Am_0001.pdf

PDF 1 MB Posted

Attached to
Physical Fitness Facility at Fort Carson, Colorado
Solicitation number
W9128F21R0002
Issued by

About this file

This solicitation is for the construction of a Physical Fitness Facility at Fort Carson, Colorado. The solicitation is seeking bids for the construction of the facility including sitework. Bids are due by 1400 hours on April 5, 2021. The solicitation includes pricing schedules for basic construction items and optional items such as furniture, fixtures, equipment, and audiovisual equipment. The contractor must begin work within 10 calendar days of award and complete it within 540 calendar days. The solicitation is unrestricted and open to both large and small businesses.

View the file

Other files

File Type Posted
Am_0005.pdf PDF
Am_0004.pdf PDF
Am_0003.pdf PDF
Am_0002.pdf PDF
Am_0002-Drawings.pdf PDF
Am_0001-Drawings.pdf PDF
Drawings FCDY ADVERTISEMENT.PDF PDF
W9128F-21-R-0002-FCDY_Specs.pdf PDF
General Decision Number_CO20210022.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment No.0001 W9128F

PHYSICAL FITNESS FACILITY, PN058139

FORT CARSON, COLORADO

See attached documentation for content of the amendment revisions to solicitation.

Date for receipt of proposals is 5 APR 2021 at 1400 hours

Government Point of Contact: Bill Rawe, Contract Specialist, William.T.Rawe@usace.army.mil_

U.S ARMY CORPS OF ENGINEERS, OMAHA DISTRICT

CONTRACTING OFFICE

5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919

See Item 6

W9128F-21-R-0002

03/25/2021

03/04/2021

03/25/2021

Am #0001 - 2 (Continuation of SF 30)

DEPARTMENT OF THE ARMY

Omaha District, Corps of Engineers

1616 Capitol Avenue Omaha, Nebraska 68102-4901

:NOTICE: Failure to acknowledge : Solicitation No. W9128F-21-R-0002 :all amendments may cause rejec-:

:tion of the bid. See FAR : Date of Issue: 4 MAR 2021 :52.214-3 of Section 00 21 00. : Date of Opening:

5 APR 2021

Amendment No. 0001

25 MAR 2021

SUBJECT: Amendment No. 0001 to Specifications and Drawings for Design and Construction of PHYSICAL FITNESS FACILITY AT FORT CARSON, COLORADO

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages as noted below. The substituted pages are revised and reissued with this amendment. Sections should have changes tracked within them but all language shall apply regardless of the accuracy of this effort.

Pages Deleted Pages Substituted or Added 00 10 00 00 10 00 01 30 00.24 01 30 00.24 02 41 00 02 41 00 03 45 00 03 45 00 08 71 00 08 71 00

b. Drawings (Reissued). The following drawings are revised, with revision date(s) indicated in the title block(s), and reissued with this amendment.

(1) Sheet FCDYA-201, BUILDING AREA ELEVATIONS,

(2) Sheet FCDYA-300, COMPOSITE BUILDING SECTIONS

(3) Sheet FCDYA-600, ROOM FINISH SCHEDULE

(4) Sheet FCDYAE200, PRECAST CONCRETE PANEL ELEVATIONS

(5) Sheet FCDYAE201, PRECAST CONCRETE PANEL ELEVATIONS

(6) Sheet FCDYAE202, PRECAST CONCRETE PANEL ELEVATIONS

(7) Sheet FCDYAE203, PRECAST CONCRETE PANEL ELEVATIONS

(8) Sheet FCDYAE210, TYPICAL PRECAST FINISHING ELEVATIONS AND

DETAILS

Am #0001 - 3 (Continuation of SF 30)

(9) Sheet FCDYF-113, FIRST FLOOR LIFE SAFETY PLAN – AREA C

2. This amendment is a part of the bidding papers and its receipt shall be acknowledged on the Standard Form 1442. All other conditions and requirements of the specifications remain unchanged.

