W9128F23Q0010_Big Bend Servomotor Rehab.pdf
PDF 1 MB Posted
- Solicitation number
- W9128F23Q0010
About this file
This is a solicitation for the rehabilitation of servomotors at the Big Bend Dam in South Dakota. The U.S. Army Corps of Engineers seeks a contractor to remove, refurbish, reinstall, and test two servomotors for Unit 6 and optionally perform the same work for two servomotors in Unit 8. Key requirements include disassembly, inspection and repair of components, replacement of bushings and seals, refurbishment of the cushioning system, reassembly and pressure testing. Optional line items include chrome plating parts, bore machining, and other specialized repairs. Quotes are due by September 14, 2023 and work must be completed within 365 days, with an optional 180-day extension for Unit 8. Pricing shall be provided for all line items and payment will be made upon inspection and acceptance of completed work. The solicitation includes detailed performance work statements, submittal requirements, and contractor responsibilities for safety, quality control, and other contract provisions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W9128F23Q0010 14-Aug-2023
b. TELEPHONE NUMBER
402-996-3754
8. OFFER DUE DATE/LOCAL TIME
02:00 PM 14 Sep 2023
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W9128F9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MICAH N SUGIURA
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 968806 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
BIG BEND PROJECT OFFICE
COLBY BRAKKE
COE BIG BEND PROJECT OFFICE
CENWO-OD-BB BIG BEND PROJECT
33573 NORTH SHORE RD
CHAMBERLAIN SD 57325-4513
TEL: 605-245-1825 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$12,500,000
NAICS:
811310
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF61
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W9128F23Q0010
Section SF 1449 - CONTINUATION SHEET
PRICE SCHEDULE
***Contractors shall submit completed Price Schedule below with quote***
CONTRACT LINE ITEM PRICE SCHEDULE
ITEM NO.
DESCRIPTION
QUANTITY
UNIT
AMOUNT
BASIC LINE ITEMS
Site Mobilization, Tools, Demobilization.
Job
Shipping, Disassembly, and Servomotor Inspection for Units 6.
All plant, material, equipment, and labor to Refurbish Unit 6 Wicket Gate Servomotor including but not limited to on site welding work, piping demo & installation work, pressure testing, and NDT.
All plant, material, equipment, and labor to Reinstallation and pressure test Unit 6 Wicket Gate Servomotor.
TOTAL BASIC AMOUNT $_____________________________
OPTION LINE ITEMS
Chrome Plate Gate Servo Piston Rod for Unit 6.
Restore Unit 6 Wicket Gate Servomotor Head Spigot Fit.
Wicket Gate Servomotor Bore Machining for (for Unit 6).
Piston Head Chrome Build-Up to Maintain
Clearance (for Unit 6).
Piston Head Modification and Sleeves to Maintain Clearance (For Unit 6).
2nd Site Mobilization, Tools, Demobilization (For Unit 8).
1 Job
Shipping, Disassembly, and Servomotor Inspection for Unit 8.
All plant, material, equipment, and labor to Refurbish Unit 8 Wicket Gate Servomotor including but not limited to on site welding work, piping demo & installation work, pressure testing, and NDT.
All plant, material, equipment, and labor to Reinstallation and pressure test Unit 8 Wicket Gate Servomotor.
All plant, material, equipment, and labor to Chrome Plate Gate Servo Piston Rod for Unit 8.
All plant, material, equipment, and labor to Restore Unit 8 Wicket Gate Servomotor Head Spigot Fit.
All plant, material, equipment, and labor to Wicket Gate Servomotor Bore Machining for (for Unit 8).
Piston Head Chrome Build-Up to Maintain Clearance (for Unit 8)
2 Job
Piston Head Modification and Sleeves to Maintain Clearance (For Unit 8)
2 Job
TOTAL AMOUNT (BASIC PLUS OPTION) $_____________________________
NOTES:
1. The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru 180 days from date of contract award. No aditional time will be added when an option is exercised. The period of performance for the option line item is required for the completion of the work.
