This solicitation is for the design and construction of Offutt Air Force Base Flight Line Support Facilities located in Nebraska. The project includes the construction of new facilities to replace those damaged in flooding, including a Fuel Operations Facility, LOX Maintenance Facility, LOX Storage Canopy, and De-Icing Fluid Storage Building. The project also includes demolition of existing damaged buildings, site improvements, utilities, and new pavement. Mechanical, electrical, and fire protection systems will be installed. Bidders must acknowledge receipt of amendments by the specified date of August 19, 2021 at 14:00 hours. The contract will be awarded on an best-value basis.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Am_0005.pdf | ||
| Am_0004.pdf | ||
| Am_0004-Drawing.pdf | ||
| Am_0003-Drawings.pdf | ||
| Am_0002.pdf | ||
| Am_0002-Drawings.pdf | ||
| Appendix D-Rcd Dwgs-All Buildings Combined-AM03.pdf | ||
| Appendix H.pdf | ||
| Appendix G.pdf | ||
| Appendix F.pdf | ||
| Am_0001.pdf | ||
| Am_0001-Drawings.pdf | ||
| W9128F-21-R-0092-Specs.pdf | ||
| OF64 - ADVERTISEMENT.PDF | ||
| Appendix D - Record Drawings.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Amendment No.0003 W9128F
FLIGHTLINE HANGARS CAMPUS, SGBP212907/1080944 (FY20), AT OFFUTT AFB, NE
See attached documentation for content of the amendment revisions to solicitation.
Date for receipt of proposals is 19 AUG 2021 at 1400 hours
Government Point of Contact: Dawn Barnett, Contract Specialist, Dawn.S.Barnett@usace.army.mil_
U.S ARMY CORPS OF ENGINEERS, OMAHA DISTRICT
CONTRACTING OFFICE
1616 Capitol Avenue Omaha, Nebraska 68102-4901
See Item 6
W9128F-21-R-0092
08/11/2021
06/29/2021
08/11/2021
Am #0003 - 2 (Continuation of SF 30)
DEPARTMENT OF THE ARMY
Omaha District, Corps of Engineers
Omaha, Nebraska 68102-4901
:NOTICE: Failure to acknowledge : Solicitation No. W9128F-21-R-0092 :all amendments may cause rejec-:
:tion of the bid. See FAR : Date of Issue: 29 JUN 2021 :52.214-3 of Section 00 21 00. : Date of Opening:
19 AUG 2021
Amendment No. 0003
11 AUG 2021
SUBJECT: Amendment No. 0003 to Specifications and Drawings for Design and Construction of FLIGHTLINE SUPPORT FACILITIES AT OFFUTT AFB, NE
TO: Prospective Offerors and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages as noted below. The substituted pages are revised and reissued with this amendment. Sections marked with asterisks have changes tracked. All language shall apply regardless of the accuracy of this tracking effort.
Pages Deleted Pages Substituted or Added 01 81 00 01 81 00* 01 86 10 01 86 10* 01 86 13 01 86 13* 01 86 26 01 86 26*
** ** ** 01 86 26AT1
** ** ** 01 86 26AT2
02 41 00 02 41 00* Appendix A Appendix A Appendix D Appendix D
b. Drawings (Reissued). The following drawings are revised, with revision dates indicated in their title blocks, and reissued with this amendment.
(1) Sheet OF64ED101, ELECTRICAL DEMO PLAN AREA 101
(2) Sheet OF64AED102, ELECTRICAL DEMO PLAN AREA 102
(3) Sheet OF64ED103, ELECTRICAL DEMO PLAN AREA 103
(4) Sheet OF64ED104, ELECTRICAL DEMO PLAN AREA 104
(5) Sheet OF64ED105, ELECTRICAL DEMO PLAN AREA 105
(6) Sheet OF64ED106, ELECTRICAL DEMO PLAN AREA 106
Am #0003 - 3 (Continuation of SF 30)
(7) Sheet OF64I-111, FURNITURE FLOOR PLAN
2. This amendment is a part of the bidding papers and its receipt shall be acknowledged on the Standard Form 30. All other conditions and requirements of the specifications remain unchanged.
3. Bids will be received until 2:00 p.m., local time at place of bid opening, 19 AUG 2021.
Attachments:
Specification Pages listed in 1.a., above (except Appendix D, which is provided under separate cover) Drawings listed in 1.b., above (provided under separate cover)
U.S. Army Corps of Engineers, Omaha District
Omaha, Nebraska 68102-4901
11 AUG 2021
jlb/2099
Flightline Support Facilities OF64
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 81 00
SUMMARY OF THE WORK
05/18
PART 1 GENERAL
1.1 REFERENCES
1.2 DESIGN AND CONSTRUCTION OBJECTIVES
1.3 PROJECT SCOPE
1.3.1 Facility Functions
1.3.2 Site and Infrastructure Functions
1.3.3 Project Site
1.3.4 Base Bid and Bid Option
1.3.4.1 Base Bid
1.3.4.2 Bid Options
1.3.4.2.1 Bid Option - Procure and Install Furniture, Fixtures and Equipment (FF&E) Package.
1.3.4.2.2 Bid Option - Procure and Install a CCTV Package
1.3.4.2.3 Bid Option - Procure and Install Infrastructure for Keyless Access Control.
1.3.4.2.4 Bid Option - Procure and Install Outside Plant
Communication Lines
1.3.4.2.5 Bid Option - Procure and Install 0ne (1) new
[*AM-0001][**AM-0001]De-Icing Tank Assembly.