3. Bids will be received until 2:00 p.m., local time at place of bid opening, 5 APR 2021.

Attachments:

Specification Pages listed in 1.a., above Drawings listed in 1.b., above (under separate cover)

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

25 MAR 2021

jlb/2099

00 10 00 - 1

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

W9128F-21-R-0002

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

4 MAR 2021

PAGES OF PAGES

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

7. ISSUED BY CODE CT 8. ADDRESS OFFER TO

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Contracting Division (CENWO-CT-M) 5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Attn: CONTRACTING DIVISION (CENWO-CT-M) 5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919

9. FOR INFORMATION

E-MAIL:

A. NAME

Bill Rawe

B. E-MAIL ADDRESS

william.t.rawe@usace.army.mil

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

The offeror hereby agrees to do all work described in the documents entitled:

PHYSICAL FITNESS FACILITY

PN058139 (FY21)

FORT CARSON, COLORADO

RETURN WITH OFFER: INFORMATION REQUIRED BY SECTION 00 10 00 (SF1442 AND CLIN PRICING SCHEDULE)

THIS SOLICITATION IS UNRESTRICTED AND OPEN TO BOTH LARGE AND SMALL BUSINESS PARTICIPATION.

11. The Contractor shall begin performance within 10 calendar days and complete it within 540* calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (* - See notes below 00 10 00-3 CLIN Pricing Schedule)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and *See Block 10 copies to perform the work required are due at the place specified in Item 8 by 1400 (hour) local time 5 APR 2021. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than ___90_____ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442(REV. 4-85)

Prescribed by GSA FAR(48 CFR) 53.236-1(d)

Am_0001

00 10 00 - 2

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

DUNS Number:

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within 90 calendar days after the date offers are due.

AMOUNTS

SEE ATTACHED CLIN PRICING SCHEDULE

Contractor’s Fax No. CAGE CODE Contractor’s E-Mail address

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

U.S. Army Engineer District, Omaha 1616 Capitol Ave.

Omaha, Nebraska 68102-4901

USAED Omaha c/o USACE Finance Center 5722 Integrity Drive Millington, TN 38054-5005

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (contractor is required to sign this document and return _______ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,

(b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation, is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

STANDARD FORM 1442 BACK (REV. 4-85)

PRICING SCHEDULE

ITEM

NO.

DESCRIPTION ESIMATED

QUANTITY

UNIT UNIT

PRICE

ESTIMATED AMOUNT

BASIC ITEMS

Entire work complete to Construct Physical Fitness Facility, extending to 5’ outside the building

(MILCON)

Job

XXX

complete to Construct Sitework, from the 5’ line outside the PFF to the limits of construction

(MILCON)

TOTAL BASIC AMOUNT (ITEMS 0001 AND 0002) $_____________________________

OPTION ITEMS

[Option]

Procure and Install Furniture, Fixtures, and Equipment package (OMA)

0004000

Procure and Install A/V

(OMA)

0005000

Procure and Install ESS

(OMA)

TOTAL AMOUNT OPTIONS (ITEMS 0003 THRU 00050004) $_________________________________

TOTAL AMOUNT BASIC PLUS OPTIONS (ITEMS 0001 THRU 00050004)

Proposed period of performance: _______ days

NOTES:

1. See 00 21 00, INSTRUCTIONS TO OFFERORS for evaluation of options. The Government reserves the right to exercise the options at any time during the period of performance for this project.

2. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. In case of variation between the Job (lump-sum) prices and the total amount, the Job (lump-sum) prices will be considered the price submitted. In case of variation between the unit prices and the extensions, the unit prices will be considered the price submitted.

3. A modification to a proposal which provides for a single adjustment to the total amounts, should state the application of the adjustment to each respective Job (lump-sum) price and unit price affected. If the modification is not so apportioned, the single adjustment will be applied to Item No. 0001.