2. Prices must be entered for all items of the schedule. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.
PERFORMANCE WORK STATEMENT
Performance Work Statement (PWS) Rehab Units 6 Servomotors and Optional Unit 8
Servomotors Big Bend Dam, SD
1.0 General Information.
Background: Big Bend Dam is a major dam on the Missouri River in Central South Dakota, United States, creating Lake Sharpe. The Government intends to rehabilitate the Unit 6 servomotors, including cushioning valve system and optional work of chroming the servomotor rods, restoring the servomotor head fits, bore machining, piston head chrome, and piston head sleeves. In addition, options to perform the same scope is included for Unit 8.
Unit servomotors appear to leak oil past the piston and back through the opening service port, especially when in the closed squeeze position as this is when the system sees full pressure differential. This was found by the short governor cycle. These shorter than average cycle times have been noticed for 20 years but appeared to come and go with no major change. Most recently this condition is consistently occurring and noticeably more severe.
1.1 Scope of Work: The Government will remove the generator rotor to give access to the turbine pit area.
The scope of work for two servomotors addressed in this section includes:
a. Servomotor removal: including rigging and handling equipment, removal of lower generator covers, disconnecting servomotor fasteners, provision of shipping cradle, and shipping. (leave wicket gates in full open position). The Government will provide a bridge crane operator to support a direct lift of servo motor to and from staging area within the walls of the unit. Also loading of servomotors onto and off a truck and/or trailer.
b. Wicket gate servomotor refurbishment: including inspection, replacement bushings, chevron packing, honing, cast iron rings, lead-based paint abatement and repainting.
Optional cylinder bore clean-up cut. Optional rod chrome-built up. Optional piston rod chrome-built up. And optional piston spacers will be included.
c. Replacement cushioning/dampening system shown on T7652F160, items 1-29, converted to equivalent new stainless Swagelok fittings, piping, unions, gauges, and joint connections.
d. Installation of the servomotors: including reconnecting any pipes, fasteners, pins, and any needed adjustment to ensure proper connection and alignment to the operating ring.
The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government. This is a fixed priced, performance-based service contract where the Government defines and measures desired outcomes, while Contractor methods are generally not constrained or directed.
1.2 Period of Performance: The contractor shall complete all work within 365 days from issuance of the award. Work shall be completed with mutually agreeable dates coordinated between the Government and the Contractor described in 5.0 Specific Tasks. The Contractor shall efficiently execute work to minimize the outage periods.
1.3 Contractor Personnel.
1.3.1 The Contractor shall perform all work under this contract using his or her own forces except as provided in Paragraph 1.4.2 Subcontracting. Employees who perform this work shall be qualified persons on the Contractor’s own payroll.
1.3.2 Subcontracting: The Contractor shall not subcontract any work without written approval of the Contracting Officer. Compliance with the provisions of this contract by subcontractors shall be the responsibility of the Contractor.
1.4 Quality Control:
1.4.1 The Contractor, not the Government, is responsible for quality control actions necessary to meet the quality standards set forth by the PWS. The contractor shall develop and submit a Quality Control Plan (QCP) for Government approval within thirty (30) calendar days after Notice to Proceed. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product that complies with the contract requirements. The system shall cover all on-site operations and shall be keyed to the proposed rehab sequence of the servomotors. Utilize established in-house quality control procedures to assure full compliance with all off-site work.
Once accepted, the QCP will be incorporated into the Quality Assurance Surveillance Plan (QASP). The QASP will be utilized to monitor the Contractor’s efforts. The QASP is made part of the solicitation, but not a part of the resultant contract. The QASP is not a contractual instrument and may be changed at the COR’s discretion. The Contractor then uses the QASP to guide and document the implementation of the required management and quality control actions to achieve the specified results. The Government reserves the right under the Contract Terms and Conditions-Commercial Items (FAR 52.212-4) to inspect and test the services called for by the Contract, to the extent practicable at all times and places during the term of the task order. Non-conforming services shall be rejected.
Responsible Individuals for Quality Control must maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. Submit qualifications of the responsible individuals showing a minimum of 5 years of experience over the past 10 years performing Contractor Quality Control (CQC) on projects of similar scope as this project. CQC staff will be subject to acceptance by the COR.