1.4 DESIGN AND CONSTRUCTION REQUIREMENTS
1.4.1 Changes to RFP Criteria Requirements
1.4.2 Codes and Criteria
1.4.3 Phasing of Work, Security, and Construction Staging
1.4.4 Sustainability
1.4.4.1 Criteria
1.4.4.2 Total Building Commissioning
1.4.4.3 Cybersecurity
1.4.4.4 Third Party Certification/Validation
1.4.5 Bridging Documents
1.4.6 Design and Construction Measurement Units
1.4.7 Personnel Qualifications and Experience
1.4.8 Design and Construction Deliverables
1.4.9 Advanced Modeling and Facility Data Requirements
1.4.10 Operations and Maintenance Requirements
PART 2 PRODUCTS
-- End of Section Table of Contents --
SECTION 01 81 00 Page 1
Am_0003 x
SECTION 01 81 00
SUMMARY OF THE WORK
05/18
PART 1 GENERAL
1.1 REFERENCES
The design publications listed below shall be used as sources of criteria for the design. Where a date is not specified, the most current edition of the code or standard in effect, including errata and addenda available at the RFP proposal submission deadline shall be used as criteria for the design. The criteria from these sources may be supplemented but not supplanted, by applicable criteria contained in nationally recognized codes and standards.
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-200-01 [*AM-03](2019c1)[**AM-03] DoD Building Code
UFC 1-200-02 High Performance and Sustainable Building Requirements
UFC 3-101-01 Architecture
UFC 3-210-10 Low Impact Development
UFC 4-010-06 Cybersecurity of Facility-Related Control Systems
[*AM-03]
1.2 DESIGN AND CONSTRUCTION OBJECTIVES
Offutt Air Force Base (AFB) had numerous buildings damaged during the base wide flood event in the spring of 2019. One user group that had damaged facilities was the Flightline Hangars Campus. Their existing buildings and storage facilities were damaged to the point of being total losses and being uninhabitable. The POL Operations are currently working out of temporary renovated facilities with degraded capabilities compared to their original facilities. The primary objective for this project is to provide new facilities to replace the existing damaged facilities and restore lost capabilities and functions to the campus. The final objective is a phased demolition of existing flood damaged facilities.
1.3 PROJECT SCOPE
The project includes the construction of new facilities for the Flightline.
Building types are listed below. The requirements of the criteria noted above in the references shall be met, except as modified by these specifications.
SECTION 01 81 00 Page 2
Fuel Operations Facility - 4,780 square feet
LOX Maintenance Facility - 1,862 square feet
LOX Storage Canopy - 4,800 square feet
De-Icing Fluid Storage Building/Tank Canopy - 1,040 square feet
TACAN Equipment Facility - 161 square feet with separate Generator Equipment Pad (See Civil). Demolish the existing TACAN Building after completion and full operability of the new TACAN Building.
UFC criteria referenced herein as well as other relevant design guides can be found on the Whole Building Design Guide (WBDG) website.
The project includes demolition of existing buildings, site improvements, site utilities, and new pavement. New communications, mechanical, electrical, and fire protection systems will need to be installed. Provide a new fire sprinkler in the Fuel Operations Facility. Provide a new fire alarm and mass notification system for the Fuel Operations Facility, LOX Maintenance Facility, and the TACAN Equipment Facility. [*AM-02] All facilities shall meet applicable life safety requirements. [**AM-02] The Fuel Operations Facility and the LOX Maintenance Facility shall [*AM-02] meet life safety, anti-terrorism/force protection (ATFP), and [**AM-02] accessibility requirements. [*AM-02] The Fuel Operations Facility shall meet all applicable anti-terrorism/force protection (ATFP) requirements in accordance with UFC 4-010-01. [**AM-02]
Tanks, accessories, utility support, tank supports and anchorage, elevated concrete pads, and all features for the new 20,000 gallon De-Icing Fluid storage tank assembly and for the existing 6,000 gallon skid mounted relocated and reinstalled LOX Storage Tank assmbly [*AM-02] assembly [**AM-02] shall be designed and constructed. A second existing 6,000 gallon skid mounted LOX Storage Tank assembly (NIC) shall have have an elevated concrete pad with provisions for anchorage and connection to utilites [*AM-02] utilities [**AM-02] in place to receive the tank.
Coordinate with the COR for additonal [*AM-02] additional inforamtion information . [**AM-02]
Reference the Site Work Requirements for additional information on site demolition.
A groundwater contamination plume lies under portions of the area that make up the Flightline Hangar Campus. See specification section 02 61 13 for additional information. See also the Final Phase I Environmental Site Assessment (ESA) attached to specification section 01 35 29 13 for additional information and vapor intrusion control.
1.3.1 Facility Functions
The Fuel Operations Facility includes administrative offices, a conference room, common area (readiness), and fuels operations spaces such as a Type C++ fuels testing laboratory, fuels lab office, control center, a break room, and associated standard building support spaces such a telecommunications room, mechanical room, electrical room, restrooms, and a janitor's room. The primary functions of the facility are for housing the fuels control center for receiving orders for aircraft refueling and
SECTION 01 81 00 Page 3 service, for testing of jet fuel samples, providing administrative support, fuel operations support, and for storage functions.
The LOX Maintenance Facility includes an open POL office with a laundry area for washer and dryer, a LOX maintenance bay, a cylinder storage cage, along with associated support spaces such a mechanical/electrical room, and toilet rooms. The primary functions include liquid oxygen tanks and cylinders storage, cart storage, equipment, and maintenance of LOX related equipment.
The LOX Storage Canopy is an open sided covered canopy containing liquid oxygen tanks and LOX cart/tank trailers with a drive-through lane beneath the canopy for LOX delivery truck access. Tanks are filled by semi-tanker truck and LOX is despensed [*AM-01] dispensed [**AM-02] to LOX cart assemblies.
The De-Icing Fluid Storage Building/Tank Canopy is an open sided (on three sides) and a covered canopy to protect a 20,000 gallon De-Icing fluid tank, and to provide semi-truck access adjacent to the canopy for filling the De-Icing fluid into the tank. De-Icing fluid is also dispensed into de-icing fluid vehicles for treatment of aircraft near the flightline.
