Abstract of Bids for W9128F24B0018.pdf

PDF 368 KB Posted

Attached to
Bank Stabilization, Spillway Channel, Oahe Dam, Pierre, SD
Solicitation number
W9128F24B0018
Issued by

About this file

This document is an Abstract of Bids for solicitation W9128F24B0018 for the Bank Stabilization, Spillway Channel, Oahe Dam project in Pierre, SD. The solicitation is for stabilizing the emergency spillway upstream channel through excavation, shaping, geotextile fabric installation, and riprap stone placement. The solicitation was issued on 13-Aug-24 with bids due on 18-Sep-24. The government estimate for the base bid is $1,930,190.00, with additional options totaling $840,201.00. Six offerors submitted bids, with prices ranging from $2,669,217.00 to $5,253,609.50 for the base bid and all options. The procurement is being conducted by the U.S. Army Corps of Engineers, Engineering District Omaha.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE DUE

13-Aug-24 18-Sep-24

I CERTIFY THAT I HAVE OPENED, READ

AND RECORDED ON THIS ABSTRACT

ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED

Unique ID: HWSZR9YRRHV4 Unique ID: F1JWKEL887A6 Unique ID: CHWKANT8L8N3 Unique ID: QGKURV69M6H9 Unique ID: S4AHBH6KJXM1 Unique ID: JCP6F9KM9TN9

AMENDMENTS

7A 7B 7C D. E. F.

ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL

0001 Mobilization & Demobilization 1 Job xx 53,440.00$ xx 100,000.00$ xx 260,000.00$ xx 209,500.00$ xx 250,837.57$ xx 350,000.00$ xx 600,000.00$

0002 Develop and Restore Random Fill Borrow Site

0002A Strip Topsoil from Borrow Sites 1,700 CY 6.09$ 10,353.00$ 5.50$ 9,350.00$ 1.95$ 3,315.00$ 5.00$ 8,500.00$ 11.78$ 20,026.00$ 20.00$ 34,000.00$ 4.00$ 6,800.00$

0002B Excavate Random Fill for Spillway Slope Regrading 26,660 CY 15.23$ 405,118.00$ 4.00$ 106,400.00$ 3.40$ 90,440.00$ 3.00$ 79,800.00$ 9.36$ 248,976.00$ 15.00$ 399,000.00$ 12.00$ 319,200.00$

0002C Replace Topsoil 7,700 CY 14.53$ 24,701.00$ 10.00$ 17,000.00$ 2.35$ 3,995.00$ 5.00$ 8,500.00$ 3.37$ 5,729.00$ 20.00$ 34,000.00$ 4.00$ 6,800.00$

0003 Topsoil - Upstream Spillway Channel Area and Riprap Stockpile Areas

8,700 CY 14.53$ 126,411.00$ 50.00$ 435,000.00$ 8.40$ 73,080.00$ 5.00$ 43,500.00$ 14.60$ 127,020.00$ 20.00$ 174,000.00$ 4.00$ 34,800.00$

0004 Compacted Fill for Grading Upstream Spillway Channel Side Slopes

26,600 CY 13.24$ 352,184.00$ 10.00$ 266,000.00$ 3.60$ 95,760.00$ 7.00$ 186,200.00$ 3.66$ 97,356.00$ 15.00$ 399,000.00$ 10.00$ 266,000.00$

0005 Stone for Riprap – Contractor upplied (Type A) 24,080 Tons 120.80$ 1,833,744.00$ 95.50$ 1,449,690.00$ 80.90$ 1,228,062.00$ 68.00$ 1,032,240.00$ 117.97$ 1,790,784.60$ 85.00$ 1,290,300.00$ 68.00$ 1,032,240.00$

0006 Stone for Riprap – Government Supplied (Type A) 6,600 Tons 46.43$ 812,525.00$ 20.00$ 350,000.00$ 20.00$ 350,000.00$ 13.00$ 227,500.00$ 16.41$ 287,175.00$ 30.00$ 525,000.00$ 12.00$ 210,000.00$

0007 Geotextile 22,800 SY 3.94$ 89,832.00$ 5.00$ 114,000.00$ 3.30$ 75,240.00$ 2.75$ 62,700.00$ 6.96$ 156,688.00$ 7.00$ 159,600.00$ 3.00$ 68,400.00$

