This solicitation requests proposals for a Multiple Award Task Order Contract to provide power generation and construction services to support countries in the CENTCOM Area of Responsibility. The Army Corps of Engineers seeks to award indefinite delivery/indefinite quantity contracts for a guaranteed minimum of $10,000 and maximum aggregate amount of $249 million over five years and six month option periods. Proposals are due by specified dates in 2021. The scope includes constructing power plants up to 20 megawatts, underground and overhead distribution systems, and operating and maintaining generation and distribution assets. Offerors must have relevant experience and past performance. The solicitation provides sample task orders outlining 8 megawatt power plant and distribution system construction and long-term operation and maintenance requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Power Construction and Services Support 237130, newest first.
File Type Posted
Award Notice_W912BU20R0008 Power Construction and Services Support.pdf PDF
Amendment 0004_W912BU20R0008.pdf PDF
Amendment 0003_W912BU20R0008.pdf PDF
Amendment 0002_W912BU20R0008_PCS MATOC Solicitation.pdf PDF
Amendment 0001_W912BU20R0008.pdf PDF
W912BU-20-R-0008 PCS MATOC RFI (Vendor Name).xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A. Project Tittle: Multiple Aw ard Task Order Contract (MATOC) - Indefinite Delivery/Indefinite Quantity (IDIQ) for Pow er Construction and Services Support w hich provides pow er generation to all countries in the CENTCOM Area of Responsibility.

B. This is a full and open acquisition. NAICS Code for this acquisition is 237130, small business size standard is $39.5M.

C. The guaranteed minimum amount for the life of this contract is $10,000.00.

D. The total aggregate maximum amount expendable under all MATOC contracts aw arded shall not exceed $249 million.

E. Companies intending to submit a proposal must ensure they have a current and active registration in the System for Aw ard Management(SAM).

RICHARD RIVERA 215.656.6563

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

23-Dec-2020

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days af ter receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY ENGINEER DISTRICT, PHILADELPHIA

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

W912BU

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W912BU20R0008 230

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 10 00 - Solicitation

DELIVERY INFORMATION

Section 00 10 00 – Solicitation

DELIVERY INFORMATION

CLIN DELIVERY SCHEUDLE QUANTITY SHIP TO ADDRESS DODAAC CAGE

Section 00 10 00 – Supplies or Services and Prices

SOLICITATION CLIN SCHEDULE

CONTRACT MINMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM MINIMUM MAXIMUM MAXIMUM

QUANTITY AMOUNT QUANTITY AMOUNT

$10,000.00 $249,000,000.00

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

MINIMUM MINIMUM MAXIMUM MAXIMUM

QUANTITY AMOUNT QUANTITY AMOUNT

$10,000.00 $50,000,000.00

EQUIPMENT BID SCHEDULE

See Section 01 00 00, Paragraph 1.3 for a description of each CLIN.

CLIN Description Qty Unit Yr. 1 Yr. 2 Yr. 3 Yr. 4 Yr. 5 6 Mo.

0001 Mobilization/Phase‐In NOT PRICED AT MATOC– PRICED AT TASK ORDER

0002 LABOR SEE LABOR BID SCHEDULE STARTING ON PAGE 6

0003 PLAN NOT PRICED AT MATOC– PRICED AT TASK ORDER

0004 Equipment

0004AA 55 kW Generator, New 1 EA 0004AB 55 kW Generator, Rebuilt 1 EA 0004AC 55 kW Generator, Used 1 EA 0004AD 100 kW Generator, New 1 EA 0004AE 100 kW Generator, Rebuilt 1 EA 0004AF 100 kW Generator, Used 1 EA 0004AG 250 kW Generator, New 1 EA 0004AH 250 kW Generator, Rebuilt 1 EA 0004AI 250 kW Generator, Used 1 EA 0004AJ 550 kW Generator, New 1 EA 0004AK 550 kW Generator, Rebuilt 1 EA 0004AL 550 kW Generator, Used 1 EA 0004AM 1 MW Generator, New 1 EA 0004AN 1 MW Generator, Rebuilt 1 EA 0004AO 1 MW Generator, Used 1 EA 0004AP 1.5 MW Generator, New 1 EA 0004AQ 1.5 MW Generator, Rebuilt 1 EA 0004AR 1.5 MW Generator, Used 1 EA 0004AS 2 MW Generator, New 1 EA 0004AT 2 MW Generator, Rebuilt 1 EA 0004AU 2 MW Generator, Used 1 EA 0004AV 5MW Generator, New 1 EA 0004AW 5MW Generator, Rebuilt 1 EA 0004AX 5MW Generator, Used 1 EA

Note: For CLIN 0004 and all SLINs, generator sizes are nominal (plus or minus 10%; i.e. a 90kW generator would be acceptable for the 100kw generator requirement) in order to provide opportunity for various manufacturers. Generators include all materials to connect to load to include cabling appropriate to generator rating, all grounding materials, etc.

Assume 50' from load.