The TACAN Equipment Facility (B568) is an existing 30 feet by 40 feet concrete masonry unit building. The existing building will be demolished in its entirety and replaced with a new 12'-8" by 12'-8" concrete masonry unit buiding [*AM-02] building [**AM-02] and a concrete generator equipment pad. The pad will be designed and constructed to support a new generator and distribution conduit. (See Civil)
Demolish twelve (12) existing buildings totaling approximately 1,244 SM (13,391) SF that are damaged beyond repair [*AM-03], are part of phased demolition associated with new replacement facilities, [**AM-03] and/or in the way of new construction. The Buildings to be demolished are as follows: #389, #393, #496 [*AM-03] including the exterior concrete underground tank assembly and piping that is south of the existing building [**AM-03] , #568, #571, #572, #573, #585, #595, #599, #660, and #683. Demolish also (remove) without replacement 220 LF of fencing at west end of the Flightline Hangars Campus from B517 to existing turnstile.
Demolition of the existing Fuel Operations Facility, existing LOX Maintenance Facility, existing LOX Storage Canopy, and existing De-Icing Fluid Storage Building/Tank Canopy cannot occur until the new replacements for these facilities have been constructed and are fully operational.
1.3.2 Site and Infrastructure Functions
Site improvements include site preparation, associated utilities infrastructure, road realignment, and parking. The planned site for the Flightline Hangars Campus improvements is the same general location as the existing facilities. These facilities all support the flightline and the aircraft, and their location needs to be immediately adjacent to the aircraft and the Flightline.
1.3.3 Project Site
The project is located at Offutt Air Force Base, south of the airfield, SECTION 01 81 00 Page 4 north of Looking Glass Avenue, south and east of the existing Bennie Davis Hangar facility, and integral with the airfield perimeter security fencing. Site location can be found in the drawings provided with this RFP. The finished floor elevations of several of the new facilities will be raised to an elevation at or two feet above the top of the 100-year levees along the adjacent Missouri River and the Papillion Creek. See Section 01 89 00 SITE WORK REQUIREMENTS for additional information.
1.3.4 Base Bid and Bid Option
1.3.4.1 Base Bid
The base bid includes the design and construction of the complete and usable facilities as described in all sections of these specifications, appendices and drawings. See also the Contract Line Item Pricing Schedule.
1.3.4.2 Bid Options
Bid Options are summarized here. See the Contract Line Item Pricing Schedule, discipline specific requirements sections, and drawings for additional information.
1.3.4.2.1 Bid Option - Procure and Install Furniture, Fixtures and Equipment (FF&E) Package. See Section 01 84 00 Interior Design Requirements for additional information.
[*AM-0001] 1.3.4.2.2 Bid Option - Procure and Install a CCTV Package
See the Contract Line Item Pricing Schedule, discipline specific requirements sections, drawings, and Room Data Sheets for additional information
[**AM-0001]
1.3.4.2.3 Bid Option - Procure and Install Infrastructure for Keyless Access Control.
See Section 01 82 00 Architectural Requirements, 01 86 26 Electrical Requirements, 01 86 29 Communications Requirements, and Room data sheets.
[*AM-0001] 1.3.4.2.4 Bid Option - Procure and Install Outside Plant Communication Lines
See the Contract Line Item Pricing Schedule, discipline specific requirements sections, drawings, and Room Data Sheets for additional information
[**AM-0001] 1.3.4.2.5 Bid Option - Procure and Install 0ne (1) new [*AM-0001] 20,000 Gallon [**AM-0001] De-Icing Tank Assembly.
See the Contract Line Item Pricing Schedule, discipline specific requirements sections, drawings, and Room Data Sheets for additional information.
1.4 DESIGN AND CONSTRUCTION REQUIREMENTS
1.4.1 Changes to RFP Criteria Requirements
This Request for Proposal provides requirements expected of the
SECTION 01 81 00 Page 5
Design-Build Contractor during the design and construction of this project.
The RFP bridging documents present an overall design concept of the project; provide useful project information; establish some definition of the systems to be used; and incorporate requirements expected by the Using Service.
It shall be the responsibility of the Design-Build Contractor to assemble the best-value-priced construction systems for this project that meet or exceed the design criteria set forth herein.
Offerors should not consider changes to RFP criteria requirements during proposal preparation. After contract award, any changes to the RFP criteria requirements require approval by the Contracting Officer.
See Section 01 33 00.32 DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES for additional requirements.
1.4.2 Codes and Criteria
All pertinent building codes, life safety codes, and reference criteria shall be met or exceeded. This project utilizes the DoD Building Code, as defined by UFC 1-200-01 and its references.
If there is a conflict in requirements, order of precedence shall be as follows,in order of decreasing precedence:
a. Life Safety, as defined by DoD Building Code UFC 1-200-01 and its references
b. RFP Specifications
c. RFP Drawings
d. Non-life safety criteria, as defined by DoD Building Code UFC 1-200-01 and its references
e. Other criteria as listed herein
1.4.3 Phasing of Work, Security, and Construction Staging
Phasing of the demolition work shall require complete construction of the new Fuel Ops Building, De-Icing Fluid Storage Building/Tank Canopy, LOX Stroage [*AM-01] Storage [**AM-02] Canopy, and the LOX Maintenance Facility before demolition of existing buildings 496 (De-Icing Storage), 571 (Oxygen Maintenance), and 585 (Fuel Operations) can occur.
The Contractor shall maintain a construction area fence throughout the duration of the contract. See Section 01 89 00 SITE WORK REQUIREMENTS for additional information.
See drawings for construction staging areas.
1.4.4 Sustainability
1.4.4.1 Criteria
This project shall at a minimum incorporate high performance and sustainable site and building features as listed in UFC 1-200-02 HIGH
PERFORMANCE AND SUSTAINABLE BUILDING REQUIREMENTS, UFC 3-210-10 LOW IMPACT
DEVELOPMENT, and UFC 3-101-01 ARCHITECTURE as applicable to the project scope.
