14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
THIS AMENDMENT DOES NOT EXTEND THE BID OPENING DATE OF 22 AUGUST AT 2:00 P.M.
CONTINUED ON NEXT PAGE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
MODIFICATION OF CONTRACTS/ORDER
NO.
E. IMPORTANT: Contractor
15B. CONTRACTOR/OFFEROR
is not, copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer tended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
is extended, B.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CON-
TRACT ORDER NO. IN ITEM 10A.
2. AMENDMENT/MODIFICATION NO.
6. ISSUED BY
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) is required to sign this document and return
15A. NAME AND TITLE OF SIGNER (Type or print)
PAGE OF PAGES 1. CONTRACT ID CODE
5. PROJECT NO. (If applicable) 4. REQUISITION/PURCHASE REQ. NO. 3. EFFECTIVE DATE
7. ADMINISTERED BY (If other than Item 6)
15C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16B. UNITED STATES OF AMERICA
BY
16C. DATE SIGNED
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10B. DATED (SEE ITEM 13)
CODE CODE
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
is not ex-copies to the issuing office.
NSN 7540-01-152-8070
PREVIOUS EDITION UNUSABLE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
(Signature of person authorized to sign) (Signature of Contracting Officer)
USAPPC V2.00
10A.
30-105-02
US ARMY ENGINEER DISTRICT, PHILADELPHIA
POC: MICHELLE BERTOLINE
WANAMAKER BUILDING, 100 PENN SQUARE EAST
PHILADELPHIA, PENNSYLVANIA 19107-3390
US ARMY ENGINEER DISTRICT, PHILADELPHIA
WANAMAKER BUILDING, 100 PENN SQUARE EAST
PHILADELPHIA, PENNSYLVANIA 19107-3390
CODE
FACILITY CODE
0001 7/31/2008
W912BU-08-B-0017
22 Ju.y 2008
Beach Nourishment, Delaware Coast, Dewey Beach, with Options for Rehoboth Beach, Bethany Beach and S. Bethany Beach, This page was intentionally left blank for duplex printing.
Amendment No. 0001 Invitation for Bids
W912BU-08-B-0017
14. DESCRIPTION OF AMENDMENT (continued)
a. TECHNICAL SPECIFICATIONS:
(1) Section 01 35 30 - MUNITIONS AND EXPLOSIVES OF CONCERN (MEC) CONSTRUCTION SUPPORT: Please delete pages 01 35 30-3 and 4 in their entirety and substitute revised pages 01 35 30-3 and 4, annotated Amendment No. 0001, attached hereto.
(2) Section 01 71 23 – SURVEY REQUIREMENTS: Please delete page 01 71 23-5 in its entirety and substitute revised page 01 71 23-5, annotated Amendment No. 0001, attached hereto.
(3) Section 35 31 00 – BEACHFILL: Please delete page 35 31 00-6 in its entirety and substitute revised page 35 31 00-6, annotated Amendment No. 0001, attached hereto.
b. Please indicate receipt of this amendment on Standard Form 1442(SOLICITATION, OFFER, AND AWARD) as Amendment No. 0001. Failure to acknowledge all amendments may be cause for rejection of the offer.
This page was intentionally left blank for duplex printing.
beach shall prevent the passage of any material greater than one and one-quarter inches in diameter. The openings on the screening device shall be of uniform dimension (i.e. a grid or a series of round holes;
slotted openings will not be permitted). The maximum allowable opening size is 1-1/4" x 1-1/4".
c. The screening devices shall be made of rugged steel or composite material, one-piece or welded members, and constructed to cover the entire area where installed, except where basket type devices are used on the discharge end, relief windows will be permitted only at the top of the baskets. Windows shall be sized and located to prevent large items, and MEC items from escaping the basket during pumping operations.
d. The screening devices utilized shall be demonstrated on site by the Contractor to meet all requirements as specified and are subject to approval of the Contracting Officer.
e. The screening devices shall be removable for easy replacement if damaged and shall provide a production rate that allows the Contractor to complete all dredging and beachfill placement within the contract duration.
f. The Contractor shall maintain adequate replacement parts and additional screening devices on site to ensure production for the work does not stop due to damaged devices or delays in the inspection process.