0005 13.8 kV Power Plant Construction

0005AA 1 MW Power Plant 1 JOB 0005AB 5 MW Power Plant 1 JOB 0005AC 10 MW Power Plant 1 JOB 0005AD 15 MW Power Plant 1 JOB 0005AE 20 MW Power Plant 1 JOB

0006 4160 V Power Plant Construction

0006AA 1 MW Power Plant 1 JOB 0006AB 5 MW Power Plant 1 JOB 0006AC 10 MW Power Plant 1 JOB 0006AD 15 MW Power Plant 1 JOB 0006AE 20 MW Power Plant 1 JOB

0007 Medium Voltage Underground Distribution Construction

0007AA MV Underground Distribution 1 KM

0008 Low Voltage Distribution Construction

0008AA 100 amps 25 M 0008AB 200 amps 25 M 0008AC 400 amps 25 M 0008AD 800 amps 25 M 0008AE 1200 amps 25 M 0008AF 1600 amps 25 M 0008AG 2000 amps 25 M

0009 Overhead Distribution Construction

0009AA Overhead Distribution 1 KM

0010 NOT USED

0011 13.8 kV Power and O&M Service / Contractor Owned Contractor Operated Power Plant and Distribution System

0011AA 1 MW

1 Month

0011AB 5 MW 1 Month 0011AC 10 MW 1 Month 0011AD 15 MW 1 Month 0011AE 20 MW 1 Month

0012 4160 V Power and O&M Service / Contractor Owned Contractor Operated Power Plant and Distribution System

0012AA 1 MW 1 Month 0012AB 5 MW 1 Month 0012AC 10 MW 1 Month 0012AD 15 MW 1 Month 0012AE 20 MW 1 Month

0013 13.8 kV Power Plant O&M

0013AA 1 MW Power Plant 1 Month 0013AB 5 MW Power Plant 1 Month 0013AC 10 MW Power Plant 1 Month 0013AD 15 MW Power Plant 1 Month 0013AE 20 MW Power Plant 1 Month

0014 4160 V Power Plant O&M

0014AA 1 MW Power Plant 1 Month 0014AB 5 MW Power Plant 1 Month 0014AC 10 MW Power Plant 1 Month 0014AD 15 MW Power Plant 1 Month 0014AE 20 MW Power Plant 1 Month

0015 Medium Voltage Underground Distribution O&M

0015AA 1 km 1 Month

0016 Low Voltage Distribution O&M 0016AA 100 amps; 25 m 1

Month

0016AB 200 amps; 25 m 1 Month 0016AC 400 amps; 25 m 1 Month

0016AD 800 amps; 25 m 1 Month 0016AE 1200 amps; 25 m 1 Month 0016AF 1600 amps; 25 m 1 Month 0016AG 2000 amps; 25 m 1 Month

0017 Overhead Distribution O&M

0017AA 1 km 1 Month

5000 Incidental Construction to Services NOT PRICED AT MATOC – PRICED AT TASK ORDER 6000 Emergency Equipment

Replacement and Repair

NOT PRICED AT MATOC – PRICED AT TASK ORDER

7000 COTR Logistical Support NOT PRICED AT MATOC – PRICED AT TASK ORDER 8000 Demobilization/Phase‐Out NOT PRICED AT MATOC – PRICED AT TASK ORDER

9000 Equipment Buyback and Demob NOT PRICED AT MATOC – PRICED AT TASK ORDER

9000AA Equipment Buyback NOT PRICED AT MATOC – PRICED AT TASK ORDER 9000AB Equipment Demobilization NOT PRICED AT MATOC – PRICED AT TASK ORDER

