W9128F21B0022 Switchyard Drain Tile Replacement Oahe.docx
DOCX document 180 KB Posted
- Attached to
- W9128F21B0022 - Replacement subsurface drainage system in the 115kV and 230kV Oahe SD Switchyard Federal contract opportunity
- Solicitation number
- 7987
About this file
This solicitation is for a construction project to replace the subsurface drainage system in the 115kV and 230kV switchyards at Oahe Dam in South Dakota. The work requires removing the existing subsurface drainage pipes and aggregates and installing new perforated and solid PVC pipes, pipe casing under roadways, aggregate materials for pipe bedding and cover, and new gate valves. Care must be taken during construction to avoid damaging nearby electrical structures, grounding mats, and underground utilities located in close proximity to the work area. Bids are due by the date specified in Block 13 of the SF1442 form and will be evaluated for award to the responsible bidder providing the most advantageous offer to the Government, considering only price and price-related factors. The solicitation is issued by the Department of the Army Corps of Engineers Omaha District.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ABSTRACT W9128F21B0022.pdf | ||
| Amendment 0001 Specs W9128F21B0022.pdf | ||
| Amendment 0001 W9128F21B0022 Switchyard Drain Tile.pdf | ||
| Amendment 0001 Drawings W9128F21B0022.pdf | ||
| Site Visit Sign in W9128F21B0022.pdf | ||
| W9128F21B0022 Switchyard Drain Tile Replacement 7987.pdf | ||
| Specs - W9128F21B0022 Switchyard Drain Tile Replacement Oahe.pdf | ||
| Dwgs - W9128F21B0022 Switchyard Drain Tile Replacement Oahe Dam SD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W9128F21B0022
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
BID SCHEDULE
BIDDING SCHEDULE
| ITEM NO. |
| DESCRIPTION |
| ESIMATED |
QUANTITY
| UNIT |
| UNIT PRICE |
| ESTIMATED AMOUNT |
BASIC ITEMS
Entire work complete for construction and replacement of switchyard drain piping, cleanouts, valves, partial manhole replacement, and associated replacement of aggregate material, excavation and fill. Except for the option item listed below.
Job
XXX
TOTAL BASIC AMOUNT $_____________________________
OPTION ITEMS
Option Entire work complete for the removal of oil lines and associated replacement of aggregate material, excavation and fill.
Job
XXX
TOTAL AMOUNT BASIC PLUS OPTIONS $___________________________
NOTES:
1. See 00 21 00, INSTRUCTIONS TO OFFERORS for evaluation of options. The Government reserves the right to exercise the options within 60 calendar days after issuance of Notice to Proceed.
2. Bid prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. In case of variation between the Job (lumpsum) prices and the total amount, the Job (lumpsum) prices will be considered the bid.
3. A modification to a bid which provides for a single adjustment to the total amounts, should state the application of the adjustment to each respective Job (lumpsum) price. If the modification is not so apportioned, the single adjustment will be applied to Item No. 0001.
4. Also see Section MEASUREMENT AND PAYMENT for more information.
Section 00 21 00 - Instructions
INSTRUCTIONS TO BIDDERS
1.1 GENERAL BIDDING INFORMATION
Bidders shall e-mail bids to the below individuals no later than the date and time established in Block 13 of the Standard Form (SF) 1442, or Block 14 of the most recent SF 30, as applicable:
Constance R. Ellard, Contracting Officer: Constance.R.Ellard@usace.army.mil
Wayne C. Weidenhamer, Contract Specialist: Wayne.C.Weidenhamer@usace.army.mil
Each e-mail shall contain the following information:
a. Solicitation No: W9128F21B0022
b. Bid Due Date and Time: (See Block 13 of the SF 1442 or Block 14 of recent SF 30)
c. Bid Validity Date: 60 Days
Bids received after the date and time stated within Block 13 of the SF 1442 or Block 14 of the most recent SF 30, as applicable, will be considered late and will not be considered for award. To avoid rejection of a bid, the bidder must ensure the e-mail submission is virus-free. The government will follow FAR 14.406 if an e-mail bid is unreadable.
