US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC:SANDI FLETCHER

WANAMAKER BLDG

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

THE PROPOSAL RECEIPT DATE IS EXTENDED TO APRIL 13, 2010 AT 2:00 P.M., LOCAL TIME.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU-10-R-0014

X 9B. DATED (SEE ITEM 11)

03-Mar-2010

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

JOB ORDER CONTRACT, JOINT BASE M-D-L, WRIGHTSTOWN, NEW JERSEY

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Mar-2010

CODE

4. REQUISITION/PURCHASE REQ. NO.

CODE

US ARMY ENGINEER DIS RICT, PHILADELPHIAT

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

W912BU E5CTCSGF7. ADMINISTERED BY (If other than item 6)

CODE FACILITY CODE

EMAIL:TEL:

Amendment No. 0002

W912BU-10-R-0014

14. DESCRIPTION OF AMENDMENT (continued)

a. Section 00 110 00—REQUEST FOR PROPOSAL SUBMITTAL REQUIREMENTS:

Please delete “Attachment D” pages 1 through 24 in its entirety and substitute with revised pages 00 110 00

– 22 through 00 110 00 – 45 annotated Amendment No. 0002, attached hetero.

Please delete pages 11 through 14 in their entirety and substitute revised pages, annotated Amendment No.

0002, attached hereto

Please delete pages 23 and 24 in their entirety and substitute revised pages, annotated Amendment No.

0002, attached hereto.

Please delete pages 39 and 40 in their entirety and substitute revised pages, annotated Amendment No.

0002, attached hereto.

Please delete page 45 in its entirety and substitute revised page, annotated Amendment No. 0002, attached hereto.

b. Section 00800—SPECIAL CONTRACT CLAUSES:

Please make a pen and ink change to page 24, paragraph 1 under “Submittals” to delete the words “Page 45 of 98”.

c. Section 00815—WAGE RATES:

Please delete the cover page in its entirety and substitute revised page, annotated Amendment No. 0002, attached hereto.

Please delete this section in its entirety and substitute revised pages, annotated Amendment No. 0002, attached hereto.

Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0002. Failure to acknowledge all amendments may be cause for rejection of your offer.

W912BU-10-R-0014 00 110 00 - 22

ATTACHMENT “D”

SAMPLE TASK ORDER

SCOPE OF WORK

TEST BUILDING 8810 FORT DIX N.J.

1.0. SUMMARY: If there is a difference between the drawings and written scope of work, use the measurements in the written scope.

1.1. The Contractor shall construct a building. The building will be concrete block with brick veneer, 36 feet wide and 116 feet long. The building will have a vestibule 10 feet wide and 12 feet long with double doors at the center of the building facing Doughboy Loop. The roof will be wood truss system with multi layered shingles.

1.2. The Contractor shall provide a complete set of drawings to include footings, foundation, floor, structure, roof, electrical, HVAC. The drawings will be paper and a CD. All engineering drawings will be raised seal and signed by a PE.

2.0. SITE WORK

2.1.LANDSCAPING

2.1.1. Restore damage to grounds and plantings caused by contractor’s personnel or equipment.

2.1.2. Dumpsters and waste containers shall be kept ten (10) feet away from building.

2.1.3. The contractor shall remove all contract-generated debris from the construction site and dispose of the debris off site at an approved landfill. Disposal shall be in accordance with Local, State and Federal laws and regulations.

2.1.4. It is the responsibility of the contractor to locate and mark all underground utilities before excavation.

2.2. EXCAVATION:

2.2.1. The contractor will layout and excavate for the footings and foundation of a building 36 feet wide x 116 feet long, with a vestibule that is 10 feet wide and 12 feet long, at the center of the building, facing Doughboy Loop. The excavation will be a minimum of 32 inches below grade, for a footing 16 inches wide, 1 foot thick. The finish floor elevation will be eight inches above grade.

W912BU-10-R-0014 00 110 00 - 23

2.2.2. Support the block foundations, back fill and compact the fill for a concrete floor.

2.2.3. The contractor will excavate trenches for the gas supply, water supply, sewer and electrical and communication lines or conduit. After each line is installed the trench will be back filled, using six inch lifts, tamped in between. The appropriate marking tape will be installed half way between the line and the surface.

2.2.3.1. The water supply runs along the rear fire line, forty (40) feet from the Mechanical Room.

2.2.3.2. The sewer line runs along Doughboy Loop, sixty (60) feet from the Mechanical Room.

2.2.3.3. The gas line runs along Doughboy Loop, fifty (50) feet from the Mechanical Room.

2.2.3.4. The electrical conduit runs from the power pole on Doughboy loop sixty (60) feet to the Mechanical Room.

2.2.3.5. The communication conduit runs from the DOIM closet of building 5616 forty (40) feet to the DIOM closet of building 5616.

2.2.4. The contractor will excavate for sidewalks. The sidewalks will be graded to meet the entrance pads and not exceed ADA standards. Sidewalks will be four feet wide and three inches thick.

2.2.4.1. The sidewalk will be from the front doors, 12 feet, and then run perpendicular 64 feet to the drop off lane.

2.2.4.2. One sidewalk 20 feet from the side door to the drop off area.

2.2.4.3. One sidewalk 29 feet from the side door to the fire lane.

2.2.4.4. One drop off area, 37 feet long x 13 feet wide, 34 LF from Doughboy loop.

2.2.4.5. One equipment pad, 10 feet x 10 feet behind Office 1.

2.2.4.6. Entrance pad, 10 feet x 10 feet at the front entrance.

2.2.4.7. Two (2) entrance pads, one each at the side doors, six feet x six feet.

2.2.5. FINAL GRADING: The area to be graded and seeded is 200 feet long, 75 feet wide.

This area includes the building.

