This pre-solicitation notice seeks proposals for two indefinite delivery, indefinite quantity single award task order contracts to provide emergency temporary roof repairs in Puerto Rico in response to natural disasters. The contracts have a total maximum value of $45 million each and a period of performance of five years base with a two-year option. The primary NAICS code is 238160 for roofing contractors with a small business size standard of $16.5 million. The solicitation will be released on or around January 29, 2020 and close on or around February 28, 2020. It will be set aside for small businesses only. Interested parties should monitor the contract opportunities website for solicitation release and amendments. The point of contact for additional information is the named contracting specialist.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fact Sheet ACI Emergency Temporary Roofing.docx | DOCX document | |
| Pre-Solicitation Notice ACI Temp Roof Puerto Rico.DOC | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
W9128F20R0040
2. TYPE OF SOLICITATION
SEALED BID (IFB)
X NEGOTIATED (RFP)
3. DATE ISSUED
03-Feb-2020
PAGE OF
PAGES 1 OF 82
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
W59XQG93449774
6. PROJECT NO.
7. ISSUED BY CODE W9128F 8. ADDRESS OFFER TO (If Other Than Item 7) CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
See Item 7
OMAHA NE 68102-4901
TEL: FAX: TEL: FAX:
9. FOR INFORMATION
CALL:
A. NAME
WAYNE C WEIDENHAMER
B. TELEPHONE NO.
(402) 995-2074
(Include area code) (NO COLLECT CALLS)
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED INTHESE DOCUMENTS (Title, identifying no., date):
ADVANCED CONTRACT INITIAITIVE (ACI) EMERGENCY TEMPORARY ROOFING PUERTO RICO EAST AND WEST REGIONS / $45,000,000
SMALL BUSINESS SET-ASIDE
11. The Contractor shall begin performance w ithin calendar days and complete it w ithin calendar days after receiving aw ard, notice to proceed. This performance period is mandatory, negotiable. (See .)
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and 1 copies to perform the w ork required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 150 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
OFFER (M ust be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
See Item 14
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specified below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OFPRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
20B. SIGNATURE 20C. OFFER DATE
21. ITEMS ACCEPTED:
AWARD (To be completed by Government)
22. AMOUNT 23. ACCOUNTING AND APPROPRIATIONDATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
26. ADMINISTERED BY CODE
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
27. PAYMENT WILL BE MADE BY: CODE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this 29. AWARD (Contractor is not required to sign this document.)
document and return _ copies to issuing office.) Contractor agrees to f urnish and deliv er all items or perf orm all work, requisitions identif ied on this f orm and any continuation sheets f or the consideration stated in this contract. The rights and obligations of the parties to this contract shall be gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
30B. SIGNATURE 30C. DATE
NSN 7540-01-155-3212
Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-summates the contract, which consists of (a) the Gov ernment solicitation and y our of f er, and (b) this contract award. No f urther contractual document is necessary .
31A. NAME OF CONTRACTING OFFICER (Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
STANDARD FORM 1442 BACK (REV. 4-85)
W9128F20R004
0 Page 3 of 82
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 45,000,000 Job
ACI TEMP ROOFING CONTRACT
FFP
BASE PERIOD (5 years) for the Regions East and West of the Commonwealth of Puerto Rico, to include the Islands of Vieques and Culebra.
Period of Performance: 01 June 2020 through 31 May 2025.
FOB: Destination
PURCHASE REQUEST NUMBER: W59XQG93449774
MAX
NET AMT
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0002 Job
OPTION ACI TEMP ROOFING CONTRACT
FFP
OPTION PERIOD (Years 6 and 7) for the Regions East and West of the Commonwealth of Puerto Rico, to include the Islands of Vieques and Culebra.
Period of Performance: 01 June 2025 through 31 May 2027.
