This is a Bid Schedule for the Lower Brule North Ecosystem, Element 1, Phase 2 project. The document details ten line items of work including L-Head Breakwater Structure placement, mobilization/demobilization, stone riprap, excavation (cut and fill), borrow source excess material, loamy topsoil material, aggregate surface course, and culvert pipe placement. The estimated quantities range from 9 culvert pipes to 115,000 cubic yards of excavation fill. Notable contractual details include a 4.5% Tribal Employment Rights Ordinance (TERO) tax assessed on 48.77% of the contract award amount, and a specification that no government-furnished materials will be provided. The bid requires unit pricing for each line item, with a warning that total bids submitted without individual line item prices will be rejected.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

Lower Brule North Ecosystem, Element 1, Phase 2

Item Estimated Unit

No. Description Quantity Unit Price Amount

0001 Entire work, complete, for placement of the L-Head

Breakwater Structures

(Placement of riprap stone

/ Choke stone in the water) as shown on the drawings and in the specifications 1,175 LF $_________ $___________

0002 Entire work, complete, for the mobilization / demobilization of all equipment as shown on the drawings & in the specifications 1 Job N/A $___________

0003 Entire work, complete, for all plant, material, and labor required for: Stone (Riprap) as shown on the drawings and in the specifications 65,500 Tons $_________ $___________

0004 Entire work, complete, for All plant, material, and labor required for:

Excavation Cut in the specifications 90,000 CY $_________ $___________

0005 Entire work, complete, labor required for:

Excavation Fill in the specifications 115,000 CY $_________ $___________

0006 Entire work, complete, labor required for:

Borrow Source Excess Material in the specifications 25,000 CY $_________ $___________

0007 Entire work, complete, labor required for:

Loamy Topsoil Material in the specifications 35,525 CY $_________ $___________

0008 Entire work, complete, for aggregate surface course in the specifications 6,600 CY $_________ $___________

0009 Entire work, complete, labor required for:

Placement of culvert pipes in the specifications 9 EACH $_________ $___________

0010 All remaining work

Except for

Items listed below 1 Job N/A $___________

TOTAL AMOUNT (0001 – 0010) $________________________

Notes:

1. See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of line items.

2. The quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun subject to Contract Clauses "Variation in

Estimated Quantity."

3. Bid prices must be entered for all items of the schedule. Total amount bids submitted without bid prices being entered on individual items will be rejected. Extensions will be subject to verification by the Government. In case of variation between the unit prices and the extensions, the unit prices will be considered the bid.

4. A modification to a bid which provides for a single adjustment to the total amount bid should state the application of the adjustment to each respective unit price and lump sum price affected.

If the modification is not so apportioned, the single adjustment will be applied to Item No.10.

5. TRIBAL EMPLOYMENT RIGHTS ORDINANCE (TERO): A Tribal Employment Rights

Ordinance (TERO) tax will be assessed on 48.77% of the contract award amount (base and options) since this project is located on both federal and tribal property. The Lower Brule Sioux

Tribe TERO tax rate is 4.5%. The successful contractor should not sign any agreement allowing the Tribe to exercise authority over the Contractor's operations.

6. No government furnished material or rock will be provided for this project. There are no preferred sources or required sources for material to complete this project.

7. See Section 01 22 00 MEASUREMENT AND PAYMENT for additional information.