3.1.2 Dredge Cutterhead Screening Device
If a cutterhead is used, the dredge cutterhead screening shall be a device similar to that as provided by Dredging Supply Company, (contact information and example are shown at the end of this Section) or may be of the Contractor's own configuration (the device shall satisfy screen requirements specified above).
3.2 VISUAL INSPECTION OF PIPELINE DISCHARGE END
Visual inspections by the Contractor's personnel (who have been trained and approved by the OESS) shall be required at all times dredged material is being placed on the beach. The Contractor shall perform visual inspections of the interior and exterior of the discharge-end screening device after each in-flow cycle for the presence of MEC. Contractor personnel shall perform visual inspections from outside the screening device. Contractor personnel shall not enter a screening device with dredged material in it until the screening device has been inspected and cleared by the OESS. Under no circumstances shall a screening device be emptied until inspected by the OESS. After a screening device has been inspected and cleared by the OESS, all debris collected in the screening device shall be removed from the work site. The debris may be temporarily stored on-site in a dumpster or roll-off box. Do not bury any debris collected in the screening device in the beachfill.
3.3 INSPECTION OF INTAKE SCREEN
The Contractor shall inspect the intake or pipeline screening device a minimum of every 8 hours for hydraulic pipeline dredging, and every load for hopper dredging to ensure its effectiveness.
SECTION 01 35 30 Page 3
3.4 DETECTION OF MEC
The Contractor shall stop work immediately upon notification by the Contractor's inspector of the presence of MEC in any screening device or on the beach.
When MEC is detected on the beach, the Contractor shall implement the following procedures:
a. All personnel shall leave the area in the vicinity of the detected
MEC.
b. The Contractor shall stop dredging and beachfill work.
c. The Contractor shall notify the OESS.
d. The Contractor shall report the incident to the COR.
e. Beachfill and/or dredging work will not be permitted to re-commence until notification from the Contracting Officer.
3.5 MEASUREMENT AND PAYMENT
The work specified in this section will not be measured for payment and all cost in connection therewith shall be included in the contract lump sum prices for Base Bid Item Nos. A3 and B3, "MEC Modifications and Monitoring."
This work shall include the preparation of submittals associated with MEC;
the design and installation of screening devices on the intake and on the discharge end of the pipe line; and, the labor and materials associated with cleaning and maintaining those screening devices. The costs associated with, and, avoidance of MEC, to complete the work associated with Options 1 through 11 (if awarded) shall be included in the unit prices for the Option Beachfill Bid Items.
-- End of Section --
SECTION 01 35 30 Page 4
3.2 SURVEY BASELINE CONTROL
Survey baseline control descriptions are provide in Section 00830 and are as shown on the contract drawings. The baseline shall be surveyed utilizing surveying procedures and methodology that meet or exceed accuracy tolerances of +/- 0.10 feet in the vertical and +/- 0.10 feet in the horizontal.
3.3 CONSTRUCTION BASELINE
The Contractor shall stake and flag, every 100 feet, a construction baseline, located such that it provides easy reference by QA and QC personnel. The location of the construction baseline is subject to the approval of the COR.
3.4 PRE-PLACEMENT CONDITION SURVEYS
3.4.1 General
The beachfill area conditions are dynamic in nature. Conditions existing during the preparation of this contract may not be an accurate representation of the beachfill area conditions existing at the commencement of beachfill operations. Consequently, the Contractor shall obtain pre-placement condition survey cross sections . Surveys are only required in Rehoboth Beach, Bethany Beach and South Bethany if options for those areas are awarded
3.4.2 Completion Time Requirements
The pre-placement condition surveys shall be completed and submitted for Government review not later than 30 calendar days after the date of receipt by him of the notice to proceed.
3.4.3 Daily Data Submission
Raw and edited data from the pre-placement condition surveys, in HYPACK formats i.e. .RAW, .EDT, .HSX, shall be submitted to the COR on a daily basis.