9990 Contractor Manpower Reporting NOT PRICED AT MATOC – PRICED AT TASK ORDER

AFGHANISTAN LABOR BID SCHEDULE

AFGHANISTAN

U.S. TCN LN

Year 1

0002 Personnel Quantity Unit

0002AA Journeyman Electrician 1 Hour

0002AB Master Electrician 1 Hour

0002AC High Voltage Electrician 1 Hour

0002AD Power Generation Maintenance Technician 1 Hour

0002AE Logistics Manager 1 Hour

0002AF Site Manager 1 Hour

0002AG Quality Control Manager 1 Hour

0002AH Site Safety Health Officer 1 Hour

0002AI Project Manager 1 Hour

0002AJ Plant Operator 1 Hour

0002AK Plant Manager 1 Hour

Year 2

1002 Personnel Quantity Unit

1002AA Journeyman Electrician 1 Hour

1002AB Master Electrician 1 Hour

1002AC High Voltage Electrician 1 Hour

1002AD Power Generation Maintenance Technician 1 Hour

1002AE Logistics Manager 1 Hour

1002AF Site Manager 1 Hour

1002AG Quality Control Manager 1 Hour

Personnel Quantity Unit

1002AH Site Safety Health Officer 1 Hour

1002AI Project Manager 1 Hour

1002AJ Plant Operator 1 Hour

1002AK Plant Manager 1 Hour

Year 3

2002 Personnel Quantity Unit

2002AA Journeyman Electrician 1 Hour

2002AB Master Electrician 1 Hour

2002AC High Voltage Electrician 1 Hour

2002AD Power Generation Maintenance Technician 1 Hour

2002AE Logistics Manager 1 Hour

2002AF Site Manager 1 Hour

2002AG Quality Control Manager 1 Hour

2002AH Site Safety Health Officer 1 Hour

2002AI Project Manager 1 Hour

2002AJ Plant Operator 1 Hour

2002AK Plant Manager 1 Hour

Year 4

3002 Personnel Quantity Unit

3002AA Journeyman Electrician 1 Hour

3002AB Master Electrician 1 Hour

3002AC High Voltage Electrician 1 Hour

3002AD Power Generation Maintenance Technician 1 Hour

3002AE Logistics Manager 1 Hour

3002AF Site Manager 1 Hour

3002AG Quality Control Manager 1 Hour

3002AH Site Safety Health Officer 1 Hour

3002AI Project Manager 1 Hour

3002AJ Plant Operator 1 Hour

3002AK Plant Manager 1 Hour

Year 5

4002 Personnel Quantity Unit

4002AA Journeyman Electrician 1 Hour

4002AB Master Electrician 1 Hour

4002AC High Voltage Electrician 1 Hour

4002AD Power Generation Maintenance Technician 1 Hour

4002AE Logistics Manager 1 Hour

4002AF Site Manager 1 Hour

4002AG Quality Control Manager 1 Hour

4002AH Site Safety Health Officer 1 Hour

Personnel Quantity Unit

4002AI Project Manager 1 Hour

4002AJ Plant Operator 1 Hour

4002AK Plant Manager 1 Hour

FAR 52.217-8 Option to Extend Services (6 Month Max)

5002 Personnel Quantity Unit

5002AA Journeyman Electrician 1 Hour

5002AB Master Electrician 1 Hour

5002AC High Voltage Electrician 1 Hour

5002AD Power Generation Maintenance Technician 1 Hour

5002AE Logistics Manager 1 Hour

5002AF Site Manager 1 Hour

5002AG Quality Control Manager 1 Hour

5002AH Site Safety Health Officer 1 Hour

5002AI Project Manager 1 Hour

5002AJ Plant Operator 1 Hour

5002AK Plant Manager 1 Hour

CENTCOM COUNTRIES LABOR BID SCHEDULE – COEFFICIENTS USING AFGHANISTAN LABOR BID

SCHEDULE AS THE BASELINE

Year 1

Year 2

Year 3

Year 4

Year 5 FAR Clause 52.217-8 Option to Extend Services (up to 6 months)

U.

S.

TC

N

L N

U.

S.

TC

N

TC

N

TC

N

TC

N

TC

N

L N

Bahrain

Egypt

Iraq

Jordan

Kazakhstan

Kuwait

Kyrgyzstan

Lebanon

Oman

Pakistan

Qatar

Saudi Arabia

Syria

Tajikistan

Turkmenist an

U.A.E.

Uzbekistan

Yemen

Section 00 21 16 - Instructions to Proposers

PROPOSAL SUBMISSION

Section 00 21 16 - Proposal Submission Requirements

1. Introduction

The Offeror’s proposal shall be submitted in hard copy, with accompanying digital copies, as set forth below. The RFP provides the Government address and receipt date for proposal submittal. Any proposal that does not adhere to the requirements as set forth in this section may be deemed nonresponsive and the proposal may be rejected.

The Offeror’s proposal shall consist of an Introductory Packet and three (3) volumes with separate binders for the Introductory Packet and each Volume. Offerors shall provide four

(4) hard copies and one (1) electronic copy. The electronic copy shall be provided on CDs, one for the Introductory Packet and each Volume. The Volumes are Volume I – Approach to Sample Task Order, Volume II – Past Performance, and Volume III – Price. Files shall not contain classified data. The use of hyperlinks in proposals is prohibited.

Offerors are cautioned that “parroting” of the Technical requirements of the RFP with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation. Proprietary information shall be clearly marked.

Any Request for Information (RFI) or Questions about this solicitation must be submitted to the Contracting Office POC’s No Later Than 08 Jan 2021 by 5PM EST. Contracting POC’s are as follows:

Primary POC: Susan Li Email: Susan.Li@usace.army.mil

Secondary POC: Jamaal Edwards Email: Jamaal.A.Edwards@usace.army.mil

2. Proposal Submission Requirements

a. Each Volume shall be submitted in a separate three-ring binder. Any pages that are changed (as a result of negotiations or proposal revisions) should be a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated. Each binder shall be clearly labeled with its title and a copy number (e.g., copy 1 of 4).

b. Printing should be single spaced. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required. Table and illustrations may use a reduced font size no less than 8-point and may be landscape.

c. The following volumes of material shall be submitted:

Volume and Title # of Hard Copies

Maximum Pages Per Volume

I – Approach to Sample Task Orders 4 50 II – Past Performance (not including questionnaires) 4 25 III – Price 4 N/A

NOTE: The Introductory Packet will not be included in the proposal submission page counts. Pages that exceed the maximum page limits set forth in the chart above will be removed or not read and will not be evaluated by the Government. Price information must be solely contained in Volume III. For Volume I, proposed power plant site layout and power plant one-line diagram drawings, milestone schedule Gantt chart, and product cut sheets will not be included in the proposal submission page count and shall be submitted in an Appendix to Volume 1, Tabs 1 and 2, respectively.