FOB: Destination
PURCHASE REQUEST NUMBER: W59XQG93449774
MAX
NET AMT
0 Page 4 of 82
CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE
The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
$2,500.00 $45,000,000.00
DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE
The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
$2,500.00 $45,000,000.00
CLIN MINIMUM/MAXIMUM QUANTITY AND CLIN VALUE
The minimum quantity(s) and CLIN value(s) for all orders issued against the CLIN(s) on this contract shall not be less than the minimum quantity(s) and CLIN value(s) stated in the following table. The maximum quantity(s) and CLIN value(s) for all orders issued against the CLIN(s) on this contract shall not exceed the maximum quantity(s) and CLIN value(s) stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
0001 1.00 $2,500.00 1.00 $45,000,000.00
CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE
The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
0 Page 5 of 82
0001 1.00 $2,500.00 1.00 $45,000,000.00
0002 $ $
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-JUN-2020 TO
31-MAY-2025
N/A CORPS OF ENGINEERS READINESS
BRANCH
MATT KRAJEWSKI
USAED, OMAHACENWO-OD-E
1616 CAPITOL AVE
OMAHA NE 68102-4901
402-995-2448 FOB: Destination
966527
0002 POP 01-JUN-2026 TO
31-MAY-2028
N/A CORPS OF ENGINEERS READINESS
BRANCH
BARBARA KIMBALL
USAED, OMAHACENWO-OD-E
1616 CAPITOL AVE
OMAHA NE 68102-4901
402-995-2498 FOB: Destination
966527
PRICE SCHEDULE
W9128F20R0040
SEE THE ATTACHED
ACI EMERGENCY TEMPORARY ROOF REPAIRS
PRICE SCHEDULE
Section 002100 - Bidding Schedule/Instructions to Bidders
INSTRUCTIONS TO OFFERORS
SECTION 002100
INSTRUCTIONS TO OFFERORS
1. SOLICITATION DESCRIPTION
1.1 Indefinite Delivery Type Contracts: As part of the Advanced Contract Initiative (ACI) Emergency Temporary Roof Repair acquisition strategy, the Government intends to issue two (2) solicitations and award four (4) subsequent single award task order contracts (SATOCs) for the Commonwealth of Puerto Rico to include the Islands of Vieques and Culebra:
Acquisitions to be awarded under this solicitation:
Primary Region Secondary Region Set-Aside Capacity
West East and remaining area in Puerto Rico to include Vieques and Culebra
Small Business $45,000,000.00
East West and remaining area in Puerto Rico to include Vieques and Culebra
Small Business $45,000,000.00
Acquisitions to be awarded in 2021: (For informational purposes only)
Primary Region Secondary Region Set-Aside Capacity West East and remaining area in Puerto Rico to include Vieques and Culebra Unrestricted $45,000,000.00
East West and remaining area in Puerto Rico to include Vieques and Culebra
Unrestricted $45,000,000.00
Total Capacity 2020-2021 $180,000,000.00
This solicitation is for the 2020 contracts only. A separate solicitation will be issued for the 2021 contracts at a later date. The geographic scope of this solicitation allows for work on the entire island of Puerto Rico if needed.
All task orders issued under the SATOCs will be Firm Fixed Price.
Each SATOC will not exceed $45,000,000.00 in capacity, with a minimum guarantee of $2,500.00 (to include the base and option period). Award will be made to the two (2) most responsible offerors whose proposals conform to the criteria established in this solicitation, and are considered most advantageous to the Government for each region; price and other factors considered. In any case, the Government may not award any contract if the resulting contract would not represent the “best value” to the Government using trade-off selection procedures as required by the DFARS and using guidance as prescribed by the Department of Defense (DoD) Source Selection Procedures. I t is strongly encouraged that the provisions stated in the solicitation be fully studied prior to assembly of the proposal.
The period of performance for the SATOCs consists of a 5-year base period and a 2-year option period for a total 7-year performance period. The Government’s decision to exercise an option will be contingent on satisfactory contactor performance and an informal survey of current market conditions. The decision to exercise the option is at the discretion of the Government.
An offeror will only be considered for one (1) $45,000,000 SATOC in Puerto Rico. This includes any combination of teaming arrangements, Joint Ventures or mentor-protégé arrangements as prime contractors.
This restriction does not include subcontracting. If an offeror is awarded a SATOC under this solicitation, it will not be considered for award in the 2021 solicitation for Puerto Rico. An offeror will still be considered for SATOCs in solicitations for areas other than Puerto Rico. The Government may reject any or all offers if such action is determined to be in the best interest of the Government.
1.2 Set-Aside: This solicitation is set aside for small business participation only.
1.3 Eligibility Verification: The System for Award Management or (https://www.SAM.gov) website will be checked to verify an offeror’s current classification under North American Industry Classification Code (NAICS) 238160, Roofing Contractors with a small business size standard of $16.5 million.