Bidders should enter a description for every file submitted. Bidders should separate files over 20 megabytes (MB) into smaller files and send separate e-mails. Bidders shall identify each e-mail with the number relative to the total number of e-mails submitted (i.e., “e-mail 1 of 4”). Bidders may send the individuals listed in 1.1 a test email to determine if any technical issues exist. Bidders should request government receipt upon sending all e-mails. Bidders should not assume e-mail submissions are instantaneous and must consider file size and number of files sent.
Bidders must be registered in the System for Award Management (SAM) when sending the bid to comply with the annual representations and certifications requirements. The offeror certifies with its offer that the representations and certifications included in SAM are current, accurate, and complete.
1.1.1 INFORMATION TO BE PROVIDED WITH BID
Bidders must include the below information with the bid:
a. Standard Form (SF) 1442 with Blocks 14 through 20c completed and a person’s signature authorized to sign. Bidders must include their CAGE Code in Block 14, under “CODE.”
b. Bidding Schedule (SECTION 00 10 00).
c. Bid Bond (SF-24); and
d. Bidder must complete provisions from SECTION 00 45 00 – Representations and Certifications, as applicable and listed below.
i. Bidders must complete and include the certification at FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification.
ii. Bidders must complete and include the representation at FAR 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment ONLY based on its online representation in the provision at 52.204-26 Covered Telecommunications Equipment or Services-Representation in SAM.
iii. Bidders must include the representation at 252.204-7017 Prohibition on the Acquisitions of Covered Defense Telecommunications Equipment or Services-Representation ONLY based on its online representation in the provision at 252.204-7016 Covered Defense Telecommunications Equipment or Services-Representation in SAM.
1.1.2 BID OPENING
The government will NOT conduct a physical bid opening for this solicitation. The government will hold the bid opening by conference call at 3:00 pm CST. The government scheduled the bid opening an hour after the due time to allow enough time to download all e-mail documents. No hard copy documents will be accepted.
1.1.3 INFORMATION FOR MODIFYING BIDS
If a bidder needs to modify its bid, the bidder shall send the revised offer by e-mail before the date submitted within Block 13 of the SF 1442 or Block 14 of the most recently issued SF 30 applicable.
1.1.4 ARITHMETIC DISCREPANCIES
Any clerical mistake, including arithmetic discrepancies in a bid, will be handled according to FAR 14.407-2. Any clerical error, apparent on its face in the offer, may be corrected by the contracting officer before award, but only after first obtaining bidder verification of the bid intended. The following are examples of mistakes that may be fixed:
(1) Obviously misplaced decimal points;
(2) Discrepancies between unit price and extended price (unit price will govern);
(3) Apparent errors in extension of unit prices;
(4) Apparent errors in addition of lump sum and extended prices.
1.1.5 BASIS FOR AWARD
Per FAR 52.214-19 Contract Award-Sealed Bidding-Construction in Section 00 21 00 (Instructions), the government will evaluate bids in response to this solicitation without discussions. It will award a contract to the responsible bidder whose offer, conforming to the solicitation, will be most advantageous to the government, considering only price and the price-related factors specified elsewhere in the solicitation.
1.1.6 DESCRIPTION OF WORK
The scope of this project is to furnish all plant, labor, materials, and equipment to perform all work for the:
Replacement Switchyard Drain Tile Replacement, Oahe Project, South Dakota.
1.1.7 ESTIMATED CONSTRUCTION COST
The estimated magnitude of construction is between $500,000 and $1,000,000.
1.1.8 BID GUARANTEE
See 52.228-1, Bid Guarantee in Section 00 72 00 (General Conditions). The bid guarantee must be on SF 24 and include a Power of Attorney appointing an attorney-in-fact with authority to bind the surety. At the time of bid opening, the bond is enforceable against the surety should the bidder fail to meet its obligation. A power of attorney must include a certification as to the authority of the surety’s agents supported by a resolution of the surety authorizing their use and committing it bound by them. Electronic signatures and electronic, mechanically-applied, or printed dates may be used and considered original signatures and dates, without regard to the order in which affixed. A corporate seal on the SF-24 is not required. Mailing a bid guarantee is not allowed.