3.4.4 Locations of Survey Lines
The Contractor shall obtain pre-placement condition surveys between Station 133+92 and Station 169+23 in Dewey Beach, Station 27+96 and Station 58+16 in Rehoboth Beach (if awarded), Station N-12+00 and Station N64+11.18 in Bethany Beach (if awarded), and Station S-15+00 and Station S52+70.60 in South Bethany (if awarded). The cross sections shall be obtained at the locations of the cross sections shown on the contract drawings.
3.4.5 Description of Required Survey Lines
The survey cross sections shall be long lines, and shall extend from the survey baseline to a minimum 1,900 feet seaward
3.4.6 Intervals Required
Elevations along the cross-sections shall be taken at a maximum of 10 foot intervals, with additional elevations taken at breaks in grade and as necessary to describe all hydrographic and topographic features.
SECTION 01 71 23 Page 5
3.4.7 Quality Control
Data from previous surveys will be provided to the Contractor in advance of the pre-placement surveys. The Contractor shall overlay the previous surveys with pre-placement surveys as a quality control measure.
3.4.8 Photographic Documentation of Surveys
During the completion of pre-placement condition surveys, digital color photographs shall be taken at each profile line to provide visual documentation of the beach. The digital photographs shall be taken from a point on the baseline located approximately halfway between the water line and the Contractor work limit. The photographs shall be taken in three directions. The first shall be taken facing perpendicular to the baseline azimuth. The direction of the photographs shall be defined by facing the ocean while standing on the baseline and turning counterclockwise approximately 90 degrees (generally facing a northerly or easterly direction along the coast of Delaware). The second shall be taken parallel to the baseline azimuth and facing seaward. The third shall be taken parallel to the baseline azimuth and facing landward. Any obstructions along the baseline azimuth which preclude collection of data shall be documented with additional digital photographs. Digital files and a set of hardcopy images shall be provided to the Government in a brief report documenting the surveys, weather conditions, beach conditions and field notes.
3.5 BEFORE- AND AFTER-BEACHFILL SURVEYS
3.5.1 Completion Time Requirements
Before-beachfill surveys of a location shall be conducted no more than 10 calendar days before after-beachfill surveys of that location. Any variations from these requirements require pre-approval of the Government Survey Point of Contact - that is, in advance of the survey's required completion date.
3.5.2 Daily Data Submission
Raw and edited data from the before- and after-beachfill surveys, in HYPACK formats i.e. .RAW, .EDT, .HSX, shall be submitted to the COR on a daily basis.
3.5.3 Locations of Survey Lines
The survey cross-sections shall be taken every 100 feetand also at the locations of the pre-placement surveys in the locations requiring beachfill. Surveys are only required in Rehoboth Beach, Bethany Beach and South Bethany if options for those areas are awarded.
3.5.4 Description of Required Survey Lines
The survey cross sections shall extend 1,000 feet seaward from the survey baseline. The origin of the new profile lines shall be the survey baseline, as shown on sections on the contract drawings.
3.5.5 Intervals Required
Elevations along the cross-sections shall be taken at a maximum of 10 foot intervals, with additional elevations taken at breaks in grade and as
SECTION 01 71 23 Page 6
3.2 PRE-PLACEMENT CONDITION SURVEYS
The beachfill area conditions are dynamic in nature. Conditions existing during the preparation of this contract may not be an accurate representation of the beachfill area conditions existing at the commencement of beachfill operations. Consequently, the Contractor shall obtain pre-placement condition survey cross sections, in accordance with Section 01 71 23 SURVEY REQUIREMENTS. Upon receipt of the pre-placement surveys as specified in Section 01 71 23 SURVEY REQUIREMENTS, the Government will re-issue revised beachfill sections. Commencement of beachfill will not be permitted until these surveys have been submitted and approved, and revised beachfill section re-issued by the Government.
3.3 MAINTENANCE OF DRAINANGE OUTFALLS
The Contractor shall maintain drainage of all outfalls at all times throughout the duration of the contract.