1.4.2 The Contractor shall designate, in writing, an employee who shall serve as the contact for matters involving quality and performance or nonperformance of the required work stated in this PWS. The employee(s) shall be qualified and fully competent with full authority to act for, and on behalf of, the Contractor as necessary to ensure that the required work is performed in accordance with the standards contained herein. The quality control personnel shall be present full time both on-site and off-site. The Contractor shall furnish the above written designation to the Contracting Officer’s Representative (COR) no later than the first day of work. The Contractor shall include the name(s), address(s), and telephone number(s) of the responsible individual(s).
1.4.3 The Contracting Officer reserves the right to disapprove any individual whom he considers incompetent to perform the work required. The Contracting Officer will provide a written notice of any disapproval to the Contractor.
1.5 Quality Assurance: The Government will use a Quality Assurance Surveillance Plan (QASP) to ensure that the Contractor is performing the services required by this PWS in an acceptable manner. The Government may use Quality Assurance Evaluators (QAE(s)) to provide assistance with the quality assurance methods.
1.5.1 The Government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government shall perform inspections in a manner that will not delay the work.
1.5.2 If any of the services do not conform to contract requirements, the Government may require the Contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the Government may (1) require the Contractor to take necessary action to ensure that future performance conforms to contract requirements or (2) reduce the contract price to reflect the reduced value of the services performed.
1.5.2.1 Upon verification of a validated customer complaint or corrective action report, the COR will notify the Contractor that they are required to re-perform specific services.
1.5.3 The Government may take action, if the Contractor fails to perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements. The Government may (1) by contract, or otherwise, perform the services and charge to the Contractor any cost incurred by the Government that related to the performance of such service or (2) terminate the contract in whole or in part.
1.5.4 The Contractor is responsible to replace/repair any damage to Government property due to negligence, at his or her own cost. The Government may take action, if the Contractor fails to replace/repair any damage to Government property. The Government may (1) by contract, or otherwise, replace/repair damaged Government property and charge to the Contractor any cost incurred by the Government to replace/repair any damage.
1.6 Hours of Operation: The Contractor is responsible for conducting business, between the hours of 6:30 A.M. and 4:30 P.M., Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Requests for working outside of these hours must be made in writing to the COR. The Government will not provide for outage, or hazardous energy clearance support, or crane support, on Fridays, Saturdays, Sundays, or Federal holidays. The Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.7 Pre-Work Meeting: Prior to commencing any activities, the Contractor shall arrange a Pre-work Meeting with the COR. The Meeting shall discuss the work requirements, scheduling, submittal process, review of the Activity Hazard Analysis (AHA), and Abbreviated Accident Prevention Plan (AAP). At least one (1) week prior to commencing work, the Contractor shall coordinate their proposed work schedule with the COR.
1.8 Submittals.
1.8.1 See the attached Submittal Register for more details about required submittals.
1.8.2 Prior to commencement of services, the Contractor shall submit the following documents to the COR for review and approval:
a. Activity Hazard Analysis (AHA);
b. Abbreviated Accident Prevention Plan (APP);
c. Quality Control Plan (QCP);
d. List of who will perform work on this contract;
e. Proof of insurance for Contractors and Subcontractor’s; The Contractor shall show certificates or other written evidence of reliable insurance coverage and assets to indemnify against long-term liabilities and/or catastrophic occurrences as follows:
aa. Environmental Impairment Expense - $1,000,000 per occurrence covering sudden and accidental spills of hazardous waste material from the transport vehicles.
bb. Comprehensive General Liability - $1,000,000 combined single limit per occurrence.
cc. Comprehensive Automobile Liability - $1,000,000 combined single limit per occurrence.
dd. Contractors Pollution Liability - $1,000,000 per occurrence covering sudden and accidental spills at the Big Bend Power plant.
ee. Pollution Legal Liability - $1,000,000 per occurrence covering non-sudden, sudden and accidental environmental pollution from the Contract site.
ff. Workman's Compensation and Employer's Liability Insurance -$100,000.
f. Submit documentation of the qualifications of the Services Supervisor.
g. Submit a plan for Spill Prevention and Spill Countermeasures, including clean-up procedures.
1.8.3 Submittal Form: The attached submittal form (ENG Form 4025-R) shall be used for transmitting the submittal. This form may be reproduced by the Contractor and shall be properly executed by filling out all the heading blank spaces and identifying each time submitted. Special care should be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the date submitted for each item. The Contractor shall provide copies for each submittal to the locations stated below.