Physical Fitness Facility FCDY

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00.24

OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS

07/20

PART 1 GENERAL

1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING

CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR

PAYROLLS

1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.4 COMPLETION OF WORK

1.5 CONTRACTOR PERFORMANCE EVALUATIONS

1.6 MANPOWER REPORTING

1.7 LIQUIDATED DAMAGES-CONSTRUCTION

1.8 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS

1.9 GENERAL REQUIREMENTS

1.10 CONTRACT DRAWINGS AND SPECIFICATIONS

1.10.1 SETS FURNISHED

1.10.2 DISTRIBUTION

1.10.3 NOTIFICATION OF DISCREPANCIES

1.10.4 OMISSIONS

1.11 SUBMITTALS

1.12 CONCURRENT CONSTRUCTION

1.13 PAYMENT

1.13.1 PROMPT PAYMENT ACT

1.13.2 PAYMENT FOR MATERIALS DELIVERED OFFSITE

1.13.3 PAYMENTS FOR SPECIAL MECHANICAL, ELECTRICAL AND ENVIRONMENTAL

SYSTEMS

1.13.4 CONTRACTOR PAYROLL RECORD

1.14 AVAILABILITY OF UTILITY SERVICES

1.15 UTILITY SERVICE INTERRUPTIONS

1.15.1 Advance Notice

1.15.2 Overtime Work by Base Operating and Maintenance (O&M)

Personnel

1.15.3 Buried Utilities

1.16 DIGGING PERMITS AND ROAD CLOSINGS

1.17 QUANTITY SURVEYS

1.18 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS

1.19 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.20 INSURANCE REQUIRED

1.21 SECURITY REQUIREMENTS

1.21.1 Contractor's Employee Identification

1.21.2 Fort Carson Entry Requirements

1.21.2.1 AT/OPSEC

1.21.2.2 Real ID Act

1.21.2.3 Foreign Nationals (FN)

1.21.3 Fort Carson Installation Access Control Card

1.21.4 Visitor Day Pass

SECTION 01 30 00.24 Page 1

1.21.5 Vehicle Registration Requirements and Documentation

1.21.5.1 General Requirements

1.21.5.2 Authorized Access Points (Cantonment Area)

1.21.5.2.1 Commercial Vehicle Access

1.21.5.3 Types of Vehicles

1.21.5.4 Motor Vehicle Operator Access Documentation

1.22 CONTRACTOR QUALITY CONTROL (CQC)

1.23 NONDOMESTIC CONSTRUCTION MATERIALS

1.24 DAILY WORK SCHEDULES AND WEEKLY COORDINATION MEETINGS

1.25 AS-BUILT DRAWINGS

1.26 SIGN

1.27 EQUIPMENT ROOM DRAWINGS

1.28 CONTRACTOR FURNISHED EQUIPMENT DATA

1.29 PARTNERING

1.30 PROFIT

1.31 LABOR CONDITIONS APPLICABLE TO TEMPORARY FACILITIES

1.32 DRAWING SCALES

1.33 WAGE RATE APPLICATION

1.34 FEDERAL HOLIDAYS

1.35 BASE HOURS

1.36 COST AND TIME IMPACT (CTI) LOG

PART 2 NOT USED

PART 3 EXECUTION

3.1 APPENDIX A- CONTRACT DOCUMENT DISTRIBUTION LIST

ATTACHMENTS:

Appendix A - Contract Document Distribution List

Utility Outage Guidance: FC Reg 420-19 and Request Form: FC FORM 420-E

Project Sign Details

General Wage Decision No. CO20210022

-- End of Section Table of Contents --

SECTION 01 30 00.24 Page 2

SECTION 01 30 00.24

OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS

07/20

PART 1 GENERAL

Attachments:

Appendix A - Contract Document Distribution List Utility Outage Guidance: FC Reg 420-19 and Request Form: FC FORM 420-E Project Sign Details General Wage Decision No. CO20210022

1.1 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

In accordance with FAR 31.105(d)(2)(i)(b), for the predetermined schedule of construction equipment use rates, use Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule. Copies of each regional schedule may be obtained through the following internet site:

https://www.publications.usace.army.mil/USACE-Publications/Engineer-Pamphlets/ on pages 10 and 11 of 13.