3. Proposal Files.

a. Format. The submission shall be clearly indexed and logically assembled. Each Volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be numbered and identified by the complete company name, date, and RFP number in the header and/or footer. A Table of Contents should be created using the Table of Contents feature in MS Word. MS Word (doc) files shall use the following page setup parameters:

Margins – Top, Bottom, Left, Right – 1” Gutter – 0” From Edge

– Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11”

NOTE: 11x17 folded pages are acceptable for tables/graphic representations. However, each 11x17 page counts as two (2) pages.

In addition to providing hard copies, the Offerors shall also provide electronic copies as set forth below.

b. File Packaging. The Introductory Packet and each volume shall be on a separate CD. All of the proposal files in each Volume shall be in read-only PDF files, except for price breakdown information to aid in the price evaluation, which shall be submitted in Microsoft Office Excel Read/Write format. Each CD shall be externally labeled with either “Introductory Packet” or the Volume number, as well as the date and the Offeror’s name.

NOTE: Self extracting exe files are not acceptable.

NOTE: If the hard-copy proposal differs from the electronic version, the hard copy will govern.

c. Content Requirement. All information shall be confined to the appropriate file. The Offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each Volume shall consist of a Table of Contents and Summary Section. The Summary Section shall contain a brief abstract of the volume. Proprietary information shall be clearly marked.

Introductory Packet

The Introductory Packet shall include the following:

Cover Letter Organization Chart. Include an organizational chart, illustrating the organization and including key personnel.

Teaming arrangements. The Offeror shall document unequivocal teaming arrangements with its major subcontractors. Major subcontractors are contractors who will perform more than 20% of the total contracted price. Provide a narrative describing any contractual arrangements that have been established with subcontractors and their roles and responsibilities. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. A copy of the teaming or joint venture agreement(s) shall be provided.

Representations and Certifications from System for Award Management

Volume I – Factor 1: Approach to Sample Task Orders. There are two (2) sample task orders in Section 00 40 00 of the RFP. Sample Task Order 1 is for the Extension of Design, Construction, Operation, and Maintenance of an 8 megawatt (MW) Prime Power Plant and Distribution System. Sample Task Order 2 is for the provision of 8 MW of power as a service and includes operation, maintenance, and distribution.

Sample Task Order 2 is essentially the same requirement as Sample Task Order 1; however, in Sample Task Order 2, the power plant is owned by the Contractor and the Contractor is responsible for providing power as a service. For each of the two (2) sample task orders there should be a separate Tab for each sample task order under Volume I (Approach to Sample Task Orders) and under Volume III (Price).

Volume III – Price, Tab 1 and Tab 2 shall consist of the Offeror’s price proposal for each respective sample task order.

TAB 1 – Approach to Sample Task Order 1

The proposal shall include each of the required items below: Written Narrative, Staffing Plan, Milestone Schedule, and Equipment List for Sample Task Order 1.

TAB 2 – Approach to Sample Task Order 2

The proposal shall include each of the required items below: Written Narrative, Staffing Plan, and Milestone Schedule for Sample Task Order 2.

a. Written Narrative

The Offeror shall include a written narrative detailing its technical approach toward performing each of the sample task orders. The written narrative shall include the following

(i) Phase-in plan as defined in CLIN 0001.

(ii) The Offeror shall provide drawing(s) depicting proposed power plant site layout and power plant one-line diagram based on information contained within the Performance Work Statement (PWS). Plan shall explicitly address how offeror proposes to meet the redundancy requirement(s) to include de-rated values and to meet the 96-hour run-time requirement(s) specified in each Sample Task Order.

One-line diagram and any other documentation shall match equipment list quantities.

De-rated values for generators shall be shown. Generator output capacity (kW or MW) shall be adjusted for location and environmental conditions. Calculations and justification shall be provided for each de- ration factor applied to determine the final de-ration output capacity.

(iii) Plan for commissioning, operation, maintenance and service of the power plant to include at a minimum: generator services and if deviating from manufacturer’s recommendations, provide justification; preventative/predictive and emergency maintenance; generator shutdown/failure response plan;

documentation procedures; proposed commissioning process; operation and maintenance tasks to include frequency and task objective(s); and fuel delivery coordination approach.

(iv) Plan for commissioning, operation, and maintenance of the distribution system to include at a minimum: proposed commissioning process, preventative/predictive and emergency maintenance, documentation procedures, and proposed schedule.

(v) Phase Out Plan to include at a minimum concept of operations and phasing plan.