1.4 Awards: The U. S. Army Corps of Engineers intends to conduct this acquisition by use of competitive source selection procedures in accordance with the provisions set forth in this solicitation.
These contracts will be awarded to fulfill the Government’s anticipated need for numerous rapid-response temporary roofing projects in the Commonwealth of Puerto Rico to include the Islands of Vieques and Culebra.
The effect will be to have numerous capable and responsible contractors that can facilitate and maximize the Government’s response capability in the event of an emergency, as it is the Government’s intent to maximize the number of contracts, and thus contractors to draw upon, to respond to a catastrophic event. Having numerous contractors with contracts that have scopes with overlapping geographic coverage is crucial to meeting the Government’s needs here, which is to ensure that the Government has adequate coverage and contract capacity in the event of an emergency event in any one (1) location.
2. PROPOSAL INFORMATION
There are no drawings associated with this solicitation. Copies of the solicitation and amendments will be available by INTERNET ACCESS ONLY. All solicitation documents will be posted to Contracting Opportunities (formerly known as FedBizOpps or FBO) at the betaSAM.gov website https://beta.sam.gov.
It shall be the contractor’s responsibility to check the website for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.
2.1. Offeror’s Questions and Comments
Questions relating to the proposal are to be submitted via Bidder Inquiry in ProjNet at: h ttps://www.projnet.org/projnet/ no later than (NLT) ten (10) calendar days before due date of proposals, in order that they may be given consideration or actions taken prior to receipt of offers.
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via ProjNet email notification after an answer to the comment/question after it has been processed by our technical team.
NOTE: The ProjNet Bidder Inquiry is for all FY20 ACI Emergency Temporary Roof Repair solicitations. If a question is particular to a specific solicitation, please specify. Any changes to a solicitation resulting from a bidder inquiry will be issued as an amendment. Offerors are advised to prepare proposals IAW with the respective solicitation and amendments.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: W9128F20R0040
The Bidder Inquiry Key is: QA9UBX-EA3TTN
a. Registration for ProjNet Bidder Inquiry Access
If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
http://www.projnet.org/projnet/
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
8. Follow online screen instructions to enter specific bidder inquiries for the project.
c. The Bidder Inquiry System will be unavailable for new inquires after ten (10) calendar days in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
d. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
2.2. Pre-proposal Conference / Fact Sheet
There will not be a pre-proposal conference for this solicitation. Instead a fact sheet of topics normally covered at a pre-proposal conference is posted on betaSAM.gov with this solicitation.
2.3. Proposal Expenses and Pre-Contract Costs
This solicitation does not commit the Government to pay any costs incurred in the preparation and submission of a proposal or for any other costs incurred by any firm submitting a proposal in response to this solicitation.
2.4. Method of Procurement
2.4.1. Proposals must set forth full, accurate, and complete information as required by this solicitation, (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.
2.4.2. The Government reserves the right to discuss aspects of proposals with offerors in the competitive range and to award a contract to other than the lowest priced offer. Offerors are advised that the Government intends to make award without discussions, clarifications or any contact concerning the proposals received. Therefore, proposals should be submitted initially on the most favorable terms, price and technical standpoint. Do not assume that offerors will be contacted or afforded an opportunity to clarify, discuss, or revise theirproposal.
2.5. Proposal Submittals
The offeror shall submit two (2) copies of Volumes I and II on separate CD/DVDs NLT the time and date specified on SF 1442, Item 13A of the solicitation. All CD/DVD submissions with the exception of the pricing schedule submitted in Volume II shall be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software.
The pricing schedule shall be submitted in Excel format only. The two (2) volumes listed below shall be submitted as SEPARATE and SINGLE files.
Volume I: Technical Proposal and Past Performance Information Volume II: Price Information and Representations, Certifications, and Other Statements of Offerors
Title the single files in the following format:
W9128F20R000X_Company Name_Vol_I_Technical Proposal
W9128F20R000X_Company Name_Vol_II_Price_Proposal
*NOTE: The company name may be abbreviated.
The package containing the CD/DVDs shall be marked:
U.S. ARMY CORPS OF ENGINEERS, OMAHA DISTRICT
ATTN: Wayne Weidenhamer, CENWO-CT-C 1616 Capitol Avenue Omaha, NE 68102-4901
PROPOSAL - DO NOT OPEN.