1.1.9 PERFORMANCE AND PAYMENT BONDS OR ALTERNATE PAYMENT PROTECTION
See 52.228-15 Performance and Payment Bonds-Construction (JUN 2020) (DEVIATION 2020-O0016) in Section 00 72 00 (General Conditions). The performance bond must be on SF-25, and the payment bond must be on SF-25A. Electronic signatures and electronic, mechanically-applied, or printed dates may be used and considered original signatures and dates, without regard to the order in which affixed. A corporate seal on the SF-25 or SF-25A is not required.
1.1.10 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS
Copies of the solicitation and amendments are available by internet access only. The government will post all solicitation documents to SAM.gov | Home. The bidder is responsible for checking the website for amendments.
To view a list of interested vendors and receive notifications or e-mail of changes regarding the solicitation, bidders must register as vendors on the website listed above. If a bidder is already registered, enter the user name and password to log in and search for the solicitation number. If you wish for general contractors, subcontractors, suppliers, plan rooms, or print shops to have the ability to contact you, click on the “Add Me to Interested Vendors” for this solicitation.
1.1.11 REJECTION OF BIDS
The government will handle the rejection of bids per FAR 14.404. The government may reject an offer if the prices for line items or subline items are materially unbalanced (see 15.404-1(g)). Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly over or underestimated as indicated by the application of cost or price analysis techniques.
1.1.12 NOTICE REGARDING BUY AMERICAN STATUE
The Buy American statute (41 USC 83 chapter 83, Buy American) generally requires that contractors use only domestic construction material during the performance of this contract. Exception from the Buy American statute is permitted only in the case of non-availability of domestic construction materials or allowed under Trade Agreements if included in the solicitation. A bid offering non-domestic construction material will not be accepted unless specifically approved by the government or authorized under Trade Agreements if included in the solicitation. When a bidder proposes to furnish non-domestic construction material, the bid must set forth an itemization of the quantity, unit price, and intended use of any non-domestic construction material.
1.1.13 FEDERAL, STATE AND LOCAL TAXES
The bidder is responsible for investigating applicable federal, state, and local taxes and any specific exemptions that may exist and includes applicable Value-Added Taxes (VAT), sales, use, and excise taxes. See 52.229-3 Federal, State, and Local in Section 00 72 00 (General Conditions).
1.1.14 BIDDER’S QUESTIONS AND COMMENTS
Bidders must submit questions and comments relative to the bidding documents via Bidder Inquiry as indicated below.
Bidders may submit questions and comments relative to any proprietary concerns or bidding documents, or if the Bidder Inquiry system is out of service, to the individuals below:
Wayne C. Weidenhamer, Contract Specialist: Wayne.C.Weidenhamer@usace.army.mil
Constance R. Ellard, Contracting Officer: Constance.R.Ellard@usace.army.mil
1.1.14.1 BIDDER INQUIRY
Bidders shall submit all questions via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet/, ten calendar days before bid opening, to allow the government time to respond before receipt of bids or issue an amendment.
Bidders must use the Bidder Inquiry Key and instructions below to submit and review inquiry items. A bidder who enters a comment/question will receive an acknowledgment of their comment /question by e-mail, followed by an answer to the comment/question after the government has processed it.
The government will make available all timely questions and approved answers in ProjNet.
The Solicitation Number is: W9128F21B0022
The Bidder Inquiry Key is: X33688-J8UQHY
a. Registration for ProjNet Bidder Inquiry Access
1. From the ProjNet home page listed above, click on Quick Add on the upper right side of the screen.
2. Select USACE for the Agency.
3. Enter the Bidder Inquiry Key above.
4. Enter the primary e-mail address to use for communication for.
5. Check the “I agree to the Privacy & Security Notice” box and click Continue. A page will open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, E-mail, Secret Question, Secret Answer, and Time Zone. Bidders will use the answer to the Secret Question from this point on to access the ProjNet system.