(vi) Safety Plan (written safety plan which addresses each major phase of the PWS, emergency spill response, internal safety SOP, and procedures, emergency response plan for periods of limited visibility, PPE provided to employees during periods of limited visibility, Logistics Support Area (LSA) provided, key safety personnel and their qualifications, training and experience levels, activity hazard analysis (specifically for specialized equipment used in the performance of work for each major phase of work). The Safety Plan shall conform to EM 385-1-1 (edition published on the date the solicitation was issued). Demonstrated knowledge of international and federal safety requirements.

b. Staffing Plan

The Offeror shall include a staffing plan for each sample task order. The staffing plan shall describe the positions, number of personnel needed to fill each position, job description, and nationality (US National, Other Country National, Host National) of personnel the Offeror proposes to use to perform the sample task order requirements. The staffing plan shall also provide appropriate qualifications and/or certifications for key technical positions to include at a minimum master electricians, journeymen electricians, plant operators, maintenance technicians, and quality control personnel in accordance with the solicitation as specified in Section 00 40 00, Sample Task Order 1, paragraph 2.1.1 and Sample Task Order 2, paragraph 2.2.1 and in Section 01 00 00, paragraphs 4.1, 7.8.2, and 8.5.1.2.

Teaming or joint venture arrangements, if applicable, shall include a clear description of each firm’s roles and responsibilities, and the staff to be provided by each.

c. Milestone Schedule

The Offeror shall provide a milestone schedule in Gantt Chart format for each of the sample task orders. Milestone schedule shall identify timelines, milestones, tasks, and illustrate the Offeror’s ability to meet the periods of performance for each of the sample task orders.

Milestones and tasks shall be identified and shown in a Notice to Proceed (NTP) + days format. Schedule shall demonstrate the Offeror’s understanding of requirements to execute the sample task order to include, but not limited to, phase- in/mobilization, phase-out/demobilization, procurement (as applicable), equipment manufacturing (as applicable), shipping, transportation methods (air, ground, sea, etc.), installation/construction (as applicable), commissioning (as applicable), and operation and maintenance periods.

d. Equipment List (For Sample Task Order 1 only)

The Offeror shall provide an equipment list that matches the Offeror’s proposed drawings and one-line diagram for the proposed power plant submitted as part of the Written Narrative. The Offeror’s proposed equipment list shall include but not be limited to the following items: generators, transformers, switchgear, fuel tanks, and pad mounted switches. The proposed equipment list shall demonstrate the Offeror’s understanding of the Sample Task Order requirements and demonstrate a complete and operable power plant and distribution system. The equipment list shall include quantities, make, model, size, and equipment description. Product cut sheets shall be provided for the following items:

generators, transformers, switchgear, fuel tanks, and pad mounted switches, and included as an appendix to Volume 1, Tab 1.

Volume II – Factor 2: Past Performance: Offerors shall submit a minimum of three (3) and a maximum of five (5) projects for the Offeror (projects done by major subcontractors may also be used within the overall limit of 3-5 projects) awarded within ten years of the date the solicitation is issued and at least 50% complete or completed, which are relevant to the efforts required by this solicitation. Projects are defined as a task order on an IDIQ contract or a standalone contract. IDIQ contracts are not considered projects. Relevancy:

The second aspect of the past performance evaluation is to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. Projects with a total contract value equal to or greater than $3,000,000.00 USD and involving either medium voltage power generation or medium voltage power distribution in a contingency environment will be considered relevant. In order to receive an minimum overall rating of “Relevant” for Factor 2, the Offeror shall demonstrate experience in both medium voltage power generation and medium voltage power distribution between all projects submitted, though medium voltage power generation and medium voltage power distribution experience does not necessarily need to be within the same individual project. Contingency environments are defined as areas with active military operations, stability operations, natural disasters, humanitarian events, and/or other calamitous events.

The relevancy of the Offeror’s past performance will be rated in accordance with the above table located in Section 00 22 16 Basis for Award and Evaluation Criteria under Factor 2, Section C, Subsection ii. If more than five (5) projects are submitted only the first five in the list submitted by the Contractor will be evaluated.

Offeror’s past performance shall be provided first, followed by each proposed major subcontractor (if provided). The Offeror shall also submit the written consent of its major subcontractor to allow the disclosure of its subcontractor’s past performance information to the Offeror. Major subcontractors are contractors who will perform more than 20% of the total contracted price. Past Performance by major subcontractors will be rated equally to that of the Offeror and will satisfy the requirements provided that projects and narratives meet the requirements listed above. The page limit for this volume includes pages for each major subcontractor but excludes Past Performance Questionnaire forms.

In addition, letters of commitment and written consent forms shall be included at time of proposal submission for all major subcontractors for their past performance to be considered. Letters of commitment and consent forms shall cover the entire ordering period of the MATOC (eg: five years).