The Government will not be responsible for proposals delivered to any location nor to anyone other than those designated to receive proposals on its behalf. The Offeror is responsible for ensuring that the proposal reaches the designated recipient and must allow sufficient time for the proposal to be received on time. In addition, the Offeror must take into account the potential delay in getting through security if the Offeror plans to hand deliver the package. Proposals received after the specified due date and time will be considered untimely and will be rejected.
The following individuals are available to provide information if there are questions concerning delivery instructions of the proposal:
Mr. Lee McCormick, lee.m.mccormick@usace.army.mil, 402-995-2084
Mr. Wayne Weidenhamer, wayne.c.weidenhamer@usace.army.mil, 402-995-2074
3. PROPOSAL FORMAT
3.1. Cover letter
mailto:ee.m.mccormick@usace.army.mil mailto:ayne.c.weidenhamer@usace.army.mil
Each Offeror shall submit a cover letter that contains the items stated in Section 007200, FAR Clause 52.215- 1, Instructions to Offerors – Competitive Acquisition, paragraph (c)(2) including the solicitation number, points of contact, statement specifying agreement with all terms and conditions, authorized negotiators, and authorized signers. In addition, the offeror may identify if it has a preferred primary region (East or West) for the Government's consideration in the event that the offeror is among the highest ranked proposals for both SATOCs. The offeror may also identify that it has no preference for a primary region. Regardless of a preference for a primary region, the offeror still must provide pricing and coverage to both regions. The cover letter may also inform the Government of any other proposal or offeror elements such as key subcontractors, teaming arrangements, joint ventures, or business size and classification. A proposal that does not agree with all terms and conditions in the solicitation or a proposal that qualifies its agreement will be rejected. A proposal that states it only covers a specific region or only includes prices for a specific region will be rejected. The cover letter will not count towards the page limitation.
3.2. Page Limitation, Volume I
The number for pages per section may be varied by the offeror to suit its needs for certain identified sections, however, the total number of pages for Volume I of the proposal may not exceed 60 pages. There is no page limitation for Volume II.
NOTE: Items excluded from the page count are the Proposal Cover letter, the Table of Contents, Title or Index Page(s), Volume I Factor 3, and Volume II in its entirety.
Each page should be numbered consecutively within each section. The page size of the offeror’s proposal shall not exceed an 8-1/2 by 11 inches. Offerors are permitted to use 11 by 17 inch page size for Volume I, Factor 2, Element 2. For this factor, each 11 by 17 inch page will count as a single page. All text shall be no less than 12-point font and easily read. All text shall be typed and single-spaced.
Top, right, left and bottom margins should be no less than 1”. No information should be included in any margin except the following information which shall be added to the bottom margin. Exact placement (center, off center, etc.) and sequence of presentation is at the discretion of the offeror:
a. Page number. Pages for each factor should be separately and sequentially numbered (i.e., the first page submitted for evaluation of each factor should be “Page 1”).
b. Factor number and title. For example, “Factor 1 – Mobilization/Strategic Management Plan”. It is not necessary to label individual elements within the factors.
c. Solicitation Number
d. Company Name of Offeror and (at the offeror’s discretion) the company’s logo.
Page limitation shall include typewritten text pages, charts, graphs, figures, diagrams, schematics, etc., aside from those items specifically stated as exempt from the page count. Outlines and other similar information documents shall be included as numbered pages – no exceptions. A smaller type may be used on charts, graphs, figures, diagrams, and schematics to accommodate a “make to fit” software capability, however all text shall be legible and easily read.
Proposals which exceed the stated page count will have only the first pages that are within the required limits evaluated. All information appearing thereafter will not be evaluated.
4. VOLUME CONTENT
Proposals submitted in response to this solicitation shall consist of the contents required in the subparagraphs described below to be rated in descending order of importance:
4.1 Volume I, Factor 1 – Mobilization/Strategic Management Plans
4.1.1 Volume I, Factor 1, Element 1 – Deployment Plan – Mobilizing to Meet the Mission
This portion of the proposal is a detailed narrative that describes an offeror’s strategic ability to plan and execute a temporary roofing mission of varying magnitude. The following are suggested but not all inclusive of items that may demonstrate proficiency in this area:
Provide a corporate plan that demonstrates the firm’s ability to deploy and mobilize effective teams to include the number, types of disciplines, levels of expertise of each employee that may be required to deploy in response to a disaster. Include any established corporate policies or programs that demonstrate the offeror’s ability to plan, prepare, and execute the work. Offerors are encouraged to identify when and how subcontractors will be used and how these relationships are developed. The contractor is also responsible to verify key management personnel each year the contract is in place. The plan might include a description on corporate policy regarding rotational assignments for employees. The plan should demonstrate how the contractor will achieve the targeted production rate of 200+ roofs per day.