W912BU-10-R-0014 00 110 00 - 24

2.2.5.1. After completion of construction the area around the building will be graded and raked level and cover with top soil.

2.2.5.2. The final grade will be covered with grass seed, a hydro seed type product.

3.0. CONCRETE

3.1. FOOTING

3.1.1. Install forms in the excavation in paragraph 2.2.1. The forms will be for a concrete footing, 12 inches thick and 16 inches wide.

3.1.2. Place a footing, 12 inches thick, 16 inches wide. The footings will be 4000 PSI concrete with reinforcing bars.

3.2. FLOOR

3.2.1. Place a six inch concrete floor on the foundation erected in paragraph

4.1. The floor will be 4000 PSI, reinforced with 4 inch x 4 inch welded wire. The floor will be screed and trowel finished. The floor will be eight inches above grade.

3.3. STEPS and SIDEWALKS: Pads and sidewalks will be boomed finished; the sloop will not exceed ADA requirements.

3.3.1. Form and place 3000 PSI sidewalks and drop off area six inches thick, 4000 PSI excavated in paragraph 2.2.4.1. thru 2.2.4.4.

3.3.2. Form and place (1) 3000 PSI pad, 10 feet wide and 10 feet long behind office 1.

3.3.3. Form and place 3000 PSI pads excavated in paragraphs 2.2.4.6. and 2.2.4.7.

4.0. MASONRY

4.1. FOUNDATION

4.1.1. Install a concrete block foundation on the footings installed in paragraph 3.1.1 and 3.1.2. The foundation will have a ledge for the brick veneer.

4.1.2. Construct block walls to form a building 36 feet wide x 116 feet long x 10 feet high. The walls will have headers for the two (2) 5-0 x 7-0 double doors, three (3) 3-0 x 7-0 single door and for nineteen (19) windows.

W912BU-10-R-0014 00 110 00 - 25

4.1.3. Construct a vestibule in the center of the building, facing Doughboy Loop. The vestibule will be 10 feet wide and 12 feet long (from the building). The vestibule will have a header for one (1) 5-0 x 7-0 double door.

4.1.3. Install a brick veneer tied to the block walls constructed in paragraphs

4.1.2. and 4.1.3. The brick will match the existing brick in the area for color, size and style. The veneer will start approximately eight inches above grade and rest on a ledge of the foundation.

5.0. METALS:

5.1. EXTERIOR:

5.1.1. Install a continuous ridge ventilation system. Manufactured ridge vents shall be self-flashing, pre-finished of dark bronze, and complete with end caps, connectors, integral filter material, and integral wind guard. Ridge vent shall provide 18 square inches of net free ventilation per linear foot. Installation shall be according to the manufacturer’s recommendations and specifications.

5.2.1. Install a 5” commercial type, .032” thick, dark bronze enameled aluminum gutter along the edges of roofs. All seams of gutters shall be sealed and complete with all required hardware, (cleats, spikes, hangers, end caps, and fasteners.)

Gutters shall terminate at least ½ inch away from vertical surfaces. Supporting cleats shall be anchored to the structure at spacing not exceeding 16” on center. Gutters shall be installed with high points at ends or equidistant from down spouts and shall have a slope of not less than 1/16” per foot.

5.3.2. Install a drop-in, or snap-on type gutter screens for leaf protection to the new 5” commercial gutters. Screens shall be of expanded rigid aluminum mesh complete with a mill finish and reinforced edge that fits directly to gutters lip.

5.3.3. Install a 3” x 4” rectangular dark bronze enameled,.024” thick, aluminum down spouts. Down spouts shall be complete with all required accessories, clips, anchors, straps, and fasteners. Down spouts shall be set plumb and not less than 1 inch from the wall. Leaders shall connect gutters on overhanging eaves to down spouts.

Leaders shall be set with a slope not less than 1/16” per foot or more than 30 degrees below the horizontal line. Leaders shall fit over the outlet in the gutter bottom and shall fit into, and riveted to the downspout. Rivet spacing shall not be more than 2 inches.

Joints between length of down spouts shall be made by telescoping the end of the upper lengths at least ¾” into the lower lengths. Down spouts terminating at splash blocks or pans shall be provided with stock elbow type fittings. Down spout hangers shall be provided adjacent to the joint at the top of each section of down spout, except that the bottom section shall have additional strap adjacent to the bottom joint when splash blocks or pans are required. Hangers shall be 1/16” x 1” flat stock of the same material as the downspout.

W912BU-10-R-0014 00 110 00 - 26

5.3.4. Install dark bronze aluminum material over the cornice.

5.3.5. Install continuous vented aluminum soffit material on the soffits.

6.0. WOOD AND PLASTIC

6.1. ROOF:

6.1.1. Install wood truss system, 5 in 12 pitch. The truss system will be designed to span the building, without any bearing partitions in the building. Both ends of the building will have a hip roof style truss. The contractor will provide shop drawings and calculations for approval. The drawings will be raised seal and signed by a PE.

6.1.2. The truss system will be firmly attached to a 2 x 10 firmly attached to the walls and the truss attached to the 2 x 20.

6.1.3. The roof will be decked with CDX 5/8 tongue and groove plywood, CDX. Clips may be used in place of the T&G.

6.2. DOIM Room: Install one (1) four x eight sheet of ¾ inch fire rated plywood to the wall common to the Mechanical Room.

6.3. BLOCKING:

6.3.3. Install blocking in the following partitions to support sinks. Offices 1 and 2, Offices 2 and 3, office 3 and Provider, Conference Room and Office 4, Offices 4 and 5.

7.0. THERMAL AND MOISTURE PROTECTION

7.1 INSULATION

7.1.1. Install 3 ½ inch fiberglass insulation between the metal stud furring strips installed in paragraph 9.1.1 on the walls of the outside of the building. The insulation will have a vapor barrier to the inside of the building.

