W9128F22B0015 Drawings VOL 1 OF 2.pdf

PDF 44 MB Posted

Attached to
Oahe Project Pier 10 Bridge Rocker Bearing Modification
Solicitation number
W9128F22B0015
Issued by

About this file

This solicitation is for intake bridge pier bearing modification work at Oahe Dam in South Dakota. The U.S. Army Corps of Engineers Engineering District Omaha is seeking bids for rocker bearing replacement and related modification work at Pier 10 of the Intake Bridge. A site visit will be held on August 31st at 1:00 PM Central Time, with bid responses due by September 19th at 2:00 PM Central Time. This is a 100% small business set-aside opportunity. Interested parties can find additional specification details incorporated in Solicitation W9128F22B0015.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DS: AEC_Screen_FullSize.dscriptPD: AEC_pdf.pltcfg2:27:39 PM 8/18/2022

...\...\OA00100\...\OA00100G-001.dgn

C O

V E

R

I N

D E

X

M

A H

A

N E

F

IL

E N

A M

E

A N

S I

D

G-001

C A

P

IT

O L

A V

E

F

IL

E N

U M

B E

R

O A

G

-0 .d g n

O M

A H

A D

IS

T

R

IC

T

O A

H E

D A

M S

O U

T H

D A

K O

T A

IN

T

A K

E B

R

ID

G E

P

IE

R

B E

A R

IN

G

M O

D

IF

IC

A

T

IO

N

J U

L Y

M H

O F

F M

A N

M H

O F

F M

A N

M H

O F

F M

A N

M H

O F

F M

A N

W

F

B

OMAHA DISTRICT

OAHE DAM, SOUTH DAKOTA

INTAKE BRIDGE PIER 10

BEARING MODIFICATION

W9128F22B0015

JULY 2022

OMAHA DISTRICT

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

SOLICITATION NO.:

CONTRACT NO.:

ISSUE DATE:

of Engineers

US Army Corps

ADVERTISEMENT

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

N

S

B

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

IC

T

F

IL

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

IN

G

P

O J E

C T

L O

C A

T

IO

N

S

IT

E P

L A

N

GA101

D

M E

IE

R

S D

E N

N

G

A .d g n

M E

IE

PROJECT LOCATION

INTAKE BRIDGE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

A K

E B

R

ID

G E

P L

A N

E

L E

V A

T

IO

N

S-101

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

EXISTING CONSTRUCTION

SHEET ARE NOT TO SCALE.

RELATING TO NEW WORK. ITEMS DEPICTED ON THIS

CUTS, PHOTO REFERENCE POINTS, AND NOTES

EXCEPT FOR LOCATION REFERENCES, SECTION

EXISTING CONSTRUCTION FOR GENERAL REFERENCE,

INFORMATION SHOWN ON THIS DRAWING DEPICTS

BEARING TO BE MODIFIED

EXISTING PIER 10 GIRDER

PHOTO

S-104

4'-0"

1'-6"

1'-6"

BRIDGE GIRDERS

EXISTING PRECAST CONCRETE

12'-0"

/2

/2

5'-8 1/4 "5'-9 3/4 "

/4

6'-3 3/4 "5'-8 1/4 "

6'-0"6'-0"6'-0" 3'-0"

6"

A N

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

ID

G

E P

IE

R

M

O D

IF

IC

A T

IO

N

D E

T A

IL

S

S-102

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

C OF BRIDGE & PIERL

C OF BRIDGE GIRDERSL C OF BRIDGE GIRDERSL

3'-0"6'-0"3'-0"

BELOW

PIER STEM

OUTLINE OF

S P

A N

N O

S

P A

N N

O

C OF PIERL

E X

IS

T

IN

G

P

IE

R C

A P

B E

A M

W

ID

T

H V

A R

IE

S

@ 16" O.C.

5 - # 5 VERT.

INNER LAYER

# 5 VERT. @ 18" O.C.

@ 12" O.C.

# 5 TIES

12"

12"

AS REQUIRED

COUPLERS, TYP.

MECHANICAL BAR

HORIZ. 'U' SHAPED TIES AS INDICATED

VERTICALLY, COUPLED TO FORM

THROUGH PIER, & @ 12" O.C.

BARS TYP. @ HOLES DRILLED

# 6 ASTM A 722 TYPE II DEFORMED

TYP. AS INDICATED

TENSIONED BARS,

CAP BEAM FOR

EXISTING PIER

DRILLED THROUGH

1 1/2" O HOLES

INNER LAYER

# 5 VERT. @ 18" O.C.

BEARINGS, TYP.