4.1.2 Volume I, Factor 1, Element 2 - Organizational and Managerial Structure to Support Rapid and/or Long-term Deployment The organizational structure of the offeror's proposed team (all subcontractors shall be included in this organizational structure) for this contract shall be outlined through a narrative and a diagrammed organizational chart. The relationship of these capabilities to the offeror shall be described; i.e. owned, subcontracted effort, joint venture, member of consortium, etc. The corporate/organizational narrative shall include a list of the projects, which have been executed under this organizational structure and the length of time the sub-organization(s) not owned by the offeror has been a part of the organizational structure (or the team). It is important that the offeror clearly define the organizational roles/responsibilities and the contractual/legal responsibilities of the team or joint venture units and describe how the project(s) will be accomplished under the proposed organizational structure. The contractor shall be aware of the percentage of work to be performed by its own organization as stated in Section 007200, FAR Clause 52.236-1, Performance of Work by the Contractor.
4.1.3 Volume I, Factor 1, Element 3 – Safety Programs
The offeror shall provide a narrative that describes its corporate Safety Program.
4.1.4 Volume I, Factor 1, Element 4 – Quality Control (QC) Programs The offeror shall provide a detailed narrative of its corporate Quality Control (QC) Program and its business practices, which demonstrates adherence to the QA/QC Program.
4.2 Volume I, Factor 2 – Experience, Personnel and Specialized Expertise
4.2.1 Volume I, Factor 2, Element 1 - Resumes of Key Personnel The offeror shall provide the resumes of the key management personnel, which it expects will execute the work that may be awarded under this contract. The resumes should clearly display proposed job title, education, special qualifications and experience record showing title, specific duties, responsibilities and assignments within at least the last five years. The purpose of this submittal is to identify the level of expertise available for this contract. After contract award, replacement of any key personnel shall be approved by the Contracting Officer after verifying that they meet or exceed the requirements of the solicitation. If further key management personnel are required to perform any work under this contract, the contractor will be required to submit their resumes for approval by the Contracting Officer. The following key personnel shall be identified:
4.2.1.1 Contractor Superintendent - The Contractor shall assign and provide a Superintendent to serve as the principal liaison with the Corps’ Contracting Officer.
4.2.1.2 Operations Manager - The offeror shall designate one individual as the Operations Manager that will be assigned to this contract. The Operations Manager shall be competent, experienced, and knowledgeable in the field of disaster recovery operations with at least five years’ experience in the management of disaster recovery operations and available by telephone 24 hours per day during hurricane season (1 June through 1 December). The Contractor shall designate an Operations Manager to act as a single point of contact (POC) for coordination with USACE temporary roofing management cell. The Operations Manager shall be prepared to pre-deploy to a disaster site or participate in partnering and planning meetings as needed and requested by USACE Contracting Officer. The contractor may be notified verbally by the Contracting Officer of a forthcoming task order, to be later confirmed in writing. The Operations Manager shall be responsible for the overall management of the contract including negotiation of task orders, schedule, and technical quality.
Accordingly, the Operations Manager must have the capacity and authority to act on behalf of the offeror and legally bind the contractor. The Operations Manager shall take immediate corrective action when performance is not acceptable to USACE. The Contractor shall oversee the development and implementation of necessary record keeping, administrative and quality control programs.
4.2.1.3. Other Key Personnel – The offeror shall provide the resumes of the following key personnel: Quality Control Manager, Contractor Database/Reporting Manager, Safety and Health Officer, and Contractor Strike- Team Leader) that would be required to execute a substantial portion of the work that may be awarded under this contract. The resumes should clearly display proposed job title, education, special qualifications and experience record showing title, specific duties, responsibilities and assignments within at least the last five (5) years. The purpose of this submittal is to identify the level of expertise available for this contract. Key personnel that result from a subcontract arrangement should be clearly annotated as such.