SECTION 01 81 00 Page 6
1.4.4.2 Total Building Commissioning
Apply total building commissioning principles and fully commission the Fuel Operations facility, in compliance with Section 01 91 00.15 TOTAL BUILDING COMMISSIONING and UFC 1-200-02 . [*AM-03] Commissioning to include coordination with and support for cybersecurity on behalf of Commissioning Agent and Controls Venders. Commissioning Plan shall include implementation of cybersecurity controls and functional testing. [**AM-03]
1.4.4.3 Cybersecurity
All control systems (including systems separate from an energy management control system) shall be planned, designed, acquired, executed, and maintained in accordance with UFC 4-010-06 , and as required by each individual DoD Service's implementation policy. Systems requiring cybersecurity include, but are not limited to, the following:
a. Fire Alarm/Mass Notification Reporting System(s)
b. Building Automation, DDC, and EMCS System(s)
c. Building Lighting System(s) (if networked)
d. Building Electrical System(s)
e. Building Telecommunication System(s)
f. Utility Metering System(s) (advanced meters, AMI, etc.)
g. Building Security Systems
h. Any other building system or component installed which may be networked or is provided with Ethernet, USB, or other ports or analog or digital connections to or through which connections to another electronic device may occur.
See Sections 01 86 10 MECHANICAL REQUIREMENTS, 01 86 26 ELECTRICAL REQUIREMENTS,[*AM-03] 01 86 29 COMMUNICATIONS REQUIREMENTS [**AM-03] and UFC 4-010-06 for additional requirements.
1.4.4.4 Third Party Certification/Validation
The Fuel Operations facility and the LOX Maintenance facility meet applicability requirements for use of UFC 1-200-02, HPSB for third party validation of Guiding Principles and air barrier requirements as indicated in UFC 3-101-01, Architecture. The contractor shall design and construct a project that is 100% compliant with UFC 1-200-02 and Guiding Principles, demonstrated by receiving a "Certificate of Compliance" thru USGBC/GBCI.
Included with this RFP are blank Air Force Sustainability Requirements Scoresheet for each applicable building as a part of this project. The contractor shall complete, maintain and update the Scoresheets, and have the Scoresheets available at any time for auditing and Air Force reporting. At project completion, the Scoresheets should be completely fill out with only "Yes" and "N/A" indicated in the Compliance column. All N/A responses must have justification included. See 01 33 29 SUSTAINABILITY REPORTING for additional requirements.
The contractor shall be responsible for all registration, review and certification/validation fees. The contractor shall provide a LEED AP or equivalent accredited professional. The Guiding Principles registration process can be started by contacting the GBCI via email at GuidingPrinciplesAssessment@gbci.org .
The A-E/Contractor shall coordinate with the Omaha District Resiliency/Sustainability Coordinator Karen Jarvis (402) 995-2176
SECTION 01 81 00 Page 7
[*AM-0002] or another designated point of contact, and the Omaha District Architectural and Interior Design Section Chief Bernard Gorup (402) 995-2167 [**AM-0002] and provide [*AM-0002]her them [**AM-0002] with access to the project directory. The contractor shall make Karen Jarvis [*AM-0002] or another designated point of contact [**AM-0002] a project administrator as a part of project closeout.
1.4.5 Bridging Documents
Conceptual drawings of the site plans, floor plans, and elevations are included for use in developing this design. For information only as-built drawings or record drawings that are available are included as an appendix for information on building demolition. Room data sheets with minimum space and space-type requirements have also been attached as an appendix.
1.4.6 Design and Construction Measurement Units
Design, products, and construction for the project shall be accomplished using English units of measurement. All measurement in the technical specifications sections shall be shown in English.
1.4.7 Personnel Qualifications and Experience
Design and construction personnel qualifications and experience shall be per the requirements of Section 01 33 00.32 DESIGN AND CONSTRUCTION
DELIVERABLES/PROCEDURES.
1.4.8 Design and Construction Deliverables
See Section 01 33 00.32, DESIGN AND CONSTRUCTION DELIVERABLES/PROCEDURES.
1.4.9 Advanced Modeling and Facility Data Requirements
The contractor shall design and construct this project by leveraging BIM, CIM and electronic facility data to the greatest extent practical under the scope of this project. See 01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS for minimum project requirements. This project also requires the development and turnover of electronic facility data (via a Facility Data Workbook (FDW)) to the Government. See
01 78 24.00 10 FACILITY DATA REQUIREMENTS.
1.4.10 Operations and Maintenance Requirements
See Section 01 78 23 OPERATION AND MAINTENANCE DATA for requirements.