CENTERED ON GIRDER

# 5 VERT. @ 9" O.C.# 5 HORIZ. @ 12" O.C.

# 5 HORIZ. @ 12" O.C.

BEARINGS, TYP.

CENTERED ON GIRDER

# 5 VERT. @ 9" O.C.

C L

R

C L

R

TENSIONED BARS, TYP.

THREADED ENDS OF

EXTENSION COUPLED TO

# 6 ASTM A 615 BAR

SIDE OF PIER AS SHOWN

BAR EXTENSIONS THIS

TYP. @ TENSIONED

HEADED BAR ENDS

CLR.2"

COUPLER, TYP.

THEADED BAR

ANCHORAGE &

POST-TESIONING

2'-0" 2'-0"

8"

1'-4"

8" 9" 9"

4'-6"

2'-3" 2'-3"

AS REQUIRED

COUPLERS, TYP.

MECHANICAL BAR

SPECIFICATIONS

PLACEMENT #2. SEE

PLACEMENT #1 AND

BETWEEN CONCRETE

CONSTRUCTION JOINT

ABOUT C

IS SYMETRICAL

CONSTRUCTION

L

PIER CAP

BARS THROUGH

OF TOP TENSIONED

# 5 HORIZ. @ LEVEL

REINFORCEMENT

2 # 5 HORIZ. TOP

# 5 BAR

# 5 HORIZ. @ 12" O.C.

SHOWN

SIDE OF PIER AS

EXTENSIONS THIS

OF TENSIONED BAR

DEVELOP TOP ROW

BAR ENDS TO

THREADED HEADED

C OF BRIDGE GIRDERL C OF BRIDGE GIRDERL

C OF BRIDGE & PIERL

REQUIRED

@ TIE SETS AS

COUPLERS, TYP.

MECHANICAL BAR

1'-6" O. C., CENTERED UNDER GIRDER

IN HOLES DRILLED THROUGH PIER CAP @

4 # 6 ASTM A 722 TYPE II DEFORMED BARS

WALL

PIER STEM

PIER CAP BEAM

EXISTING CONCRETE

BEARINGS

ROCKER

GIRDER

EXISTING

@ 12" O.C.

# 5 TIES

12"

12"

@ 16" O.C.

5 - # 5 VERT.

ON GIRDER BEARINGS, TYP.

# 5, & SPACED @ 9" O.C.; CENTERED

TOP & BOTTOM, LAPPED WITH VERT.

DRILLED INTO EXIST. PIER, TYP.

# 5 ADHESIVE ANCHORED DOWELS

S P

A C

E D

O

.C V

E R

T

IC

A L

L Y

P

IE

R C

E N

T E

R E

D U

N D

E R

E X

IS

T

G

IR

D

E R

T

IE

S

E T

S

H O

L E

S D

R

IL

L E

D T

H R

O U

H

A

S T

M A

T

Y P

E I

I T

E N

S

IO

N E

D B

O

.C

V E

R T

IC

A

L L

Y E

X

IS

T

G

IR

D E

R

S P

A C

P

R

C

E N

T E

R E

D U

N D

L

E S

D R

IL

L

E D

T H

R O

U

N S

IO

N

E D

B A

R T

IE

S

E T

A

S T

M A

T

Y P

E I

I

1'-7" O. C., CENTERED UNDER GIRDER

IN HOLES DRILLED THROUGH PIER CAP @

4 # 6 ASTM A 722 TYPE II DEFORMED BARS

ABOUT C

IS SYMETRICAL

CONSTRUCTION

L

EL 1647.16

BEARING SURFACE

TOP OF EXISTING PIER

C OF BRIDGE & PIERL

EL 1647.96

ROCKER BEARING SURFACES

TOP OF EXISTING GIRDER

(PLACEMENT #1)

BEAM AT SPAN 10 FACE

EXISTING PIER CAP

BEARING ADDITION TO

CAST-IN-PLACE CONCRETE

S-102

PIER 10 BASE

EXISTING CONCRETE

PIER CAP BEAM

EXISTING CONCRETE

SPAN 10 FACE, TYP.

