Amendment 0002_W912BU20R0008_PCS MATOC Solicitation.pdf

PDF 3 MB Posted

Attached to
Power Construction and Services Support 237130
Solicitation number
W912BU20R0008
Issued by

About this file

This solicitation is for a Multiple Award Task Order Contract to provide power construction and services support to all countries in the CENTCOM Area of Responsibility. The solicitation includes two sample task orders, one for the extension, construction, operation and maintenance of an 8 megawatt prime power plant and distribution system, and another for providing 8 megawatts of power as a service including operation, maintenance and distribution, with the power plant owned by the contractor. The proposal due date is February 5, 2021. The contract has a minimum value of $10,000 and maximum value of $249 million across all awarded MATOC contracts. The contractor must be registered in the System for Award Management and provide power generation and distribution experience of at least $3 million. The technical evaluation will assess the offeror's approach to the sample task orders, past performance, and price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Provide responses to the Request for Information RFI). RFIs submitted after 08 Jan 2021 by 5PM EST as stated in the solicitation w ill not be accepted.

2) Applicable changes in the solicitation are noted in red and deletions with strikethrough.

3) Adding Past Performance Questionnaire (PPQ)

The proposal due date is not extended.

Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment 0002. Failure to acknowledge all amendments be cause for rejection of the offers.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect,

1. CONTRACT ID CODE PAGE OF PAGES

1 186

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU20R0008

X 9B. DATED (SEE ITEM 11)

23-Dec-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

1(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jan-2021

CODE

US ARMY ENGINEER DISTRICT, PHILADELPHIA

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

W912BU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

X 1

W912BU20R0008

PCS MATOC

REQUEST FOR INFORMATION

RFI# Section Page Question/Description USG Response

1 N/A N/A

Do you want us to provide the power genrators or it is already exist?

Contractors will provide the generators for Sample Task #1 and #2. Sample Task #1, the generators will become property of the Government upon installation; Sample Task #2, the generators will remain property of the Contractor during the period of performance. Future task orders may request that the Contractor install or operate/maintain generators that are existing/Government Owned.

2 N/A N/A Can we use the labor with Afghanistan's nationality in this project?

All labor for Sample Task #1 and #2 needs to meet the requirements in Section 2.1.1, Key Personnel. Contracted personnel must also meet FAR Clause 5152.225-5916 and any specific local/base security requirements at the task order level.

3 N/A N/A Can you specify the place of performance in Afghanistan?

The place of performance for Sample Task #1 and #2 is Baghlan Province, Afghanistan.

Future task orders may be located within any country in the CENTCOM AOR. Countries are listed on Page 9 of 230.

4 N/A N/A

Can we bid only for Afghanistan, or is it mandatory to bid for all countries mentioned in RFP?

To be considered acceptable, offerors must supply rates for all countries in the CENTCOM

AOR.

5 00 40 00 25

Does USACE require the construction of secondary containment if containized UL142 certified fuel tanks are used in the fuel storage system?

Per RFP paragraph 10.3.5 Oil Storage Including Fuel Tanks, secondary containment is required. If there is a specific style of containment required it will be specified at the task order level.

6 00 40 00 26 Will the contractor be authorized to double stack the living containers?

Yes, this is acceptable for Sample Task Orders #1 and #2.

For future task orders, this would be site specific.

7 00 01 00 9

Is the offeror expected to use the State Department Office of Allowances uplifts when calculating the US National coefficents as shown in the Centcom Conuntries Labor Bid Schedule on page 10?

There is no expectation to use State Department Allowances for USN personnel. Any uplifts that are applied to the USN fully burdened labor rates will be at the discretion of the Contractor.

8 12A 1

Standard Form 1442 is checked NO to the requirement of Performance and Payment bonds but on Page 91 Paragraphs 52.211-11 Liquidated Damages

- Supplies and Services and Paragraph 52.211-12 Liquidated Damages - Construction Liquidated Damages are indicated. Are Liquidated Damages included?

Per clauses 52.211-11 and 52.211-12 in the solicitation, liquidated damages will be identified and specific clauses included at the task order level.

9 13B 1

Standard Form 1442 is checked NO to the requirement of Bid Guarantee. On Page93, there is an outline of Bid Bond requirements. Is a bid bond required?

Bid guarantee will not be required at the IDIQ level BUT may be required at the Task Order level if performance and payment bond is required.

Further description is provided in 52.228-1 Bid Guarantee.

Vol 2 Factor 2:Past

Performance Tab 3 PPQ

The paragraph states that the PPQ is required and is included in the Solicitation but there is no PPQ included.

Amendment 0002 has been posted to include the standard PPQ Form.

Volume II – Factor 2:

Past Performance:

Regarding the past performance evaluation, can a Master BPA agreement be considered as a project?

A Master BPA is not a project and will not be used. A purchase order under a BPA may be used toward past performance.

Volume II – Factor 2:

Past Performance:

We understand the contractor shall demonstrate that they have completed a project with a minimum contract value of $3M USD as their experience part. What about the JV partners, can they collectively fulfil this requirement of $3M USD to be rated acceptable? If so, is there any specific ratio for each partner of the JV?

If a JV offeror does not have its own record of experience or past performance, the Government will evaluate the relevant experience or past performance history of each individual JV member. Projects that meet the $3M requirement will be considered acceptable.