7. Click Add User. Once completed, ProjNet registration is complete, and the bidder is logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1. For future access to ProjNet, bidders will not receive a password by e-mail. Bidders will utilize the Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Select USACE for the Agency.
4. Enter the Bidder Inquiry Key above.
5. Enter the primary e-mail address used to register.
6. Check the “I agree to the Privacy & Security Notice” box and click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once complete, the bidder is logged into the system.
8. Follow online screen instructions to enter specific bidder inquiries for the project.
c. Bidders are requested to review the plans and specifications in their entirety and review the Bidder Inquiry System for answers to questions prior to submitting a new inquiry.
d. The call center operate weekdays from 8 am to 5 pm Central Standard Time Zone (Chicago). The telephone number for the call center is 800-428-HELP.
1.1.15 AVAILABILITY OF BID RESULTS
Bid results will be available after bid opening on SAM.gov | Home.
CLAUSES INCORPORATED BY REFERENCE
| 52.204-7 |
| System for Award Management |
| OCT 2018 |
| 52.204-16 |
| Commercial and Government Entity Code Reporting |
| AUG 2020 |
| 52.204-22 |
| Alternative Line Item Proposal |
| JAN 2017 |
| 52.211-2 |
| Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) |
| APR 2014 |
| 52.214-3 |
| Amendments To Invitations For Bids |
| DEC 2016 |
| 52.214-4 |
| False Statements In Bids |
| APR 1984 |
| 52.214-5 |
| Submission Of Bids |
| DEC 2016 |
| 52.214-6 |
| Explanation To Prospective Bidders |
| APR 1984 |
| 52.214-7 |
| Late Submissions, Modifications, and Withdrawals of Bids |
| NOV 1999 |
| 52.214-18 |
| Preparation of Bids-Construction |
| APR 1984 |
| 52.214-19 |
| Contract Award-Sealed Bidding-Construction |
| AUG 1996 |
| 52.214-34 |
| Submission Of Offers In The English Language |
| APR 1991 |
| 52.214-35 |
| Submission Of Offers In U.S. Currency |
| APR 1991 |
| 52.222-5 |
| Construction Wage Rate Requirements--Secondary Site of the Work |
| MAY 2014 |
| 52.225-9 |
| Buy American--Construction Materials |
| FEB 2021 |
| 52.225-10 |
| Notice of Buy American Requirement--Construction Materials |
| MAY 2014 |
| 252.204-7019 |
| Notice of NIST SP 800-171 DoD Assessment Requirements |
| NOV 2020 |
| 252.236-7008 |
| Contract Prices-Bidding Schedules |
| DEC 1991 |
CLAUSES INCORPORATED BY FULL TEXT
FIR52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
(End of provision)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
U.S. Army Corps of Engineers - Omaha District Attn: Constance Ellard 1616 Capitol Ave Omaha, NE 68102-4901
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
| Name: Phillip Schroeder - Phillip.P.Schroeder@usace.army.mil |
| Address: Oahe Dam, Pierre South Dakota |
| Telephone: (605) 945-3406 |
52.243-4 CHANGES (JUN 2007)
(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes--
(1) In the specifications (including drawings and designs);
(2) In the method or manner of performance of the work;
(3) In the Government-furnished property or services; or
(4) Directing acceleration in the performance of the work.
(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating
(1) the date, circumstances, and source of the order and
(2) that the Contractor regards the order as a change order.
(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.
(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.
(e) The Contractor must assert its right to an adjustment under this clause within 30 days after
(1) receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of the proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.
(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.
(End of clause)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
The full text FAR provisions can be found:
https://www.acquisition.gov/browse/index/far
The full text of DFARS provisions can be found at:
https://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Acquisition Regulations System, Department of Defense (48 CFR Chapter 2 ) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.215-7008 ONLY ONE OFFER (JUL 2019)
(a) Cost or pricing data requirements. After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was received, the Offeror agrees to--
(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 2306a and FAR 15.403-3); and
(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.