PART 2 PRODUCTS
NOT USED
SECTION 01 81 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 86 10
MECHANICAL REQUIREMENTS
PART 1 MECHANICAL REQUIREMENTS
1.1 MECHANICAL SYSTEM CRITERIA
1.1.1 General Parameters/Reference
1.2 EXISTING CONDITIONS
1.3 DEMOLITION
1.4 FACILITY DESCRIPTION
1.5 MECHANICAL SCOPE OF WORK
1.5.1 Mechanical General Requirements
1.5.2 Submittal Requirements
1.5.3 Sustainable Design
1.5.4 Description of Work
1.6 DESIGN CONDITIONS
1.6.1 Site Elevation
1.6.2 Latitude
1.6.3 Longitude
1.6.4 Outside Design Conditions
1.6.5 Inside Design Conditions
1.6.6 Minimum Ventilation Requirements
1.6.7 Cooling Load
1.6.8 Building Heating Load
1.6.9 Noise Levels
1.6.10 Structural
1.6.11 Operation
1.6.12 Mechanical/Electrical Equipment Coordination
1.6.13 Utility Interruption
1.6.14 Spare Parts List
1.7 EQUIPMENT IDENTIFICATION AND ABBREVIATIONS
1.7.1 Abbreviations
1.8 SEISMIC PROTECTION FOR MECHANICAL PIPING, DUCTWORK, AND EQUIPMENT
1.8.1 Piping
1.8.2 Ductwork
1.8.3 Miscellaneous Equipment
1.9 PLUMBING SYSTEM REQUIREMENTS
1.9.1 Pipe Materials
1.9.2 Sanitary Drainage and Vent System
1.9.3 Domestic Water Systems
1.9.4 Meters
1.9.5 Plumbing fixtures
1.9.6 Water Hammer Arresters
1.9.7 Wall Hydrants
1.9.8 Yard Hydrants
1.9.9 Floor Drains
1.10 NATURAL GAS WORK
1.10.1 Exterior Gas Distribution System
1.10.1.1 Service Line Sizing
1.10.1.2 Service Line Materials
1.10.1.3 Gas Service Entrance
SECTION 01 86 10 Page 1
1.10.2 Gas Pipe Sizing
1.10.3 Equipment Connections
1.11 THERMAL INSULATION OF MECHANICAL SYSTEMS
1.11.1 Insulation Covers
1.11.2 Duct Liner
1.12 AIR SUPPLY AND DISTRIBUTION SYSTEM REQUIREMENTS
1.12.1 Equipment Capacities
1.12.2 Outdoor Air Ventilation Rates
1.12.3 Noise Criteria
1.13 VENTILATION AND EXHAUST SYSTEMS
1.13.1 Intake, Relief and Exhaust Requirements
1.13.2 Exhaust Fans
1.13.3 Ceiling Mounted Exhaust Grilles
1.13.4 Ventilation of Battery Charging Areas
1.14 HYDRONIC SYSTEM REQUIREMENTS
1.14.1 Hydronic Piping Requirements
1.14.1.1 Piping Layout
1.14.1.2 Pipe Sizing
1.14.1.3 Pipe Materials
1.14.1.4 Pipe Joints
1.14.1.5 Pipe Expansion
1.14.1.6 Isolation Valves
1.14.1.7 Identification of Piping
1.14.2 Chemical Treatment
1.14.3 Glycol
1.14.4 Chemical Feeder
1.15 Cybersecurity
1.16 BUILDING TEMPERATURE CONTROL SYSTEM
1.16.1 General DDC Requirements
1.16.2 Alarm Monitoring
1.16.3 Stand-Alone Operation
1.16.4 Input / Output Devices
1.16.5 Control Wiring
1.16.6 Control Valves
1.16.7 Control Dampers and Actuators
1.17 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC SYSTEMS
1.17.1 Balancing Firm Qualifications
1.17.2 Balancing, Commissioning and Integration
1.18 COMMISSIONING OF HVAC SYSTEMS
1.18.1 General
1.18.2 Commissioning Firm Qualifications
1.18.3 Checklists
1.18.4 Pre-commissioning Checks
1.18.5 Functional Performance Tests
1.19 OPERATION AND MAINTENANCE REQUIREMENTS
1.19.1 Facility Operation and Maintenance Manuals
1.19.2 Operation and Maintenance Training Course and Manuals
1.20 TECHNICAL SPECIFICATIONS
1.21 BALANCE OF EQUIPMENT AND MATERIALS
PART 2 NOT USED
PART 3 NOT USED
-- End of Section Table of Contents --
SECTION 01 86 10 Page 2
SECTION 01 86 10
MECHANICAL REQUIREMENTS
PART 1 MECHANICAL REQUIREMENTS
1.1 MECHANICAL SYSTEM CRITERIA
1.1.1 General Parameters/Reference
Mechanical systems shall be designed to comply with this section and the documents listed below. The publications are referred to in the text by basic designation only. The latest edition of the following standards and codes in effect and amended as of the date of the supplier's proposal, and any subsections thereof as applicable, shall govern design and selection of equipment and material supplied:
ASSOCIATED AIR BALANCE COUNCIL (AABC)
AABC MN-1 (2002; 6th ed) National Standards for Total System Balance
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI A13.1 (2015) Scheme for the Identification of Piping Systems
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE Handbooks (2016-2019)
ASHRAE 15 (2013) ANSI/ASHRAE Standard 15-Safety Standard for Refrigeration Systems and ANSI/ASHRAE Standard 34-Designation and Safety Classification of Refrigerants
ASHRAE 189.1 (2014) Standard for the Design of High-Performance Green Buildings Except Low-Rise Residential Buildings
ASHRAE 55 (2013) Thermal Environmental Conditions for Human Occupancy
ASHRAE 62.1 (2013) Ventilation for Acceptable Indoor Air Quality
ASHRAE 90.1 (2013) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASME INTERNATIONAL (ASME)
ASME CSD-1 (2016) Control and Safety Devices for Automatically Fired Boilers
SECTION 01 86 10 Page 3
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM D1785 (2012) Standard Specification for Poly(Vinyl Chloride) (PVC), Plastic Pipe, Schedules 40, 80, and 120
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2015) International Building Code
ICC IMC (2015) International Mechanical Code
ICC IPC (2015) International Plumbing Code
ICC IEC (2012) International Energy Code
ICC IGC (2012) International Gas Code
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB-01 (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 54 (2015) National Fuel Gas Code
NFPA 70 (2017) National Electrical Code
NFPA 72 (2016) National Fire Alarm and Signaling Code
NFPA 90A (2015) Standard for the Installation of Air Conditioning and Ventilating Systems
NFPA 90B (2015) Standard for the Installation of Warm Air Heating and Air Conditioning Systems
NFPA 91 (2015) Standard for Exhaust Systems for Air Conveying of Vapors, Gases, Mists and Noncombustible Particulate Solids
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA Guidelines (2007) IAQ Guidelines for Occupied Buildings Under Construction, 2nd Edition
SMACNA 1966 (2005) HVAC Duct Construction Standards Metal and Flexible, 3rd Edition
SECTION 01 86 10 Page 4
U.S. ARMY CORPS OF ENGINEERS (USACE)
ODDG (2014; REV JAN 2015) Omaha District Design Guide for Design Solicitations
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-200-01 (8 October 2019) DOD Building Code
UFC 1-200-02 (2016; Change 04, 01 OCT 2019) High Performance and Sustainable Building Requirements
UFC 3-301-01 (1 October 2019) Structural Engineering
UFC 3-400-02 (20 September 2018) Design: Engineering Weather Data
UFC 3-401-01 (2013; Change 1, OCT 2015) Mechanical Engineering