1.8.4 Means of Approvals: Action Codes will be as indicated on the back of ENG Form 4025-
R. The Contracting Officer’s Representative will mark an Action Code on each submitted ENG Form 4025 prior to returning a copy to the Contractor. The approval of a submittal by the Contracting Officer shall not be construed as a complete check but will indicate only that the general method of prosecution and detailing is satisfactory. Approval will not release the Contractor of the responsibility for any error that may exist, as the Contractor is responsible for satisfactory prosecution and detailing of all work.
1.8.5 When Not Approved: The Contractor shall make all corrections required by the
Contracting Officer’s Representative and promptly furnish a corrected submittal in the form and number of copies as specified in the initial submittal.
1.8.6 Submittal Delivery: The Contractor shall provide an electronic copy of ENG Form 4025-
R with each submitted item to the Contracting Officer’s Representative (COR) at the Big Bend Project.
TBD
1.9 Safety, Standards and Regulations: The Contractor shall perform to the standards in the contract and comply with all local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations.
Applicable regulations include, but are not limited to the following:
a. Code of Federal Regulations (CFR), Title 36, Chapter III, Part 327, Rules and
Regulations Governing Public Use on Corps of Engineers Water Resource Development Projects EP 1165-2-316 (http://www.publications.usace.army.mil/Portals/76/Publications/EngineerPamphlets/EP_1 165-2- 316.pdf?ver=2013-08-22-104526-670);
b. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated November 2014;
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf;
c. Occupational Safety and Health Standard (29 CFR 1910) regulations related to the Management and Control of Hazardous Wastes;
d. RCRA - Resources Conservation and Recovery Act (Primarily 40 CFR 268);
e. TSCA - Toxic Substances and Control Act (Primarily 40 CFR 761);
f. DOT - Department of Transportation Regulations for the Transportation of Toxic Wastes;
g. CERCLA-Comprehensive Environmental Response, Compensation, and Liability
Act of 1980 (SUPERFUND);
h. CWA - Clean Water Act of 1972;
i. Safe Drinking Water Act of 1974;
j. All other applicable Federal, State, Country and City codes, laws, standards and regulations;
k. Reference attached technical specification Section 05 05 33.20 26 - paragraph 1.2, and Section 48 13
13.04 26- paragraph 1.2 for technical standards.
1.9.1 Activity Hazard analysis (AHA): Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA and review it with the work crew that will perform the work. AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the Contracting Officer Representative. An AHA template is attached.
1.9.2 Hazardous Energy Control (HEC) Plan and HED Procedure Training Certificate:
The Contractor must submit certification of completion for HEC Plan and Procedure for Affected Person for Contractor and Subcontractor personnel working under, or in the vicinity of, clearances as defined in EM 385-1-1. All costs for this training must be considered incidental to the work, and therefore, no additional payment will be made.
Cost for the training is $55 per individual. Training is furnished by Vivid Learning Systems and is available online at http://contractor.vividlms.com/. Submit the training completion certification a minimum of seven (7) calendar days prior to the individual’s arrival on- site. Maintain training documentation on-site, including the individual’s name and date of training completion, in accordance with EM 385-1-1.
1.9.3 Abbreviated Accident Prevention Plan (APP): The contractor is to prepare and submit an abbreviated APP to the government for approval that covers plans regarding hazards for the work being performed. The contractor is to review the Abbreviated APP outline in the Corps of Engineers safety and health manual EM 385-1-1 to determine the safety plans that will be required for the scope of work and prepare their document for approval.
The contractor shall use a qualified person to prepare the site-specific abbreviated Accident Prevention Plan (APP). The contractor shall prepare the APP in accordance with the format and requirements of EM 385-1- 1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite. See the abbreviated APP Checklist in the Appendix to these specifications for requirements.
1.9.4 Fall Protection and Prevention (FP&P) Plan: The plan must be in accordance with the requirements of EM 385-1-1, Section 21.D and ASSP Z359.2, be site specific, and address all fall hazards in the workplace and during different phases of construction.
Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A competent person or qualified person for fall protection must prepare and sign the plan documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, roles and responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Review and revise, as necessary, the Fall Protection and Prevention Plan documentation as conditions change, but at a minimum every six months, for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Plan documentation at the job site for the duration of the project. Include the Fall Protection and Prevention Plan documentation in the Accident Prevention Plan (APP).
1.9.5 Servomotor Lift Plan: Submit a Servomotor Lift Plan for Government approval that outlines all proposed lifts required for the removal and re-installation of the existing servomotors. Descriptions must include step by step written procedures that will be used in all lifts required in the performance of this contract. Descriptions shall include plans to stage the servomotor for lifting outside of the turbine pit to the powerhouse deck.
Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Do not begin work without an approved plan.
1.9.6 Site Safety and Health Officer (SSHO): Provide an SSHO that meets the requirements of EM 385- 1-1 Section 1. The SSHO must ensure that the requirements of 29 CFR
1926.16 are met for the project. Provide one person at the project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Alternate SSHO must be at the work site at all times to implement and administer the Contractor's safety program and Government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO must have the required training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs. If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed. Note that the DR is a collateral duty safety position, with safety duties in addition to their full time occupation.
1.9.3.1 Additional Site Safety and Health Officer (SSHO) Requirements and Duties:
The SSHO may also serve as the Superintendent.
1.10 Physical Security:
1.10.1 The Contractor shall be responsible for safeguarding all Government facilities, property, and materials provided for Contractor use.
1.11 Antiterrorism/Operation Security Requirements:
1.11.1 General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
1.11.2 Antiterrorism (AT) Level I training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil (website subject to change).
1.11.3 Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.
1.11.4 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See
Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
1.11.5 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements.
Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
1.12 Payment:
1.12.1 The Government will make payment monthly, after the Government has inspected and accepted the services, and the Government has reviewed, approved, and processed the Contractor’s invoice. The Contractor shall submit the invoice to the COR and/or any other person that has been designated in the contract to receive the invoice.
1.12.2 The Contractor must provide the Contractor’s name, address, contract number, period of services completed (i.e., for the month of January or for the period of performance of January 1 through February 23), CLIN number and specific quantities of work performed (i.e., 1 Month, 40 days, 100 acres, etc.), and total requested, for an invoice to be considered proper. The Contractor shall submit the invoice by the fifth (5th) of the month for services completed the previous month or submit the invoice upon completion of all services, in accordance with the period of performance stated in the
CLIN.
1.13 Warranties: Contractor shall provide standard industry warranty for all equipment installed and for all repairs made. This will cover at minimum one year of service. It will include all equipment, costs and, work associated with replacement of defective part.
2.0 Definitions: The following definitions and descriptions apply wherever the word(s) or phrase(s) is/are stated in this PWS:
Acceptable Level of Performance (ALP): The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot considered satisfactory on the average. The allowable leeway or variance from a standard before the Government will reject the specific service.
Contracting Officer’s Representative (COR): means an individual designated an authorized in writing by the Contracting Officer to perform specific technical or administrative functions.
Performance-Based Contract (FAR 2.101): Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.
Performance Requirements Summary (PRS): The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.
Quality Assurance Surveillance Plan (QASP): An organized written document used by the Government for quality assurance surveillance. Document contains sampling/evaluation guides, checklists, and the performance requirements summary (PRS).
3.0 Government Furnished Items and Services:
3.1 Utilities: The Government will make 120 volt and 480 volt electrical service available to the
Contractor. Station service air, at 110 psi, is available as well. The Contractor shall provide all extension cords, ladders, and any other tools, equipment and materials needed to perform the contract.
3.2 Use of Government Equipment:
3.2.1.1. Bridge Crane Operation: Government personnel only will operate the bridge crane.
The Contractor will be responsible for certifying, furnishing and performing all rigging for all lifts. The Government must inspect all rigging prior to performing the lift.
Rigging must meet the EM 385-1-1 safety requirements. The Contractor will be responsible for all off-loading, movement, and loading of required equipment. The bridge crane will be used to support a direct lift of servo motor to and from staging area within the walls of the unit. Also loading of servomotors onto and off a truck and/or trailer.