(b) Canadian Commercial Corporation. If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:
(1) Profit rate or fee (as applicable).
(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).
(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable [U.S. Contracting Officer to provide description of the data required in accordance with FAR 15.403-3(a)(1) with the notification].
(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.
(c) Subcontracts. Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.
Section 00 45 00 - Representations and Certifications
| 52.204-24 |
| Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment. |
| OCT 2020 |
| 52.204-26 |
| Covered Telecommunications Equipment or Services--Representation. |
| OCT 2020 |
| 52.209-7 |
| Information Regarding Responsibility Matters |
| OCT 2018 |
| 52.209-12 |
| Certification Regarding Tax Matters |
| OCT 2020 |
| 252.203-7005 |
| Representation Relating to Compensation of Former DoD Officials |
| NOV 2011 |
| 252.204-7008 |
| Compliance With Safeguarding Covered Defense Information Controls |
| OCT 2016 |
| 252.204-7016 |
| Covered Defense Telecommunications Equipment or Services -- Representation |
| DEC 2019 |
| 252.204-7017 |
| Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation |
| MAY 2021 |
| 252.225-7974 (Dev) |
| Representation Regarding Business Operations with the Maduro Regime (DEVIATION 2020-O0005) |
| FEB 2020 |
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.
(2) The small business size standard is $39,500,000.00.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
( ) Paragraph (d) applies.
( ) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services--Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.
(D) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[Contracting Officer check as appropriate.]
(i) 52.204-17, Ownership or Control of Offeror.
(ii) 52.204-20, Predecessor of Offeror.
(iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
(iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.
(v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Certification.
(vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
(vii) 52.227-6, Royalty Information.
(A) Basic.
(B) Alternate I.
(viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [ offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS--CERTIFICATION (FEB 2021)
(a) This provision does not apply to acquisitions at or below the simplified acquisition threshold or to acquisitions of commercial items as defined at FAR 2.101.
(b) Certification. [Offeror shall check either (1) or (2).]
____ (1) The Offeror certifies that--
(i) It does not engage and has not engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; and
(ii) No entity owned or controlled by the Offeror has engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; or
____ (2) The Offeror is providing separate information with its offer in accordance with paragraph (d)(2) of this provision.
(c) Procedures for reviewing the annual unclassified report (see paragraph (b)(1) of this provision). For clarity, references to the report in this section refer to the entirety of the annual unclassified report, including any separate reports that are incorporated by reference into the annual unclassified report.
(1) Check the table of contents of the annual unclassified report and the country section headings of the reports incorporated by reference to identify the foreign countries listed there. Determine whether the Offeror or any person owned or controlled by the Offeror may have engaged in any activity related to one or more of such foreign countries.
(2) If there may have been such activity, review all findings in the report associated with those foreign countries to determine whether or not each such foreign country was determined to be in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or to be not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. For clarity, in the annual report an explicit certification of non-compliance is equivalent to a determination of violation. However, the following statements in the annual report are not equivalent to a determination of violation:
(i) An inability to certify compliance.
(ii) An inability to conclude compliance.
(iii) A statement about compliance concerns.
(3) If so, determine whether the Offeror or any person owned or controlled by the Offeror has engaged in any activity that contributed to or is a significant factor in the determination in the report that one or more of these foreign countries is in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. Review the narrative for any such findings reflecting a determination of violation or non-adherence related to those foreign countries in the report, including the finding itself, and to the extent necessary, the conduct giving rise to the compliance or adherence concerns, the analysis of compliance or adherence concerns, and efforts to resolve compliance or adherence concerns.
(4) The Offeror may submit any questions with regard to this report by email to NDAA1290Cert@state.gov. To the extent feasible, the Department of State will respond to such email inquiries within 3 business days.