1.2 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING

CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR PAYROLLS

a. The Contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Wage Rate Requirements statute.

b.The Contractor is responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Wage Rate Requirements statute. When the Contractor uses an electronic payroll system, use the electronic payroll service used by the Contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract. The electronic payroll service must be capable of preserving these payrolls and related basic records for the required three years after contract completion. The Contractor must obtain and provide electronic system access to the Government, as required to comply with the Wage Rate Requirements over the duration of the construction contract.

SECTION 01 30 00.24 Page 3

(c) The Contractor's provision and use of an electronic payroll processing system must meet the following basic functional criteria:

(1) commercially available;

(2) compliant with appropriate Wage Rate Requirements statute payroll provisions in the FAR;

(3) able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;

(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be imported into the contractor's mode of Resident Management System 3.0;

(5) demonstrated security of data and data entry rights;

(6) ability to produce Contractor-certified electronic versions of weekly payroll data;

(7) ability to identify erroneous entries and track the data/time of all versions of the certified Wage Rate Requirements statute payrolls submitted to the government over the life of the contract;

(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system must be provided to the Government during contract closeout.

d. All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service must be included in the Contractor's price for the overall work under the contract. The costs for compliance with the Wage Rate Requirements statute by using electronic payroll processing services must not be a separately bid or reimbursed item under this contract.

1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

- U.S. Department of Labor Veterans’ Employment and Training Service

(VETS):

https://www.dol.gov/vets/

- Federal Veteran Employment Information: https://www.fedshirevets.gov/

- Veterans Opportunity to Work (VOW) Program:

https://www.benefits.va.gov/vow/

- U.S. Army Warrior Transition Command Employment Index:

SECTION 01 30 00.24 Page 4 https://wct.army.mil/modules/employers/index.html

- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes

1.4 COMPLETION OF WORK

See Section 00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT

REQUIREMENTS), FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984).

1.5 CONTRACTOR PERFORMANCE EVALUATIONS

Federal Acquisition Regulation (FAR) Subpart 36.201(Evaluation of Contractor Performance) requires evaluation of the construction contractor's performance throughout the contract period of performance.

For construction contracts valued at or above $700,000.00, including all modifications, the USACE will evaluate Contractor's performance using the web-based Contractors Performance Assessment Reporting System (CPARS).

After the USACE drafts an evaluation (interim or final), the Contractor will have the opportunity to access, review, comment and either concur or non-concur with the evaluation in the CPARS system for a period of 60 days. Access to the CPARS system requires either specific software called PKI certification (recommended method) or a username and password. The PKI certification is a Department of Defense recommendation and to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and may be purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and contacting vendors can be found on the web site: https://www.cpars.gov .

1.6 MANPOWER REPORTING

Contractors may direct technical questions to the "Send an Email" link at website or email contractormanpower@hqda.army.mil for current information on CMRA. Information regarding changes to the reporting process, when data should be entered, general policy information, how data is protected, and how to enter certain data can be found under the Frequently Asked Questions (FAQ) section at the CMRA website. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013.

The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor will report ALL contractor manpower (including subcontractor manpower) required for performance of this contract. The contractor is required to completely fill in all the information in the format using the following web address: https://ecmra.mil (https://cmra.army.mil). The required information includes: (1) Contracting Office, Contracting Officer, Contracting Officer's Technical Representative; (2) Contract number, including task and delivery order number; (3) Beginning and end dates covered by reporting period; (4) Contractor name, address, phone number, e-mail address, identity of contractor employee entering data; (5) Estimated direct labor hours (including sub-contractor); (6) Estimated direct labor dollars paid this reporting period (including sub-contractor); (7) Total payments (including

SECTION 01 30 00.24 Page 5 subcontractor); (8) Predominant Federal Service Code(FSC) reflecting services provided by contractor (and separate predominant FSC for each sub-contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the contractor with its UIC for the purposes of reporting this information; (11) Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and nearest City, Country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and, (13) Number of contractor and sub-contractor employees deployed in theater this reporting period (by country). As part of its submission, the contractor will also provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. "*

*Note: Information from the secure web site is considered to be proprietary in nature when the contract number and contractor identity are associated with the direct labor hours and direct labor dollars. At no time will any data be released to the public with the contractor name and contract number associated with the data. For internal Army analysis, the reports and queries from the database shall not contain proprietary data.