This volume shall be organized into the following sections:

a. Tab 1 – Contract Descriptions. This section shall include the following information for each project submitted:

a. Contractor/Subcontractor place of performance, CAGE Code and DUNS Number. If the work was performed as a subcontractor, also provide the name of the prime contractor and Point of Contact (POC) within the prime contractor organization (name, current address, e-mail address, telephone and fax numbers)

b. Government contracting activity and current address. Procuring Contracting Officer’s name, e-mail address, telephone and fax numbers.

c. Government technical representative/COR and current email address, telephone and fax numbers

d. Government contract administration activity and the Administrative Contracting Officer’s name, and current e-mail address, telephone and fax number.

e. Government contract administration activity’s Pre-award Monitor’s name and current e-mail address, telephone and fax number.

f. Contract Number and, in the case of Indefinite Delivery type contracts, GSA contracts, and Blanket Purchase Agreements, include Delivery Order Numbers.

g. Contract Type (specific type such as Fixed-Price (FP), Cost Reimbursement (CR), Time & Material (T&M), etc. In the case of Indefinite Delivery contracts, indicate specific type (Requirements, Definite Quantity, and Indefinite Quantity) and secondary contract type (FP, CR, T&M, etc.).

b. Tab 2 – Performance. Offerors shall provide a narrative of each contract in Tab 1, Contract Description, describing the objectives achieved and detailing how the effort is relevant to the requirement of this solicitation. The narrative at a minimum shall include the following:

a. Objectives achieved and detail how the contract is relevant to the requirement of this solicitation.

b. Explanation shall be provided for projects that have experienced delays.

Explanation shall provide the reasons for the shortcomings and corrective actions taken to avoid recurrence.

c. Detail transportation methods (air, ground, sea, etc.) used to ship assets.

d. Describe how mobilization, demobilization and rotating personnel to/from project sites were completed.

e. Understanding of and experience with host country customs procedures.

f. Understanding of and experience with obtaining military base access and badging requirements.

g. Provisions provided for life support for employees.

h. Logistical issues or difficulties experienced during the execution of the contract and how the Offeror identified and managed risks, and overcame the issues or difficulties.

i. Ability to manage more than one project in different locations at the same time.

j. The Offeror shall provide a copy of any Cure Notices or Show Cause Letters received on each contract and a description of corrective action(s) implemented by the Offeror or proposed major subcontractor.

k. Indicate contracts that were terminated and the type and reason(s) for the termination.

c. Tab 3 – Past Performance Questionnaire. The Past Performance Questionnaire (PPQ) included in the solicitation shall be completed in its entirety by the client for each project and submitted with the proposal Completed PPQs must be submitted with the proposal. If the Offeror is unable to obtain a completed PPQ from a client before the proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ. PPQs completed prior to the solicitation date are unacceptable. This does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Other Proposal Submission Information:

Offerors may also include performance recognition documents received within the last ten years of the date the solicitation is issued, such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition.

In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by Offeror.

While the Government may elect to consider data from other sources, the burden of providing detailed, current accurate and complete past performance information rests with the Offeror.

Offerors are discouraged from providing points of contact with another contractor’s facility, i.e., in case an offeror (or one of his/her team members) is in a subcontract with another contractor who has submitted a proposal on the same requirement. Offerors shall provide and submit the prime contract number and all Governmental agency points of contact (POCs) in lieu of subcontract numbers or prime contract POCs in situations as described above.

VOLUME III – Price. This volume shall consist of all information, required to support proposed prices. Certified cost and pricing data are not currently required; however, the Government reserves the right to request such data prior to award. There are no page limitations for this volume. The Offeror shall ensure that the information submitted in this volume is consistent with and fully supports the amounts set forth in the SF1442 and continuation sheets. The Price Volume will consist of three (3) tabs:

Tab 1 – Price for Sample Task Order #1 Tab 2 – Price for Sample Task Order #2 For Tabs 1 and 2, the Offeror’s proposal for each sample task order shall include the completed respective sample task order bid schedule, to include a Summary and Breakdown, in RFP Section 00 40 00, which is described below. A Summary and Breakdown template is not provided for Sample Task Orders #1 and #2; however, offerors may provide a Summary and Breakdown in their own format. The rates (i.e., labor rates, operation and maintenance rates, etc.) proposed for Tabs 1 and 2 shall be reflective of any applicable corresponding CLINs on the Solicitation CLIN schedule in Section 00 10 00.

a) Summary

i. The Offeror shall submit a Microsoft Excel file (workbook) that calculates and includes the formulas necessary to develop a summary worksheet (single tab within workbook) which provides the summary of total cost/price for the base and option period.

b) Worksheet for the base and options

i. Each worksheet shall have a summary by cost element. Instructions for Cost

Elements are identified in following subparagraphs of this section.

ii. Offerors shall propose any costs associated with Contractor Manpower Reporting, as a separate cost on your summary, or specifically state that this is not separately priced in the pricing methodology (separate worksheet if necessary).

c) Please include the fully burdened labor categories and rates on a separate labor worksheet.