7.1.2. Install 3 ½ inch fiberglass insulation between the metal studs for all the interior walls. This insulation does not require a vapor barrier.

7.1.3. Install 6 inch fiberglass insulation above the drop ceilings and the gypsum ceilings. The insulation will have a vapor barrier installed to the heated side of the room. The insulation will be above the sprinkler pipes.

7.1.4. All ductwork shall be insulated with rigid board insulation, one & one-half inches (1 ½”) thick with foil back vapor barrier. The insulation shall be secured to

W912BU-10-R-0014 00 110 00 - 27

the duct work by metal fasteners and adhesive. All seams shall be taped with aluminum tape, which has been properly adhered to the surfaces.

7.1.5. All hot water lines will be covered with one and a half inch fiberglass insulation. All joints taped and coated, elbows mitered.

7.2. SHINGLES: Shingles shall have self-sealing strips, be Premium laminated multi layered shingles 300 to 385 lb and four (4) bundles a square. Shingle shall meet a wind velocity rating of –60 mph plus or minus 15% in accordance with ASTM D 3161. Organic shingles shall comply with ASTM D225, TYPE I and ASTM E 108, and conforming to UL 55B and UL 997, Fire rating of Class A. Before any shingles are applied provide and install a double layer of 15# asphalt saturated underlayment over the new substrate. In areas subjected to ice damning, (eaves, rakes, valleys, and along the ridge) provide and install an adhered modified bitumen membrane underlayment. (Winter-guard or equal.) Waterproofing membrane shall be 18 inches wide.

7.2.1. Install shingles and Winter-guard on the roof deck of the building. Shingles will be selected from samples provided by the contractor.

8.0. DOORS AND WINDOWS: All locks and cylinders will have a removable "BEST" core and be keyed per the customer's requirements.

8.1. DOORS and JAMBS: All jambs shall be 16 gage metal. Exterior jambs will be welded. All exterior doors will be 3-0 x 7-0 solid metal, with a core for exterior use. The doors will have three (3) 4 1/2 x 4 1/2 inch ball bearing hinges, full mortise, High Frequency, stainless steel finish. The exterior door hinges will be non-removable type.

Interior doors will be solid core birch veneer clean coated 3-0 x 7-0. All latching devices will be Series 4000, grade 1, stainless steel finish.

All doors will have a surface mounted heavy duty closer, stainless steel finish. All doors will have a stainless steel kick plate.

8.1.1. Install twenty three (23) 3-0 x 7-0 jambs and solid core birch veneer doors from the corridor into the Offices, Exam Rooms, Janitor Closet and Male, Female and Staff Latrines. From the Provider to Exam Room, Admin to the Records room. The doors to the latrines will have a passage sets, the doors into Offices, Exam Rooms, and Janitor’s Closet will have heavy duty 2 ¾ lockets with a lever and return to the door and removable core. All doors will have a closer and a door stop.

8.1.2. Install two (2) 3-0 x 7-0 jambs and metal doors, at the side entrance doors.

Each door will have a panic bar with a locking leaver handle on the exterior, a closer and threshold. The doors will have a 3’ x 30 inch window.

8.1.3. Install one (1) 5-0 x 7-0 double jamb and two vented 2-6 x 7-0 metal doors into the Mechanical Room. One door will have a closer, 2 ¾ inch backset key and knob lock with a leaver handle and a door stop. The second door a head and foot bolt and door stop. The doors will swing out of the Mechanical Room.

W912BU-10-R-0014 00 110 00 - 28

8.1.4. Install one metal (1) 3-0 x 7-0 door jamb and solid metal door into the DOIM closet. The door will have a 2 ¾ inch heavy duty key and knob with a return to the door and a removable core. The door will have a closer and a threshold.

8.1.5. Install one (1) 5-0 x 7-0 double jamb and two 2-6 x 7-0 metal doors into the vestibule. Both doors will have Panic devices with rods, with a leaver handle with a removable core and 3” x 30” window.

8.1.6. Install one (1) 5-0 x 7-0 double jamb and two 2-6 x 7-0 birch veneer from the vestibule to the Waiting Area. Both doors will have Panic devices with rods, with a leaver handle with a removable core and 3” x 30” window.

8.2. WINDOWS: Window will be counter balance to remain in place during operation and both sash tilt in for cleaning. Sill will have a wall thickness of 0.078”. The jambs, heads, millions, stiles and rails main wall thickness of 0.062”. Glazing of 7/8” thick insulation glass of two sheets of 3/32” clear annealed glass.

8.2.1. Install nineteen (19) bronze colored, aluminum framed 3 foot wide, 5 foot high, thermo pane glass and double hung windows with full screens.

8.2.1.1. Front: One window in the Mechanical Room, Office 6, 7, Admin, Waiting, Office 8, 9 and 10.

8.2.1.2. Side: One window in Office 5 and 11.

8.2.1.3. Rear: One window in Office 1, 2, 3, Provider and Exam, Break Room, Conference Room, Office 4 and 5.

8.2.1.4. Admin/Reception: Install one (1) slider reception window in the rough opening of paragraph 9.1.4.4. The window will be locked from the Admin side.

9.0. FINISHES

9.1. PARTITIONS: All studs are to be 16 inches on center, 16 gage. All corridors when finished will be 5’ wide.

9.1.1. Install 3 ½ inch metal studs for furring strips on the block walls installed in paragraph 4.1.2. and 4.1.3.

9.1.2. Corridor: The finished corridor will be 5 feet wide.

9.1.2.1. FRONT PARTITION: Install one (1) 3 ½ inch metal studs partitions 114 feet long 14 feet from the front wall. The partition will have rough openings for eight 3-0 x 7-0 doors.

