This document provides an amendment to a solicitation and responses to bidder questions regarding solicitation number W912BU20B0005 from the Department of the Army Corps of Engineers Engineering District Philadelphia. The solicitation is for reconstruction of approximately 27,000 square yards of access road and parking areas at the Dry Brooks Day Use Area, including milling and repaving the existing asphalt, extending one 18-inch corrugated metal pipe culvert by 8 feet, and adding a pavement drainage layer to three localized areas. The amendment extends the bid response date from June 29, 2020 to July 14, 2020. It also revises the pre-award survey submittal requirements to request experience with at least 10 similar projects of 15,000 square yards or 3,000 tons placed in the last 5 years, rather than the original 300,000 square yards or 70,000 tons. The estimated cost range for the project is $1,000,000 to $5,000,000.

View the file

Other files

File Type Posted
Formal Abstract 20B0005 BML Road Repair and Paving (1).pdf PDF
W912BU20B0005-Specs.pdf PDF
W912BU20B0005-Dwgs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The perpose of this amendment is to provide industry a response to their questions and to extend the bid opening date to July 14, 2020. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Jun-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU20B0005

X 9B. DATED (SEE ITEM 11)

29-May-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Jun-2020

CODE

US ARMY ENGINEER DISTRICT, PHILADELPHIA

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

W912BU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BU20B0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT

Response to questions regarding solicitation W912BU20B0005

Question 1. Section 00 50 05 Part 1.3 states in part that the bidder must “Demonstrate experience with at least 5 completed satisfactory projects of a similar nature and must have been at least 300,000 SY or 70,000 tons of bituminous pavements placed. Satisfactory projects must have been completed within the last 5 years.” Given the nature and scope of the proposed project, this responsibility criteria appears much too restrictive and may significantly limit competition. The square yardage and tonnage requirements appear to be many times more than that of the proposed project. Would the Government consider revising this criteria?

Answer 1. SECTION 00 50 05 – PRE-AWARD SURVEY SUBMITTAL REQUIREMENTS:

Please delete Section 00 50 05 in its entirety and substitute revised Section:

SECTION 00 50 05

PRE-AWARD SURVEY SUBMITTAL REQUIREMENTS

PART 1 GENERAL

1.1 DEFINITIVE RESPONSIBILITY CRITERIA

Award of this Contract will be made as a whole to the lowest responsive and responsible Bidder whose bid conforms to all requirements of the specifications. Subsequent to the bid opening, the apparent low Bidder shall submit Pre-Award Survey Information that demonstrates compliance with the requirements set forth in this section as a precondition to receiving award.

1.2 GENERAL PRE-AWARD SURVEY INFORMATION

Complete the pre-award survey information sheets attached to this section, and submit to the Contracting Officer within 5 calendar days after bid opening.

1.3 SPECIALIZED EXPERIENCE ON SIMILAR TYPE WORK AND PROJECT

EXPERIENCE

The Bidder must have performed as the prime contractor, or as a subcontractor having substantial responsibility for the work, and have been in business for at least the last 5 years.

Successful documentation can include but may not be limited to letters of recommendation, favorable ratings, etc. To demonstrate specialized experience, the apparent low Bidder shall provide the following as part of the pre-award survey information package:

a. Demonstrate experience with at least 10 completed satisfactory projects of a similar nature and must have been at least 15,000 SY or 3,000 tons of bituminous concrete pavements placed per project.

The satisfactory projects must have been completed within the last 5 years.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

Question 2. In reference to the responsibility criteria stated in section 00 50 05 Part 1.3, can key subcontractor experience be used to supplement the General Contractors experience?

Answer 2. No, key subcontractor experience cannot be used to supplement the General Contractors experience.

Question 3. BETA . SAM.gov shows the subject solicitation was updated on June 10th however I do not see any new documents posted. Have there been any additional documents posted since the original posting on May 29th?

Answer 3. No additional documents where posted. This response to questions from industry will create amendment 0001.

Question 4. The plans call for bituminous base/concrete while the specs call for HMA for the paving material. Please clarify.

Answer 4. Specification Section 32 12 16 and drawings refer to the individual HMA layers as “bituminous concrete base course” and “bituminous concrete wearing course.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 29-Jun-2020 01:00 PM to 14-Jul-2020 01:00 PM.

The required performance has changed from Invitation for bid number: W912BU20B0005Project title:

Blue Marsh Lake Road Repair and PavingIssue date: 29 May 20Bid opening date; 29 June 20This procurement for NAICS code 237310, Highway, Street and Bridge Construction to Invitation for bid number:

W912BU20B0005Project title: Blue Marsh Lake Road Repair and PavingIssue date: 29 May 20Bid opening date; 14

July 2020This procurement for NAICS code 237310, Highway, Street and Bridge Construction.

(End of Summary of Changes)