Volume II – Factor 2:

Past Performance

We have Pgen repairs, maintenace and power distribution Master BPA/IDVs constract (XXX-REDACTED-XXX) for period of performance up to 2023 with total contract amount of $6.4m and we have done more than $2.4m projects under this IDV contract so far. So, will the total amount of completed of this IDV contractsis enough to bid on this solicitation? as we have done multiple projects under this IDV/BPA contract with amount of $2.4m and we are getting more.

No. Per section 00 22 16, "projects with a total contract value equal to or greater than $3,000,000.00 USD and involving either medium voltage power generation or medium voltage power distribution in a contingency environment will be considered relevant."

14 N/A N/A

If the above experince referenced in RFI #13 is not acceptbale, then Can we go JV to complete the past performance requirements?

See Response to RFI #12

15 N/A N/A

Can a Afghanistan based companies bid for this Solicitation?

Yes, Afghan based companies may bid. The awardee(s) will be required to be listed in SAM and be in good standing.

16 00 21 16 10

We respectfully request a two week extension to the cutoff date for RFIs. Currently all RFIs are due on 1/8/21; we request to be able to submit RFIs until 1/22/21.

Due to the present procurement schedule, the RFI period cannot be extended.

17 1442 Form 1

Please include a bid date on the 1442 form.

The proposal delivery deadline was added to Block 14 of the SF-30 and Section 00 10 00 in Amendment 0001 (Bid Date: 05

FEB 2021 @ 1700 EST).

Other Proposal

Submission Information

Solicitation: Offerors may also include performance recognition documents received within the last ten years of the date the solicitation is issued, such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition.

Question: Can this information be added in Volume II, Past Performance, as an appendix? If so, can you confirm that it would not count against page count limits?

Awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition will count against the page limit.

19 00 21 16 12

Solicitation: Written Narrative states "The Offeror shall include a written narrative detailing its technical approach toward performing each of the sample task orders. The written narrative shall include the following."

Those narrative specifics are detailed in subsections "i" through "vi" of the solicitation.

Question: We will provide a written narrative or summary of subsections "i" through "vi", should we include full plans for each as an appendix? If so, please confirm if that would impact the page count limit?

If offerors choose to include full plans for subsections i through vi, the plans will count against the page limit.

Factor 2:

Past Performance

This section states to use forms and questionaires included with Appendix D.

Please provide Appendix D.

Amendment 0002 has been posted to include the standard PPQ Form.

21 00 40 00 25

Solicitation: Sample Task Order #1, "1. Background / Scope of Work" states "The power plant shall be capable of supplying 8 MW of power at all times including during maintenance and repair periods."

Question: Please confirm this is an N+1+1 situation. In Part 2 - Technical Requirements, paragraph 5.6.2 Reliability, on page 168 it states "Redundancy of the generator sources shall be provided with a minimum redundancy of N+1+1", so we would assume this is the approach as well with Sample Task Order #1.

Both Sample Task #1 and #2 will apply N+1+1. Amendment 0002 has been posted to clarify this item.

Part 1 - General

Requirements, CLIN 0016

(and associated options)

Solicitation: CLIN 0016 (and associated SLINs and option periods): Power services - Low Voltage Distribution Systems Offeror’s price shall include a monthly rate for all labor, material, and equipment costs to operate and maintain 1 km of the Low Voltage Distribution system detailed in CLIN 0008 (and associated SLINs and option periods.

Question: Can you clarify this is to be 25 meters, not 1km? All references in the pricing matrix point to "25 m", which are seen on page 5 of the solicitation.

The intent was for CLIN 0016 to be 25m. Amendment 0002 has been posted to clarify this item.

Proposal Submission Requirements 3.c. Content Requirement

"Each Volume shall consist of a Table of Contents and Summary Section."

Are the Table of Contents and Summary Section included in Volume I page count?

The Table of Contents will not count against the page limit, but the Summary will count against the page limit.

Amendment 0002 has been posted to clarify this item.

Section 00 70 00 - Conditions of the Contract

52.228-1 BID

GUARANTEE

(SEP 1996)

(a)

"Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid."

Please confirm that bonds are not required to be submitted with the proposal.

Bid guarantee will not be required at the IDIQ level BUT may be required at the Task Order level if performance and payment bond is required.

Further description is provided in 52.228-1 Bid Guarantee.

Proposal Submission Requirements

c. Tab 3 – Past Performance Questionnaire

"The Past Performance Questionnaire (PPQ) included in the solicitation shall be completed in its entirety by the client for each project and submitted with the proposal Completed PPQs must be submitted with the proposal."

Will the Government be providing a template for PPQs?

Amendment 0002 has been posted to include the standard PPQ Form.

Proposal Submission Requirements

N/A

Please confirm the SF# 1442 and SF# 30 amendments are not required to be with the printed copies or on the CD.

Please include signed 1142 and SF30's with the proposal submission. Offerors shall indicate receipt of any/all amendments on Standard Form

1442 (SOLICITATION, OFFER, AND

AWARD). Failure to acknowledge all amendments may be cause for rejection of the offers.

27 CLIN 0004

Will the genenrators under CLIN 0004 be GFE or CFE

The generators listed in CLIN 0004 will become property of the Government upon installation and commissioning.

CLIN 0005

CLIN 0005

Should CLIN 0005 be priced or is it just a header for SLINs 0005AA and 0005AB?

CLIN 0005 does not require pricing, only the SLINs under

CLIN 0005.