W912BU-10-R-0014 00 110 00 - 29

The partition will have a six foot opening 54 feet from the side wall with the DOIM Room.

9.1.2.1.1. The rough openings for Offices 6 and 7 will be near their common partition. The rough opening for Records will be near the partition common to Office 7. The rough openings for Admin and Office 8 will be near the partitions for the waiting room. The rough opening for Offices 9 and 10 will be near their common partition.

The rough opening for Office 11 will be near the side wall.

9.1.2.2. Install one (1) 3 ½ inch metal studs partitions 114 feet long 14 feet from the rear wall. The partition will have rough openings for thirteen 3-0 x 7-0 doors. The partition will have an alcove in from the Janitor’s closet for an ADA water fountain.

9.1.2.2.1. The rough opening for Office one will be near the partition of Office 2. The rough opening for Office 2, 3 near their common partition. The rough opening for Provider will be near the partition common to Office 3. The rough openings for the Exam Room and Female Latrine will be near their common partition. The rough openings for the Janitor’s Closet and Male Latrine will be near their common partition. The rough openings for the Staff Latrine and Break Room will be near their common partition. The rough opening for the Conference Room will be near the partition common to Office 4. The rough openings for Office 4 and Office 5 will be near their common partition.

9.1.3. Mechanical Room/DOIM Closet: Install six inch metal studs to fabricate a ceiling.

9.1.3.1. Mechanical Room: Install one (1) partition from the partition installed in paragraph 9.1.2.1. to the outside front wall. The partition will be 15 feet from the side wall.

9.1.3.2. DIOM Closet: Install one (1) partition five long, from the partition installed in paragraph 9.1.2.1. the partition will be eight feet from the side wall. Install one (1) eight foot partition perpetual from that partition to the outside wall.

9.1.4. Front: Install eight (8) partitions 14 feet long to form nine rooms.

9.1.4.1. Office 6: Install one partition nine feet from the Mechanical Room to form Office 6.

9.1.4.2. Office 7: Install one partition nine feet from Office 6 to form Office 7.

9.1.4.3. Records Room: Install one partition from seven feet from Office 7 to form the Records Room. This partition will have rough opening for a 3-0 x 7-0 near the corridor.

W912BU-10-R-0014 00 110 00 - 30

9.1.4.4. Admin/Reception Room: Install one partition nine feet from the Records Room to form the Admin/Reception Room. This partition will have a rough opening for a three foot high, four foot long reception window three feet above the floor.

9.1.4.5. Lobby/Waiting Area: Install one partition twenty four feet from the Admin/Reception Room to form the Lobby/Waiting area.

9.1.4.6. Office 8: Install one partition nine from the Lobby/Waiting Area to form Office 8.

9.1.4.7. Office 9: Install one partition nine feet from Office 8 to form Office 9.

9.1.4.8. Offices 10 and 11: Install one partition nine feet from Office 9 to form Offices 10 and 11.

9.1.5. REAR: Install eight (8) partitions 14 feet long to form nine office, the latrines and Janitor’s Closet.

9.1.5.1. Office 1: Install one partition nine feet from the outside wall to form office 1.

9.1.5.2. Office 2: Install one partition nine feet from office 1 to form office 2.

9.1.5.3. Office 3: Install one partition nine feet from office 2 to form office 3.

9.1.5.4. Provider: Install one partition nine feet from office 3 to form Provider office. This partition will have a rough opening for 3-0 x 7-0 door next to the corridor.

9.1.5.5. Exam Room: Install one partition 7 feet 6 inches from the Provider Room to form the Exam Room.

9.1.5.6. Latrines: Install one partition 29 feet from the Exam Room to form the Latrines. Install 6 inch metal studs for a ceiling over the three latrines and the Janitor’s Closet.

9.1.5.6.1. Female Latrine and Janitor’s Closet: Install one (1) partition 10 feet 6 inches from the Exam Room to form the Female Latrine. This partition will be the one foot chase wall and be 8 feet long and perpetual from the outside wall. Install one (1) partition perpetual to the chase wall, 10 feet 6 inches long, and six feet from the Exam room. Install two

(2) partitions form that partition to the partition installed in paragraph 9.1.5. to form the

W912BU-10-R-0014 00 110 00 - 31

Janitor’s Closet. The first partition will be eight feet from the Exam Room, the second partition will be 7 feet 6 inches from that.

9.1.5.6.2. Male Latrine: Install one (1) partition twelve feet from the Female latrine to form the Male Latrine and the Staff Latrine.

9.1.5.7. Break Room: Install one (1) partition nineteen feet from the Latrines to form the Break Room/Conference Room.

9.1.5.8. Office 4 and 5: Install one (1) partition nine feet from the Conference Room to form Offices 4 and 5.

9.2. WALLBOARD: The wall and ceilings forming the Mechanical Room and DIOM will be fire rated one hour. All wallboard will be spankeled three coats, sanded smoothed between each coat.

9.2.1. Install ½ inch wallboard on the furring strips installed in paragraph 9.1.1.

The wallboard in the Male, Female and Staff Latrines, Janitor’s Closet will be moisture resistant.

9.2.2. Install ½ inch wallboard on the studs installed in Paragraph 9.1.2. Inside the DOIM and Mechanical room will be two layers of 5/8 fire rated.

9.2.3. Install two layers of 5/8 fire rated wallboard on the ceiling joist install in Paragraph 9.1.3. the DOIM Closet and Mechanical Room. The partition between Mechanical Room and the DOIM Closet and Office 6 and the Corridor will be double layer of 5/8 wallboard on the Mechanical Room and DOIM side.

9.2.4. Install ½ wallboard on the studs installed in paragraph 9.1.4.

9.2.5. Install ½ wallboard on the studs installed in paragraph 9.1.5. The wall board in the latrines and janitor’s closet will be moisture resistant.