ADDITION TO PIER CAP BEAM

FOR CONCRETE BEARING

ANCHORAGE REINFORCEMENT

CAP BEAM

ADDITION TO END OF PIER

CAST-IN-PLACE CONCRETE

GRADE)

PIER FOOTING (BELOW EXISTING

TOP OF EXISTING CONCRETE

/4

/4

3'-0" 3'-0"

PIER 10 ELEVATION

CONCRETE

EDGE OF NEW

CONCRETE PIER CAP

EDGE OF EXISTING

SYMETRICAL ABOUT C

CONSTRUCTION IS

ALL NEW WORK & EXISTING

L

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

SECTION 2

1"=1'-0"SCALE:

SECTION 3

1"=1'-0"SCALE:

DETAIL 1

3/8"=1'-0"SCALE:

GENERAL NOTES:

SPECIFICALLY, SEE SHEET S-117 FOR DIMENSIONS, REINFORCEMENT AND CONFIGURATION OF THE EXISTING PIER 10 CONSTRUCTION.

1. REFERENCE "FOR INFORMATION ONLY" DRAWINGS S-110 THROUGH S-121 FOR DIMENSIONS, MATERIAL NOTES, REINFORCEMENT AND OTHER INFORMATION REGARDING EXISTING CONSTRUCTION, PLACEMENTS. SEE SPECIFICATIONS

2. SEE NOTES ON SHEET S-103 FOR CONSTRUCTION PHASING AND SEQUENCING. NOTE THAT NEW CONCRETE IS APPLIED TO THE EXISTING PIER 10 CAP BEAM IN TWO DISTINCT AND SEPARATELY TIMED

REPRESENTATIVE IMMEDIATELY WHEN DISCREPANCIES ARE DISCOVERED.

3. VERIFY ALL RELEVANT EXISTING DIMENSIONS AND CONDITIONS PRIOR TO COMMENCING FABRICATION, DRILLING, AND OTHER CONSTRUCTION ACTIVITIES, AND NOTIFY THE CONTRACTING OFFICER'S

4. PROVIDE AND MAINTAIN ADEQUATE BRACING AND SHORING TO SUPPORT NEW WORK AT ALL TIMES DURING CONSTRUCTION.

DESIGN NOTES:

THE BEARING SURFACE FOR GIRDER ROCKER BEARINGS. TERMINOLOGY USED IN THE DETAILS GENERALLY FOLLOWS THE TERMINOLOGY AS DEFINED IN THIS NOTE.

SUPPORT PRECAST CONCRETE BRIDGE GIRDERS. THE CAP BEAM IS TOPPED BY A CONCRETE PIER CAP, WHICH OVERHANGS THE BEAM ON ALL SIDES, AND IS SLOPED TO DRAIN. THE PIER CAP PROVIDES

5. IN GENERAL, THE EXISTING PIER 10 CONSISTS OF A CAST-IN-PLACE CONCRETE STEM WALL TOPPED BY A CAST-INPLACE CONCRETE CAP BEAM WHICH CANTILEVERS ON BOTH SIDES OF THE STEM TO

TENSIONED AGAINST THE EXISTING CONCRETE ON THE OPPOSITE SIDE.

THE CAP BEAM, WHICH ARE TIED TOGETHER BY POST-TENSIONED REINFORCING BARS CORE DRILLED THROUGH THE EXISTING CAP BEAM AND ANCHORED IN THE NEW CONCRETE ON ONE SIDE, AND

6. THE PIER 10 MODIFICATION GENERALLY CONSISTS OF CONSTRUCTING AN EXTENSION OF THE BEARING SURFACE OF THE PIER CAP BY CASTING CONCRETE, PLACED SEPARATELY, ON OPPOSITE FACES OF

1. FACTORED DESIGN DEADL LOAD FOR EXTERIOR SPAN 10 GIRDER = 74.8 K. LOAD FACTOR = 1.25.

2. FACTORED DESIGN DEAD LOAD FOR INTERIOR SPAN 10 GIRDER = 68.0 K. LOAD FACTOR = 1.25.

CRANE w/ GROSS VEHICLE WEIGHT OF 161,800 LBS.)

3. FACTORED DESIGN VEHICLE LIVE LOAD FOR EXTERIOR & INTERIOR SPAN 10 GIRDERS = 63.5 K. LOAD FACTOR = 1.35 (STRENGTH II - OWNER SPECIFIED SPECIAL DESIGN VEHICLE - GROVE GMK5210 T MOBLIE

THAN 15% OF LIVE LOAD.)