Seeding – Spillway Slope, Riprap Stockpile Area, Borrow Site

7.5 Acre 2,568.00$ 19,260.00$ 5,000.00$ 37,500.00$ 4,320.00$ 32,400.00$ 3,500.00$ 26,250.00$ 9,470.15$ 71,026.13$ 5,000.00$ 37,500.00$ 4,000.00$ 30,000.00$

0009 Erosion Control Blanket 8,500 SY 5.27$ 44,795.00$ 5.00$ 42,500.00$ 4.05$ 34,425.00$ 3.00$ 25,500.00$ 6.55$ 55,675.00$ 5.00$ 42,500.00$ 4.00$ 34,000.00$

0010 All Remaining Work Job LS xx 84,740.00$ xx 325,000.00$ xx 422,500.00$ xx 20,000.00$ xx 103,438.52$ xx 200,000.00$ xx 700,000.00$

TOTAL BASIC AMOUNT 3,857,103.00$ 3,252,440.00$ 2,669,217.00$ 1,930,190.00$ 3,214,731.82$ 3,644,900.00$ 3,308,240.00$

Excavate Additional Random Fill From Borrow Area for SpillwaySlope Regrading

4,200 CY 13.16$ 55,272.00$ 4.00$ 16,800.00$ 2.85$ 11,970.00$ 3.00$ 12,600.00$ 19.72$ 82,824.00$ 15.00$ 63,000.00$ 12.00$ 50,400.00$

0012 Topsoil - Upstream Spillway Channel Area 745 CY 12.55$ 9,349.75$ 50.00$ 37,250.00$ 4.20$ 3,129.00$ 5.00$ 3,725.00$ 21.31$ 15,875.95$ 20.00$ 14,900.00$ 4.00$ 2,980.00$

Compacted Fill for Grading Upstream Spillway Channel Side Slopes

4,200 CY 11.44$ 48,048.00$ 10.00$ 42,000.00$ 2.70$ 11,340.00$ 7.00$ 29,400.00$ 3.47$ 14,574.00$ 15.00$ 63,000.00$ 10.00$ 42,000.00$

0014 Stone for Riprap – Contractor Supplied (Type A) 5,160 Tons 104.35$ 538,446.00$ 95.50$ 492,780.00$ 72.25$ 372,810.00$ 68.00$ 350,880.00$ 130.56$ 673,689.60$ 85.00$ 438,600.00$ 68.00$ 350,880.00$

0015 Geotextile 3,600 SY 3.41$ 12,276.00$ 5.00$ 18,000.00$ 3.10$ 11,160.00$ 2.75$ 9,900.00$ 7.33$ 26,388.00$ 7.00$ 25,200.00$ 3.00$ 10,800.00$

0016 Seeding 0.5 Acre 2,218.00$ 1,109.00$ 5,000.00$ 2,500.00$ 3,900.00$ 1,950.00$ 3,500.00$ 1,750.00$ 9,470.15$ 4,735.08$ 5,000.00$ 2,500.00$ 4,000.00$ 2,000.00$

0017 Erosion Control Blanket 1,350 SY 4.55$ 6,142.50$ 5.00$ 6,750.00$ 3.65$ 4,927.50$ 3.00$ 4,050.00$ 11.91$ 16,078.50$ 5.00$ 6,750.00$ 4.00$ 5,400.00$

0018 All Remaining Work Option 1 Job LS xx 27,610.00$ xx 25,000.00$ xx 86,000.00$ xx 8,000.00$ xx 6,035.87$ xx 100,000.00$ xx 150,000.00$

OPTION 1 TOTAL AMOUNT 698,253.25$ 641,080.00$ 503,286.50$ 420,305.00$ 840,201.00$ 713,950.00$ 614,460.00$

Excavate Additional Random Fill From Borrow Area for Spillway Slope Regrading

4,200 CY 13.16$ 55,272.00$ 4.00$ 16,800.00$ 2.90$ 12,180.00$ 3.00$ 12,600.00$ 19.72$ 82,824.00$ 15.00$ 63,000.00$ 12.00$ 50,400.00$

0020 Topsoil - Upstream Spillway Channel Area 745 CY 12.55$ 9,349.75$ 50.00$ 37,250.00$ 4.25$ 3,166.25$ 5.00$ 3,725.00$ 21.31$ 15,875.95$ 20.00$ 14,900.00$ 4.00$ 2,980.00$