(d) Do not submit an offer unless--
(1) A certification is provided in paragraph (b)(1) of this provision and submitted with the offer; or
(2) In accordance with paragraph (b)(2) of this provision, the Offeror provides with its offer information that the President of the United States has--
(i) Waived application under U.S.C. 2593e(d) or (e); or
(ii) Determined under 22 U.S.C. 2593e(g)(2) that the entity has ceased all activities for which measures were imposed under 22 U.S.C.2593e(b).
(e) Remedies. The certification in paragraph (b)(1) of this provision is a material representation of fact upon which reliance was placed when making award. If it is later determined that the Offeror knowingly submitted a false certification, in addition to other remedies available to the Government, such as suspension or debarment, the Contracting Officer may terminate any contract resulting from the false certification.
252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2021)
Substitute the following paragraphs (b), (d) and (e) for paragraphs (b) and (d) of the provision at FAR 52.204-8:
(b)(1) If the provision at FAR 52.204-7, System for Award Management, is included in this solicitation, paragraph (e) of this provision applies.
(2) If the provision at FAR 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (e) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
__ (i) Paragraph (e) applies.
__ (ii) Paragraph (e) does not apply and the Offeror has completed the individual representations and certifications in the solicitation.
(d)(1) The following representations or certifications in the SAM database are applicable to this solicitation as indicated:
(i) 252.204-7016, Covered Defense Telecommunications Equipment or Services--Representation. Applies to all solicitations.
(ii) 252.216-7008, Economic Price Adjustment--Wage Rates or Material Prices Controlled by a Foreign Government. Applies to solicitations for fixed-price supply and service contracts when the contract is to be performed wholly or in part in a foreign country, and a foreign government controls wage rates or material prices and may during contract performance impose a mandatory change in wages or prices of materials.
(iii) 252.225-7042, Authorization to Perform. Applies to all solicitations when performance will be wholly or in part in a foreign country.
(iv) 252.225-7049, Prohibition on Acquisition of Certain Foreign Commercial Satellite Services--Representations. Applies to solicitations for the acquisition of commercial satellite services.
(v) 252.225-7050, Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism. Applies to all solicitations expected to result in contracts of $150,000 or more.
(vi) 252.229-7012, Tax Exemptions (Italy)--Representation. Applies to solicitations when contract performance will be in Italy.
(vii) 252.229-7013, Tax Exemptions (Spain)--Representation. Applies to solicitations when contract performance will be in Spain.
(viii) 252.247-7022, Representation of Extent of Transportation by Sea. Applies to all solicitations except those for direct purchase of ocean transportation services or those with an anticipated value at or below the simplified acquisition threshold.
(2) The following representations or certifications in SAM are applicable to this solicitation as indicated by the Contracting Officer: [Contracting Officer check as appropriate.]
____ (i) 252.209-7002, Disclosure of Ownership or Control by a Foreign Government.
____ (ii) 252.225-7000, Buy American--Balance of Payments Program Certificate.
____ (iii) 252.225-7020, Trade Agreements Certificate.
____ Use with Alternate I.
____ (iv) 252.225-7031, Secondary Arab Boycott of Israel.
____ (v) 252.225-7035, Buy American--Free Trade Agreements--Balance of Payments Program Certificate.
____ Use with Alternate I.
____ Use with Alternate II.
____ Use with Alternate III.
____ Use with Alternate IV.
____ Use with Alternate V.
____ (vi) 252.226-7002, Representation for Demonstration Project for Contractors Employing Persons with Disabilities.
____ (vii) 252.232-7015, Performance-Based Payments--Representation.
(e) The Offeror has completed the annual representations and certifications electronically via the SAM website at https://www.acquisition.gov/. After reviewing the SAM database information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in FAR 52.204-8(c) and paragraph (d) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer, and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [Offeror to insert changes, identifying change by provision number, title, date____]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
| FAR/DFARS provision No. |
| Title |
| Date |
| Change |
Any changes provided by the Offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications located in the SAM database.