9.2.6. The walls will have a wallboard return to the window frames.

9.3. DROP CEILINGS: All drop ceilings will be 2' X 2' X 5/8" thick, mineral tile with a reveled edge. No boarder tile will be less than half a full tile wide. All lights, fixtures, fans, shall be wired or supported independent of the ceiling grid. All tile will be class A fire rated.

9.3.1. Install drop ceilings in the Corridor, Waiting Room, Admin, Records, Break Room, Conference Room, Provider, Exam, Offices, and Entry.

9.4. PAINT: All paint will be primed and two coats finished. The walls will be flat, the doors and trim semi gloss. Colors will be selected from submittals provided by the contractor.

W912BU-10-R-0014 00 110 00 - 32

9.4.1. Paint the walls in the Offices, Exam Rooms, DOIM Room, Janitor’s Closet, Corridor, Latrines and Mechanical Room.

9.4.2. Paint the ceilings in DOIM closet, Janitor’s Closet, Male Latrine, Female Latrine, Mechanical Room.

9.4.3. Paint the interior jambs and exterior doors and jambs, and window frames.

9.5. FLOOR: All tile and cove will be selected from samples provided by the contractor.

The Mechanical Room floor will be bare concrete.

9.5.1. Install 12 inch x 12 inch vinyl composite tile in Corridor, Waiting Room, Admin, Records, Break Room, Conference Room, Provider, Exam, Offices, Entry, and DOIM Room.

9.5.2. Install four inch vinyl cove base in the Corridor, Waiting Room, Admin, Records, Break Room, Conference Room, Provider, Exam, Offices, Entry, and DOIM Room.

9.5.3. Install ceramic floor tile in the Male, Female and Staff Latrine, Janitor’s Closet.

9.5.4. Install ceramic cove base tile in the Male, Female and Staff Latrine, Janitor’s Closet.

9.6. WALL

9.6.1. Install ceramic wall tile on the walls of the Male, Female, Staff Latrine and Janitor’s Closet.

9.7. CABINETS:

9.7.1. Install one (1) three foot base sink cabinet. The cabinet will have double door front and a plastic laminate top. Install one (1) three foot wall cabinet over the base cabinet.

10.0. SPECIALTIES

10.1. EXTINGUISHER

10.1.1. Install three (3) semi-recessed fire extinguisher cabinets and three (3) 10 lb ABC dry chemical fire extinguishers. One cabinet and extinguisher located at each exit door.

W912BU-10-R-0014 00 110 00 - 33

10.2. TOILET PARTITIONS: All partitions will be painted steel.

10.2.1. MALE LATRINE: Install two (2) toilet stalls, One will be ADA. Each stall will have a coat hook and double toilet paper dispenser. The ADA stall will have two grab bars, the bars will be firmly attached with backer blocks. Install two (2) urinal partitions.

Install two (2) soap dispensers, one at each lavatory. Install one (1) standard mirror and one

(1) ADA mirror above the ADA sink. Install two (2) paper towel dispensers.

10.2.2. FEMALE LATRINE: Install two (2) painted metal toilet stalls. One will be ADA. Each stall will have a coat hook and double toilet paper dispenser, sanitary napkin disposal. The ADA stall will have two grab bars, the bars will be firmly attached with backer blocks. Install two (2) soap dispensers, one at each lavatory. Install one (1) standard mirror and one (1) ADA mirror above the ADA sink. Install two (2) paper towel dispensers.

10.2.3. STAFF LATRINE: Install one (1) privacy partition between the toilet and lavatory. Install one (1) stall with door to form a change room next to the shower stall.

Install a double toilet paper dispenser, paper towel dispenser and one mirror above the lavatory.

10.3. SIGNAGE: All signs will be laminated plastic, three inches high, twelve inches long, engaged with the type of room and number. The signs for the latrines will have brail, the Staff Latrine will “Staff Only”.

10.3.1. Install twenty one (21), one each for;

Male Latrine, Female Latrine, Staff Latrine, Office 1, Office 2, Office 3, Office 4, Office 5, Office 6, Office 7, Janitor’s Closet, Storage, Exam Room 1, Exam Room 2, Exam Room 3, Exam Room 4, Exam Room 5, Exam Room 6, M.D. Office 1, M.D. Office 2, M.D. Office 3.

11.0. EQUIPMENT - NONE

12.0. FURNISHINGS

12.1. WINDOW TREATMENT

12.1.1. Install PVC vertical blinds on the nineteen (19) windows of the Offices, Exam Rooms and M.D Offices. The blinds will be room darkening.

13.0. SPECIAL CONSTRUCTION - NONE 14.0. CONVEYING SYSTEMS – NONE

15.0. MECHANICAL: See paragraphs 2.2.3.2 to 2.2.3.5. for utility ties in locations.

15.1. PLUMBING: All copper water supply pipes will be K, joints silver soldered, pipes insulated. All water supplies to plumbing fixtures will have shut off valves. The drain line

W912BU-10-R-0014 00 110 00 - 34

to the building will be 4 inch schedule 40 PVC connected to the existing cast iron sewer line with an approved saddle connector. The water line to the building will be 3 inch L grade copper, connected to the existing water line with a shut off value in a curb box.

15.1.1. DRAIN LINE: Install one four inch schedule forty drain line, approximately 96 L.F, from the partition between Office 1 and 2 along the rear wall of the building to Office 4 and 5.

15.1.1.2. Floor Drains. Install four (4) floor drains, one in each of the latrines and one in the Janitor’s Closet connected to the main drain installed in paragraph 15.1.1.

The floor drains will have a slotted cover and the traps feed by water supply to keep the traps filled.