1.7 LIQUIDATED DAMAGES-CONSTRUCTION

See Section 00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT

REQUIREMENTS), FAR 52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION (SEPT 2000).

1.8 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS

1. AT Level I Training

All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.

2. Access and General Protection/Security Policy and Procedures

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity

SECTION 01 30 00.24 Page 6

Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

2b. for Contractors Who Do Not Require CAC, But Require Access To A Dod Facility Or Installation

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3. Not Used

4. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something)

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

5. Contractor Employees Who Require Access to Government Information Systems.

Not Applicable

6. OPSEC Standing Operating Procedure/Plan

Not Applicable

7. OPSEC Training

All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training.

OPSEC awareness training is available at the following websites:

https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.

8. Information Assurance (IA)/Information Technology (IT) Training

SECTION 01 30 00.24 Page 7

Not Applicable

9. Information Assurance (IA)/Information Technology (IT) Certification

Not Applicable

10. Not Used

11. Not Used

12. Handling or Access to Classified Information.

Not Applicable

13. Will be Escorted in Areas Where They May be Exposed to Classified and/or Sensitive Materials and/or Sensitive or Restricted Areas

If applicable, all contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

14. Contractor Company to Obtain a Facility Clearance and Individual Clearances at the Appropriate Level

The Prime Contractor Company must have (or will have) a Facility Clearance (FCL) at the appropriate level (IAW the NISPOM DOD 5220.22-M and AR 380-49) prior to the start of the contract awarded period of performance.

Contractor personnel performing work under this contract must have the required security clearance, per AR 380-67, at the appropriate level at the start of the period of performance. Security Clearances and FCL requirements are required to be maintained for the life of the contract IAW the DD254 attached to the contract. If no FCL, the supporting Government Contracting Activity will sponsor the prime contract company in obtaining the FCL.

15. Pre-Screen Candidates using E-Verify Program

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

16. Required Armed Security Guards

Not Applicable

17. Threat Awareness Reporting Program (TARP) Training

All new contractor employees will complete annual Threat Awareness and Reporting Program (TARP) Training provided by a Counterintelligence Agent, IAW AR 381-12 . The contractor shall submit certificates of completion for each affected contractor and subcontractor employee(s) or a memorandum for the record, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. Authorized webbased TARP training for CAC card holders is available at the following website: https://www.us.army.mil/suite/page/655474

SECTION 01 30 00.24 Page 8

1.9 GENERAL REQUIREMENTS

Record of Non-Applicability (RONA) or Information Required for General Conformity Review must be completed before project commencement. The Information Required for General Conformity Review Document is enclosed.

1.10 CONTRACT DRAWINGS AND SPECIFICATIONS

1.10.1 SETS FURNISHED

Utilize the bid drawings and specifications as amended in the performance of the work until the electronic Adobe Acrobat.pdf conformed specifications and contract drawings (i.e., bid drawings that have been posted with all amendment changes) are sent electronically to the Contractor. See paragraph below for contract drawing distribution requirements. The work must conform to the contract drawings, set out in the drawing index, all of which form a part of these specifications. The work must also conform to any of the standard details bound or referenced herein.

1.10.2 DISTRIBUTION

The Government will process no progress payments prior to distribution of electronic contract drawings and conformed specification sets by the Government. The Government will provide the Contractor with a CD-ROM or DVD-ROM or sent electronically containing Adobe Acrobat .pdf contract drawings and conformed specification sets and editable CAD file drawings (format defined in Section 01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS. Prepare final record or as-built drawings as defined in Section 01 33 39.00 10 ADVANCED MODELING

(BIM/CIM/GIS/CAD) REQUIREMENTS.