CLIN 0005

(and associated SLINs and option periods):

13.8 kV Power Plant Construction

"Assume one weather-tight and lockable building envelope built on a concrete slab on sandy soil. As an alternative to a building envelope, trailers may be provided, but shall be removed and returned at the end of the task order Building temperature shall be kept within the required operating temperature of the generators, with an outside ambient temperature ranging from 0 degrees F to 120 degrees F."

Is it the governments intent to have these plants housed within building or will modular containerized systems be acceptable?

It is not the Government's intent to have the power plants associated with Sample Tasks #1 and #2 housed within a building. Amendment 0002 has been posted to clarify this item.

CLIN 0005

(and associated SLINs and option periods):

13.8 kV Power Plant Construction

Are these plant CFE or GFE? The 13.8 kV Power Plants under CLIN 0005 will become property of the Government upon installation and commissioning.

CLIN 0006

(and associated SLINs and option periods):

4160 V Power Plant Construction

Are these plant CFE or GFE? The 4160 V Power Plants under CLIN 0006 will become property of the Government upon installation and commissioning.

CLIN 0006

(and associated SLINs and option periods):

4160 V Power Plant Construction

"Assume one weather-tight and lockable building envelope built on a concrete slab on sandy soil. As an alternative to a building envelope, trailers may be provided, but shall be removed and returned at the end of the task order Building temperature shall be kept within the required operating temperature of the generators, with an outside ambient temperature ranging from 0 degrees F to 120 degrees F."

Is it the governments intent to have these plants housed within building or will modular containerized systems be acceptable?

It is not the Government's intent to have the power plants associated with Sample Tasks #1 and #2 housed within a building. Amendment 0002 has been posted to clarify this item.

CLIN 0007

(and associated SLINs and option periods):

Medium Voltage Underground Distribution System

"Offeror shall plan and construct a medium voltage underground distribution system."

There is a discrepency in the bid schedule for this requirement: In the descriptiom on page 116 the government states " System shall be 5 kV or 15 kV class" in the Bid schedule (page 4) there is only a requirement for one entry.

Which class should we price?

SLIN 0007AB has been added to the bid schedule on page 4.

Amendment 0002 has been posted to clarify this item.

PWS Sample TO1 and T02

"Fuel Farm shall consist of above ground fuel storage tanks with secondary containment" Is it the intent of the government to require secondary containment even if the proposed tanks are double-wall tanks?

Per RFP paragraph 10.3.5 Oil Storage Including Fuel Tanks, secondary containment is required. If there is a specific style of containment required it will be specified at the task order level.

PWS Sample TO #2

Understanding that the Background and PWS for Task Order #2 is similar to that of Task Order #1 with the exception that TO # 2 is a single phase operation consisting of Plan and Construct an 8MW CFE Plant with a 5KM Distribution.

Should the Bid Schedule for Task Order #2(page 67) include a construction CLIN for both the 8MW plant and 5KM Distribution similar to Task Order #1?

There is no need for a power plant construction CLIN needed for Sample TO #2 because this is a Contractor-Owned plant.

All power plant phase in costs shall be captured in CLIN 0001.

CLIN 0007 has been added to the Bid Schedule for Sample Task #2 to capture distribution construction costs. Amendment 0002 has been posted to clarify this item.

PWS Sample TO #2

"The power plant shall be capable of providing 8MW's of power and the 5 km distribution system shall be operational no later than 120 calendar days after issuance of the initial Notice to Proceed (NTP)."

There appears to be a discrepency between the Bid schedule (page 67), which shows O&M Period of Performance to be 305 day;

making the plan, construct and mobilization period for

This section of the PWS has been revised to differentiate between the power plant phase in and construction of the distribution grid. The period of performance for CLIN 0011 and CLIN 7000 is 305 days.

Amendment 0002 has been posted to clarify this item.

both the plant and distribution only 60 days.

Please clarify.

PWS Sample TO #2

N/A

Should Task Order 2 include a the equivalent CLIN 0007 from Task Order 1 “Medium Voltage Underground – 5km Distribution system Construction”

Yes. See Response to RFI #35 above. Amendment 0002 has been posted to clarify this item.

Volume II - Factor 2, Past Performance

15 of 230 Can you provide the Past Performance Questionnaire as noted in this section? It is also referred to as Appendix D on page 21, where it says to "utilize the forms and questionnaires set forth in Appendix D".

Amendment 0002 has been posted to include the standard PPQ Form.

Scope of Work 114 of 230 Define the ranges of “low voltage”, “medium voltage” and “high voltage” in the scope requirements.

The guidelines set forth in ANSI C84.1-2020, Section 3, Voltage System Classes are to be used. Page 115 has been revised. Amendment 0002 has been posted to clarify this item.

Specs, and Sample Task Order

25 of 230 Is the main breaker within the main distribution panel provided considered the first means of disconnect?

Yes, for the Sample Task Orders #1 and #2. For future task orders, this would be site specific/defined at the task order level.

00 21 16

Instructions to Proposers

10 and 11

Due to the current public health emergency and for the safety of our personnel, will the government please change the Proposal Submission Requirement to an email or DoD SAFE submission instead of printed volumes and CDs?

Printing and assembling a proposal package of this size requires multiple people within an enclosed space.

Printed/Hard Copies are no longer required. Proposals shall only be submitted via CD/DVD. See revisions to Section 00 21 16 for more information. Amendment 0002 has been posted to clarify this item.

