FP BFV Industry Day Presentation.pdf
PDF 6 MB Posted
- Attached to
- Fort Peck Butterfly Valves Virtual Industry Day
- Solicitation number
- W9128F23R0009
About this file
This document provides details for a federal contract opportunity to refurbish butterfly valves and associated systems at the Fort Peck Dam powerhouse in Montana. The U.S. Army Corps of Engineers, Omaha District intends to award a firm fixed price construction contract between $1-5 million to remove, replace, and refurbish eighteen foot diameter butterfly valves and related equipment for two generator units. Key work includes refurbishing valve discs and seals, coating internal surfaces, inspecting and potentially repairing welds, replacing bearings and lubrication systems, upgrading bypass piping and valves, and furnishing new hydraulic power units and controls. Optional items involve non-destructive testing of penstock tunnels and repairs to external penstock paint. The solicitation is expected to be posted in late December 2022 with a 30-day response period and award by March/April 2023. Work must be complete by January 2025 during a 130-day outage. Evaluation criteria emphasize past performance, technical approach, and personnel qualifications. The primary NAICS code is 237990 and questions must be submitted through ProjNet by specified deadlines.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FT Peck BFV Rehab Industry Day 17Nov22 Non-Gov Sign In Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WELCOME
FORT PECK DAM
POWERHOUSE #2 BUTTERFLY
VALVE REHABILITATION
INDUSTRY DAY
SOLICITATION: W9128F23R0009
17 NOV 2022 / 11:00 MST
To join the meeting:
https://usace1.webex.com/meet/ronald.s.beyer
Conference line: 1-844-800-2712 (Toll-Free)
1-669-234-1177 (US)
Access Code: 199 032 3791 https://usace1.webex.com/meet/ronald.s.beyer
INTRODUCTIONS
USACE, Omaha District Office Ron Beyer Project Manager Robin Puskar Program Manager Dan Monahan Contracting Officer Lynne Reed Contract Specialist Mo Al Soufi Mechanical Engineer
Fort Peck Dale Pugh Maintenance and Operations Manager Tom Grant Mechanical Engineer Mike Bratz Senior Power Plant Mechanic Irene Whitmer Electrical Engineer
Missouri River Construction Office
Tom Westenburg Resident Engineer
Hydroelectric Design Center (HDC), Portland
Dan Lundy Mechanical Engineer
Kwadwo Amankwa-Poku Electrical Engineer
Sean Kim Structural Engineer
AGENDA – NOV 17, 2022
1100 – 1105 Introductions / Project Overview
1105 – 1110 Contracting Briefing / Rules of Engagement
1110 – 1130 Statement of Work / Project Specs
1130 – 1200 Project Site Specifics
1200 – 1230 Q&A
PROJECT OVERVIEW
Objective is to reduce internal bypass leakage on Units 4 and 5 valve discs and address component end of life and system reliability
1) Refurbish the eighteen (18) foot spiral case butterfly valve in Units 4 and 5
2) Manufacture and install new Hydraulic Power Units (HPUs) and related equipment in Units 4 and 5
3) Optional Items
• Ultrasonic testing of Tunnel 2, and the Units 4 and 5 penstock
• Penstock External Paint System Repairs
• Butterfly Valve Weld Repairs as needed
RULES OF ENGAGEMENT
DAN MONAHAN, CONTRACTING OFFICER
• No side bars or independent conversations between contractors and government personnel.
• No discussions relating to other Corps acquisitions.
• No corporate denigration or sabotage will be tolerated.
• Hold all questions until the designated question and answer session.
• The Government will address general questions during this briefing. Specific questions must be entered into ProjNet via the published Bidder Inquiry Key.
• There will be a site visit opportunity once the solicitation is posted.
PROJECTED PROJECT SCHEDULE
Pre-solicitation Late Dec 2022
Advertise Period Jan-Feb 2023 (30-day advertisement period)
Contractor Site Visit TBD (posted with solicitation)
Award Mar/Apr 2023
Penstock Outage
Start 16 September 2024
End 24 January 2025 (130 calendar days)
CONTRACT AND EVALUATION INFORMATION
Contract Information
• Contract Type: Firm Fixed Price Construction
• Solicitation Type: Request for Proposal (RFP)
• Contract Magnitude: $1M-$5M
• Period of Performance: NTP (Est. April 2023) – Jan 2025 (Note: onsite work must be completed by 24Jan2025)
Evaluation Factors
• Factor 1 Past Performance (most important)
• Factor 2 Technical Approach (second most important)
• Factor 3 Personnel Qualifications and Experience (equal to factor 2)
• Factor 4 Small Business Participation (significantly less important than factors 1-3)
• Factor 5 Price (Least important factor. All evaluation factors other than price, when combined, are considered significantly more important than Price.)