15.1.1.3. Laterals: The male, female, staff latrines, exam rooms, janitor’s closet and break room will be connected to the main drain installed in paragraph 15.1.1.

15.1.1.4. Capped lines: Partitions between Offices 1 and 2, 2 and 3, 3 and MD/Provider Office, Conference Room and Office 4, Office 4 and 5 will have drain lines connected to the main drain installed in paragraph 15.1.1. The drain lines will be three feet above the finished floor and be capped off for future use.

15.1.2. Female latrine: Install two (2) toilet drains and two (2) cold water supplies for toilets along the chase wall common to the male latrine. One drain and supply will be for an ADA stall. Install two (2) sink drains and four (4) water supplies along the partition common to the Janitor’s Closet. The water supplies will be two hot and two cold. One drain and supply will be for ADA.

15.1.2.1. Female latrine Fixtures: Install two (2) wall mounted lavatories, vitreous china, with soap dish depression and ADA lever faucet fixture, Delta or Moen on the partition common to the Janitor’s Closet. The one nearest the door will be mounted to ADA specifics, the supply and drain pipes will be covered. Install two (2) water closets, oval front with seat and cover. The water closet nearest the outside wall will be ADA.

15.1.3. Male Latrine: Install two (2) toilet drains and two (2) cold water supplies for toilets along the toilets along the chase wall common to the female latrine. One of the drains and supply will be for an ADA stall. Install two (2) urinal drain and two cold water supply on the partition common to the Staff latrine. The urinal nearest the lavatories will be for an ADA urinal. Install two (2) sink drains and four (4) water supplies along the partition common to the staff latrine. The water supplies will be two hot and two cold. One drain and supply will be for ADA.

15.1.3.1. Male latrine Fixtures: Install two (2) wall mounted lavatories, vitreous china, with soap dish depression and ADA lever faucet fixture, Delta or Moen on the partition common to the staff latrine. The one nearest the urinals will be mounted to ADA specifics, the supply and drain pipes will be covered. Install two (2) water closets, oval front with seat and cover. The water closet nearest the outside wall will be ADA.

W912BU-10-R-0014 00 110 00 - 35

Install one (1) wall mounted ADA urinal on the rear wall.

15.1.4. Staff Latrine: Install one (1) toilet drains and one (1) cold water supply or the toilet along the chase wall common to the male latrine. Install one (1) sink drain and two (2) water supplies along the partition common to the male latrine. Install one drain and a water supply on the wall common to the Break Room for a shower. The water supplies will be one hot and one cold.

15.1.4.1. Staff Latrine Fixtures: Install one (1) one piece stall shower in the corner of the outside wall and partition common to the break room. Install one wall mounted lavatory, vitreous china with fixture, Delta or Moen. Install one water closet.

15.1.5. Exam Room: Install one (1) sink drain and two water supplies along the partition common to Staff Latrine. One water supply will be hot and one cold.

15.1.5.1. Exam Room Fixtures: Install one wall mounted lavatory, vitreous china with fixture, Delta or Moen.

15.1.6. Break Room: Install one (1) drain and two water supplies for a cabinet mounted sink.

15.1.6.1. Break Room Fixtures: Install one drop in sink in the cabinet and counter top installed in paragraph 9.7.1.

15.1.7. Domestic Hot Water: Install one gas fired hot water heater, 50 gallon in the Mechanical Room of the building. This heater will supply the buildings domestic hot water requirements and the supply will have a circulator pump.

15.1.8. Water Cooler: Install one (1) ADA style recessed water cooler, located one the partition common to the Janitor’s Closet.

15.1.9. Supply Lines: Interior water supply lines will be ¾ inch L copper and ½ inch L copper for the circulator line. All joints will be lead free silver solder.

15.2. HVAC: Contractor will provide calculations for HVAC sizing to DPW. These will be based on medical facility requirements. If calculations change the size, this will be negotiated with DPW before changes are made.

15.2.1. Install two five ton HVAC split systems in the main mechanical room to provide heating and air conditioning to all areas of the building. One system will support the east side of the building and the other will support the west. The condensing units shall be located on an exterior preformed pad. One service disconnect shall be supplied at each condensing unit and be weather tight.

W912BU-10-R-0014 00 110 00 - 36

15.2.2. Install two 110,000 BTU 80% efficient gas fired hot air furnaces in the new Mechanical Room.

One furnace will condition the east side of the building and the second the west side. The furnace will have an upgraded blower.

The Blower CFM will be rated according to Air conditioning manufacturer’s recommendations for five tons of cooling

15.2.3. The new unit shall be equipped with an outside air economizer package.

The combination mixing box and filter section shall have factory assembled filter tracks with replaceable filters and filter access doors for ease of changing. Outside air damper will be manually operated and set at the minimum percentage of outside air brought into the system will be based on the BOCA code for a medical facility

15.2.4. To minimize stratification and to assure that all zones have access to uniform heating and cooling, the re-circulated air should be brought to the unit across the full width of the unit.

15.2.5. All suction lines for the new units shall be covered with ½” thick unicellular insulation

15.3. Ventilation:

15.3.1. Install three (3) 300 CFM exhaust Fans one in each latrine. These fans as well as the lights for each room will be controlled by a motion activated switch with a 10 minute off delay

15.4. DUCTWORK

15.4.1. The new heating and air-conditioning system shall have all new ductwork installed in the building. Each room will have a minimum of one Supply and one return duct with exception of the latrines and DOIM, they will have a supply duct only. The contractor shall provide a layout of the proposed duct system for approval prior to installation. Layout will detail size and location of entire system. All duct will be insulated with foil back wrap and will be sealed with high quality foil tape. After installation a set of formal as-builds shall be provided to the government for updating of real property records.