4. FACTORED DESIGN VEHICLE IMPACT LOAD FOR EXTERIOR & INTERIOR SPAN 10 GIRDERS = 9.5 K. LOAD FACTOR = 1.35 (BASED UPON MOBLIE CRANE DESIGN VEHICLE, IMPACT ASSUMED TO BE NOT GREATER

5. FACTORED DESIGN DEAD LOAD FOR ADDITIONAL NEW CONCRETE AT EXTERIOR GIRDER, SPAN 10 FACE = 7.2 K. LOAD FACTOR = 1.25.

6. FACTORED DESIGN DEAD LOAD FOR ADDITIONAL NEW CONCRETE AT INTERIOR GIRDER, SPAN 10 FACE = 8.8 K. LOAD FACTOR = 1.25.

7. ALL PIER 10 DESIGN LOADS DETERMINED AND APPLIED IN ACCORDANCE WITH AASHTO LRFD BRIDGE DESIGN SPECIFICATIONS - 8TH EDITION, 2017.

8. DESIGN PIER EDGE REACTION WAS APPLIED AS INDICATED IN DETAIL 3 ON SHEET S-103, AT 2" MAXIMUM ALLOWABLE ECCENTRICITY FROM THE SPAN 10 FACE OF THE EXISTING PIER CAP.

S-103

S-103

S-102

S-102

S-103

S-103

/2

1'-0" 1'-0"4'-0"

T

Y P

8"

10"

A N

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

ID

G

E P

IE

R

M

O D

IF

IC

A T

IO

N

D E

T A

IL

S

S-103

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

C OF BRIDGE PIERL

SPAN NO. 11SPAN NO. 10

EXISTING PRECAST

CONCRETE BRIDGE

GIRDER

EXISTING PRECAST

CONCRETE BRIDGE

GIRDER

EXISTING FIXED

GIRDER BEARING

EXISTING ROCKER

GIRDER BEARING

TOP OF EXISTING PIER

BEARING SURFACE

EL 1647.16

TOP OF EXISTING

GIRDER ROCKER

BEARING SURFACE

EL 1647.96

SLOPE CONCRETE SURFACE

1/4" PER FOOT TO MATCH

EXIST. TOP OF PIER CAP,

TYP. EACH SIDE

PIER STEM

WALL

CAST-IN-PLACE CONCRETE

BEARING SURFACE ADDITION

TO EXISTING PIER CAP BEAM

@ SPAN NO. 11 FACE

(CONCRETE PLACEMENT # 2)

ANCHORAGE REINFORCEMENT

FOR CONCRETE SPAN NO. 10

BEARING SURFACE ADDITION

(CONCRETE PLACEMENT # 1)

EXISTING CONCRETE PIER

CAP BEAM

EXISTING PIER CAP

E

N D

O F

C A

N T

IL

E

V E

R

S-103

8"

6'-0"

TOP OF EXISTING CONCRETE

PIER FOOTING (BELOW

EXISTING GRADE)

EDGE OF NEW

CONCRETE

ANCHORAGE REINFORCEMENT

FOR CONCRETE SPAN NO. 11

BEARING SURFACE ADDITION

(CONCRETE PLACEMENT # 2)

CAST-IN-PLACE CONCRETE

BEARING SURFACE ADDITION

TO EXISTING PIER CAP BEAM

@ SPAN NO. 10 FACE

(CONCRETE PLACEMENT # 1)

SPAN NO. 10 SPAN NO. 11

C BRIDGE PIERL

# 6 ASTM A 722 TYPE II DEFORMED BAR

TIES IN HOLES DRILLED THROUGH PIER,

TENSIONED PER NOTES ON THIS SHEET,

ANCHORED & PRESSURE GROUTED, TYP.

# 6 ASTM A 615 HEADED BAR

EXTENSIONS COUPLED TO

THREADED ENDS OF

TENSIONED BARS, TYP.

# 5 HORIZ.

@ 12" O.C., TYP.

# 5 HORIZ., TYP.

EACH FACE

# 5 TOP BARS,

TYP. EACH FACE

M

IN

L

A P

T

Y P

# 5 x 3'-4" VERT. INNER

LAYER @ 18" O.C.,

TYP. EACH FACE

2" CLR. TYP.

# 5 CONTINUOUS

HORIZ. @ EACH

SET OF # 6 TIES

# 5 DOWEL ADHESIVE ANCHORED

INTO PIER FACE @ 9" O.C., TYP

EACH FACE

1'-4"

C

L R

MIN.