1.10.3 NOTIFICATION OF DISCREPANCIES

Check all electronically sent drawing files furnished by the government immediately upon their receipt and promptly notify the Contracting Officer of any discrepancies. Follow dimensions marked on drawings in lieu of scale measurements. Enlarged plans and details govern where the same work is shown at smaller scales. All scales shown are based on a standard drawing size of 22" x 34". If any other size drawings are furnished or plotted adjust the scales accordingly. The Contractor must also advise his sub-contractors of the above. The Contractor must compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.

1.10.4 OMISSIONS

Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, does not relieve the Contractor from performing such omitted or misdescribed details of the work but work must be performed as if fully and correctly set forth and described in the drawings and specifications.

SECTION 01 30 00.24 Page 9

1.11 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit items below in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Equipment Room Drawings; G-RO.

1.12 CONCURRENT CONSTRUCTION

Construction work closely related to and/or located at the site of the work under a concurrent contract, may be in progress simultaneously with work under this contract. Cooperate with others as necessary in the interest of timely completion of all work. In the event of interference, notify the Contracting Officer (CO) immediately for resolution and the CO decision is final.

1.13 PAYMENT

1.13.1 PROMPT PAYMENT ACT

Pay requests authorized in GENERAL CONDITIONS (CONTRACT CLAUSES) clause:

"Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause, "Prompt Payment for Construction Contracts". Submit pay requests on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation". All information and substantiation required by the identified contract clauses must be submitted with the ENG Form 93, and the required certification included on the last page of the ENG Form 93a, signed by an authorized contractor official and dated when signed. The designated billing office is the Office of the Area Engineer.

1.13.2 PAYMENT FOR MATERIALS DELIVERED OFFSITE

a. Pursuant to Federal Acquisition Regulation (FAR) 52.232-5, Payments Under Fixed Price Construction Contracts, materials delivered to the contractor at locations other than the site of the work may be taken into consideration in making payments, if included in payment estimates and if all the conditions of the General Provisions are fulfilled. Payment for items delivered to locations other than the work site are limited to:

(1) Materials required by the technical provisions; or

(2) Materials that have been fabricated to the point where they are identifiable to an item of work required under this contract; or

SECTION 01 30 00.24 Page 10

(3) Items specifically listed below in paragraph b.

b. Payment for materials delivered off-site must be made only after receipt of paid invoices listing the value of material and labor incorporated in the items along with a canceled check showing the prime contractor's title to the items delivered off site. Payment for materials delivered off-site must be limited to the following items: [List specific material items to be considered for payment when off-site delivery is made].

1.13.3 PAYMENTS FOR SPECIAL MECHANICAL, ELECTRICAL AND ENVIRONMENTAL

SYSTEMS

In accordance with the clause "Payment Under Fixed - Price Construction Contracts" which provides for progress payments on estimates of work accomplished which meets the standards of quality established under the contract, $_______________ will be withheld from payment for the purchase, installation and testing of _______________ system until all specified performance tests for the _______________ system are successfully completed including any necessary corrections/replacements.

1.13.4 CONTRACTOR PAYROLL RECORD

Contractor is required to log payrolls for all their own employees and subcontractors utilizing ENG Form 3180. Each subcontractor requires a separate ENG 3180 for their payrolls. The Contractor must maintain the ENG 3180, along with the payrolls, on site and available for review by the Contracting Officer's Representative. Update the ENG 3180's weekly as payrolls are submitted. After making copies for their files, the Contractor is required to submit the originals of each week’s payrolls to the Resident Office. Before final payment, provide the completed ENG 3180’s to the Contracting Officer's Representatives. If the Contractor has elected to use an electronic payroll system, as described in paragraph

CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING

CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE CERTIFIED LABOR PAYROLLS, the payroll inventory produced by the electronic payroll system will satisfy the requirements in this paragraph and FAR 52.222-8, Payrolls and Basic Records.