15.4.1.1. Each zone shall have fire dampers installed in the mechanical room fire wall.

15.4.2. Install diffusers in the suspended ceiling and gypsum ceiling. The diffusers shall be high capacity, four-way blow with adjustable butterfly dampers for balancing the air flow. The contractor will provide shop drawings for approval.

W912BU-10-R-0014 00 110 00 - 37

15.4.2.1. The drops to the diffusers may be installed using insulated flexible duct work. If so, the flex duct MUST be secured to the collars using wire ties installed with a tension tool, then taped with fiber duct tape or aluminum tape.

15.4.3. The branch ducts shall have fire dampers installed at the fire wall of the mechanical room.

15.4.3.1 Each system will be controlled by an independent thermostat. Each thermostat will have a sensor reading return air temp at a common point of all rooms but not in an area that it can sense mixed air. These will be mounted on the wall outside of the mechanical room and be clearly marked to there function.

16.0. ELECTRICAL: All wire and cable shall meet all standards and specifications applicable, and shall be in conformance with the latest edition of the NEC. All wire shall be in EMT, flexible conduit, or shall be MC cable (three conductor black, white and a full size green ground. Wire shall be copper conductor, type THHN or THWN, unless otherwise specified. Wiring devices shall be specification grade, and colored to compliment the decor.

All wiring devices will be 125V / 20 ampere rated unless otherwise specified. Power and lighting panels shall be dead front, safety type, with thermal magnetic, quick-make, quick-break, trip free, bolted-type molded case circuit breakers. Bus bars shall be rectangular, solid copper, securely mounted and braced.

16.1. LIGHTING: Lighting fixtures shall be 2’x 2’ drop in fluorescent lights with prismatic lens, unless otherwise specified. The fixture shall be supported independently of the drop ceiling. These will have electronic ballast(s), silver reflectors, and energy efficient fluorescent tubes installed in all these fixtures. The housing of each fluorescent lighting fixture shall be provided with a separate, factory installed grounding device.

Lamps shall be by these suggested manufacturers or equivalent, Philips Alto Lighting (F32T8/TL830/ALTO), Osram Sylvania (F032/800XP/ECO), or General Electric Ecolux Lighting (F32T8XL/SP35/ECO).

16.1.1. Install twenty eight (48) light fixtures, four each in Office 1, 2, 3, Provider, Office 4, 5, 6, 7, Admin., Office 8, 9, 10 and 11. Install fourteen (14) single pole switches, one in each office near the door to control the fixtures. One fixture in each Office will have battery backup.

16.1.2. Install four (4) light fixtures, two each in Exam Room and Records.

Install four (4) three way switches, two in the Exam Room and two in the Records Room, One by each door to control the fixtures. One fixture in each room will have battery backup.

16.1.3. Install twelve (12) fixtures, in the Waiting area. Install two three way switches, one switch by the double door and one by the opening to the corridor. Two fixtures will have battery backup.

W912BU-10-R-0014 00 110 00 - 38

16.1.4. Install one fixture in the vestibule. Install one single pole switch on the waiting area side of the double door to control the

16.1.4. Install four (4) fixtures in the male latrine The fixture will be surface mounted and controlled by one (1) switch near the door. One fixture will have battery backup. Install two (2) surface mounted fixtures above the mirrors. The fixtures will be controlled by the same switch.

16.1.5. Install four (4) fixtures in the female latrine. The fixture will be surface mounted and controlled by one (1) single pole switch near the door. One fixture will have battery backup. Install two (2) surface mounted fixtures above the mirrors. The fixtures will be controlled by the same switch.

16.1.6. Install two (2) fixtures in the staff latrine. The fixtures will be surface mounted and controlled by one (1) single pole switch near the door. One fixture will have battery backup. Install one (1) surface mounted fixture above the mirror. The fixture will be controlled by the same switch.

16.1.7. Install one (1) fixture in the Janitor’s Closet. The fixture will be surface mounted and controlled by one (1) single pole switch near the door.

16.1.7. Install one (1) fixture in the DIOM Room. The fixture will be surface mounted and controlled by one (1) single pole switch near the door.

16.1.8. Install three (3) fixtures in the Mechanical Room. The fixtures will be surface mounted and controlled by one (1) toggle switch near the door.

16.1.9. Install fourteen (14) fixtures in the Corridor The fixtures will be control by two (2) three way switches, one near the exit doors and a four way switch on the wall near the Waiting Area. Four fixtures will have battery backup.

16.1.10. Install three (3) surface mounted lighted exit signs above the three exit doors.

16.1.12. Install one (1) surface mounted lighted exit sign above the water fountain in the Corridor pointing to exits. Install one (1) double face ceiling hung Exit sign pointing to the front entrance.

16.1.13. Install three (3) 150 watt HPS light fixtures above each exit door. The lights to be controlled by photo control.

16.2. DEVICES:

16.2.1. Install seventy eight (78) duplex receptacles, six in Office 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, Provider Office and Exam Room. Each Office will be on a 20 amp dedicated circuit using 12/2 MC cable.

W912BU-10-R-0014 00 110 00 - 39

16.2.2. Install ten (10) duplex receptacles, six in the Admin/Recept Office and four in the Records room. Each will be on a 20 amp dedicated circuit using 12.2 MC cable.

16.2.3. Install nine (9) duplex receptacles, six each in Conference Room, and three in the break Room. Install one (1) GFI duplex receptacle near the sink in the break room. Each room will be on a 20 amp dedicated circuit using 12.2 MC cable.

16.2.4. Install seven (7) duplex receptacles in the Waiting area/Entry. Six in the waiting area and one in the Entry. The room will be on a 20 amp dedicated circuit using 12.2 MC cable.

