This amendment to a solicitation package provides revisions to specifications and drawings for the construction of a Company Operations Facility at Butts Army Airfield, Fort Carson, Colorado. Offerors must acknowledge receipt of this amendment by completing items 8 and 15 on the SF30 form and returning copies, or by separate letter. Proposals will be received until 2:00 PM local time on April 9, 2020. The Army Corps of Engineers, Omaha District is the issuing office. Revisions include updating the specifications table of contents to correctly list all sections. Electronic proposals must be submitted per the instructions in section 00 22 00 of the RFP.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Amendment No. 0009 W9128F
COMPANY OPERATIONS FACILITIES, PN 77303, BUTTS ARMY AIRFIELD (FY20), FORT CARSON, COLORADO
See attached documentation for content of the amendment revisions to solicitation
Date for receipt of proposals is 9 APR 2020 at 1400 hours
Government Point of Contact: Bill Rawe, Contract Specialist, William.T.Rawe@usace.army.mil
U.S.ARMY CORPS OF ENGINEERS, OMAHA
Rocky Mountain Area Office Attn: CONTRACTING DIVISION (CENWO-CT-M) 5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919
See Item 6
W9128F-20-R-0031
03/23/2020
01/23/2020
03/23/2020
Am #0009 - 1
Am #0009 - 2 (Continuation SF 30)
23 March 2020 Solicitation No. W9128F 20 R 0031
Date of Issue: 23 January 2020 Date of Receiving Proposals: 9 APR 2020
SUBJECT: Amendment No. 0009 to Request for Proposal Solicitation Package for Construction of COMPANY OPERATIONS FACILITIES, PN 77303, BUTTS ARMY AIRFIELD
TO: Prospective Offerors and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.) NONE
b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment. For convenience, on the revised specification pages, changes have been identified with highlighting, all portions of the revised specification pages apply regardless of whether changes are shown with highlighting.
Pages or Sections Deleted Pages or Sections Substituted or Added 00 01 10 Table of Contents 00 01 10 Table of Contents**
**Note: Am #0009 corrects the specifications Table of Contents to list sections inadvertently left out of the Table of Contents; however, the advertised set of specifications included these sections. The Table of Contents is also updated to show sections added and deleted by previous amendments.
2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.
3. Electronic Proposals. Provide proposals via the instructions provided in Section 00 22 00 of the Request for Proposal.
4. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 9 APR 2020.
Attachments:
Specifications listed in 1.b., above
U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901
23 MAR 2020
nep/2160
00 01 10 - 1 PROJECT TABLE OF CONTENTS
SPECIFICATIONS FOR CONSTRUCTION
OF
COMPANY OPERATIONS FACILITIES
PROJECT NO. 77303
BUTTS ARMY AIRFIELD (FY20)
FORT CARSON, COLORADO
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00-SF1442 SOLICITATION/CONTRACT FORM (SF 1442)
00 10 00-CLIN CONTRACT LINE ITEM PRICING SCHEDULE
00 21 00 INSTRUCTIONS TO OFFERORS (RFP)
00 22 00 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA AND BASIS
OF AWARD
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 GENERAL CONDITIONS (CONTRACT CLAUSES – RFP)
00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)
DIVISION 01 - GENERAL REQUIREMENTS
01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS
FCREG FORT CARSON SPECIFIC REGULATIONS AND GUIDANCE
PROJSIGN PROJECT SIGN DETAILS
CO200002 COLORADO GENERAL WAGE DECISION – HEAVY
CO200008 COLORADO GENERAL WAGE DECISION – HIGHWAY
CO200022 COLORADO GENERAL WAGE DECISION – BUILDING
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
REGISTER SUBMITTAL REGISTER
E4025 ENGINEERING FORM 4025 TRANSMITTAL FORM
01 33 29 SUSTAINABILITY REPORTING
01 33 29AT1 HPSB CHECKLIST
01 33 29AT2 TPC CHECKLIST
01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 41 26.05 24 (FEDERAL FACILITIES COLORADO) NPDES PERMIT REQUIREMENTS FOR STORM
WATER DISCHARGES FROM CONSTRUCTION SITES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.00 10AT SAMPLE QUALITY CONTROL REPORT
01 45 00.15 10 RESIDENTIAL MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 57 20.00 10AT ATTACHMENTS TO SECTION 01 57 20.00 10
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
01 78 24.00 10 FACILITY DATA REQUIREMENTS
01 78 36.00 24 WARRANTY OF CONSTRUCTION
01 78 39.00 24 AS-BUILT DRAWINGS
01 78 39.00 24AT MODIFICATIONS AND TITLE BLOCK EXAMPLES
01 91 00.15 TOTAL BUILDING COMMISSIONING
01 91 00.15A 01 91 00.15 APPENDIX A – OWNER’S PROJECT REQUIREMENTS
Am #0009
00 01 10 - 2 PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS (CONTINUED)
01 91 00.15B 01 91 00.15 APPENDIX B – BASIS OF DESIGN
01 91 00.15C 01 91 00.15 APPENDIX C – Cx DESIGN PHASE PLAN
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 35 43 GROUND AND POLISHED CONCRETE
03 39 00.00 10 CONCRETE CURING
03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION
03 45 00 PRECAST ARCHITECTURAL CONCRETE
03 45 33 PRECAST STRUCTURAL CONCRETE
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 36 SPRAY FOAM INSULATION
07 42 13 METAL WALL PANELS
07 54 19 POLYVINYL-CHLORIDE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 34 59 VAULT DOORS AND DAY GATES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 51 13 ALUMINUM WINDOWS
00 01 10 - 3 PROJECT TABLE OF CONTENTS
DIVISION 08 – OPENINGS (CONTINUED)
08 62 00 *TUBULAR DAYLIGHTING DEVICES
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 06 00 SCHEDULES FOR FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
[*Am-4]
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 14 00.20AT INTERIOR SIGNAGE SCHEDULE
10 14 53 TRAFFIC SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 13 WIRE MESH PARTITIONS
<TEXT DELETED>
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
10 51 14 TA-50 MILITARY LOCKERS
10 81 13 BIRD CONTROL DEVICES
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 13 17.00 10 DRY PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL
00 01 10 - 4 PROJECT TABLE OF CONTENTS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) (CONTINUED)
23 11 25 FACILITY GAS PIPING
23 52 00.10 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 COOLING AND HEATING WATER PIPING SYSTEMS
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
[*Am-4]
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.02 FT CARSON COF - HVAC (BUILDING LEVEL CONTROLS ONLY)
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
26 42 14.10 10 FORT CARSON CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
[*Am-9]
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
[*Am-2]
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING
32 11 23 AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.03 CONCRETE PAVEMENT FOR ROADWAYS AND SITE FACILITIES
32 15 00 AGGREGATE SURFACING
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 00.00 10 CHAIN LINK FENCE
32 92 19 SEEDING
32 93 00 EXTERIOR PLANTS
00 01 10 - 5 PROJECT TABLE OF CONTENTS
DIVISION 33 - UTILITIES
33 05 23 TRENCHLESS UTILITY INSTALLATION
33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING
33 40 00 STORM DRAINAGE UTILITIES
33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
| Standard_Form_30 |
| Am-0009_W9128F-20-R-0031_Narrative |
| 00 01 10 Table of Contents |
File details come from the government source that posted it. Updated .