1.14 AVAILABILITY OF UTILITY SERVICES

All reasonably required amounts of domestic water and electricity will be made available to the Contractor by the Government from existing system outlets and supplies. The Contractor is reponsible to , at their own expense, make all temporary connections and install distribution lines.

Furnish to the Contracting Officer a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. Make arrangements with the Using Service, through the Contracting Officer, as to the method of determining the amount of water and electricity to be used by and the method of payment therefore. All temporary lines must be maintainedin a workmanlike manner satisfactory to the Contracting Officer and removed by the Contractor in like manner prior to final acceptance of the construction. Normal quantities of electricity and water used to make final tests of completely installed systems will be furnished by the Government.

1.15 UTILITY SERVICE INTERRUPTIONS

Submit written notification not less than 15 calendar days in advance of each interruption of each utility and communication service to or within

SECTION 01 30 00.24 Page 11 existing buildings and facilities being used by others. No single outage will exceed 4 hours unless approved in writing. The time and duration of all outages will be coordinated and approved with the Using Agency by the Contracting Officer.

1.15.1 Advance Notice

To request and notify for planned utility outages, the Contractor shall submit written notification on FC FORM 420-E (attached) within the advance notice time stated on the request form. No single outage will exceed 4 hours unless approved in writing. The time and duration of all outages will be coordinated and approved with the Using Agency by the Contracting Officer.

1.15.2 Overtime Work by Base Operating and Maintenance (O&M) Personnel

The normal working hours for Government O&M personnel whose services may be required for utility outages or similar services are from 7:00 a.m. to 3:30 p.m. Overtime work by Government O&M personnel due to Contractor delays in scheduled outages, interruptions of known utility services, or other negligent acts, is the responsibility of the Contractor. Pay the Government for such additional overtime costs at the existing overtime wage rates established for the Government personnel involved.

1.15.3 Buried Utilities

Coordinate all excavation work including excavation for sign posts, fence posts, and utility poles with the Using Service Facilities Engineer and the telephone company prior to beginning work. Coordinate and apply for dig permits for all excavations and must be renewed every 30 days.

Excavation will not be permitted without a digging permit. Digging permits typically only provide indications on where existing utilities are. The Contractor is responsible for locating all existing buried utilities affected by construction activities.

1.16 DIGGING PERMITS AND ROAD CLOSINGS

The Contractor must allow 14 calendar days from date of written application to receive permission to dig and to close roads. Only close roads one lane at a time and allow vehicular traffic to pass through the construction area. Flag work on or near roadways in accordance with the safety requirements in Safety and Health Requirements Manual EM 385-1-1, which forms a part of these specifications. Do not cause blockage of work located along the alert force route and maintain unobstructed access for alert force traffic at all times.

1.17 QUANTITY SURVEYS

See Section 00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT

REQUIREMENTS) FAR 52.236.16 QUANTITY SURVEYS (APR 1984).

1.18 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS

See Section 00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT

REQUIREMENTS).

SECTION 01 30 00.24 Page 12

1.19 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default:

(Fixed-Price Construction)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Jan 5 Feb 4 Mar 3 Apr 3 May 3 Jun 3 Jul 5 Aug 5 Sep 2 Oct 2 Nov 2

Dec 6

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the RMS daily CQC report, any occurrence of adverse weather and resultant impact to normally scheduled work, within 24 hours of the event. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day. Describe in the RMS daily CQC reports the critical path item that is being affected and provide the critical path activity number(s) from the current schedule. The COR must acknowledge and accept the agreed upon occurrence of each adverse weather delay in RMS for the delays to be considered as adverse weather delays.

At the end of each month, identify the number of actual adverse weather delay days that includes days impacted by actual adverse weather (even if adverse weather occurred in previous month), calculated chronologically from the first to the last day of each month, and recorded as full days.