Section 00 21 16.3.c Content

Requirement.

The RFP states "Each Volume shall consist of a Table of Contents and Summary Section.

The Summary Section shall contain a brief abstract of the volume." Can the government confirm if these summary sections are excluded from the page count?

The Table of Contents will not count against the page limit, but the Summary will count against the page limit.

Amendment 0002 has been posted to clarify this item.

43 2.2.1,2.3.2, Appendix 2

29, 51, and

Pages 29 and 51, under CLIN 6000, indicates that emergency repair work cannot be started until after direction is received from the CO (a two-day minimum process). Appendix 2, on page 64, list the performance threshold as 4 hours (if parts are available) or 4 hours from parts availability. Please clarify the response time for emergency repairs.

CLIN 6000 under Sample Task Orders #1 and #2 is not separately priced ("NSP"), as the emergencies are presently unknown. Emergency Maintenance and Emergency Repair response times and dollar amount thresholds will be defined at the Task Order level. For Sample Tasks #1 and #2 the threshold is $2,500, but again, there are no present emergencies in the Sample Tasks.

11.33.1.2 and

13.8.1 195 and 205

Section 13.8.1 states that the government will provide fuel for testing. Section

11.33.1.2 states that the contractor provides fuel.

Please clarify.

Fuel has been removed from

11.33.1.2. Amendment 0002

has been posted to clarify this item.

00 21 16

Introductory Packet

The instructions for the Introductory Packet require contractors to provide org chart, including key personnel. Do contractors determine which positions will be key?

Yes, contractors determine which positions/personnel will be included in their organization chart.

00 21 16 Introductory Packet, b.

Staffing Plan, and

2.1.1

12, 13, 27

If contractors do not determine which positions will be key, would the government please clarify what the key positions are.

The key position section lists various positions, and it is unclear which are key.

See response to RFI #45 above.

00 21 16 Vol

I a. 13-14

The government is requesting in the Written Narrative in Volume 1 detailed information for 5 plans within a 50-page limit, allowing only a couple of pages per plan. Would the government please provide guidance on the level of detail required to achieve an acceptable score within the 50-page limit?

If offerors choose to include full plans for subsections i through vi, the plans will count against the page limit.

48 00 21 16 Vol I a.

13-14

Would the government please clarify whether each plan outlined in the Written Narrative is meant to address all parenthetical items with a.(i)-(vi) within the 50-page limit?

If offerors choose to include full plans for subsections i through vi, the plans will count against the page limit.

49 FAR 52.288-1 93

FAR 52.288-1 BID GUARANTEE

has been included in the RFP.

Is a bid guarantee required at the IDIQ level?

Bid guarantee will not be required at the IDIQ level BUT may be required at the Task Order level if performance and payment bond is required.

Further description is provided in 52.228-1 Bid Guarantee.

50 FAR 52.288-1 93

If a bid guarantee is required at the IDIQ level, what is the appropriate amount of the bid guarantee?

52.288-1(c) indicates 20% of the bid price or $3,000,000, whichever is less; however, the pricing submission requirements do not aggregate values for the per month calcuations nor calculate the hours for each labor personnel position.

Bid guarantee will not be required at the IDIQ level BUT may be required at the Task Order level if performance and payment bond is required.

Further description is provided in 52.228-1 Bid Guarantee.

51 FAR 52.288-1 93

Would the government consider allowing bidders to provide a letter from their surety providing the company's per project and aggregate bonding as evidence of bonding capacity?

Bid guarantee will not be required at the IDIQ level BUT may be required at the Task Order level if performance and payment bond is required.

Further description is provided in 52.228-1 Bid Guarantee.

Bid Schedule and Technical requirements

4-5 and 115-

The technical description states that construction CLINs/SLINs are to be priced based on CLIN 0002 labor rates, however, there are no labor categories for construction trades included in the labor rate tables.

Also, the provided labor rates are adjustable on a country-by-country basis, but the construction CLINs have no such adjustment.

Q: Are the CLIN 0005-CLIN 0009 prices supposed to be specific to one country?

Offeror's pricing for CLINs 0005-0009 will be applied to all countries of the CENTCOM

AOR.

Bid Schedule and Technical requirements

4-5 and 115-

The technical description states that construction CLINs/SLINs "...are to include all labor, material and equipment costs for supplied components, cost of the use of the tools, supplies, and machinery and equipment necessary to construct the systems defined in the individual line items, and all other costs necessary to provide functional electrical installations, except as specifically exempted above." The costs of labor, materials and equipment varies greatly country-to-country in the

AOR.

Q: Are the CLIN 0005-CLIN 0009 prices supposed to be a maximum for the AOR or specific to one country?

See RFI Response #52 above.

Bid Schedule and Technical requirements

5-6 and 117-

The technical description states that "Offeror's price shall include a monthly rate for all labor, material, and equipment costs to operate and maintain…" Labor, material and equipment costs vary greatly across the AOR, and there is no way to tie this price to the adjustable CLIN 0002 labor rate tables.

Q: Are the CLIN 00011-CLIN 0016 prices supposed to be a maximum for the AOR or specific to one country?

Offeror's pricing for CLINs 0011-0016 will be applied to all countries of the CENTCOM

AOR.

55 FAR Clauses 93

There is a requirement for Bid Guarantees at the Task Order level.