3.2.1.2. A crane operator will not be furnished on a standby basis. The Contractor shall coordinate with the Contracting Officer Representative, in writing 24 hours in advance, his needs for a crane operator. The Government will operate the crane during the normal daytime working hours of 7:30 am to 4:00 pm Monday thru Thursday.
4.0 Contractor Furnished Items and Responsibilities:
4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2 The Contractor shall furnish replacement bushings, chevron packing, honing material, cast iron rings, and all required equipment, and all necessary equipment and materials needed to rehab the servomotors for Big Bend Unit 6 and optional Unit 8 as specified in section 5.1.
5.0 Specific Tasks:
The Contractor must perform the tasks as described below and must furnish the deliverables described within this entire Performance Work Statement (PWS). These tasks are summarized in the Performance Requirement Summary (PRS) Table found in Section 6.0. A schedule for Contract deliverables is located in Section 7.0. On-site work must not begin without approval from the Contracting Officer. All plans, designs, and product data must be approved by the Government prior to procurement of any associated materials and equipment. If there are conflicts between design criteria herein and listed in referenced documents, the most stringent approaches must govern unless otherwise approved in writing by the Government; the Government must be notified of Contractor’s course of action.
The Contractor must notify the Government a minimum of twenty (20) days prior to the start of any on-site work and testing of the servomotor.
The Contractor will work closely with the government to develop a schedule that incorporates all aspects of the work from mobilizing, servo motor removal, transporting, refurbishing, reinstalling, and commissioning. The schedule will cover both the least amount and most amount of reconditioning time that can be expected at the repair facility. This schedule will be developed and submitted within 20 days after notice to proceed which will be used to determine unit outage windows and availability to take this outage at time requested. The government reserves the right to require contractor to fluctuate the start date depending on time of year and ability to get outage approval as submitted. Early accurate outage requests have more favorable approval rates. The government will add one week to the beginning and end of the contractor work for generator disassembly and reassembly performed by the government to facilitate this work. Only one unit may be out of service at a time. Outage windows between June 15th and September 1st in addition to January 1st thru February are not permitted and should be avoided to have greatest probability of being approved. The governments preferred window to schedule and perform this work is September 1st thru December.
5.1 Task 1: Rehabilitate the Unit 6 Servomotors and Optional Unit 8 Servomotors
1. HYDRAULIC PACKING
a. Chevron Style Packing: Replace in kind or approved equal. The current seal is Chesterton, material AWL 800
• Bottom adapter 27k, (1ea)- Pt # 2005335, 10.5 x 11.75
• Seal rings 27k (7ea)- Pt # 2005333, 10.75 x 11.75
• Top adapter 27k (1ea)- Pt # 2005327
b. Rod Wipers: Nitrile or approved equal.
2. BRONZE BUSHINGS
Bronze bearings, bushings and thrust discs shall conform to SAE J462, SAE No. 64 or ASTM B22/B22M Copper Allow UNS No. C93700.
3. SWAGELOCK FITTINGS
Swagelok style piping, valves, and gauges to replace the existing 2-inch pipe cushioning system. The portion of the existing cushioning pipe (item 16, 17 on drawing T7652F160) hidden in the wall is a welded pipe, this portion shall be duplicated with new welded stainless pipe (extra thickness) with similar features to allow it to interface with the replacement Swagelok piping. The intention is to limit leak areas hidden in the wall.
The replacement Swagelok might require a custom-made adapters/unions/flange to connect to the threaded connections on the servomotor.
4. MEASUREMENTS
All measurements taken shall be made with instruments capable of measuring to the nearest
0.001 inch without interpolation, unless otherwise stated or approved.
5. CLEANING, RECOMMENDATIONS AND REPAIR
Cleaning, inspections, recommendations and the preparation of reports shall be considered incidental to the refurbishment work and separate payment shall not be made.
Components and assemblies that shall be reused shall be cleaned of all rust, scale, oil, scum, grease and foreign matter. The Contractor shall disassemble and then inspect the physical condition of each component, submit an inspection report and submit recommendations for corrective action prior to performing any refurbishment. All nondestructive testing shall conform to the requirements set forth in Task 2.