3.4 REMOVAL OF STRUCTURES
All existing structures, including but not limited to, the volleyball poles and bases, will be removed by others.
3.5 PLACEMENT OF BEACHFILL
3.5.1 General
Beachfill material shall be placed and shaped to the beachfill template lines, grades, slopes, and elevations shown on the contract drawings. There shall be no pronounced ridges or wash holes in the final grades and slopes unless otherwise indicated. Beachfill lines and grades shall extend linearly between payment sections with no scallops in planform contours.
The required placement quantity of sand in each acceptance section will be determined by the difference in cross-sectional area between (1) the cross-section surveys obtained by the Contractor before the beachfill operations in accordance with Section 01 71 23 SURVEY REQUIREMENTS and (2) the template lines shown on the drawings.
For placement, a vertical tolerance of plus 0.2 feet and minus 0 will be permitted on the berm portion of the beach. Beachfill shall be placed to the minimum seaward edge of berm and to the foreshore slope indicated on the drawings, however the Contractor may adjust the construction template by advancing the seaward edge of berm (at the same elevation) and adjusting the foreshore slope to achieve the required placement quantity within the footprint of the beachfill template shown on the drawings. An example of an adjusted construction template is attached to this section.
In the event that the berm elevation, the minimum seaward edge of berm or the required placement quantities are not met in each acceptance section, the Contractor shall recommence beachfill operations until the requirements are met.
Payment will be made for placement only to the lines and grades shown on the contract drawings (see Measurement and Payment paragraph below). In the event the Contractor adjusts the construction template as specified herein, payment will be made for measured quantity, not exceeding the required placement quantity. Payment will not be made for material placed above the required berm elevation, or placed seaward of the toe of slope. The toe of
SECTION 35 31 00 Page 5 slope shall be defined as the point of intersection of the template as shown on the drawings with the before-placement survey cross section.
The Contractor shall conduct his work operations so that no areas landward of the work limits shown on the Contract Drawings are disturbed.
Land-based equipment shall be used for grading the beachfill material.
3.5.2 Removal of Debris
When MEC or MEC-like items are detected on the beach, the Contractor shall implement the procedures specified in Section 01 35 30 MUNITIONS AND EXPLOSIVES OF CONCERN (MEC) CONSTRUCTION SUPPORT. When any non-MEC item that physically should not be able to pass through the intake screening opening is detected in the discharge screening device, the Contractor shall implement the following procedures:
a. The Contractor shall stop dredging and beachfill work.
b. The Contractor shall report the incident to the COR.
c. Intake and/or discharge screening devices shall be repaired if necessary.
d. Beachfill and/or dredging work will not be permitted to re-commence until notification from the Contracting Officer.
During the operation of placing beachfill material, all debris resulting from construction operations shall be removed from the work site and disposed of at no additional cost to the Government. Such disposal shall comply with all applicable Federal, state and local laws. Such materials shall be removed from the site of the work before the date of completion of the work under these specifications. Debris may be temporarily stored on-site in a dumpster or roll-off box. Do not bury any debris collected in the screening device in the beachfill.
3.5.3 Placement of Beachfill Beneath Existing Beach Structures
Placement and grading of beachfill material by hand may be required beneath existing beach structures. The Contractor shall protect the existing beach structures from damage. Placement of beachfill material beneath structures shall be done in a manner that minimizes the ponding of water. If ponded areas are created due to the Contractor's operations the Contractor shall pump these areas dry at no additional cost to the Government. Any structures damaged shall be repaired at no additional cost to the Government.
3.5.4 Hydraulic and Hopper Dredges
All pipelines used with hydraulic dredges shall be kept in good condition at all times, and any leaks or breaks shall be promptly repaired. Material excavated by hopper dredge shall be loaded into bins or hoppers and pumped directly to the beachfill area by a means which shall prevent the loss of any material into the ocean. Special care shall be taken to ensure that hoppers do not leak during any phase of the contract work.
3.5.5 Submerged Dredge Pipe
Barricades, warning signs, and lights shall be provided by the Contractor, SECTION 35 31 00 Page 6