4.2.2 Volume I, Factor 2, Element 2 - Expertise in Disaster Response Provide at least three (3) and not more than five (5) examples of completed projects which demonstrate the offeror's and its team members' experience in performance of the work similar to that described in this solicitation. Each project identified must include a contract number, a reference contact name, address and telephone number, as well as email address if available. The projects must have been completed within the last six (6) years. A completed project is defined as: Work performed under a “project” that is physically complete and has been accepted by the customer. The offeror may provide additional narrative on any or all projects provided the offeror does not exceed the page count as specified in Section 002100. The offeror should present projects, which demonstrate its experience in project management and execution of disaster recovery related work. The offeror may include both federal and commercial work. The offeror must indicate whether it was the prime or subcontractor on each project. If the offeror was the prime contractor, the offeror shall also describe its primary role/duties in execution of the work (i.e. the major components of the project which were completed by the prime’s staff and major components which were subcontracted out). The offeror shall also provide information on the project as to the size, complexity, and distinctive and/or unique features of the project. The offeror should provide specific information to demonstrate that it has relevant experience to all of the possible activities for this project as listed in this solicitation.
4.2.3 Volume I, Factor 2, Element 3 - Expertise in Roofing or Roofing Missions Provide at least three (3) and not more than five (5) examples of completed projects which demonstrate the offeror's and its team members' experience in performance of the work similar to that described in this solicitation. Each project identified must include a contract number, a reference contact name, address and telephone number, as well as email address if available. The projects must have been completed within the last six (6) years. A completed project is defined as: Work performed under a “project” that is physically complete and has been accepted by the customer. The offeror may provide additional narrative on any or all projects provided the offeror does not exceed the page count as specified in Section 002100. The offeror should present projects, which demonstrate its experience in project management and execution of residential roof replacement or roofing repairs in response to hurricanes or other natural disasters. The offeror may include both federal and commercial work. The offeror must indicate whether it was the prime or subcontractor on each project. If the offeror was the prime contractor, the offeror shall also describe its primary role/duties in execution of the work (i.e. the major components of the project which were completed by the prime’s staff and major components which were subcontracted out). The offeror shall also provide information on the project as to the size, complexity, and distinctive and/or unique features of the project. The offeror should provide specific information to demonstrate that it has relevant experience to all of the possible activities for this project as listed in this solicitation.
4.2.4 Volume I, Factor 2, Element 4 - Expertise in Electronic Database Management to Track and Schedule Work
Describe an electronic tracking and database system for work assigned that provides continuity and efficiency in the field, and allows for enhanced documentation. It is suggested the offeror include their past performance information in their proposal to document historically the use of such systems in related work. The offeror shall clearly define roles and responsibilities associated with said proposal.
4.3 Volume I, Factor 3 - Past Performance
The offeror shall provide past performance ratings for each project submitted in Factor 2. The title of the project shall be consistent with the project experience description as required Factor 2.
If the offeror’s Contractor Performance Assessment Report (CPAR) is available, then the contractor shall not submit a Past Performance Questionnaire (Form PPQ-0, Attachment 1). For those offerors whose past performance information is not located in the automatic systems, offerors shall contact their references and request each reference complete the PPQ. The PPQ should be completed by an owner or owner’s representative not affiliated with the offeror’s firm and shall be signed by the customer.
CPARS ratings are preferred for any federal project. Past Performance Questionnaires (PPQs) completed by the customer are also acceptable (to include those previously completed), as are evaluations in other formats (Not CPAR or PPQ) if the evaluation criteria and rating types are similar to those used in a CPAR and/or PPQ evaluation, the evaluation includes a level of detail (or greater) as a CPAR and/or PPQ evaluation, and it is signed by the customer.
All evaluations or surveys shall contain the name, address, telephone number, and e-mail address of the customer evaluator who issued the evaluation or survey. The Government reserves the right to contact the customer to verify the offeror’s performance. Under no circumstances should the evaluation or survey be initiated by the offeror or a team member.
Completed PPQs shall be submitted with your proposal or to the designated personnel listed below NO LATER THAN the proposal due date. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the designated Government points of contact, via email at wayne.c.weidenhamer@usace.army.mil and lee.m.mccormick@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Do not submit PPQs for projects evaluated via CPARS. In the event an Offeror submits a PPQ for a project for which a CPARS evaluation is available, the CPARS evaluation will be considered authoritative.