Q: Since the sample Task Orders will not be awarded, is an actual bid guarantee required for the Sample Task Orders?

Bid guarantee will not be required at the IDIQ level BUT may be required at the Task Order level if performance and payment bond is required.

Further description is provided in 52.228-1 Bid Guarantee.

Bid Schedule and Technical requirements

4-5 and 115-

The technical description states that construction CLINs/SLINs "...are to include all labor, material and equipment costs for supplied components, cost of the use of the tools, supplies, and machinery and equipment necessary to construct the systems defined in the individual line items, and all other costs necessary to provide functional electrical installations, except as specifically exempted above." The costs of labor, materials and equipment varies greatly country-to-country in the AOR. Q: Will the CLIN 0005- CLIN 0009 prices be adjusted based on the country of performance?

No

Bid Schedule and Technical requirements

5-6 and 117-

The technical description states that "Offeror's price shall include a monthly rate for all labor, material, and equipment costs to operate and maintain…" Labor, material and equipment costs vary greatly across the AOR, and there is no way to tie this price to the adjustable CLIN 0002 labor rate tables.

Q: Will the CLIN 00011-CLIN 0016 prices be adjusted based on the country of performance?

No

APPENDIX D

PAST PERFORMANCE QUESTIONNAIRE

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT YOUR

EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.

Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.

There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract Rating will be neither positive nor negative.

Contractor Information (Firm Name): Client Information (Name):

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The Issued By organization has changed from

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC: RICHARD RIVERA CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST, PHILADELPHIA PA 19107

to

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC: SUSAN LI

WANAMAKER BUILDING

100 PENN SQUARE EAST, PHILADELPHIA PA 19107-3390

The required performance has changed from A. Project Tittle: Multiple Award Task Order Contract

(MATOC) - Indefinite Delivery/Indefinite Quantity (IDIQ) for Power Construction and Services Support which provides power generation to all countries in the CENTCOM Area of Responsibility. B. This is a full and open acquisition. NAICS Code for this acquisition is 237130, small business size standard is $39.5M.C. The guaranteed minimum amount for the life of this contract is $10,000.00.D. The total aggregate maximum amount expendable under all MATOC contracts awarded shall not exceed $249 million.E. Companies intending to submit a proposal must ensure they have a current and active registration in the System for Award Management(SAM).F. Proposal due date: 05 February 2021, 5:00 PM EST. to A. Project Tittle: Multiple Award Task Order Contract (MATOC) -

Indefinite Delivery/Indefinite Quantity (IDIQ) for Power Construction and Services Support which provides power generation to all countries in the CENTCOM Area of Responsibility. B. This is a full and open acquisition. NAICS

Code for this acquisition is 237130, small business size standard is $39.5M.C. The guaranteed minimum amount for the life of this contract is $10,000.00.D. The total aggregate maximum amount expendable under all MATOC contracts awarded shall not exceed $249 million.E. Companies intending to submit a proposal must ensure they have a current and active registration in the System for Award Management(SAM).F. Proposal due date: 05 February

2021, 5:00 PM EST.G. Proposals shall be delivered to the address as specified: US ARMY ENGINEER DISTRICT, PHILADELPHIA CONTRACTING DIVISION, WANAMAKER BUILDING - 6th Floor, 100 PENN SQUARE

EAST, PHILADELPHIA PA 19107-3390 Attn: Jamaal Edwards/Susan Li.

The following have been modified:

DELIVERY INFORMATION

Section 00 10 00 – Solicitation

DELIVERY INFORMATION

CLIN DELIVERY SCHEUDLE QUANTITY SHIP TO ADDRESS DODAAC CAGE

Section 00 10 00 – Supplies or Services and Prices

SOLICITATION CLIN SCHEDULE

CONTRACT MINMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM MINIMUM MAXIMUM MAXIMUM

QUANTITY AMOUNT QUANTITY AMOUNT

$10,000.00 $249,000,000.00

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each

Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

MINIMUM MINIMUM MAXIMUM MAXIMUM

QUANTITY AMOUNT QUANTITY AMOUNT

$10,000.00 $50,000,000.00

EQUIPMENT BID SCHEDULE

See Section 01 00 00, Paragraph 1.3 for a description of each CLIN.

CLIN Description Qty Unit Yr. 1 Yr. 2 Yr. 3 Yr. 4 Yr. 5 6 Mo.