Section 00 72 00 - General Conditions
| 52.202-1 |
| Definitions |
| JUN 2020 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| MAY 2014 |
| 52.203-6 |
| Restrictions On Subcontractor Sales To The Government |
| JUN 2020 |
| 52.203-7 |
| Anti-Kickback Procedures |
| JUN 2020 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| MAY 2014 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| MAY 2014 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| JUN 2020 |
| 52.203-13 |
| Contractor Code of Business Ethics and Conduct |
| JUN 2020 |
| 52.203-19 |
| Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements |
| JAN 2017 |
| 52.204-4 |
| Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |
| MAY 2011 |
| 52.204-9 |
| Personal Identity Verification of Contractor Personnel |
| JAN 2011 |
| 52.204-10 |
| Reporting Executive Compensation and First-Tier Subcontract Awards |
| JUN 2020 |
| 52.204-13 |
| System for Award Management Maintenance |
| OCT 2018 |
| 52.204-18 |
| Commercial and Government Entity Code Maintenance |
| AUG 2020 |
| 52.204-19 |
| Incorporation by Reference of Representations and Certifications. |
| DEC 2014 |
| 52.204-23 |
| Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities. |
| JUL 2018 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| JUN 2020 |
| 52.209-9 |
| Updates of Publicly Available Information Regarding Responsibility Matters |
| OCT 2018 |
| 52.209-10 |
| Prohibition on Contracting With Inverted Domestic Corporations |
| NOV 2015 |
| 52.209-13 |
| Violation of Arms Control Treaties or Agreements -- Certification. |
| FEB 2021 |
| 52.211-18 |
| Variation in Estimated Quantity |
| APR 1984 |
| 52.214-26 |
| Audit and Records--Sealed Bidding |
| JUN 2020 |
| 52.214-27 |
| Price Reduction for Defective Certified Cost or Pricing Data - Modifications - Sealed Bidding |
| JUN 2020 |
| 52.214-28 |
| Subcontractor Certified Cost Or Pricing Data--Modifications--Sealed Bidding |
| JUN 2020 |
| 52.219-6 (Dev) |
| Notice of Total Small Business Set-Aside (DEVIATION 2020-O0008). |
| OCT 2020 |
| 52.219-8 |
| Utilization of Small Business Concerns |
| OCT 2018 |
| 52.219-28 |
| Post-Award Small Business Program Rerepresentation |
| NOV 2020 |
| 52.222-1 |
| Notice To The Government Of Labor Disputes |
| FEB 1997 |
| 52.222-3 |
| Convict Labor |
| JUN 2003 |
| 52.222-4 |
| Contract Work Hours and Safety Standards - Overtime Compensation |
| MAY 2018 |
| 52.222-5 |
| Construction Wage Rate Requirements--Secondary Site of the Work |
| MAY 2014 |
| 52.222-6 |
| Construction Wage Rate Requirements |
| AUG 2018 |
| 52.222-7 |
| Withholding of Funds |
| MAY 2014 |
| 52.222-8 |
| Payrolls and Basic Records |
| AUG 2018 |
| 52.222-9 |
| Apprentices and Trainees |
| JUL 2005 |
| 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| 52.222-11 |
| Subcontracts (Labor Standards) |
| MAY 2014 |
| 52.222-12 |
| Contract Termination-Debarment |
| MAY 2014 |
| 52.222-13 |
| Compliance With Construction Wage Rate Requirements and Related Regulations |
| MAY 2014 |
| 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| 52.222-15 |
| Certification of Eligibility |
| MAY 2014 |
| 52.222-21 |
| Prohibition Of Segregated Facilities |
| APR 2015 |
| 52.222-26 |
| Equal Opportunity |
| SEP 2016 |
| 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| APR 2015 |
| 52.222-35 |
| Equal Opportunity for Veterans |
| JUN 2020 |
| 52.222-36 |
| Equal Opportunity for Workers with Disabilities |
| JUN 2020 |
| 52.222-37 |
| Employment Reports on Veterans |
| JUN 2020 |
| 52.222-40 |