PROJNET AND CONTACT INFORMATION
ProjNet
• Used for Contractor(s) to submitted questions
• Website: https://www.projnet.org
• Virtual Industry Day Bidder Inquiry Key: E3BCGG-7ABR3E
• Questions need to be submitted before 4 pm Mountain Standard Time, 20 NOV 2022
Contract Specialist Contact Information
Lynne Reed
• Email: Lynne.D.Reed@usace.army.mil
• Phone: 402-995-2039
9File Name
STATEMENT OF WORK
AND
PROJECT SPECS
HYDROELECTRIC DESIGN CENTER
DAN LUNDY, MECHANICAL ENGINEER
Functional Areas
• Mechanical Scope of Work
• Butterfly Valves
• Hydraulic Power Systems
• Scroll Case and Tunnel Drain Valves
• Other
»Tunnel 2, Unit 4, and Unit 5 Penstock Ultrasonic Testing (optional)
»Penstock Paint Repairs - 10 Locations (optional)
• Electrical Scope of Work
• Electrical Equipment for Hydraulic Power Systems
• Electrical Equipment for Motor Operated Bypass Valves, and Misc.
Mechanical Scope of Work:
(1) Refurbishment of two (2) 216-inch diameter penstock BFVs, performed simultaneously.
• valve disc seal;
• stainless-steel overlay body seat;
• valve internal surfaces (LBP abatement, blast, and recoating);
– Inspect butterfly valve welds;
– Repair butterfly valve welds (OPTION);
Removal and replacement of:
• upper stub shaft (trunnion) bearing and seals;
• lower stub shaft (trunnion) bearing and seals, and thrust bearing assemblies;
– Adjust and align disc leaf seals (contact bluing check);
Mechanical Scope of Work:
(2) Two new complete Penstock BFV grease lubrication systems, including:
Removal and replacement of:
• grease lines;
• grease lubrication components and supporting systems;
Mechanical Scope of Work
(3) Refurbishment of two Penstock BFV bypass systems, including:
Removal and replacement of:
– Limitorque motor operated gate valve with manual handle;
– bypass system piping;
– absolute pressure switch,
– system controls;
Install new manually operated isolation gate valve; and new equalizing line pressure monitoring system;
(4) Refurbishment of two spiral case drain valves:
Removal and replacement of:
• manual gate valve with new manual operated gate valve;
• insulation;
• limit switch;
(5) Refurbishment of tunnel drain valve:
Removal and replacement of:
• one manual gate valve (current location, as shown);
• piping and insulation;
• heating cable and thermostat;
(6) Provide new second manual operated gate valve located as shown;
(7) New maintenance platforms, ladders and guardrails for each BFV;
(8) Modify access hatch for each BFV;
(9) Furnish spare parts, including two sets of bronze metal disc seals.
Hydraulic Scope of Work
• The work specified includes, but is not limited to, all appurtenances required for a complete, fully functional installed hydraulic power system.
• The new BFV operators, HPUs, and associated systems must be identical and interchangeable.
(1) Design and provide two BFV operators (quarter-turn hydraulic cylinder actuators) with integral mechanical locking device:
–Remove existing BFV operator and associated plumbing;
–Install new BFV operator with integral mechanical locking device, and new plumbing;
Hydraulic Scope of Work
(2) Design and provide two BFV HPUs with controls and offline oil filtration system:
•Remove existing BFV HPU and associated plumbing;
• Install new BFV HPU and associated plumbing;
Electrical Scope of Work
Supply and installation of:
(1) New motor actuators for the penstock fill bypass valves and remote operators, remote open/close indicators and control systems, one each for Unit 4 and Unit 5;
(2) Limit switches and wiring for new manually operated spiral case drain valves one each for Unit 4 and Unit 5;
Electrical Scope of Work