UFC 3-410-01 (2013; Change 6, 30 March 2020) Heating, Ventilating, and Air Conditioning Systems
UFC 3-410-02 (2018) Direct Digital Control for HVAC and Other Building Control Systems
UFC 3-420-01 (2004; Change 11, 01 NOV 2019) Plumbing Systems
UFC 3-430-01FA (2003) Heating and Cooling Distribution Systems
UFC 3-430-07 (2003; Change 5, 07 MAY 2019) Operations and Maintenance: Inspection and Certification of Boilers and Unfired Pressure Vessels
UFC 4-010-01 (12 December 2018) DoD Minimum Antiterrorism Standards for Buildings
UFC 3-450-01 (2003) Noise and Vibration Control
UFC 3-600-01 (2016; Change 4, 07 FEB 2020) Fire Protection Engineering for Facilities
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
EO 13423 (2007) Strengthening Federal Environmental, Energy, and Transportation Management
PL 109-58 Energy Policy Act of 2005 (EPAct05)
PL 110-140 Energy Independence and Security Act of
SECTION 01 86 10 Page 5
1.2 GENERAL REQUIREMENTS
The mechanical portion of the project primarily consists of the demolition and renovation at Fort Carson, CO. Heating and cooling equipment shall include all required pumps, piping, expansion tanks, and other equipment necessary to provide a complete and operational system. A new dedicated split-system unit will be provided to condition the Communication room.
New LON based Direct Digital Controls shall be provided for all new equipment and shall be connected to the base-wide Utility Monitoring and Control System. Domestic water service and waste lines for all new fixtures and washing machines shall be provided. Existing water piping may be reused but is most likely undersized for the new building function. Verify domestic water service is adequate for the new laundry function of the building and upsize if necessary.
Drawings, specifications, design analysis and calculations shall be provided as required for the 60 percent design and the Final design submittals, and shall be in accordance with Section 01 33 00.36 60 PERCENT DESIGN REQUIREMENTS, and Section 01 33 00.38 100 PERCENT DESIGN
REQUIREMENTS.
The mechanical engineering design and construction of the following systems shall be included:
a. Heating, Ventilation, Exhaust Systems, and Air Conditioning Systems
b. Plumbing Systems
c. Building Management System (DDC Controls for HVAC
d. Operation and Maintenance Requirements
e. Testing
All systems description and performance requirements in this specification indicate the minimum requirements. Calculations shall be performed to determine equipment capacities and sizing.
a. Provide mechanical systems, complete and ready for operation. The design and construction of all mechanical systems, including manufacturer's products, shall meet the instructions and requirements contained herein and the requirements of the referenced technical guide specifications. Where conflicts between these instructions and the guide specifications or above mentioned criteria exist, the most stringent shall take precedence. Any installation requirements within these instructions, but not contained in the specifications, shall be added to the specification or shown on the drawings.
b. The design shall be economical, maintainable, energy efficient and shall take into account the functional requirements and planned life of the facility. Ease of access to components and systems in accordance with industry standards and safe working practices is a design requirement.
c. Standard Products - Material and equipment shall be a standard product of a manufacturer regularly engaged in the manufacture of the product that have been in satisfactory use for at least 2 years prior to bid opening. The label or listing of the Underwriters Laboratories, Inc., will be accepted as evidence that the materials or equipment conform
SECTION 01 86 10 Page 6 to the applicable standards of that agency. In lieu of this label or listing, a statement from a nationally recognized, adequately equipped testing agency indicating that the items have been tested in accordance with required procedures and that the materials and equipment comply with all contract requirements will be accepted.
d. Calculations shall be provided for all new mechanical equipment such as piping, pumps, fans, ducts, unit heaters, domestic water heaters, and cooling units regardless of end use. Heating and cooling calculations for the building must be performed by computer analysis i.e., Elite Software Inc., Trane Trace Load 700, Carrier E20-II Hourly Analysis Program (HAP) etc. Documentation shall include complete input and output summaries.
e. It shall be the responsibility of the Design Build Contractor to assume full responsibility of all final calculations, equipment designs, equipment selections, equipment layouts, and to provide fully operational systems, regardless of whether calculations, equipment designs, equipment selections or equipment layouts where provided as part of the request for proposal.
1.3.1 Facility Description
See Section 01 81 00 for a description of the facility and overall scope of work.
1.3.2 Sustainable Design
The design of the facility shall incorporate and promote sustainable design principles for the built environment, as outlined in UFC 1-200-02
HIGH PERFORMANCE AND SUSTAINABLE BUILDING REQUIREMENTS.
1.3.2 Design Conditions
The following conditions shall be taken into consideration for the design. Location and weather related design information is provided by UFC 3-400-02 , Design: Engineering Weather Data and shall be used in designing the mechanical systems.
1.3.2.1 Site Elevation
Equipment design elevation is 5,870 feet above sea level.
1.3.2.2 Latitude
38.75º North
1.3.2.3 Longitude
104.78º West
1.3.2.4 Outside Design Conditions
Summer Conditions 87ºF dry bulb - 1%
58ºF MCWB - 1%
Mean Daily Range 26.1ºF dry bulb
SECTION 01 86 10 Page 7
Winter Conditions -2ºF dry bulb - 99.6%
9ºF MCWB - 99%
Cooling Degree Days 2312 Note: CDD50
Heating Degree Days 6415 Note: HDD65
1.3.2.5 Inside Design Conditions
Space Temperature Requirement Humidity Requirement
Occupied Areas 70 F dry bulb - heating
Comm Room 72 F - year round
1.3.2.6 Minimum Ventilation Requirements
All normally occupied spaces shall be mechanically ventilated in accordance with ASHRAE 62.1 -2013.
