Q&A Barge PEGASUS Maintenance 3299

W912BU-20-Q-0013

June 5, 2020

Q1: Will the 45 day schedule begin with the NTP which I assume will be given when the barge is delivered to the shipyard. Or will the 45 day schedule begin with contract award as indicated in Section F03 paragraph b?

A: This is not a construction project where it requires a NTP. The NTP is concurrent with the delivery of the vessel.

Q2: We would like to submit a Quote for the ABS Hull Gauging Portion but I don’t know. Who are the Main Ship Repair Yards that will be sending in a Solicitation to the government for this Project? Can you direct me to the person that can help me out with the MSR so we can submit to them?

A: The Government does not facilitate partnerships for procurement notices. We recommend subcontractors to reach out to shipyards that might fall within the travel distance outlined in the solicitation.