16.2.5. Install four (4) GFI duplex receptacles, one each in the Male Latrine, Female Latrine, Staff Latrine and Janitor’s Closet. These will be on a dedicated circuit using

12.2 MC cable.

16.2.6. Install four (4) duplex receptacles in the DIOM Room. The DOIM Room will be on a 20 amp dedicated circuit using 12.2 MC cable.

16.2.7. Install three (3) duplex receptacles in the Mechanical Room. The Mechanical Room will be on a 20 amp dedicated circuit using 12.2. MC cable.

16.2.9. Install six (6) duplex receptacles in the corridor. The receptacles will be on the same 20 amp dedicated circuit using 12.2. MC cable.

16.3. COMMUNICATION: Install a NEMA 12 enclosure made by Hoffman Engineering Part# A-242410LP box on the exterior wall of the DOIM Room. Install four inch schedule 40 PVC conduit 40 feet from building 5608 and 10 feet up the wall to the existing Hoffman.

16.3.1. Install thirty four (34) boxes, two each in Offices 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, Provider, Exam, Conference Room, Records, Admin/Recept and Waiting. Each drop for communications will be four (4) green Cat 6 plenum rated cables. The cable will be run from the drop to the DOIM Room and coiled (10 foot lengths) and tagged. Final connections will be made by others.

16.3.1.1. ASSUME installing 12,000 LF of Cat. 6 green plenum

rated cable.

16.4. POWER:

16.4.1. Install a 225 amp 3 phase 4 wire 42 circuit breaker panel with main and full panel in the Mechanical Room.

W912BU-10-R-0014 00 110 00 - 40

16.4.1.1. Install two (2) 30 amp 208 volt 3 phase circuits to the condensing units with two 30 amp NEMA 3R disconnects.

16.4.1.2. Install two (2) 20 amp 120 volt circuits in ceiling for air handler with two single pole switches.

16.5 SERVICE AND DISTRIBUTION

16.5.1. Install all main runs, and other circuits according to set of plans. All electrical circuits above the suspended ceiling shall properly supported and hung independent of the ceiling.

16.5.2. Install one 4 inch conduit sixty feet from the mechanical room of building 5616 to the utility pole on Doughboy Loop and ten feet up the pole. Install the service cable from the building to the utility pole and leave excess coiled.

16.6. ALARMS

16.6.1. Install wall mounted Manual Dual Action Pull stations located at exits and corridors to ADA height. The pull stations connected to four alarm devices with lights, two on each station.

16.7. ACCEPTANCE

16.7.1. Upon completion of electrical work all contract drawings and load list documents shall be verified during “Final Inspection” and documented “As-Built" before final acceptance tests. Before the final acceptance test the installation contractor shall fully test the system.

16.7.2. Acceptance Tests shall be performed on all detection and alarm system components to verify operability and acceptance criteria. Testing shall be conducted by contractor certified test personnel and witnessed by local Fire Prevention and RDPW technical staff. The test method shall consist of demonstration of 100% smoke and heat detection with the appropriate zone response and function to provide indication, local and /or remote alarm. Acceptance criteria shall be as required by NFPA 72 and NFPA 101 for horns and flashers.

17.0. MATERIALS: All work and materials shall conform to all applicable JOC specifications.

17.1. SUBMITTALS: The contractor shall submit the following materials for approval: Doors, jambs, hard ware, windows, paints, ceiling tile, floor tile, toilet partitions, plumbing fixtures, electrical fixtures and devices, boiler, AC unit, hot water heater, window treatments, plastic laminate, cabinets.

18.0. General Requirements

W912BU-10-R-0014 00 110 00 - 41

18.1. National Fire Alarm Code; A-5-3.5.1,Detectors shall not be located in a direct airflow, and not closer than 3 feet (1m)from an air supply diffuser and ceiling fans. When installing fans, the detector shall be moved not less than 3 feet or the fan shall be installed not less than 3 feet from the existing or new detector.

18.2. The contractor shall be advised that all fire alarms, smoke and heat detectors shall be protected from dirt, dust and damage during demolition and reconstruction of the facility by covering them with a plastic or other viable covering to prevent these devices from inadvertently being set off by airborne dust and dirt. The disconnection of the existing fire protection system and alarms requires prior approval of the Fire Prevention Bureau at the below telephone numbers.

18.3. The contractor shall comply with the most current editions of the National Fire Protection Codes, Installation fire prevention standards, Army Regulation 420-90. All open/hot work or disconnection of fire protection alarms or suppression systems requires prior approval of the Fort Dix Fire Prevention Bureau at (609) 562-5484/6430/6001. Any disconnection, connection or installation of fire protection alarms or suppression systems shall require an acceptance test performed by the contractor and witnessed by the Fire Prevention Bureau.

18.4. Contractor will comply with all the requirements of the National Fire Code Standard 241 Safeguarding Construction, Alteration, and Demolition Operations 2002 edition. Contractor shall be very familiar with the requirements of Chapter 9 Safeguarding Roofing Operations of the National Fire Code Standard 241.

The requirements can be viewed at the Fort Dix Fire Prevention Bureau. (609) 562-5484.

18.5. The contractor shall comply with Installation safety regulations, Engineer Manual 385-1-1 and all applicable OSHA Regulations. Contact the Fort Dix Safety Office for further information and prior to work. (609) 562-3754/2900

18.6. The contractor shall ensure compliance with all Federal, State and local environmental regulations. The type and quantity of all hazardous materials brought to the work site shall be reported to the Fort Dix Environmental office at

(609) 562-3050/5325.

18.7. The contractor shall provide material safety data sheets (MSDS) for all hazardous materials used on the job site. The contractor shall not turn in hazardous waste generated during the performance of the contract, for disposal by the Government, unless such disposal is explicitly provided for in the contract. If specified in the contract, the contractor shall provide and MSDS for each hazardous material/waste turn-in to the government for disposal.