(3) Supply and installation of new wall mounted 480VAC panels which contain a disconnect switch, motor starter and control power transformer as follows:
• 2-480VAC panel (BVQ) for the HPU pump motors for each unit:
•BVQ1 - 480VAC panel for HPU pump 1
•BVQ2 - 480VAC panel for HPU pump 2
• Two (2) - oil filtration system 480VAC panels (FSQ), one for each unit's HPU
• Two (2) - 480VAC panel (VP), one for each bypass valve motor actuator
(4) Supply and installation of new heat tape and thermostat for the tunnel drain valve
20File Name
PROJECT SITE
SPECIFICS
FORT PECK PROJECT BRIEF
DAN LUNDY AND TOM GRANT
CONTRACTOR STAGING & WORK AREAS (SHEET G-401 & MD201)
CONTRACTOR STAGING & WORK AREAS (SHEET MD201)
EL 2070.0 SURGE TANK STRUCTURE
EL 2052.0 BFV CORRIDOR
EL 2023.5 BUTTERFLY VALVE ROOM
CONTRACTOR STAGING & WORK AREAS
TUNNEL #2 PENSTOCKS 4 & 5
BIFURCATION
CONTRACTOR STAGING AND WORK AREAS (SH MD101)
SURGE TANK STRUCTURE, EL 2070.00
Office
Trailer
10T MONORAIL HOIST
SURGE TANK
STRUCTURE
BFV ACCESS
HATCHES
CONTRACTOR STAGING AND WORK AREAS (SH MD102)
BUTTERFLY VALVE CORRIDOR, EL 2052.00
BFV ACCESS
HATCHES
CONTRACTOR STAGING AND WORK AREAS (SH MD102)
BFV ACCESS
HATCHES
FREIGHT
ELEVATOR
CONTRACTOR STAGING AND WORK AREAS
18 FT (216 INCHES)
BUTTERFLY VALVE
EL 2023.50
EL 2023.50
NORTH EXTERIOR
IMAGES OF
18 FT (216 INCHES)
SOUTH EXTERIOR
18 FT (216 INCHES)
UPSTREAM UNDERSIDE
EXTERIOR IMAGE OF
18 FT (216 INCHES)
DOWNSTREAM
UNDERSIDE EXTERIOR
IMAGES OF
18 FT (216 INCHES)
TOPSIDE EXTERIOR
18 FT (216 INCHES)
INTERIOR IMAGE OF
BUTTERFLY VALVE
INTERNAL LEAKAGE
GOVERNMENT SEAL
ADJUSTMENT U4: 2006
UNIT 4 UNIT 5
CLOSE-UP OF VALVE DISC BRONZE SEAL
CLOSE-UP OF VALVE DISC BRONZE SEAL
STAINLESS STEEL
OVERLAY BODY
SEAT AND
INTERNAL
SURFACES
WISCO DWG H-4070
STAINLESS STEEL
OVERLAY BODY
SEAT AND
INTERNAL
SURFACES
WISCO DWG H-4070
WELDS
WISCO DWG H-4075
(UPSTREAM SIDE)
(DOWNSTREAM
SIDE)
(DOWNSTREAM
SIDE)
UPPER AND LOWER
STUB SHAFT
(TRUNNION)
BEARINGS
UPPER STUB
SHAFT (TRUNNION)
BEARING
LOWER STUB
SHAFT (TRUNNION)
BEARING & THRUST
BEARING
EXISTING GREASE LUBRICATION SYSTEM
(UNIT 4 SHOW, UNIT 5 SIMILAR)
EXISTING GREASE LUBRICATION SYSTEM
(UNIT 4 SHOW, UNIT 5 SIMILAR)
EXISTING BFV BYPASS SYSTEMS
EXISTING BFV BYPASS SYSTEMS
BYPASS VALVE & PIPING, & ABSOLUTE
PRESSURE SWITCH
EXISTING
LIMITORQUE GATE
VALVE – BYPASS
VALVE OPERATOR
BFV POSITION
INDICATOR
BFV ACCESS
HATCH
MAINTENANCE
ACCESS HATCH
EXISTING BFV HPU
BYPASS VALVE
CONTROLS &
INDICATION
BFV CONTROLS &
INDICATION
BYPASS VALVE
CONTROLS
BFV CONTROLS
EXISTING SPIRAL CASE DRAIN VALVES
EXISTING TUNNEL DRAIN VALVES
EXISTING MAINTENANCE LADDERS & PLATFORMS
EXISTING BFV MAINTENANCE ACCESS HATCH
HYDRAULIC POWER SYSTEMS
BFV OPERATOR
HYDRAULIC POWER SYSTEMS
BFV HPU
TUNNEL #2, UNIT 4 & 5 PENSTOCK ULTRASONIC TESTING
AND PAINT REPAIR LOCATIONS (S-101)
TUNNEL #2, UNIT 4 & 5 PENSTOCK ULTRASONIC TESTING
AND PAINT REPAIR LOCATIONS (S-101)
UNIT CONTROL SWITCHBOARD &
MCC’S ON TURBINE FLOOR,
EL. 2049.00 (E-101 & E-201)
ELECTRICAL WORK
MCC4 DC
DIST. PANEL
INSTRUMENT CONTROL BOARD,
CONTROL ROOM (E-202)
ELECTRICAL WORK
MOTOR ACTUATORS
FOR BYPASS VALVE
OPERATORS, W/
REMOTE
OPEN/CLOSE
INDICATORS &
CONTROLS
SUPPLY/INSTALL
NEW LIMIT
SWITCHES FOR
SPIRAL CASE DRAIN
(SH M-420)
SUPPLY/INSTALL
NEW LIMIT
SWITCHES FOR BFV
POSITION
INDICATOR
(SH M-420 &
M-601)
WALL MOUNTED
480VAC PANELS
W/ DISCONNECT
SWITCHES, MOTOR
STARTER, &
CONTROL POWER
TRANSFORMER
FOR:
HPU PUMPS 1 & 2
OIL FILT. SYST.
BYPASS VALVE
MOT. ACTUATOR
(SH E-101)
NEW HEAT TAPE
AND THERMOSTAT
FOR TUNNEL DRAIN
VALVE
(SH M-430)
POST-INDUSTRY DAY
Q & A
File details come from the government source that posted it. Updated .