The Government reserves the right to contact any persons who may be knowledgeable about the project or projects (this is not limited to contracts identified by the Offeror) submitted in an Offeror’s proposal. In addition, the Government may review and take into consideration other sources of information pertinent to the evaluation of the Offeror’s past performance including both the previous experience projects submitted and other similar projects performed by the Offeror. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), Past Performance Information Retrieval System (PPIRS, using all Commercial and Government Entity (CAGE)/DUNS numbers of team members (partnership, Joint Venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
While the Government may elect to consider data from other sources, the burden of ensuring detailed, current, accurate and complete past performance information rests with the Offeror.
mailto:ayne.c.weidenhamer@usace.army.mil mailto:ee.m.mccormick@usace.army.mil
0 Page 16 of 82
The Government intends to assess the relevancy and performance based on the past performance information provided received and/or retrieved. A significant achievement, unexplained or unresolved problem, or lack of relevant data may significantly impact the risk rating by the Source Selection Evaluation Board (SSEB).
Therefore, it is incumbent upon the offeror to include all relevant information, including demonstrated corrective actions, in its proposal.
In addition to the project information requested in this section, the offeror shall also provide notification and information concerning any projects where it’s right to proceed was terminated for default during the last six
(6) years, or so state that there were none.
Offerors that have no past performance record will be given an unknown/neutral performance rating. In rating past performance, the SSEB may consider available past performance information on predecessor companies, employment histories of key personnel, or major subcontractors performing key elements of the project.
4.4 Volume I, Factor 4 - Capacity
The offeror shall provide details regarding the fiscal, organizational, managerial, and physical capacity of the firm to manage disasters of varying magnitudes in conjunction with normal business operations and ongoing commitments. Corporate production standards, strategic business plans for future expansion, and sales projections may be included. The offeror must disclose any other disaster response contracts that it currently holds or intends to bid on with any federal, state, or local government agencies. For example, if an offeror intends to propose on other ACI contracts for the US Virgin Islands or CONUS, it should disclose that here.
4.5 Volume II – Price Proposal
4.5.1. Volume II, Section F, Tab 1 – SF1442, Solicitation, Offer, and Award The offeror shall fill out in its entirety all of SF1442 that applies to the offeror and it shall be signed and dated by an official that is able to legally bind the offeror. The offeror information entered in the SF1442 must match the information in SAM exactly.
4.5.2. Volume II, Section F, Tab 2 – Price Schedule
The offeror shall fill out the Excel spreadsheet Pricing Schedule. Prices stated must be inclusive of all overhead, markups, profit, labor, equipment and supplies for the items identified based on the performance period and the event size. Pricing must be included for each line item in the Price Schedule except Planning Effort and Work Order Processing.
In addition, the offeror shall include a written narrative explaining how pricing was determined. The offeror should account for annual Davis-Bacon wage determination increases, especially in high cost areas. The offeror should assume that task orders will be issued for urban coastal areas with high cost of living. The offeror should also account for escalation, inflation, and general supply and demand problems associated with a natural disaster when completing the Price Schedule. The effect of subcontracting to other firms, if anticipated, should be addressed as well.
The offeror should not expect approval of a request for equitable adjustment or claim due to the omission of pricing information that could have reasonably been anticipated when performing disaster recovery contract.
4.5.3. Volume II, Section F, Tab 3 - Representations and Certifications The offeror’s responsibility will be reviewed in accordance with FAR Part 9. The offeror shall complete all required Annual Representation and Certification through SAM at https://www.sam.gov.
5. PERFORMANCE AND PAYMENT BONDS
See Section 007200, Conditions of the Contract, FAR Clause 52.228-15, Performance and Payment Bonds - Construction. Bonds are not required in the proposal, but will be required for each task order awarded under http://www.sam.gov/ the contract. To have the bond considered valid, both the bond and the Power of Attorney must be original.
Facsimile copies will not be acceptable.
6. NOTICE REGARDING BUY AMERICAN ACT
The Buy American Act (41 U.S.C. 10a-10d) generally requires that only domestic construction material be used in the performance of this contract. Exception from the Buy American Act shall be permitted only in the case of non-availability of domestic construction materials. A bid or proposal offering non-domestic construction material will not be accepted unless specifically approved by the Government. When a bidder or offeror proposes to furnish non-domestic construction material, the bid or proposal must set forth an itemization of the quantity, unit price, and intended use of each item of such non-domestic construction material. When offering non-domestic construction material pursuant to this paragraph, bids or proposals may also offer, at stated prices, any available comparable domestic construction material, so as to avoid the possibility that failure of a non-domestic construction material to be acceptable under this paragraph will cause rejection of the entire bid. All bidders are cautioned that, prior Government conduct notwithstanding, the Contractor's selection of a domestic construction material (as defined in FAR 52.225-9, Buy American - Construction Materials) which would require the subsequent selection of a foreign construction material for compatibility is not a justification for waiver of the Buy American Act. It is the Contractor's responsibility to verify, prior to submitting the materials for approval that each system can be built to meet the contract specifications without the use of foreign construction materials.