If the number of actual adverse weather delay days exceeds the number of

SECTION 01 30 00.24 Page 13 days anticipated in paragraph b. above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the GENERAL CONDITIONS (CONTRACT CLAUSES) clause entitled "Default (Fixed Price Construction)". (ER 415-1-15)

1.20 INSURANCE REQUIRED

In accordance with GENERAL CONDITIONS (CONTRACT CLAUSES) clause:

"Insurance Work on a Government Installation," procure the following minimum insurance:

Type Amount

Workmen's Compensation and Employer's Liability Insurance $100,000

General Liability Insurance $500,000 per occurrence

Automobile Liability Insurance Bodily injury $200,000 per person and $500,000 per occurrence Property damage $ 20,000 per occurrence

(Coverages per FAR 28.307-2)

1.21 SECURITY REQUIREMENTS

1.21.1 Contractor's Employee Identification

The Contractor is responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. Deliver all prescribed identification immediately be delivered to the Contracting Officer, for cancellation upon release of any employees. When the contract involves work in restricted security areas, only employees who are U.S. citizens will be permitted to enter. Proof of U.S. citizenship is required prior to entry. When required by the Contracting Officer, obtain and submit fingerprints of all persons employed or to be employed on the project. (Based on FAR 52.204-2)

1.21.2 Fort Carson Entry Requirements

All personnel are required to show a Department of Defense (DOD) issued picture ID, Fort Carson Installation Access Control Card, to enter Fort Carson. Specific requirements and exceptions are outlined in the paragraphs below. AT/OPSEC and Real ID Act are additional requirements to other requirements listed herein.

Access restrictions to the base are listed in paragraph: Authorized Access Points below.

All personnel entering Fort Carson are subject to random vehicle searches IAW the Fort Carson Random Antiterrorism Measures Program (RAMP).

Motorcycle riders must comply with all Fort Carson requirements for use of appropriate safety equipment.

SECTION 01 30 00.24 Page 14

1.21.2.1 AT/OPSEC

See paragraph: ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS above.

1.21.2.2 Real ID Act

Contractor is responsible to adhere to the Real ID Act, or any other DOD security requirement(s), when applying for access to the installation, for all prime and subcontracted employees. See https://www.dhs.gov/real-id-enforcement-brief for states with Real ID Act compliant driver's license and other identification requirements.

Personnel who present an ID from a state that is not in compliance and does not have an extension will need to provide a second form of valid photo ID along with their state ID. Acceptable form of ID to be used as a secondary ID are listed below:

U.S. Passport or Passport Card, PIV or PIV-I card issued by the Federal Government, Veterans Health Identification Card issued by the Department of Veterans Affairs, DHS "Trusted Traveler" cards (Global Entry, NEXUS, SENTRI, FAST), TWIC (Transportation Worker Identification Credential), Merchant Mariner Card issued by the DHS/U.S. Coast Guard, Driver's License issued by the U.S. Department of State, Border Crossing Card (Form DSP-150), U.S. Certificate of Naturalization or Certificate of Citizenship (Form N-550), U.S. Permanent Resident Alien Card (Form I-551), Native American Tribal photo ID, Current University/College ID card containing a photograph, name and expiration date.

Identification Card issued by a federal, State or Local Government agency provided it contains a photograph and biographic information such as name, date of birth, gender, height, eye color and address.

1.21.2.3 Foreign Nationals (FN)

Foreign Nationals (FN) are persons that are not U.S. citizens, INS Naturalized Immigrants, or do not possess a valid DOD Identification Card. The Contractor is responsible for any FN worker or visitor and ensures that that each FN worker or visitor possesses a valid Passport or valid INS Visa/paperwork on their person. No other identification will be accepted. FN workers or visitors are required to be under escort by a DOD Identification Card bearing Adult at all times. The Government will not be responsible for providing escort services. Any FN workers and visitors are required to be processed through base security upon each entry to Fort Carson.