0001 Mobilization/Phase‐In NOT PRICED AT MATOC– PRICED AT TASK ORDER

0002 LABOR SEE LABOR BID SCHEDULE STARTING ON PAGE 6

0003 PLAN NOT PRICED AT MATOC– PRICED AT TASK ORDER

0004 Equipment

0004AA 55 kW Generator, New 1 EA

0004AB 55 kW Generator, Rebuilt 1 EA

0004AC 55 kW Generator, Used 1 EA

0004AD 100 kW Generator, New 1 EA

0004AE 100 kW Generator, Rebuilt 1 EA

0004AF 100 kW Generator, Used 1 EA

0004AG 250 kW Generator, New 1 EA

0004AH 250 kW Generator, Rebuilt 1 EA

0004AI 250 kW Generator, Used 1 EA

0004AJ 550 kW Generator, New 1 EA

0004AK 550 kW Generator, Rebuilt 1 EA

0004AL 550 kW Generator, Used 1 EA

0004AM 1 MW Generator, New 1 EA

0004AN 1 MW Generator, Rebuilt 1 EA

0004AO 1 MW Generator, Used 1 EA

0004AP 1.5 MW Generator, New 1 EA

0004AQ 1.5 MW Generator, Rebuilt 1 EA

0004AR 1.5 MW Generator, Used 1 EA

0004AS 2 MW Generator, New 1 EA

0004AT 2 MW Generator, Rebuilt 1 EA

0004AU 2 MW Generator, Used 1 EA

0004AV 5MW Generator, New 1 EA

0004AW 5MW Generator, Rebuilt 1 EA

0004AX 5MW Generator, Used 1 EA

Note: For CLIN 0004 and all SLINs, generator sizes are nominal (plus or minus 10%; i.e. a 90kW generator would be acceptable for the 100kw generator requirement) in order to provide opportunity for various manufacturers. Generators include all materials to connect to load to include cabling appropriate to generator rating, all grounding materials, etc.

Assume 50' from load.

0005 13.8 kV Power Plant Construction

0005AA 1 MW Power Plant 1 JOB

0005AB 5 MW Power Plant 1 JOB

0005AC 10 MW Power Plant 1 JOB

0005AD 15 MW Power Plant 1 JOB

0005AE 20 MW Power Plant 1 JOB

0006 4160 V Power Plant Construction

0006AA 1 MW Power Plant 1 JOB

0006AB 5 MW Power Plant 1 JOB

0006AC 10 MW Power Plant 1 JOB

0006AD 15 MW Power Plant 1 JOB

0006AE 20 MW Power Plant 1 JOB

0007 Medium Voltage Underground Distribution Construction

0007AA 5kV MV Underground Distribution 1 KM

0007AB 15kV MV Underground Distribution 1 KM

0008 Low Voltage Distribution Construction

0008AA 100 amps 25 M

0008AB 200 amps 25 M

0008AC 400 amps 25 M

0008AD 800 amps 25 M

0008AE 1200 amps 25 M

0008AF 1600 amps 25 M

0008AG 2000 amps 25 M

0009 Overhead Distribution Construction

0009AA Overhead Distribution 1 KM

0010 NOT USED

0011 13.8 kV Power and O&M Service / Contractor Owned Contractor Operated Power Plant and Distribution System

0011AA 1 MW

1 Month

0011AB 5 MW 1 Month

0011AC 10 MW 1 Month

0011AD 15 MW 1 Month

0011AE 20 MW 1 Month

0012 4160 V Power and O&M Service / Contractor Owned Contractor Operated Power Plant and Distribution System