EMBEDMENT

# 5 VERT. @ 9" O.C.

TYP. EACH FACE

# 5 DOWEL ADHESIVE

ANCHORED INTO PIER

CAP FACE @ 9" O,C.,

TYP. EACH FACE

1'-6"

POST-TENSIONING BEARING

PLATE, ANCHORAGE &

THREADED COUPLER, TYP.

EXISTING PIER

STEM WALL

EXISTING BRIDGE GIRDEREXISTING BRIDGE GIRDER

S-103

S

P A

C E

S

1 1/2" O HOLES DRILLED THROUGH

EXISTING PIER CAP BEAM FOR

POST-TENSIONED TIE BARS, TYP.

MECHANICALLY ROUGHEN EXISTING

PIER FACE CONCRETE SURFACES TO

AN AMPLITUDE OF 1/4" PRIOR TO

PLACEMENT OF NEW CONCRETE

AGAINST IT.

POST-TENSIONING ANCHOR

PLATE SIZE & THICKNESS PER

SYSTEM MANUFACTURER

BEVEL WASHERS AS REQUIRED

ANCHOR NUT & WASHERS

PER POST-TENSIONING

SYSTEM MANUFACTURER

THREADED BAR COUPLER

# 6 ASTM A 615 BAR EXTENSION

w/ WELDED OR THREADED

HEADED END w/ MINIMUM NET

BEARING AREA = 9 TIMES THE

BAR CROSS SECTIONAL AREA

1 1/2" DIAMETER HOLES

DRILLED THROUGH EXISTING

PIER CAP & BEAM

EXISTING # 9 BARS

w/ 4" CLEAR COVER

GRIND EXISTING CONCRETE PIER

SURFACE SMOOTH AND FLAT UNDER

ANCHOR PLATES, PER REQUIREMENTS

OF POST-TENSIONING SYSTEM

MANUFACTURER

SLOPE CONCRETE SURFACE

1/4" PER FOOT TO MATCH

EXISTING PIER CAP

CLOSEST ALLOWABLE FUTURE

POINT OF CONCENTRATED ROCKER

BEARING LOAD FROM EXTENSION

OF BEARING PLATE

PRESSURE GROUT TIE BARS

THROUGH ANCHOR PLATE AFTER

COMPLETION OF POST-TENSIONING

AND LOCK-OFF OF BARS, PER

NOTES ON THIS SHEET

MECHANICALLY THREADED HEAD

ON END OF # 6 BARS TO BE POST-

TENSIONED - FOR TOP ROW ONLY.

MINIMUM NET BEARING AREA FOR

HEADED ATTACHMENT ON TENSIONED

BARS SHALL BE 9 TIMES THE BAR

CROSS-SECTIONAL AREA.

9" MIN. EMBEDMENT

TO FACE OF HEADED END

1'-0"

12" MIN. EMBEDMENT OF

# 6 TIE BAR HOOK

SPAN NO. 10 SIDE CONCRETE SHALL

BE PLACED AND CURED TO THE

REQUIRED STRENGTH PRIOR TO POST-

TENSIOING OF TIE BARS

C OF BRIDGE PIERL

SPAN NO. 10 SPAN NO. 11

8" MIN. EMBEDMENT, TYP

C

L R

T Y

P

1'-0"

9" MIN. EMBEDMENT

TO FACE OF HEADED END

# 5 DOWEL ADHESIVE ANCHORED

INTO EXITING PIER FACE

SPAN NO. 11 SIDE CONCRETE SHALL

BE PLACED AFTER INSTALLATION ,

POST-TENSIONING AND PRESSURE

GROUTING OF # 6 TIE BARS IS COMPLETE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S1

SECTION 1

SCALE: 3/8" = 1'-0"

SECTION 2

SCALE: 1" = 1'-0"

DETAIL 3

SCALE: 3" = 1'-0"

MATERIAL NOTES:

CONSTRUCTION SEQUENCE:

POST-TENSIONING NOTES:

BE 4500 PSI.

1. MINIMUM CONCRETE COMPRESSIVE STRENGTH AT 28 DAYS (f'c) SHALL

A615, GRADE 60.

2. NON-POST-TENSIONED REINFORCING BARS SHALL CONFORM TO ASTM

Fu = 150,000 PSI.

TO ASTM A722, TYPE II, DEFORMED BARS, WITH ULTIMATE TENSILE CAPACITY,

3. POST-TENSIONED HIGH STRENGTH REINFORCING BARS SHALL CONFORM

TIMES THE CROSS-SECTIONAL AREA OF THE ATTACHED BAR.

SHALL HAVE A NET EFFECTIVE BEARING AREA NOT LESS THAN 9

OF THE BARS, AND SHALL CONFORM TO ASTM A970. HEAD PLATES

DEVELOPING 75% OF THE MINIMUM ULTIMATE TENSILE STRENGTH

THREADED MECHANICALLY ATTACHED HEADS CAPABLE OF

4. HEADED BARS INDICATED FOR POST-TENSIONED BARS SHALL HAVE

SECTIONAL AREA OF THE ATTACHED BAR.

NET EFFECTIVE BEARING AREA NOT LESS THAN 9 TIMES THE CROSS-

BARS, AND SHALL CONFORM TO ASTM A970. HEAD PLATES SHALL HAVE A

OF DEVELOPING 125% OF THE MINIMUM TENSILE YIELD STRENGTH OF THE

THREADED MECHANICALLY ATTACHED HEADS OR WELDED HEADS, CAPABLE

5. HEADED BARS INDICATED FOR NON-POST-TENSIONED BARS SHALL HAVE

OF THE MINIMUM ULTIMATE TENSILE STRENGTH OF THE BARS SPLICED.

AS INDICATED PER LOCATION, AND SHALL BE CAPABLE OF DEVELOPING 100%

TYPE OR NON-THREADED TYPE MECHANICAL COUPLERS, WITH TYPE TO BE

6. BAR COUPLERS FOR POST-TENSIONED BARS SHALL BE EITHER THREADED

TENSILE YIELD STRENGTH OF THE BAR.

MECHANICAL TYPE, CAPABLE OF DEVELOPING 125% OF THE MINIMUM

7. BAR COUPLERS FOR NON-POST-TENSIONED BARS SHALL BE THREADED

STRENGTH OF THE BAR TENSIONED.

CAPABLE OF DEVELOPING 95% OF THE MINUMUM ULTIMATE TENSILE

8. POST-TENSIONING ANCHOR BEARING PLATES AND ANCHOR NUTS SHALL BE

AND SPLICING AND ANCHORAGE ACCESSORIES.

9. MINIMUM CONCRETE CLEAR COVER SHALL BE 2" FOR ALL REINFORCING BARS

BAR HEADS SHALL BE AS DIMENSIONED.

10. MINIMUM INSTALLED DEVELOPMENT EMBEDMENT DEPTHS FOR HOOKS AND

NOT LESS THAN REQUIRED BY ACI 318 IF NOT DIMENSIONED.

11. MINIMUM LAP SPLICES OF REINFORCEMENT SHALL BE AS DIMENSIONED, AND

BY MINIMUM DISTANCE TO CONCRETE EDGES.

MINIMUM TENSILE YIELD STRENGTH OF THE BAR, EXCEPT AS REDUCED

EMBEDMENT DEPTH INDICATED, AND SHALL DEVELOP 100% OF THE

12. ADHESIVE ANCHORED REINFORCING BARS SHALL HAVE THE MINIMUM

2. MAXIMUM FORCE IN POST-TENSIONED REINFORCEMENT DURING TENSIONING SHALL BE 0.5 Fu = 33.0 K.

AND THE COMPLETED POST-TENSIONING WORK HAS BEEN INSPECTED AND APPROVED.

UNTIL AFTER POST-TENSIONING IS COMPLETED, ANCHOR NUTS AT BEARING ANCHORAGES ARE LOCKED OFF

4. HOLES DRILLED IN THE PIER CAP BEAM FOR POST-TENSIONED BARS SHALL NOT BE PRESSURE GROUTED

3. FINAL TENSION FORCE IN POST-TENSIONED REINFORCEMENT SHALL BE 0.42 Fu = 28.0 K.

ON THE SPAN 10 SIDE OF THE PIER CAP BEAM HAS BEEN ACHIEVED.

CONFIRM THAT THE SPECIFIED 28-DAY COMPRESSIVE STRENGTH OF 4500 PSI, OF THE PLACEMENT #1 CONCRETE

1. TENSIONING OF REINFORCEMENT TO BE POST-TENSIONED SHALL NOT COMMENCE UNTIL COMPRESSION TESTS

1. CORE DRILL HOLES THROUGH THE EXISTING PIER CAP BEAM AS SHOWN. SEE SPECIFICATIONS.

THE PIER CAP BEAM TO AN AMPLITUDE OF 1/4" MINIMUM.