6. AS-FOUND INSPECTIONS
a. All servomotor components shall be visually examined (inspected) for surface condition (wear, physical damage, cracks, cavitation, etc.) and measured for dimensional acceptability. Special care shall be taken to measure the bushings, piston rod, ring landings, cylinder bore, and chevron seal area. Check the front and rear cover plates for any warpage and or deterioration. Any suspected defects shall be PT, MT, or UT inspected and recorded.
b. Each component shall be examined within 45 calendar days of its removal and
Servomotor As- Found and Recommendations shall be submitted. Include a sketch of the proposed swage lock piping system and any catalog cuts and any needed product information.
7. WORK PLAN
Work plan shall address how the work is to be accomplished, including scheduling and identification of work performed at the site and work performed off-site, the work plan shall include inspections and recommendations for any modifications or repair. Include catalog cuts and any needed product information.
8. TRANSPORTATION
For the servomotor to be refurbished off site, the vendor shall provide a shipping cradle for roundtrip transportation between Big Bend dam and the refurbishment workshop.
9. FINAL INSPECTIONS
The Government shall have the option of inspecting components or equipment at any phase of the refurbishment process. The Contractor shall ship no major components from the Contractor's refurbishment shop until it has undergone a final inspection and a Notice of Final Inspection Following Refurbishment submitted.
10. PAINTING
Surfaces not exposed to direct contact to oil or oil vapors shall be prepared and painted an oil resistant Carboguard 890 (Silver color) or similar, applied according to the manufacturer's instructions. The Contractor will be responsible for off-side lead based paint abatement according to all local and state laws for disposal.
11. PACKING, O-RING, GASKETS
Packing shall be replaced in kind (dimensions must be verified) Item 4 on drawing T7652C151. The bearing gland felt wiper, item 4 on drawing T7652B157, shall be replaced with a rubber wiper. O- rings, seals and gaskets shall be replaced in kind as a consumable, or as specified herein. For reassembled refurbished items with mating surfaces that are exposed to liquid and that do not have gaskets or seals, the Contractor shall apply gasket maker.
12. EXPENDABLES, CONSUMABLES, MISCELLANEOUS PARTS
The Contractor shall provide and install all expendable or consumable and miscellaneous parts such as, but not limited to, keys, shims, spacers, electrical insulating gaskets, washers and bolt sleeves.
Existing items contained in the preceding list shall not be reused.
13. SURFACE CLEANUP
Any burrs, sharp edges, nicks, gouges, minor worn areas, scuff marks, minor pitting or corrosion found on mating components shall be removed manually. Items disassembled by removal of weldments shall be repaired by an approved welding method prior to reassembly.
Furnish, install, and remove all required lifting eyes.
14. FURNISHING OF BUSHINGS/BEARING PLATE
Detailed dimensional drawings are not available on some of the following bushings. For the bushings that do not have detailed drawings, the Contractor is responsible to measure the existing dimensions and create a drawing of necessary dimensions for bushing reproduction. Include the drawing in the as- found inspection report.
The Contractor shall furnish and install new oil lubricated bushings:
a. Item 3 on drawing T7652C151 (No detailed drawing of bushing)
b. Item 4 on drawing T7652C150 (No detailed drawing of bushing)
c. Item 1 on drawing T7652B262 & T7652C266 (Contractor to verify dimensions)
d. Item 5 on drawing T7652C155 (No detailed drawing of bushing)
e. If exercised, an optional bronze band/spacer shall be added to the piston head to restore piston to cylinder clearance to OEM dimensions.
15. MATERIAL SPECIFICATION
The material specifications for bronze bushings and bearing plates are listed in Part 2 of this specification section.
16. BORE SIZE
The new bearing bores may be required to be undersized or oversized when compared to the original manufacturer's dimensions. This change in bore size may be necessitated by the change in mating journal size (due to refurbishment or wear), or the requirements of the new bearing.
17. BUSHING CLEARANCES
The running clearance shall match the existing design unless otherwise approved by the Government.
18. BUSHING INSTALLATION FITS
All bearings, except for pads, shall be designed to have interference fits with their respective housings. The amount of interference shall be as shown on the original manufacturer drawings or as found during inspections of the existing bushings.
