3199_-_Bearings_and_Sleeves_-_RFI_Questions_and_Answers.pdf
PDF 76 KB Posted
- Attached to
- INSTALL NEW CERAMALLOY SHAFT SLEEVES
- Solicitation number
- W912BU-18-Q-0004
About this file
Questions and Responses. This is for informational purposes only and will not result in a change in the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HAYWARD_Shaft_Bearing_RFQ.pdf | ||
| HAYWARD_Drawing_574-1-00012_-_Prop_and_Shaft_Det.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Request For Information
W912BU-18-Q-0004
Question 1: Ceramalloy is an old trade name for shaft sleeves. Would it be possible to replace the old sleeves with a sleeve from Duramax like their NCB shaft sleeve?
Answer 1: It is recognized that Ceramalloy is an old name for shaft sleeves. The Duramax NCB is acceptable.
Question 2: What is the estimated size or magnitude of this project in dollars?
Answer 2: The intent of the request for quote is to obtain industry prices for the subject work. Please provide your best quote.
Question 3: Is this project for services (not construction)?
Answer 3: The work is to re-sleeve the shafts from the NAN vessel HAYWARD and provide a new shipset of four (4) bearings appropriate to the re-sleeved shafts.
Installation of the shafts and bearing will be conducted during the vessel’s scheduled dry dock period.
Question 4: Inquiries to ABS revealed they require the sleeves to be hydro tested and would like to observe the installation. Is this vessel still under ABS certification?
Answer 4: The vessel is ABS classed. The sleeved shafts and bearings are to be provided prior to the vessel entering a dry dock period early next calendar year where ABS inspections will be conducted.
Question 5: Does the scope of this project include changing the shaft seal from a stuffing box to a mechanical face seal?
Answer 5: No changing the shaft seal was not included in this scope of work.
Question 6: Will the propellers be removed by the yard prior to collection of the shafts or will removal be required by the bidders?
Answer 6: The shafts in the base contract do not currently have propellers on them.
In the event Option 1 is exercised, the shafts will be provided without propellers.
File details come from the government source that posted it.