| Notification of Employee Rights Under the National Labor Relations Act |
| DEC 2010 |
| 52.222-50 |
| Combating Trafficking in Persons |
| OCT 2020 |
| 52.222-54 |
| Employment Eligibility Verification |
| OCT 2015 |
| 52.222-55 |
| Minimum Wages Under Executive Order 13658 |
| NOV 2020 |
| 52.222-62 |
| Paid Sick Leave Under Executive Order 13706 |
| JAN 2017 |
| 52.223-2 |
| Affirmative Procurement of Biobased Products Under Service and Construction Contracts |
| SEP 2013 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-17 |
| Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts |
| AUG 2018 |
| 52.223-18 |
| Encouraging Contractor Policies To Ban Text Messaging While Driving |
| JUN 2020 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| FEB 2021 |
| 52.227-1 |
| Authorization and Consent |
| JUN 2020 |
| 52.227-2 |
| Notice And Assistance Regarding Patent And Copyright Infringement |
| JUN 2020 |
| 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| 52.228-2 |
| Additional Bond Security |
| OCT 1997 |
| 52.228-5 |
| Insurance - Work On A Government Installation |
| JAN 1997 |
| 52.228-11 |
| Individual Surety--Pledge of Assets |
| FEB 2021 |
| 52.228-12 |
| Prospective Subcontractor Requests for Bonds |
| MAY 2014 |
| 52.228-14 |
| Irrevocable Letter of Credit |
| NOV 2014 |
| 52.228-15 (Dev) |
| Performance and Payment Bonds-Construction. (Deviation 2020-O0016) |
| JUN 2020 |
| 52.229-3 |
| Federal, State And Local Taxes |
| FEB 2013 |
| 52.232-17 |
| Interest |
| MAY 2014 |
| 52.232-18 |
| Availability Of Funds |
| APR 1984 |
| 52.232-23 |
| Assignment Of Claims |
| MAY 2014 |
| 52.232-33 |
| Payment by Electronic Funds Transfer--System for Award Management |
| OCT 2018 |
| 52.232-39 |
| Unenforceability of Unauthorized Obligations |
| JUN 2013 |
| 52.232-40 |
| Providing Accelerated Payments to Small Business Subcontractors |
| DEC 2013 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.244-6 |
| Subcontracts for Commercial Items |
| NOV 2020 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.201-7000 |
| Contracting Officer's Representative |
| DEC 1991 |
| 252.203-7000 |
| Requirements Relating to Compensation of Former DoD Officials |
| SEP 2011 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2008 |
| 252.203-7002 |
| Requirement to Inform Employees of Whistleblower Rights |
| SEP 2013 |
| 252.203-7003 |
| Agency Office of the Inspector General |
| AUG 2019 |
| 252.203-7004 |
| Display of Hotline Posters |
| AUG 2019 |
| 252.203-7005 |
| Representation Relating to Compensation of Former DoD Officials |
| NOV 2011 |
| 252.204-7000 |
| Disclosure Of Information |
| OCT 2016 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.205-7000 |
| Provision Of Information To Cooperative Agreement Holders |
| DEC 1991 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism |
| MAY 2019 |
| 252.222-7006 |
| Restrictions on the Use of Mandatory Arbitration Agreements |
| DEC 2010 |
| 252.223-7001 |
| Hazard Warning Labels |
| DEC 1991 |
| 252.223-7008 |
| Prohibition of Hexavalent Chromium |
| JUN 2013 |
| 252.225-7012 |
| Preference For Certain Domestic Commodities |
| DEC 2017 |
| 252.225-7048 |
| Export-Controlled Items |
| JUN 2013 |
| 252.226-7001 |
| Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns |
| APR 2019 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| DEC 2018 |
| 252.232-7010 |
| Levies on Contract Payments |
| DEC 2006 |
| 252.232-7017 |
| Accelerating Payments to Small Business Subcontractors--Prohibition on Fees and Consideration |
This is the start of the file's text. The full file is on GovTribe.