0012AA 1 MW 1 Month

0012AB 5 MW 1 Month

0012AC 10 MW 1 Month

0012AD 15 MW 1 Month

0012AE 20 MW 1 Month

0013 13.8 kV Power Plant O&M

0013AA 1 MW Power Plant 1 Month

0013AB 5 MW Power Plant 1 Month

0013AC 10 MW Power Plant 1 Month

0013AD 15 MW Power Plant 1 Month

0013AE 20 MW Power Plant 1 Month

0014 4160 V Power Plant O&M

0014AA 1 MW Power Plant 1 Month

0014AB 5 MW Power Plant 1 Month

0014AC 10 MW Power Plant 1 Month

0014AD 15 MW Power Plant 1 Month

0014AE 20 MW Power Plant 1 Month

0015 Medium Voltage Underground Distribution O&M

0015AA 1 km 1 Month

0016 Low Voltage Distribution O&M

0016AA 100 amps; 25 m 1

Month

0016AB 200 amps; 25 m 1 Month

0016AC 400 amps; 25 m 1 Month

0016AD 800 amps; 25 m 1 Month

0016AE 1200 amps; 25 m 1 Month

0016AF 1600 amps; 25 m 1 Month

0016AG 2000 amps; 25 m 1 Month

0017 Overhead Distribution O&M

0017AA 1 km 1 Month

5000 Incidental Construction to Services NOT PRICED AT MATOC – PRICED AT TASK ORDER

6000 Emergency Equipment

Replacement and Repair

NOT PRICED AT MATOC – PRICED AT TASK ORDER

7000 COTR Logistical Support NOT PRICED AT MATOC – PRICED AT TASK ORDER

8000 Demobilization/Phase‐Out NOT PRICED AT MATOC – PRICED AT TASK ORDER

9000 Equipment Buyback and Demob NOT PRICED AT MATOC – PRICED AT TASK ORDER

9000AA Equipment Buyback NOT PRICED AT MATOC – PRICED AT TASK ORDER

9000AB Equipment Demobilization NOT PRICED AT MATOC – PRICED AT TASK ORDER

9990 Contractor Manpower Reporting NOT PRICED AT MATOC – PRICED AT TASK ORDER

AFGHANISTAN LABOR BID SCHEDULE

AFGHANISTAN

U.S. TCN LN

Year 1

0002 Personnel Quantity Unit

0002AA Journeyman Electrician 1 Hour

0002AB Master Electrician 1 Hour

0002AC High Voltage Electrician 1 Hour

0002AD Power Generation Maintenance Technician 1 Hour

0002AE Logistics Manager 1 Hour

0002AF Site Manager 1 Hour

0002AG Quality Control Manager 1 Hour

0002AH Site Safety Health Officer 1 Hour

0002AI Project Manager 1 Hour

0002AJ Plant Operator 1 Hour

0002AK Plant Manager 1 Hour

Year 2

1002 Personnel Quantity Unit

1002AA Journeyman Electrician 1 Hour

1002AB Master Electrician 1 Hour

1002AC High Voltage Electrician 1 Hour

1002AD Power Generation Maintenance Technician 1 Hour

1002AE Logistics Manager 1 Hour

1002AF Site Manager 1 Hour

1002AG Quality Control Manager 1 Hour

Personnel Quantity Unit

1002AH Site Safety Health Officer 1 Hour

1002AI Project Manager 1 Hour

1002AJ Plant Operator 1 Hour

1002AK Plant Manager 1 Hour

Year 3

2002 Personnel Quantity Unit

2002AA Journeyman Electrician 1 Hour

2002AB Master Electrician 1 Hour

2002AC High Voltage Electrician 1 Hour

2002AD Power Generation Maintenance Technician 1 Hour

2002AE Logistics Manager 1 Hour

2002AF Site Manager 1 Hour

2002AG Quality Control Manager 1 Hour

2002AH Site Safety Health Officer 1 Hour

2002AI Project Manager 1 Hour

2002AJ Plant Operator 1 Hour

2002AK Plant Manager 1 Hour

Year 4

3002 Personnel Quantity Unit

3002AA Journeyman Electrician 1 Hour

3002AB Master Electrician 1 Hour

3002AC High Voltage Electrician 1 Hour

3002AD Power Generation Maintenance Technician 1 Hour

3002AE Logistics Manager 1 Hour

3002AF Site Manager 1 Hour

3002AG Quality Control Manager 1 Hour

3002AH Site Safety Health Officer 1 Hour

3002AI Project Manager 1 Hour

3002AJ Plant Operator 1 Hour

3002AK Plant Manager 1 Hour

Year 5

4002 Personnel Quantity Unit

4002AA Journeyman Electrician 1 Hour

4002AB Master Electrician 1 Hour

4002AC High Voltage Electrician 1 Hour

4002AD Power Generation Maintenance Technician 1 Hour

4002AE Logistics Manager 1 Hour

4002AF Site Manager 1 Hour

4002AG Quality Control Manager 1 Hour

4002AH Site Safety Health Officer 1 Hour

Personnel Quantity Unit

4002AI Project Manager 1 Hour

4002AJ Plant Operator 1 Hour

4002AK Plant Manager 1 Hour

FAR 52.217-8 Option to Extend Services (6 Month Max)

5002 Personnel Quantity Unit

5002AA Journeyman Electrician 1 Hour

5002AB Master Electrician 1 Hour

5002AC High Voltage Electrician 1 Hour

5002AD Power Generation Maintenance Technician 1 Hour

5002AE Logistics Manager 1 Hour

5002AF Site Manager 1 Hour

5002AG Quality Control Manager 1 Hour

5002AH Site Safety Health Officer 1 Hour

5002AI Project Manager 1 Hour

5002AJ Plant Operator 1 Hour

5002AK Plant Manager 1 Hour

CENTCOM COUNTRIES LABOR BID SCHEDULE – COEFFICIENTS USING AFGHANISTAN LABOR BID

SCHEDULE AS THE BASELINE

Year 1

Year 2

Year 3

Year 4

Year 5 FAR Clause

52.217-8

Option to

Extend

Services (up to 6 months)

U.

S.

TC

N

L

N

U.

S.

TC

N

TC

N

TC

N

TC

N

TC

N

L

N

Bahrain

Egypt

Iraq

Jordan

Kazakhstan

Kuwait

Kyrgyzstan

Lebanon

Oman

Pakistan

Qatar

Saudi

Arabia

Syria

Tajikistan

Turkmenist an

U.A.E.

Uzbekistan

Yemen

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been modified:

PROPOSAL SUBMISSION

Section 00 21 16 - Proposal Submission Requirements

1. Introduction

The Offeror’s proposal shall be submitted in hard copy CD/DVD format only, with accompanying digital copies, as set forth below. The RFP provides the Government address and receipt date for proposal submittal. Any proposal that does not adhere to the requirements as set forth in this section may be deemed nonresponsive and the proposal may be rejected.

The Offeror’s proposal shall consist of an Introductory Packet and three (3) volumes with separate binders for the Introductory Packet and each Volume. Offerors shall provide four

(4) hard copies and one (1) electronic copy. The electronic copy shall be provided on CDs, one for the Introductory Packet and each Volume. The Volumes are Volume I – Approach to Sample Task Order, Volume II – Past Performance, and Volume III – Price. Files shall not contain classified data. The use of hyperlinks in proposals is prohibited.

The Offeror’s proposal shall consist of an Introductory Packet and three (3) volumes:

• CD/DVD #1 = Introductory Packet;

• CD/DVD #2 = Volume I - Approach to Sample Task Order;

• CD/DVD #3 = Volume II - Past Performance; and

• CD/DVD #4 = Volume III - Price

Offeror’s must also submit a second set of all CD/DVD’s, totaling eight (8) altogether. Files shall not contain classified data. The use of hyperlinks in proposals is prohibited.

Offerors are cautioned that “parroting” of the Technical requirements of the RFP with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation. Proprietary information shall be clearly marked.