1.3.2.7 Cooling Load
Per load calculations. Coordinate with Electrical Designer.
1.3.2.8 Building Heating Load
Per load calculations.
1.3.2.9 Noise Levels
Noise levels shall remain within acceptable criteria as defined by
UFC 3-450-01 .
1.3.2.12 Structural
Attach interior ceiling mounted fixtures to the supporting structural system (i.e., use seismic detailing from UFC 1-200-01 and UFC 3-310-04 ) in structures. This includes mechanical equipment, ducting, and piping.
Equipment and piping requiring structural support shall be located in such
SECTION 01 86 10 Page 8 a way to minimize support steel costs while providing adequate maintenance access.
1.3.5 Operation
The system shall be designed to operate automatically year round, twenty four (24) hours per day, seven (7) days per week. Equipment and systems shall be designed for remote operation.
1.3.11 Mechanical/Electrical Equipment Coordination
Arrangement of all mechanical equipment ductwork and piping shall be coordinated with electrical work to prevent interference with electrical conduits. Electrical conduits and mechanical piping and ductwork shall not restrict access to the mechanical equipment for maintenance or repair.
Clearances required by NFPA 70 above and in front and above of electrical panels and devices shall be maintained. Mechanical equipment (pipes, ducts, etc.) shall not be installed OVER OR WITHIN SPACE which is dedicated to transformers, panels, panelboards, or other electrical equipment unless items solely serve the area and the installation meets all applicable codes. When electrical equipment is located in a mechanical equipment space, the dedicated electrical space shall be indicated by a dashed line and noted "Electrical Equipment Space".
1.3.13 HVAC Control Instrumentation
Control instrumentation shall adhere to UFC 3-410-02 and the ODDG with Fort Carson provisions.
1.3.14 Utility Interruptions
Certain limitations on utility interruptions apply. Unauthorized utility interruptions will not be permitted. Any work that requires a utility interruption shall be scheduled in advance. Outages are subject to postponement or cancellation by site authorities without prior notification. Coordination requirements of utility interruptions shall be in accordance with Document 00 73 00 SPECIAL CONTRACT REQUIREMENTS. All utility interruptions shall be identified with notes on the project drawings.
1.3.15 Spare Parts Lists
Proprietary spare parts lists that require more than a 60 day lead time, and/or any special service tools shall be provided to the Government prior to acceptance of the system.
1.7 EQUIPMENT IDENTIFICATION AND ABBREVIATIONS
This section contains requirements for the identification and abbreviation of mechanical equipment.
1.7.1 Abbreviations
The following list of abbreviations shall be used to describe the mechanical equipment types:
Air-Cooled Condensing Unit CU
SECTION 01 86 10 Page 9
Air Filter AF
Air Handling Unit AC
Air Separator AS
Airflow Measuring Station AFS
Building Automation System BAS
Boiler BLR
Cabinet Unit Heater CUH
Exhaust Fan EF
Expansion Tank ET
Control Valve CV
Diffuser D
Domestic Hot Water DHW
Gov't Furnished Design Build Contractor Installed GFCI
Gov't Furnished Gov't Installed GFGI
Grille G
Heating Coil HC
Heating Hot Water HW
Intake Hood IH
Local Control Panel LCP
Louver L
Motor Operated Damper MOD
Heating Water Pump HWP
Boiler Pump BP
Register R
Supply Fan SF
Unit Heater UH
Utility Monitoring and Control System UMCS
The proposal shall indicate any abbreviations to be used for mechanical equipment not listed.
1.6 IDENTIFICATION OF PIPING
All .
1.58 SEISMIC PROTECTION FOR MECHANICAL PIPING, DUCTWORK, AND EQUIPMENT
Structural bracing and mounting of mechanical piping, ductwork, and equipment shall be designed in accordance with UFC 1-200-01 , UFC 3-310-04 , and the ODDG.
SECTION 01 86 10 Page 10
1.8.1 Piping
Piping within the facility, except fire protection piping, is required to have seismic restraints complying with UFC 1-200-01 and UFC 3-310-04 .
1.8.2 Ductwork
Ductwork within the facility is required to have seismic restraints complying with UFC 1-200-01 and UFC 3-310-04 .
1.8.3 Miscellaneous Equipment
Miscellaneous items which consist of a number of individual components built into an assembly by the manufacturers may require additional internal reinforcements to meet the requirements of UFC 1-200-01 and
UFC 3-310-04 .
1.9 THERMAL INSULATION OF MECHANICAL SYSTEMS
Insulation of hydronic water piping systems and equipment, refrigeration lines and equipment, and the insulation of the duct systems shall meet the more stringent of ASHRAE 189.1 , UFGS 23 07 00, and the ODDG.
Refrigeration and hydronic water piping shall be required to follow tabulated thicknesses.
1.9.1 Insulation Covers
Provide removable and reusable insulation covers at all check valves, control valves, strainers, filters, or any other piping component requiring access for routine maintenance. Exposed exterior insulation shall be covered by an embossed aluminum metal jacket. All piping with metal jacket shall be identified on the drawings.
1.7 HVAC DEMOLITION
Mechanical equipment including all HVAC air handlers, ductwork, diffusers and grilles, and piping are to be removed. See the HVAC Demolition drawings attached to this RFP for the current HVAC layout and equipment locations.
1.14 HVAC SYSTEM DESIGN
The HVAC system shall be designed and built to satisfy the thermal and indoor air quality requirements of building 2255. This includes all associated air distribution equipment, thermal conditioning and ancillary equipment. Provide a complete system.
