial Data

Federal Geographic Data Committee (FGDC)

FGDC-STD-001 (1998) Content Standards for Digital Geospatial Metadata

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM-1110-1-1000 (APR 2015) Photogrammetric and LiDAR Mapping

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Aerial Photography Qualifications; G,DO

Construction Photography Plan; G,COR

Geo-referenced Aerial Imagery Mission and Capability Plan; G,COR

Pre-Construction Photographs; G,COR

Pre-Beachfill Geo-referenced Aerial Imagery; G, DO

SD-07 Certificates

SECTION 01 32 33 Page 1

Progress Construction Photographs; G,COR

Post-Construction Photographs; G,COR

Post-Beachfill Geo-referenced Aerial Imagery; G,COR

Aerial Obliques; G, DO

1.4 AERIAL PHOTOGRAPHY QUALIFICATIONS

Aerial photography, for both aerial obliques and geo-referenced aerial imagery, shall be performed by independent aerial photography companies, that have a minimum of 5 years documented experience in aerial photography, similar in nature to the aerial photography required under this Contract.

Photography may be acquired by either the same company or separate companies, that meet the required qualifications. Submit aerial photographer qualifications prior to commencing aerial photography.

Include aerial photography examples for aerial obliques and geo-referenced aerial imagery.

1.5 PHOTOGRAPHY PLANS

1.5.1 Construction Photography Plan

Prepare a photography plan which includes the following information: items to be photographed locations, and the time the images are to be taken.

1.5.2 Geo-referenced Aerial Imagery Mission and Capability Plan

a. Design and plan geo-referenced digital image acquisition missions to acquire, process, and deliver digitally rectified imagery in GeoTiff files (with associated world files) over the project area, prior to beachfill operations and post beachfill operations. Include in the mission and capability plan sensor types, flight heights, processing techniques, and delivery formats and media. The plan shall be implemented by a person assigned within the Contractor's organization who will be present during the times work is in progress, and will be responsible for assuring that all documents on the project have been coordinated. This individual shall possess extensive, verifiable photogrammetric experience. Competent, independent reviewers shall review all documents.

b. Include in the plan a tile naming scheme that will be used for the pre and post beachfill placement aerial imagery collections.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 CONSTRUCTION PHOTOGRAPHY

Take digital images with a high quality digital camera using a minimum of 12,000,000 pixels (12 Megapixels). Identify images by number, and referenced to a listing containing the same identification information as used for the images. Photograph personnel, material, work methods, and equipment utilized during the entire contract period, as follows:

a. Pre-Construction Photographs: Prior to commencement of work in each

SECTION 01 32 33 Page 2 area, take a minimum of 25 photographs of pre-construction existing conditions, including beach structures, groins, outfall piping, supporting cribbage, timber support piles, Contractor access points, and lay down area. Take photographs as close as possible to the beginning of the work and with sufficient detail to accurately depict existing site conditions.

b. Progress Construction Photographs: During the progress of work, take a minimum of 10 photographs monthly of work activities in each of the areas currently under construction. Photographs shall capture each defineable feature of work in progress (defineable "feature of work" is defined in Section 01 45 05 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)). Photographs shall be of working personnel and equipment, depicting the work methods being utilized, taken during normal working hours. Photograph special events throughout the contract period as directed by the Contracting Officer. Photographs of the same pre-construction features of work shall be taken from the same locations, perspectives, and angles. Submit a reference plan sheet or map with the monthly construction photos, showing the locations and view of the photographs.

c. Post-Construction Photographs: After completion of work for each area, take a minimum of 25 photographs from the same pre-construction and progress construction locations, perspectives, and angles. Photography shall be taken immediately after the end of construction work.

3.1.1 Data Submittal

Submit digital images of photographs to the COR within 24 hours of when taken. Include the following identification information in the Metadata for each image: name and location of project, item/action being photographed, General Contractor, contract number, orientation of view, date and time of exposure, and name and address of photographer.

3.2 AERIAL OBLIQUES

Obtain aerial oblique photos of the entire project length prior to commencement of beachfill work, during the progress of work (monthly), and after completion of beachfill work from the same perspective and angles as the before photos. Take aerial photos with overlapping views to accurately record progress details of the project work. The photos shall exhibit good critical focus. An aerial oblique photo example is attached to this section. This example represents the altitude at which the photos should be taken (approximately 300 - 400 feet) as well as the level of detail and quality of those photos. In general, the horizon shall be approximately 1/5 down from the top of the frame with about a 2/3 land and a 1/3 water split, horizontally.

3.2.1 Data Submittal

Submit aerial obliques digital images within 10 days of when they are taken. Submit images in .jpg or .pdf format and include the following on the front of each image, as shown on the attached example: name and location of project, contract number, General Contractor,…