Attachment_A_-_Submittal_Register_-_Big_Bend_Servomotor_14AUG23.pdf
PDF 36 KB Posted
- Solicitation number
- W9128F23Q0010
About this file
This document is a submittal register for a federal contract to rehabilitate servomotors and optionally rehabilitate additional servomotors at Big Bend Dam in South Dakota. The contractor must provide various plans and reports such as an activity hazard analysis, quality control plan, project schedule, and accident prevention plan to the Corps of Engineers between 30 to 45 days prior to work. During performance, the contractor must submit servomotor as-found recordings and recommendations, leakage test reports, and NDT inspection reports within 10 to 30 days of completion. Notices of final inspection must be provided 14 days in advance for off-site work. Qualifications for NDT personnel and independent inspection qualifications are due a minimum of 45 days prior to work. The contractor must also provide notice of witness NDT testing 24 hours in advance for on-site work. Upon award, the contractor will rehabilitate units 6 servomotors and has the option to rehabilitate unit 8 servomotors at Big Bend Dam in South Dakota for the Department of the Army Corps of Engineers Engineering District Omaha.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BB Servo Rehab Pre Bid Sign-up.docx | DOCX document | |
| Attachment_B_Eng_Form_4025-R_14AUG23.pdf | ||
| W9128F23Q0010_Big Bend Servomotor Rehab.pdf | ||
| Attachment _C_ -Reference Drawings_14AUG23.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(a) (b) (c) (d) (e) (f) (g) (h) (I) (j) (k) (l) (m) (n) (o)
SD-01 Para 1.9.1 SD-01 Activity Hazard Analysis (AHA) GA AO 5 Days Prior to Work
SD-01 SD-01 Verified/Eligible Candidate List GA AO 10 Days Prior to Work
SD-01 SD-01 Proof of Insurance for Contractors and Subcontractors GA AO 5 Days Prior to Work
SD-01 SD-01 Identification of Contractor Employees & Vehicles GA AO 10 Days Prior to Work
SD-01 Para 1.4.1 SD-01 Quality Control Plan (QCP) GA AO 30 Days Prior to Work
SD-01 Para 1.4.2 SD-01 Responsible Individuals for Quality Control GA AO 5 Days Prior to Work
SD-01 SD-01 Project Schedule GA AO 30 Days Prior to Work
SD-01 Para1.9.5 SD-01 Servomotor Lift Plan GA AO 30 Days Prior to Work
SD-01 Para1.9.3 SD-01 Accident Prevention Plan (APP) GA AO 30 Days Prior to Work
SD-01 Para 1.9.4 SD-01 Fall Protection and Prevention (FP&P) Plan GA AO 30 Days Prior to Work
SD-01 Section 1.11 SD-01 Anti Terrorism (AT) Level 1 GA AO 30 Days Prior to Work
SD-01 Section 1.11 SD-01 iWATCH and/or CORPS WATCH GA AO 30 Days Prior to Work
SD-01
SD-01
SD-01
SD-01
SD-01
SD-01
SD-05 Task 1, Item 7 SD-05 Work Plan GA DO, HDC 30 Days Prior to Work
SD-05
SD-05
SD-05
SD-05
SD-05
SD-06 Task 1, Item 6 SD-06 Servomotor As-Found and Recommendations GA DO, HDC
Within 30 days of the completion of the recordings
SD-06 Task 1, Item 19, Para j SD-06 Servomotor Leakage Test Report GA DO, HDC
Within 30 days of the completion of the test
SD-06 Task 2, Item 3, Para 3.5. SD-06 NDT Inspection Reports GA DO, HDC
Within 10 calendar days following the completion of the inspection
SD-06
SD-07 Task 1, Item 9 SD-07 Notice Of Final Inspection Following Refurbishment GA DO, HDC
14 calendar days in advance of inspection for components refurbished off site
SD-07 Task 2, Item 3, Para 3.1 (a) SD-07 Qualifications of Nondestructive Testing Personnel GA DO, HDC
A minimum of 45 calendar days prior to their performance of work
SD-07 Task 2, Item 3, Para 3.5 SD-07 Independent Party's Ultrasonic Inspection Qualifications GA DO, HDC
A minimum of 45 calendar days prior to their performance of work
SD-07 Task 2, Item 3, Para 3.1 (a) SD-07 Witness NDT Testing GA DO, HDC
Notice of witness NDT testing for site work 24 hours, SD-07 Task 2, Item 3, Para 3.1 (a) SD-07 Manufacturer's Methods and Procedures of Inspection; GA DO, HDC
A minimum of 45 calendar days prior to their performance of work
TRANSMITTAL
NO.
ACTIVITY NO.
APPROVAL NEEDED BY
CONTRACTOR SCHEDULE DATES
TYPE OF SUBMITTAL
MATERIAL
NEEDED
BY
CLASSIFI-
CATION
REVIEWER
DESCRIPTION OF SUBMITTAL
FIO
or
GA
SUBMITTAL REGISTER (ER 415-1-10)
CONTRACT NO. CONTRACTOR: Sievert Electric Service and Sales Company
OFFICE / NAME
SUBMIT
NEEDED
BY
CORPS
RECORDED
DATE
GOVERNMENT
ACTION
DATE
CODE
CORPS
RECEIVED
DATE
CONTRACTOR
ACTION
CODE
TITLE AND LOCATION: Garrison Intake Bridge Crane Rehabilitation, Riverdale, South Dakota
SPEC PARAGRAPH NO.
ITEM
NO.
File details come from the government source that posted it. Updated .