1.14.4 HVAC Systems
After the demolition and removal of the HVAC equipment in building 2255, a new air handler system shall be provided. Air handlers shall be provided with prefilters and final filters. Final filter shall be MERV-13 rated.
Spaces served by the air handler shall be positively pressurized to exclude infiltration of dust and unconditioned air. New ductwork shall be provided after the removal of all existing ductwork. New aluminum or galvanized steel diffusers, registers, and grilles shall be provided.
SECTION 01 86 10 Page 11
The district chilled water shall be utilized as the cooling source for building 2255 if possible. Chilled water piping shall be provided along with all required equipment, pumps, valves, and other equipment and instruments to provide a functional and properly operating system. If connection to the existing chilled water is not possible or cost effective, an air cooled condensing unit will be used as the cooling source. The condensing unit will be located outside the building on a concrete equipment pad.
District High Temp Hot Water is available and capped near the building entrance. The water is approximately 400 degrees F and 300 PSI, a shell and tube heat exchanger will be required to reduce the temperature for building service. Heating water piping shall be provided along with all required equipment, pumps, valves, and other equipment and instruments to provide a functional and properly operating system. A split-system heat pump will be provided for the Communications Room. The indoor unit will be located as to not interfere with the comm equipment in the room or it's required clear space. The heat pump shall be sized for the anticipated heating and cooling load and shall be capable of year-round operation.
The domestic water heater shall utilize the district hot water as a heating source.
New Direct Digital Controls shall be provided for all new HVAC systems and equipment. All systems shall be capable of being monitored and controlled by the Installation wide UMCS through a connection to the building system.
1.15 VENTILATION AND EXHAUST SYSTEMS
The design of all systems shall comply with the ASHRAE Handbooks , ASHRAE Standard 62.1, NFPA 90A, NFPA 90B, and NFPA 91 , and shall meet the requirements of the ODDG. Ventilation cooling shall only be utilized if interior temperature exceeds exterior temperature except in instances when continuous exhaust/ventilation is required by code.
1.15.2 Intake, Relief and Exhaust Requirements
Outside air intakes shall be located in areas where potential for air contamination is lowest, and shall be located at least 10 feet above the adjacent finished grade. Motorized insulated low-leakage dampers with blade and jamb seals shall be provided at all outside air intake and exhausts. The maximum leakage rate permitted for outside air intakes shall be based upon UFC 3-410-01 . Louvers shall be of the storm/drainable type and shall be AMCA certified. Louvers shall be selected based on the following criteria: maximum free area face velocity of 800 feet/min;
maximum pressure drop of 0.1 in W.C.; and a water penetration of less than
0.01 oz/square foot.
1.16 TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS
Testing, adjusting, and balancing shall meet the requirements of the ODDG. The work required by this Section shall be complete, including all test and inspection reports, before starting the commissioning functional testing.
1.16.1 Balancing Firm Qualifications
TAB shall be performed by an independent firm, hired directly by the Design Build Contractor only, using certified technicians under the direct supervision of a registered engineer. Technicians shall be certified by the National Environmental Balancing Bureau (NEBB) or the Associated Air
SECTION 01 86 10 Page 12
Balance Council (AABC). The firm shall select AABC MN-1 or NEBB-01 as the standard for providing TAB of the mechanical systems.
1.12.2 Balancing, Commissioning and Integration
Design Build Contractor shall include additional time required for full balancing and commissioning once the construction of all systems are complete. Commissioning shall meet the requirements of UFC 1-200-02 and other applicable criteria.
1.17 BUILDING TEMPERATURE CONTROL SYSTEM
The instrumentation and control shall meet the requirements of UFC 3-410-02 , the ODDG with Fort Carson provisions, follow LonMARK International standards and be fully integrated with the existing Installation wide UMCS. The equipment shall be monitored and controlled through the Installation wide UMCS. System integration shall include developing interfaces for each piece of equipment and provide a graphical representation of the equipment and control menu screen. Historical data for equipment, buildings, and systems shall be stored for use in determining system maintenance and equipment operation. System integration shall include developing algorithms, analog, and discrete logic to fully automate the starting and stopping of all system equipment. The logic shall also provide for manual operator override, set point adjustments, and control loop adjustments. Provide a temperature sensor for the mechanical room that is connected to the building automation control system. The sensor shall send an alarm when the temperature drops below 40 degrees Fahrenheit or exceeds 90 degrees Fahrenheit. The alarm shall be programmed to send an alarm to the installation wide UMCS system.
1.17.1 Controls Equipment
Packaged equipment shall be provided with dedicated controls that shall interface to the building control system through communication links (Lonworks). The Design Build Contractor shall provide as many control cabinets as required for a complete design. Provide new cable, conduit and switches as necessary for a complete system. HVAC control system panels shall be provided in the mechanical equipment room; the number and size of panels shall be dictated by the equipment to be installed in the panels.
The Design Build Contractor shall develop and integrate automated algorithms in the control system which will select equipment for operation based on the load, daily environmental conditions, time of day, day of week, and building load requirements. The equipment selection shall be based on the most economical and efficient to meet the system load requirements.
1.13.2 Controls Commissioning and Integration
Design Build Contractor shall include additional time required for full controls integration and commissioning. 1.19 OPERATION AND MAINTENANCE
REQUIREMENTS
Facility Operation and Maintenance (O&M) Manuals, including associated Training Course and Training Manuals, shall be provided for the mechanical systems and shall meet the requirements of the individual Unified Facilities Guide Specifications (UFGS) Sections.
SECTION 01 86 10 Page 13
1.19.1 Facility Operation and Maintenance Manuals
The intent of the O&M Manuals is to promote and maximize the efficiency, economy, safety, and effectiveness of the life cycle operation, maintenance, and repair of the facility. Comprehensive, self-contained manuals shall include all of the identified building's interior systems, plus the exterior portions of systems that support the building.