All labor categories and rates shall be included in the worksheet in order to accomplish the work/CLINs in accordance with the PWS. Fully burdened labor rate shall include Defense Base Act (DBA) insurance (see note below).

d) Materials/Equipment worksheet. Please separate any indirect costs/profit from the cost of the material/equipment.

e) Transportation Markup. Please separate any indirect costs/profit from the cost of the transportation.

f) Mobilization/De-mobilization. Please separate any indirect costs/profit from the cost of any mobilization/de-mobilization.

g) Basis of Materials

h) Indirect Rate worksheet

i) Travel worksheet to also include an estimated number of “Contractor Employees” needed to appropriately plan for in country LOA’s.

j) ODC worksheet

k) Miscellaneous

Tab 3 – Base Contract Pricing – CLINS 0001 through 0017 (to include applicable options)

Offerors shall complete and submit the Solicitation CLIN schedule in Section 00 10 00 of the RFP.

Offerors are cautioned that the rates proposed in Section 00 10 00 will be legally binding for both the base and option periods and the rates proposed will be the maximum rates that the Offeror may use to price all firm-fixed price Task Orders issued in either the base or option period. The Offeror’s proposed labor rates are to be fully burdened labor rates exclusive of profit. Lower rates may be offered at the Task Order level at the Offeror’s discretion and in accordance with each Offeror’s’ exercise of business judgment.

NOTE: DEFENSE BASE ACT INSURANCE

The Continental Insurance Company (CNA) single-provider, DBA requirements contract, that supported U.S. Army Corps of Engineers (USACE), the U.S. Central Command Joint Theater Support Contracting Command (C-JTSCC), and the 408th Contracting Command, expired on 30 September 2013. No additional options or extensions are available. USACE did not replace its requirement contract. Therefore, contractors will obtain DBA insurance from either a Department of Labor (DOL) authorized insurance carrier or utilize a self-insurance program.

The Department of Labor (DOL) has approved multiple insurance carriers which promote a competitive market environment. Therefore, USACE or Defense Microelectronic Activity (DMEA) contractors will obtain commercially available DBA insurance, from a DOL authorized insurance carrier unless the contractor is under a self-insurance program approved by the DOL or subject to a waiver. The DOL approved carriers and self-insured employers are available at http://www.dol.gov/owcp/dlhwc/lscarrier.htm.

D. DISCUSSIONS

1. GENERAL INFORMATION. In accordance with FAR 15.306(d), discussion sessions with each offeror may be held. Should discussions take place, all offerors in the competitive range will be allowed a reasonable amount of time to submit Final Proposal Revisions after discussions are concluded.

2. DISCUSSION SCHEDULING. If discussions are conducted, the Contracting Officer will schedule the discussion sessions, and each offeror will be notified of the time and place within a reasonable amount of time prior to their discussion session. Appropriate security clearances should be provided by the offerors in sufficient time to process the requests.

The Contracting Officer will provide additional instructions with the notification. The discussion sessions will take place via conference call, in person, or by written notification.

Section 00 22 16 - Supplementary Instructions to Proposers

SECTION 00 22 16

Section 00 22 16 - Basis for Award and Evaluation Criteria

The technical evaluation approach summarizes the assessment of the Offeror’s proposal as measured against the non-price factors. It also summarizes assessment of the strengths, weaknesses and risks associated with the Offeror’s proposed approach derived from the technical evaluation.

A. Evaluation Factors

This requirement will be solicited as a Request for Proposals (RFP) in accordance with FAR

6.401 and will utilize procedures described in FAR Part 15.101.

Award will be made based on the best overall (i.e., best value) proposals that are determined to be the most beneficial to the Government, with appropriate consideration given to the three (3) evaluation factors.

Factor 1: Approach to Sample Task Orders. The Government intends to evaluate the extent of the Offeror’s approach to sample task orders, including the Written Narrative, Staffing Plan, Milestone Schedule, and Equipment List items as specified in Section 00 21 16 for completeness and substantiveness and to assign an adjectival rating in accordance with FAR 15.101-1.

Factor 2: Past Performance. The Government intends to evaluate each Offeror’s past performance. There are three aspects to the past performance evaluation:

recency, relevancy, and quality. The Government will evaluate the recency, relevancy, and quality of each Offeror’s past performance and assign a performance confidence assessment rating.

Factor 3: Price. Price will not be rated, but will be evaluated for completeness, reasonableness, and unbalanced pricing (Reference FAR15.404-1(g)).

As described in FAR15.101-1, the tradeoff process permits tradeoffs among price and non-price factors and allows the Government to select other than the lowest priced proposal for contract award and FAR 15.101-2(a). For purposes of the tradeoff process, Factor 1 (Approach to Sample Task Orders) is more important than Factor 2 (Past Performance).

ALL NON-PRICED FACTORS COMBINED ARE APPROXIMATELY EQUAL TO PRICE.

All proposals shall be evaluated by the Source Selection Team.