19. WICKET GATE SERVOMOTORS
a. Inspection, Disassembly
The wicket gate servomotors shall be leakage tested, disassembled, and cleaned of all rust, scale, scum and oil residue. The requirements listed below:
1. Prior to disassembly a leakage test shall be performed at oil pressure (350 psi, as shown on T7652F160) and ambient temperature using clean new ISO 68 oil at full extended and fully retracted. At each position pressure shall be held for 15 minutes.
The flow rate of leakage shall be recorded and submitted.
2. Remove the pistons and cylinder heads (yokes) from the cylinders and inspect. Note cast iron ring orientation as a potential as-found leak path.
3. The cylinder bore shall be checked for cracks, scoring, and excessive wear. The spigot fit from the cylinder head to the cylinder shall be measured in six locations (minimum). If cylinder bore diameter is changed the spigot fit between the cylinder and the heads shall be restored to its original dimension. Surface finish shall be measured and recorded. The cylinder diameter shall be measured at five locations; one at each end of the cylinder beyond the limit of the piston ring travel, one at each end of the cylinder 4 inches inside the limit of the piston ring travel and one in the area of the cylinder that shows the most wear. Each diameter shall be measured four times, at 45-degree intervals.
4. The exterior surface of the cylinders shall be checked for cracks.
5. All surfaces of the cylinder heads including the packing boxes shall be checked for cracks, scoring, and excessive wear.
6. The servomotor pistons and rods shall be inspected for cracking, scoring and excessive wear. Piston rod surface finish and straightness shall be measured and recorded.
7. The piston rings shall be removed and the ring grooves and the remainder of the rings inspected for cracks, scoring, and excessive wear.
8. The remaining servomotor components shall be inspected for damage, including the bushings, pins, and servomotor cushioning valve.
b. Servomotor Packing Box
1. The existing packing shall be replaced with commercially available chevron seals similar to the existing (unless otherwise approved) and with a wiper seal.
2. Furnish one spare set (total for both servomotors) of the seals provided under subparagraph "a" above. The seals shall be packaged for long term storage and delivered prior to the startup of the first unit refurbished. The spares shall be vacuum packed in sealed bags or boxes and shall have a shelf life of at least 15 years.
3. The housings into which the packing fits shall be modified to meet the size and surface requirements of the seal manufacturer.
4. The packing gland followers shall be cleaned to serve as a retainer for the new seals.
c. Replacement Servomotor Cushioning System
Replacement cushioning/dampening system shown on T7652F160, items 1-29, converted to equivalent new stainless swagelok fittings, piping, unions, gauges, valves, and joint connections.
d. Bore Wicket Gate Servomotor Cylinders (Optional)
Bore the servo cylinders up to 0.040-inch larger diameter (.020 radial cut), to remove surface damage. Following boring the cylinder shall be honed to produce a crosshatch pattern. Request Government approval if additional machining is needed beyond the .040 diametrical cut.
e. Replace Gate Servomotor Piston Rings
Provide and install one set of new servomotor piston rings for each servomotor (one set contains three piston rings). The ring material shall be cast iron and conform to ASTM A159, Grade 3000 requirements or ASTM A48/A48M, Class 40, or approved equal. The ring design shall be of the one- piece, double acting, overlapping end seal design. The piston ring dimensions shall be selected based on the cylinder refurbishment plan and the timeline for delivery shall not delay the servomotor reinstallation. Hone the wicket gate cylinder as needed for the replacement piston rings.
f. Servomotor Bushings
The Contractor shall replace the bushings on the servomotors in kind, see paragraph 14.
g. Piston Head Chrome or Sleeves (Optional)
To maintain the OEM clearance between the cylinder bore and the piston, machine the piston to allow for chrome-build up of up to .020 radial thickness. The chrome built up shall cover the whole outer diameter of the piston, not including the piston ring grooves. If cylinder machining requires more than a .040 diametrical change, provide a bronze wear band/sleeve, a minimum of 2 inches wide, and 1/4" thick, and held on with a .002 to .003" interference fit.
h. Chrome Plate Piston Rods (Optional)
Machine up to 0.020 inch radially off the servo piston rods, chrome plate larger than the original diameter and grind back to original diameter.
i. Restore Servomotor Head Spigot Fit (Optional)
If the servomotor cylinder bore is modified or refurbished, the…