Amendment 2.pdf

PDF 71 KB Posted

Attached to
2685 Quad Cities Test Tank Barge Federal contract opportunity
Solicitation number
W912BU20Q0023
Issued by
Department of the Army Corps of Engineers Engineering District Philadeplhia

About this file

This document contains an amendment to a federal solicitation for the construction of a test tank barge. Key details include:

The solicitation is for the design, fabrication, and delivery of a welded steel barge classified by ABS as Maltese Cross A1 Barge, Rivers Service with Reinforcement B. The completed barge will be used as a test tank by the U.S. Army Corps of Engineers Rock Island District and must be capable of being ballasted to 1.1 million pounds for lifting trials. The amendment provides answers to questions received, clarifying that deck winches are required and load testing of the delivered crane will not be performed. Quotes are due by July 30, 2020 and the award will be a firm fixed-price contract to the lowest priced responsive offeror meeting the requirements.

The summary focuses on the key product/service required, schedule details, and other salient information while excluding unnecessary legal language or other non-essential parts of the document per the instructions.

View the file

Other files for this federal contract opportunity

Other files attached to 2685 Quad Cities Test Tank Barge, newest first.
File Type Posted
Amendment 4 W912BU20Q0023.pdf PDF
Amendment 3 W912BU20Q0023.pdf PDF
Amendment 1.pdf PDF
731-E170-01 DRY DOCKING PLAN.pdf PDF
Spec Package.pdf PDF
865-B215-01 GENERAL ARRANGEMENT.pdf PDF
865-B406-01 MDC STANDARD FLOATING PLANT PAINT SCHEDULE.PDF PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #W912BU-20-Q-0023: For issuance of Amendment 2

Answers to Questions Received During Solicitation Period:

1. Question - Spec section C340 states the padeyes are to be removable via a bolted connection to the barge structure. Is it intended to have a flush deck or is it ok to have a welded structure on the main deck that the padeyes can be bolted too?

Answer – The main deck shall be flush after the removal of the padeyes.

2. With regards to testing and demonstrations, will Conrad be required to ballast the barge to 1,100,000 lbs and lift it or will this be done once the vessel is delivered to Iowa?

Performing the lift was not mentioned in the testing section.

Answer - Ballasting the barge during test and trials is not required by this contract. A load test of the crane will not be performed as a final demonstration under this contract.

3. Will the Corps require continuous welding on all internal structure considering the barge will be used as a test tank?

Answer - The welding shall be in accordance with ABS rules as required to receive regulatory approval and class certificate.

4. The general arrangement drawing provided with this solicitation shows (4) four winches on the main deck. The specification does not mention winches but I would like confirmation these will not be required?

Answer - Please see question and answer number 2 from Amendment 1. Deck winches are required.