Factor 1: Approach to Sample Task Orders: Factor 1 will be evaluated in accordance with FAR 15.101- 1 and given an overall adjectival rating.” The Government will evaluate the Offeror’s approaches to the sample task orders to determine whether they meet the requirements of the solicitation. The sample task orders are representative of the work to be performed under the contract, and an approach to a sample task order that does not meet the requirements of the solicitation could indicate a lack of understanding concerning mission requirements and may present a high risk of unsuccessful performance. To receive an Acceptable rating in accordance with the chart set forth below, the Offeror’s approach must completely and substantively address the Written Narrative, Staffing Plan, Milestone Schedule, and Equipment List items as specified in Section 00 21 16. To receive a minimum of an Acceptable rating, the Offeror’s approach must be responsive to and feasible for all requirements and subrequirements specified in Section 00 21 16. Failure to provide a proposal submission requirement or subrequirement specified in Section 00 21 16 will result in a proposal deficiency and a rating of Unacceptable. The Offeror’s approach shall demonstrate a full understanding of the technical and mission requirements for each sample task order. The Offeror’s proposed Milestone Schedule will be evaluated to ensure it is in the correct format, meets the overall requirements of the Sample Task Order, is in a logical order, and addresses all of the requirements to execute the Sample Task Order to include, but not limited to, phase- in/mobilization, phase-out/demobilization, procurement (as applicable), equipment manufacturing (as applicable), shipping, transportation methods (air, ground, sea, etc.), installation/construction (as applicable), commissioning (as applicable), and operation and maintenance periods. The Offeror’s proposed Equipment List will be evaluated to ensure that it matches the Offeror’s proposed drawings and one-line diagram for the proposed power plant for each of the sample task orders submitted as part of the Wriiten Narrative. The Offeror’s proposed Equipment List will be evaluated to ensure that it demonstrates the Offeror’s understanding for the Sample Task Order requirements and demonstrates a complete and operable power plant and distribution system.

To receive an overall minimum rating of “Acceptable” for Factor 1, the Offeror must receive a minimum rating of “Acceptable” for its approaches to both of the two (2) sample task orders. If either approach to a sample task order receives an “Unacceptable” rating, the Offeror will receive an overall rating of “Unacceptable” for Factor 1.

The Combined Technical/Risk Ratings excerpted below depicts how well the Offeror’s proposal meets the Technical Factor requirements:

TABLE 1 – Combined Technical/Risk Ratings

Color Rating Description

Blue Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Red Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

Factor 2: Past Performance: The Government will evaluate each Offeror’s past performance to determine the recency, relevancy and quality of each project to establish a corresponding confidence assessment adjectival rating. Each Offeror’s past performance will be reviewed to determine relevancy and a confidence assessment of recent experience. The Government will evaluate the Offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the solicitation.

a. Evaluation of past performance shall utilize the forms and questionnaires set forth in Appendix D. The

Government will also use data collected from Contract Performance Assessment Rating System

(CPARS).

b. The Government will focus its inquiries on the Offeror’s (and major subcontractor’s) record of performance as it relates to all solicitation requirements, including cost, schedule, performance and management of subcontractors. Major subcontractors are defined as members of an Offeror’s overall team who are expected to perform more than 20% of the total contracted price. A significant achievement, problem, or lack of relevant data in any aspect of the work can become an important consideration in the evaluation process. Therefore, Offerors shall include the most recent and relevant efforts within ten years of the date the solicitation is issued and at least 50% complete or completed. Absent any recent and relevant past performance history or when the performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned, the Offeror will be assigned a “neutral confidence rating” and its proposal will not be evaluated either favorably or unfavorably on past performance. The Government may use data provided by the Offeror in its proposal and data obtained from other sources, including data in Government files or data obtained through interviews with personnel familiar with the contractor and their current and past performance under Federal, State or Local government or commercial contracts for same or similar services as compared to the North American Industry Classification System (NAICS) 237130.

c. There are three aspects to the past performance evaluation: recency, relevancy, and quality. The Government will evaluate the recency, relevancy, and quality of each Offeror’s past performance and assign a performance confidence assessment rating.

(i) Recency: The first aspect of the past performance evaluation is to evaluate the recency of the Offeror’s past performance. Any past performance completed within ten years of the date the solicitation is issued and at least 50% complete or completed is considered recent.

(ii) Relevancy: The second aspect of the past performance evaluation is to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. Projects with a total contract value equal to or greater than $3,000,000.00 USD and involving either medium voltage power generation or medium voltage power distribution in a contingency environment will be considered relevant. In order to receive an minimum overall rating of “Relevant” for Factor 2, the Offeror shall demonstrate experience in both medium voltage power generation and medium voltage power distribution between all projects submitted, though medium voltage power generation and medium voltage power distribution experience does not necessarily need to be within the same individual project. Contingency environments are defined as areas with active military operations, stability operations, natural disasters, humanitarian events, and/or other calamitous events. Additional consideration will be given to offerors that submit project(s) that involve both medium voltage power generation and medium voltage power distribution within the same project. The relevancy of the Offeror’s past performance will be rated in accordance with the below table:

Adjectival Rating Description Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

(iii) Quality of Products or Services: The third aspect of the past performance…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .