This document provides an amendment to a solicitation for a bedrock maintenance excavation project on the Missouri River in Nebraska. The U.S. Army Corps of Engineers, Omaha District is seeking bids for excavating bedrock material to restore minimum navigation channel dimensions between river miles 626.4 to 625.0. Bids are due by March 3rd, 2022. The amendment provides revisions to specifications, drawings, and notes regarding completion of base work prior to starting optional work. It also inserts language allowing for interim progress payments up to 80% of contract line item amounts. The estimated value of construction is between $5-10 million. The solicitation is restricted to small businesses.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Am0002 in SF30 Block 14 Continuation Page for description of amendment changes.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Feb-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F22B0001
X 9B. DATED (SEE ITEM 11)
01-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Feb-2022
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F22B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AM0002
16 Feb 2022 Solicitation No. W9128F22B0001
Date of Issue: 01 Feb 2022 Date of Opening: 03 Mar 2022
SUBJECT: Amendment No. 0002 to Specifications and Drawings for Construction of Bedrock Maintenance Excavation, Missouri River at Florence Bend Near Omaha, NE.
TO: Prospective Bidders and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.)
(1) Section 01 22 00 Page 2, paragraph 1.1.2 Insert “Interim Progress payments will be made up to a maximum of 80% of the CLIN total.” After the sentence “Contractor quality control personnel will be allowed to perform surveys for interim progress payment of excavated areas.”
(2) Section 35 20 23 Page 6, paragraph 3.1.5
Replace first sentence with” A final survey shall be conducted by the Contractor after all excavation of awarded work (base and options) is complete”
2. This amendment is a part of the bidding papers and its receipt shall be acknowledged. All other conditions and requirements of the specifications remain unchanged.
a. See Section 00 21 00, Instructions to Bidders, on how to submit electronic bids.
3. Reference Bid Schedule note 5.d. Replace with:
The contractor shall complete all work included within the base contract first. All work included within the base shall be completed in accordance with the schedule identified in Specification 35 20 23. The contractor may proceed to Option 1 (if/when awarded) following completion of the base. Following survey review if any deficiencies are found, the contractor shall immediately address those deficiencies as a priority over all other on-going work including options. Option 1 shall be completed prior to starting work on Option 2 (if/when awarded). The contractor may proceed to
W9128F22B0001
Option 2 (if/when awarded) following completion of Option 1. Following Option 1 survey review if any deficiencies are found, the contractor shall immediately address those deficiencies as a priority over all other on-going work including options.
4. Drawings (Reissued). The following drawing is revised and reissued with this amendment.
(a)Sheet: B0.01
5. Electric bids will be received until 2:00 p.m., local time at place of bid opening, 03 Mar 2022.
U.S. Army Engineer District, Omaha Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901
16 February 2022
JAC/2100
Attachments.
a. Am0002 Drawings listed in 4(a) above.
(End of Summary of Changes)