2. MECHANICALLY ROUGHEN ALL VERTICAL SURFACES OF THE SPAN 10 RESERVOIR SIDE AND ENDS OF

HOLES SMOOTH FOR POST-TENSIONING ANCHOR PLATE BEARING.

3. GRIND CONCRETE VERTICAL SURFACE AREAS OF THE SPAN 11 LAND SIDE OF THE PIER ADJACENT TO

4. INSTALL ADHESIVE ANCHORED REINFORCEMENT ON THE SPAN 10 RESERVOIR SIDE OF THE PIER CAP BEAM.

CENTRALIZERS, AND INSTALL TENSIONING ANCHOR PLATE ASSEMBLIES.

5. INSTALL BARS TO BE POST-TENSIONED THROUGH HOLES IN THE PIER CAP BEAM, POSITION WITH

TENSIONED WHERE INDICATED ON THE SPAN 10 RESERVOIR SIDE.

THROUGH THE PIER, TO BE POST-TENSIONED. INSTALL HEADED ENDS ON BARS TO BE POST-

6. INSTALL BAR COUPLERS WHERE INDICATED TO FORM 'U'-SHAPED DOWELS WITH BARS PLACED

AND ENDS OF THE PIER CAP BEAM.

7. INSTALL ALL OTHER NON-POST-TENSIONED REINFORCING BARS ON THE SPAN 10 RESERVOIR SIDE

PIER CAP BEAM. INSTALL FORMWORK FOR PLACEMENT # 1 ON THE SPAN 10 SIDE AND ENDS.

8. INSPECT AND TEST CURED ADHESIVE ANCHORED REINFORCEMENT ON THE SPAN 10 SIDE OF THE

AND ENDS OF THE BEAM, AND CURE.

9. PLACE CONCRETE FOR PLACEMENT # 1 ON THE SPAN 10 RESERVOIR SIDE OF THE PIER CAP BEAM

THROUGH THE PIER CAP BEAM.

REQUIRED 28-DAY DESIGN STRENGTH, PREPARE FOR POST-TENSIONING OF BARS EXTENDING

10. AFTER COMPRESSION TESTS VERIFY THAT THE PLACEMENT # 1 CONCRETE HAS ACHIEVED THE

PIER CAP BEAM AND LOCK OFF ANCHORAGES AT THE REQUIRED TENSION FORCE.

11. PERFORM POST-TENSIONING OPERATIONS ON THE BARS EXTENDING THROUGH THE HOLES IN THE

12. PRESSURE GROUT THE CORE DRILLED HOLES AND POST-TENSIONED BARS.

BETWEEN POST-TENSIONING ANCHOR PLATES.

13. MECHANICALLY ROUGHEN VERTICAL SURFACES OF THE SPAN 11 LAND SIDE OF THE PIER CAP BEAM

14. INSTALL ADHESIVE ANCHORED REINFORCEMENT ON THE SPAN 11 LAND SIDE OF THE PIER CAP BEAM.

EXPOSED THREADED ENDS OF POST-TENSIONED BARS.

15. INSTALL THREADED COUPLERS AND NON-POST-TENSIONED HEADED BAR EXTENSIONS ON THE

SIDE OF THE PIER CAP BEAM.

16. INSTALL ALL REMAINING NON-POST-TENSIONED REINFORCEMENT ON THE SPAN 11 LAND

OF THE PIER CAP BEAM. INSTALL FORMWORK FOR PLACEMENT # 2 ON THE SPAN 11 SIDE.

17. INSPECT AND TEST CURED ADHESIVE ANCHORED REINFORCEMENT ON THE SPAN 11 SIDE

BEAM AND CURE.

18. PLACE CONCRETE FOR PLACEMENT # 2 ON THE SPAN 11 LAND SIDE OF THE PIER CAP

19. REMOVE FORMS WHEN CRITERIA FOR REMOVAL HAS BEEN ACHIEVED.

S-102

S-102

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

A K

E S

T R

U C

T U

R E

B R

ID

G

E P

H O

T O

G R

A P

H S

S-104

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

PIER 10

TO BE MODIFIED

EXISTING FACE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

A

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

PHOTO NO. 1: INTAKE STRUCTURE BRIDGE LOOKING SOUTHWEST PHOTO NO. 2: PIER 10 LOOKING WEST

PHOTO NO. 3: PIER 10 BEARING LOOKING NORTHEAST PHOTO NO. 4: PIER 10 BEARING LOOKING WEST

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

ID

G

E P

L A

N A

N D

E L

E V

A T

IO

N

F O

R I

N F

O R

M A

T

IO

N O

N L

Y

S-110

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

EXISTING CONSTRUCTION

SHEET ARE NOT TO SCALE.

RELATING TO NEW WORK. ITEMS DEPICTED ON THIS

CUTS, PHOTO REFERENCE POINTS, AND NOTES

EXCEPT FOR LOCATION REFERENCES, SECTION

EXISTING CONSTRUCTION FOR GENERAL REFERENCE,

INFORMATION SHOWN ON THIS DRAWING DEPICTS

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

IS

C E

L L

A N

E O

U S

D E

T A

IL

S

F O

R I

N F

O R

M A

T

IO

N O

N L

Y

S-111

D

M E

IE

R

S D

E N

N

S

-1

.d

M E

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

EXISTING CONSTRUCTION

SHEET ARE NOT TO SCALE.

RELATING TO NEW WORK. ITEMS DEPICTED ON THIS

CUTS, PHOTO REFERENCE POINTS, AND NOTES

EXCEPT FOR LOCATION REFERENCES, SECTION

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

S

P A

N R

E

IN

F O

R C

E M

E N

T D

E T

A

IL

S

F O

R I

N F

O R

M A

T

IO

N O

N L

Y

S-112

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

EXISTING CONSTRUCTION

SHEET ARE NOT TO SCALE.

RELATING TO NEW WORK. ITEMS DEPICTED ON THIS

CUTS, PHOTO REFERENCE POINTS, AND NOTES

EXCEPT FOR LOCATION REFERENCES, SECTION

S

A R

IN

G

M O

D

IF

IC

A

T

IO

N

IN

T

A K

E B

R

ID

G E

P

IE

R

O A

H E

D A

M S

O U

T H

D A

K O

T A

W

F

B

J U

L Y

A H

A

N E

C A

P

IT

O L

A V

E

O M

A H

A D

IS

T

R

E

N U

M B

E R

F

IL

E N

A M

E

S D

E N

N

S

P A

N C

O N

C R

E T

E D

E T

A

IL

S

F O

R I

N F

O R

M A

T

IO

N O

N L

Y

S-113

D

M E

IE

R

S D

E N

N

S

-1 .d

M E

B

C

D

E

F

G

H

J

K

L

M

N

P

S U

B M

IT

T

E D

B Y

C H

E C

K E

D B

Y

D R

A W

N B

Y

D E

S

IG

N E

D B

Y

C O

N T

R A

C T

N O

S O

L

IC

IT

A

T

IO

N N

O

IS

S

U E

D A

T E

S I Z

E

M A

R K

D E

S C

R

IP

T

IO

N D

A T

E

SHEET ID

®of Engineers

US Army Corps

U .S

A

R M

Y C

O R

P S

O F

E N

G

IN

E E

R S

EXISTING CONSTRUCTION

SHEET ARE NOT TO SCALE.

RELATING TO NEW WORK. ITEMS DEPICTED ON THIS

CUTS, PHOTO REFERENCE POINTS, AND NOTES

EXCEPT FOR LOCATION REFERENCES, SECTION

GENERAL
G-001COVER & INDEX (1)
G-002ABBREVIATIONS (1)
GA101PROJECT LOCATION - SITE PLAN (1)
STRUCTURAL
S-101INTAKE BRIDGE PLAN & ELEVATION (1)
S-102BRIDGE PIER 10 MODIFICATION DETAILS (1)
S-103BRIDGE PIER 10 MODIFICATION DETAILS (1)
S-104INTAKE STRUCTURE BRIDGE PHOTOGRAPHS (1)
S-110FOR INFORMATION ONLY BRIDGE PLAN AND ELEVATION (1)
S-111FOR INFORMATION ONLY MISCELLANEOUS DETAILS (1)
S-112FOR INFORMATION ONLY 150' SPAN REINFORCEMENT DETAILS (1)
S-113FOR INFORMATION ONLY 70' SPAN CONCRETE DETAILS (1)

File details come from the government source that posted it. Updated .