Any Request for Information (RFI) or Questions about this solicitation must be submitted to the Contracting Office POC’s No Later Than 08 Jan 2021 by 5PM EST. Contracting POC’s are as follows:

Primary POC: Susan Li Email: Susan.Li@usace.army.mil

Secondary POC: Jamaal Edwards Email: Jamaal.A.Edwards@usace.army.mil

2. Proposal Submission Requirements

a. Each Volume shall be submitted in a CD/DVD as specified above separate three-ring binder. Any pages that are changed (as a result of negotiations or proposal revisions) should be a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated. Each CD/DVD binder shall be clearly labeled with its title and a copy number (e.g., copy 1 of 2 ).

mailto:Susan.Li@usace.army.mil mailto:Jamaal.A.Edwards@usace.army.mil

b. Formatting Printing should be single spaced. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required. Table and illustrations may use a reduced font size no less than 8-point and may be landscape.

c. The following volumes of material shall be submitted:

Volume and Title # of Hard Copies CD/DVDs

Maximum Pages Per Volume

I – Approach to Sample Task Orders 4 2 50

II – Past Performance (not including questionnaires) 4 2 25

III – Price 4 2 N/A

NOTE: The Introductory Packet will not be included in the proposal submission page counts. Pages that exceed the maximum page limits set forth in the chart above will be removed or not read and will not be evaluated by the Government. Price information must be solely contained in Volume III. For Volume I, proposed power plant site layout and power plant one-line diagram drawings, milestone schedule Gantt chart, and product cut sheets will not be included in the proposal submission page count and shall be submitted in an Appendix to Volume 1, Tabs 1 and 2, respectively.

3. Proposal Files.

a. Format. The submission shall be clearly indexed and logically assembled. Each Volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be numbered and identified by the complete company name, date, and RFP number in the header and/or footer. A Table of Contents should be created using the Table of Contents feature in MS Word. MS Word (doc) files shall use the following page setup parameters:

Margins – Top, Bottom, Left, Right – 1” Gutter – 0” From Edge

– Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11”

NOTE: 11x17 folded pages are acceptable for tables/graphic representations. However, each 11x17 page counts as two (2) pages.

In addition to providing hard copies, the Offerors shall also provide electronic copies as set forth below.

The Offerors shall provide electronic copies as set forth below:

b. File Packaging. The Introductory Packet and each volume shall be on a separate CD/DVD. All of the proposal files in each Volume shall be in read-only PDF files, except for price breakdown information to aid in the price evaluation, which shall be submitted in

Microsoft Office Excel Read/Write format. Each CD/DVD shall be externally labeled with either “Introductory Packet” or the Volume number, as well as the date and the Offeror’s name.

NOTE: Self extracting exe files are not acceptable.

NOTE: If the hard-copy proposal differs from the electronic version, the hard copy will govern.

c. Content Requirement. All information shall be confined to the appropriate file. The Offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each Volume shall consist of a Table of Contents and Summary Section. The Summary Section shall contain a brief abstract of the volume. Proprietary information shall be clearly marked.

The Table of Contents will not count toward the page limit; however the Summary Section will count toward the page limit.

Introductory Packet

The Introductory Packet shall include the following:

• Cover Letter

• Organization Chart. Include an organizational chart, illustrating the organization and including key personnel.

• Teaming arrangements. The Offeror shall document unequivocal teaming arrangements with its major subcontractors. Major subcontractors are contractors who will perform more than 20% of the total contracted price. Provide a narrative describing any contractual arrangements that have been established with subcontractors and their roles and responsibilities. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. A copy of the teaming or joint venture agreement(s) shall be provided.

• Representations and Certifications from System for Award Management

Volume I – Factor 1: Approach to Sample Task Orders. There are two (2) sample task orders in Section 00 40 00 of the RFP. Sample Task Order 1 is for the Extension of Design, Construction, Operation, and Maintenance of an 8 megawatt (MW) Prime Power Plant and Distribution System. Sample Task Order 2 is for the provision of 8 MW of power as a service and includes operation, maintenance, and distribution.

Sample Task Order 2 is essentially the same requirement as Sample Task Order 1; however, in Sample Task Order 2, the power plant is owned by the Contractor and the Contractor is responsible for providing power as a service. For each of the two (2) sample task orders there should be a separate Tab for each sample task order under Volume I (Approach to Sample Task Orders) and under Volume III (Price).

Volume III – Price, Tab 1 and Tab 2 shall consist of the Offeror’s price proposal for each respective sample task order.

TAB 1 – Approach to Sample Task Order 1

The proposal shall include each of the required items below: Written Narrative, Staffing Plan, Milestone Schedule, and Equipment List for Sample Task Order 1.

TAB 2 – Approach to Sample Task Order 2

The proposal shall include each of the required items below: Written Narrative, Staffing Plan, and Milestone Schedule for Sample Task Order 2.

a. Written Narrative

The Offeror shall include a written narrative detailing its technical approach toward performing each of the sample task orders. The written narrative shall include the following

(i) Phase-in plan as defined in CLIN 0001.

(ii) The Offeror shall provide drawing(s) depicting proposed power plant site layout and power plant one-line diagram based on information contained within the Performance Work Statement (PWS). Plan shall explicitly address how offeror proposes to meet the redundancy requirement(s) to include de-rated values and to meet the 96-hour run-time requirement(s) specified in each Sample Task Order.

One-line diagram and any other documentation shall match equipment list quantities.

De-rated values for generators shall be shown. Generator output capacity (kW or MW) shall be adjusted for location and environmental conditions.