CLAUSES INCORPORATED BY REFERENCE
52.204-6 Unique Entity Identifier OCT 2016 52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-22 Alternative Line Item Proposal JAN 2017 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-20 Requirements for Certified Cost or Pricing Data or OCT 2010
Information Other Than Certified Cost or Pricing Data 52.215-22 Limitations on Pass-Through Charges--Identification of OCT 2009
Subcontract Effort 52.216-27 Single or Multiple Awards OCT 1995 52.222-5 Construction Wage Rate Requirements--Secondary Site of the MAY 2014
Work 252.215-7008 Only One Offer JUL 2019 252.215-7010 Requirements for Certified Cost or Pricing Data and Data JUL 2019
Other Than Certified Cost or Pricing Data
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Priced contract resulting from this solicitation.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer U.S. Army Corps of Engineers, Omaha District, Attn: Contracting Officer, Contracting Division, 1616 Capitol Ave., Omaha Nebraska 68102-4901 by obtaining written and dated acknowledgment of receipt from the Contracting Officer, Contracting Division Representative, (e.g, Contract Specialist) or Office of Counsel Representative.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/
(End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFARS (48 CFR Chapter 2 ) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
Page 19 of 82 VALUATION OF OFFERORS
SECTION 002200
SUPPLEMENTARY INSTRUCTIONS
SUBMISSION REQUIREMENTS AND EVALUATION
1. INITIAL REVIEW OF PROPOSALS
Proposals will be reviewed upon receipt for conformance with the solicitation requirements. Proposals that do not conform to the solicitation requirements may be considered to have a “deficiency”, i.e. a defect that cannot be remedied by exchanges and/or permitted proposal revisions. If a proposal is suspected of having a deficiency, it will be brought to the immediate attention of the Source Selection Evaluation Board (SSEB) Chair, the appropriate advisor, and the Source Selection Authority (SSA). If the Source Selection Authority determines a proposal to be noncompliant with submission instructions making it thereby deficient, the proposal will not be evaluated further and will be eliminated from further consideration. The affected offeror shall be promptly notified of the decision.
2. SOURCE SELECTION
All proposals conforming to the solicitation requirements will be evaluated in accordance with the requirements of Sections 002100, Instructions to Offerors and 002200, Supplementary Instructions. The principal objective of the evaluation process is to make award of a contract to the responsible offeror(s) whose proposals are determined to be the "best value" to the Government, price and other factors considered. Should the Government determine that the award of the contract is not in the best interest of the Government, contract award will not take place.
3. SOURCE SELECTION EVALUATION BOARD (SSEB)
A Source Selection Evaluation Board (SSEB) will be established to conduct the evaluation of proposals received in response to this solicitation. The evaluation will be based on the content of the proposal and any subsequent discussions required, as well as information obtained from other sources, e.g. past performance information. The SSEB will not ordinarily evaluate information or data incorporated by reference or otherwise referred to, except for past performance. The identities of the SSEB personnel are confidential, and any attempt by the offerors to contact these individuals is prohibited.
4. EVALUATION CRITERIA
As established in Sections 002100 and 002200 of the solicitation, the following criteria will form the basis of proposal evaluation. Volume I – Technical Proposal is divided into four (4) factors. Volume II – Price Proposal will be subjectively evaluated in accordance with paragraph 4.3. The following table reflects the relative importance of areas that the SSEB shall thoroughly review and evaluate.
Technical evaluation factors are listed in descending order of importance.
Volume I, Factor 1 Mobilization/Strategic Management Plan Volume I, Factor 2 Experience, Personnel, and Specialized Expertise Volume I, Factor 3 Past Performance Volume I, Factor 4 Capacity Volume II
All evaluation factors, other than cost or price, when combined, are more important than cost or price.
4.1 The evaluation ratings for Technical Factors 1, 2 and 4 will be on an adjectival basis in conjunction with a…