20200721 Ft Peck GSU Install Site Visit Presentation.pptx

PPTX presentation 22 MB Posted

Attached to
GSU Transformer Installation at Ft. Peck Powerhouse, MT
Solicitation number
W9128F20R0039
Issued by

About this file

This document provides details on a federal solicitation for transformer installation services at Fort Peck Powerhouse in Montana. The U.S. Army Corps of Engineers Engineering District Omaha is seeking bids to remove two existing single-phase GSU transformer banks and associated equipment, move two government furnished transformers to new locations, install new feeders and connections, and perform related auxiliary work. The solicitation will close on August 11, 2020. A virtual site visit was held on July 21, 2020 to provide additional project information. The estimated construction cost ranges between $5-10 million. The primary NAICS code is 237130 for power and communication line structure construction with a small business size standard of $36.5 million. Interested parties can obtain the solicitation documents through the beta SAM.gov website using the provided solicitation number. The selected contractor must commence work upon award and complete all work within 490 calendar days of the notice to proceed.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Welcome

Fort peck Dam Generator Step-Up Transformer Install virtual site visit Solicitation: W9128F20R0039 July 21, 2020

To join the meeting: https://usace.webex.com/meet/ronald.s.beyer

Conference line: 1-888-557-8511 (Toll-Free)

1-215-446-3649 (US)

Access Code: 4600292 Security Code: 1234 Photo courtesy of visitmt.com

Agenda – July 21, 2020

1000 – 1005Introductions / Project Overview
1005 – 1010Contracting Briefing / Rules of Engagement
1010 – 1020Project Site Specifics
1020 – 1045Statement of Work / Project Specs
1045 – 1100Q&A

introductions USACE, Omaha District Office

Ron BeyerProject Manager
Robin PuskarProgram Manager
Nadine CataniaContract Officer
Lucas KirkpatrickElectrical Engineer
Kalvin KalafutStructural Engineer
Klaidas HallMaterials (Geotech) Engineer

Fort Peck

Dale PughMaintenance and Operations Manager
Tim ZabrockiAssistant Maintenance and Operations Manager

Missouri River Resident Office (Bismarck, ND) Tom Westenburg Resident Engineer

Hydroelectric Design Center (HDC), Portland OR Tom Andes Electrical Engineer

Projected Project schedule Pre-solicitation 22 Jun 2020 to 07 Jul 2020

Advertise Period 10 Jul 2020 to 11 Aug 2020

Contractor Site Visit 21 Jul 2020

Award 08 Sep 2020

Outage Period Apr – Nov 2021

USACE, Omaha District Contracting Nadine Catania, contracting officer Rules of Engagement Contract Specialist is the government authority during visit All questions or concerns must be directed to the Contract Specialist No side bars or independent conversations between contractors and government personnel No discussions relating to other Corps acquisitions No corporate denigration or sabotage will be tolerated Hold all questions until the designated question and answer session All questions will be documented and posted on beta.SAM (www.beta.sam.gov) There will be a site visit opportunity once the solicitation is posted If travel restrictions prevent an onsite visit, a virtual site visit will be conducted

Contract and evaluation information

Contract Information Contract Type: Fixed price construction Solicitation Type: Request for Proposal (RFP) Contract Magnitude: $5M-$10M Period of Performance: 490 days from NTP

Evaluation Factors Experience (Company) Past performance Technical approach Personnel qualifications and experience Small business participation Price

Projnet and contact information

ProjNet Used for contractor submitted questions Web site: https://www.projnet.org Bidder Inquiry Key: MP2VCM-FMSMU7 Questions need to be submitted before 5 pm Central Monday August 3rd, 2020

Contract Specialist Contact Information Dan Monahan Email: Daniel.D.Monahan@usace.army.mil Phone: 402-995-2886

File Name

Project SITE Specifics Ft. Peck Switchyard 1

Ft Peck Project Brief Tim Zabrocki, Assistant Maintenance and Operations Manager

Project overview Remove Two existing transformer banks (T2 and T4) and associated features 15kV Oil Filled Cable system Rail System by T2, T3, T4 transformers Install KY4A three-phase transformer and associated foundations, etc.