0021 Compacted Fill for Grading Upstream Spillway Channel Side Slopes

4,200 CY

11.44$ 48,048.00$ 10.00$ 42,000.00$ 2.70$ 11,340.00$ 7.00$ 29,400.00$ 3.47$ 14,574.00$ 15.00$ 63,000.00$ 10.00$ 42,000.00$

0022 Stone for Riprap – Contractor Supplied (Type A) 5,160 Tons 104.35$ 538,446.00$ 95.50$ 492,780.00$ 73.35$ 378,486.00$ 68.00$ 350,880.00$ 130.56$ 673,689.60$ 85.00$ 438,600.00$ 68.00$ 350,880.00$

0023 Geotextile 3,600 SY 3.41$ 12,276.00$ 5.00$ 18,000.00$ 2.30$ $ 8,280.00 $ 2.75 9,900.00$ 7.33$ 26,388.00$ 7.00$ 25,200.00$ 3.00$ 10,800.00$

0024 Seeding 0.5 Acre 2,218.00$ 1,109.00$ 5,000.00$ 2,500.00$ 3,900.00$ $ 1,950.00 $ 3,500.00 1,750.00$ 9,470.15$ 4,735.08$ 5,000.00$ 2,500.00$ 4,000.00$ 2,000.00$

0025 Erosion Control Blanket 1,350 SY 4.55$ 6,142.50$ 5.00$ 6,750.00$ 3.65$ $ 4,927.50 $ 3.00 4,050.00$ 11.91$ 16,078.50$ 5.00$ 6,750.00$ 4.00$ 5,400.00$

0026 All Remaining Work Option 2 Job LS xx 27,610.00$ xx 25,000.00$ xx $ 84,800.00 xx 8,000.00$ xx 6,035.87$ xx 100,000.00$ xx 150,000.00$

OPTION 2 TOTAL AMOUNT 698,253.25$ 641,080.00$ $ 505,129.75 420,305.00$ 840,201.00$ 713,950.00$ 614,460.00$

TOTAL BASE and ALL OPTIONS 5,253,609.50$ 4,534,600.00$ $ 3,677,633.25 2,770,800.00$ 4,897,133.82$ 5,072,800.00$ 4,537,160.00$

CAGE Code: 46V78

SAM Exclusion:

POC:

C. AMENDMENTS ACKNOWLEDGED: 1

NO. 6

A. OFFEROR

Sharpe Enterprises, Inc.

1908 N Garfield Pierre, SD 57501

OMAHA, NE 68102-1618

1616 CAPITOL AVENUE

CONTRACTING DIVISION (CENWO-CT)

US ARMY CORPS OF ENGINEERS

9. OFFERS

TO THIS SOLICITATION

SIGNATURE

NAME AND TITLE OF CERTIFYING OFFICIAL (Type) Nadine L. Catania

NO. 1 NO. 2

ABSTRACT OF PROPOSALS

1. SOLICITATION NUMBER

W9128F24B00

4. ISSUING OFFICE

8. GOVERNMENT ESTIMATE5. PROJECT TITLE

A. OFFEROR A. OFFEROR

515 South Flynn Street 2972 25th St NE

A. HIRED LABOR

N/A Three Oaks Construction, Inc HSG Park JV 2 LLC

North Sioux City, SD 57049 Harvey ND 58341 CAGE Code: 9PPC1B. REASONABLE CONTRACT

SAM Exclusion:

CAGE Code: 9KD00

SAM Exclusion: (Without Profit)

POC:

C. AMENDMENTS ACKNOWLEDGED: 1

POC:

C. AMENDMENTS ACKNOWLEDGED: 1

6. NUMBER OF AMENDMENTS ISSUED - 1

OA Spillway Bank Stablization - 12348

SAM Exclusion:

POC:

C. AMENDMENTS ACKNOWLEDGED: 1

NO. 3

A. OFFEROR

Morris, Inc.

220 W. Hwy 14/34 Fort Pierre, SD 57501 CAGE Code: 0ELU6 CAGE Code: 4UDY2

SAM Exclusion:

NO. 4

A. OFFEROR

Meridiam Partners 1001 W. Arizona Ave.

Denver CO 80223 CAGE Code:

POC:

C. AMENDMENTS ACKNOWLEDGED: 1

SAM Exclusion:

POC:

C. AMENDMENTS ACKNOWLEDGED: 1

NO. 5

A. OFFEROR

AGE Corp 704 W Highway 14/34 Fort Pierre, SD 57532

19 Sept 2024