KY4A 15kV feed KZ2A three-phase transformer and associated foundations, etc.

Priority should be placed on limiting the outage period for transformer KZ2A installation.

Project overview Site Conditions Assume lead paint on everything Bushing oil has PCB contamination Switchyard will be partially energized during construction Rail System is inoperable

Transformer Bank 2 Bank 2, currently 3 Single Phase Transformers

Bank 2

Bank 2: 3 Single Phase 13.8KV to 69 KV transformers

Transformer Bank 4 Bank 4 current location in Switchyard 1

Bank 4

Bank 4, 3 single phase 13.8KV to 115KV transformers

Switchyard one Rails facing the Power House Parking lot

Same rails opposing view

New Transformers Locations, and approximate Final locations

KZ2A

New Transformers Locations, and approximate Final locations

KY4A

Proposed Locations of KZ2A and KY4A

Staging Laydown Areas

There is additional Areas for Contractor Trailers and Staging South of the Switchyard.

Oilostatic Feeders

T3 and T4 Feeders oilostatic feeders

Bank 4 Feed Bank 3 Feed

Both Feeds

Both Feeds in Tunnel Cable Tunnel Turn

Transitions Oilostatic tank and pumps

Oilostatic In Butterfly Valve Corridor Bank 3 Bank 4

Bank 3 Feed

72.5KV Sections and 115KV Sections

72.5KV

115 KV

72.5 KV Disconnect Switches

115KV Bus

Removals of 72.5KV Bus and 115KV bus

File Name

Statement of work and project Specs

Hydroelectric design center Tom Andes, electrical engineer

Statement of Work Work includes removal of the following:

Transformer Banks T2 & T4 All external connections Existing medium and high voltage connections to nearest point of termination 15kV lower bus support structures & foundations as needed for install of new GSUs low voltage power, control, annunciation, and protection conduit and cabling from transformer to first point of termination in Powerhouse Existing T2, T3, T4 transformer foundations as necessary to allow for new KZ2A and KY4A foundations.

15kV Oil Filled Cable system Cable & support brackets between powerhouse and transformer T3 & T4 Oil tank, pumping equipment, control cabinet, oil manifolds, power & control wiring to nearest point of termination.

Rail and rail ties along banks T2, T3, and T4, and North-East section to reactor

Work includes installation of the following:

Transformer KY4A Installation New Concrete foundation, Oil Containment, Seismic Anchorage Move GFE Transformer from temporary storage to permanent location Ground GSU to existing ground mat New 15kV KY4A feeder bus from powerhouse to existing bus riser at T4 Bay New 15kV overhead conductors & support structures from existing bus riser to GSU New 115kV high voltage conductors & support structures New 115kV disconnect switch 961 between KY4A and 115kV system New low voltage power, protection, control, and annunciation conduit and cabling

Work includes installation of the following:

Transformer KZ2A Installation New Concrete foundation, Oil Containment, Seismic Anchorage Move GFE Transformer from temporary storage to permanent location Ground GSU to existing ground mat Reuse existing 15kV T2 solid dielectric conductors from powerhouse to switchyard bus riser at T2 Bay New 15kV overhead conductors & support structures from existing bus riser to GSU New 69kV conductors between KZ2A and HV disconnect switch New 69kV disconnect switches 1141, 1143, and 1149 New low voltage power, protection, control, and annunciation conduit and cabling

Project specific details

Ground penetrating radar, etc. required to minimize damage and repair to existing power, ground, oil drain lines, etc.

Repair and replace ground grid as needed Control cables to powerhouse control room to be brought to spreader room with enough extra length to allow termination by the Government in the control room above.

Commissioning partnership between KTR, Transformer Field Engineer, and Government.

Virtual site visit Q & A image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.emf image15.png image16.jpeg image17.jpeg image18.JPG image19.png image20.jpeg image21.jpeg image22.jpeg image23.jpeg image24.jpeg image25.jpeg image26.jpeg image27.jpeg image28.png image29.png image30.png image31.emf image32.png image33.png image34.png image1.png image2.png image3.png image4.tiff

File details come from the government source that posted it. Updated .