This amendment to a solicitation package provides revisions to specifications and drawings for the construction of a Company Operations Facility at Butts Army Airfield, Fort Carson, Colorado. Offerors must acknowledge receipt of this amendment by completing items 8 and 15 on the SF30 form and returning copies, or by separate letter. Proposals will be received until 2:00 PM local time on April 9, 2020. The Army Corps of Engineers, Omaha District is the issuing office. Revisions include updating the specifications table of contents to correctly list all sections. Electronic proposals must be submitted per the instructions in section 00 22 00 of the RFP.

View the file

Other files

File Type Posted
Am-0008_W9128F-20-R-0031.pdf PDF
Am-0007_W9128F-20-R-0031.pdf PDF
Am-0006_W9128F-20-R-0031.pdf PDF
Am-0005_W9128F-20-R-0031.pdf PDF
Am-0004_W9128F-20-R-0031.pdf PDF
Am-0003_W9128F-20-R-0031.pdf PDF
Am-0002_W9128F-20-R-0031.pdf PDF
Am-0001_W9128F-19-R-0031.pdf PDF
SPECS_W9128F-20-R-0031.pdf PDF
FCEO VOL. 2 ADVERTISEMENT.PDF PDF
FCEO VOL. 1 ADVERTISEMENT.PDF PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amendment No. 0009 W9128F

COMPANY OPERATIONS FACILITIES, PN 77303, BUTTS ARMY AIRFIELD (FY20), FORT CARSON, COLORADO

See attached documentation for content of the amendment revisions to solicitation

Date for receipt of proposals is 9 APR 2020 at 1400 hours

Government Point of Contact: Bill Rawe, Contract Specialist, William.T.Rawe@usace.army.mil

U.S.ARMY CORPS OF ENGINEERS, OMAHA

Rocky Mountain Area Office Attn: CONTRACTING DIVISION (CENWO-CT-M) 5475 Tech Center Drive, Suite 205 Colorado Springs, CO 80919

See Item 6

W9128F-20-R-0031

03/23/2020

01/23/2020

03/23/2020

Am #0009 - 1

Am #0009 - 2 (Continuation SF 30)

23 March 2020 Solicitation No. W9128F 20 R 0031

Date of Issue: 23 January 2020 Date of Receiving Proposals: 9 APR 2020

SUBJECT: Amendment No. 0009 to Request for Proposal Solicitation Package for Construction of COMPANY OPERATIONS FACILITIES, PN 77303, BUTTS ARMY AIRFIELD

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.) NONE

b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment. For convenience, on the revised specification pages, changes have been identified with highlighting, all portions of the revised specification pages apply regardless of whether changes are shown with highlighting.

Pages or Sections Deleted Pages or Sections Substituted or Added 00 01 10 Table of Contents 00 01 10 Table of Contents**

**Note: Am #0009 corrects the specifications Table of Contents to list sections inadvertently left out of the Table of Contents; however, the advertised set of specifications included these sections. The Table of Contents is also updated to show sections added and deleted by previous amendments.

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Proposals. Provide proposals via the instructions provided in Section 00 22 00 of the Request for Proposal.

4. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 9 APR 2020.

Attachments:

Specifications listed in 1.b., above

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

23 MAR 2020

nep/2160

00 01 10 - 1 PROJECT TABLE OF CONTENTS

SPECIFICATIONS FOR CONSTRUCTION

OF

COMPANY OPERATIONS FACILITIES

PROJECT NO. 77303

BUTTS ARMY AIRFIELD (FY20)

FORT CARSON, COLORADO

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 10 00-SF1442 SOLICITATION/CONTRACT FORM (SF 1442)

00 10 00-CLIN CONTRACT LINE ITEM PRICING SCHEDULE

00 21 00 INSTRUCTIONS TO OFFERORS (RFP)

00 22 00 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA AND BASIS

OF AWARD

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

00 72 00 GENERAL CONDITIONS (CONTRACT CLAUSES – RFP)

00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)

DIVISION 01 - GENERAL REQUIREMENTS

01 30 00.24 OTHER ADMINISTRATIVE AND SPECIAL REQUIREMENTS

FCREG FORT CARSON SPECIFIC REGULATIONS AND GUIDANCE

PROJSIGN PROJECT SIGN DETAILS

CO200002 COLORADO GENERAL WAGE DECISION – HEAVY

CO200008 COLORADO GENERAL WAGE DECISION – HIGHWAY

CO200022 COLORADO GENERAL WAGE DECISION – BUILDING

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

REGISTER SUBMITTAL REGISTER

E4025 ENGINEERING FORM 4025 TRANSMITTAL FORM

01 33 29 SUSTAINABILITY REPORTING

01 33 29AT1 HPSB CHECKLIST

01 33 29AT2 TPC CHECKLIST

01 33 39.00 10 ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 41 26.05 24 (FEDERAL FACILITIES COLORADO) NPDES PERMIT REQUIREMENTS FOR STORM

WATER DISCHARGES FROM CONSTRUCTION SITES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.00 10AT SAMPLE QUALITY CONTROL REPORT

01 45 00.15 10 RESIDENTIAL MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 57 20.00 10AT ATTACHMENTS TO SECTION 01 57 20.00 10

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 FACILITY DATA REQUIREMENTS

01 78 36.00 24 WARRANTY OF CONSTRUCTION

01 78 39.00 24 AS-BUILT DRAWINGS

01 78 39.00 24AT MODIFICATIONS AND TITLE BLOCK EXAMPLES

01 91 00.15 TOTAL BUILDING COMMISSIONING

01 91 00.15A 01 91 00.15 APPENDIX A – OWNER’S PROJECT REQUIREMENTS

Am #0009

00 01 10 - 2 PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS (CONTINUED)

01 91 00.15B 01 91 00.15 APPENDIX B – BASIS OF DESIGN

01 91 00.15C 01 91 00.15 APPENDIX C – Cx DESIGN PHASE PLAN

DIVISION 03 - CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 35 00.00 10 CONCRETE FINISHING

03 35 43 GROUND AND POLISHED CONCRETE

03 39 00.00 10 CONCRETE CURING

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE CONSTRUCTION

03 45 00 PRECAST ARCHITECTURAL CONCRETE

03 45 33 PRECAST STRUCTURAL CONCRETE

DIVISION 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 21 16 MINERAL FIBER BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 36 SPRAY FOAM INSULATION

07 42 13 METAL WALL PANELS

07 54 19 POLYVINYL-CHLORIDE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 34 59 VAULT DOORS AND DAY GATES

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 51 13 ALUMINUM WINDOWS

00 01 10 - 3 PROJECT TABLE OF CONTENTS

DIVISION 08 – OPENINGS (CONTINUED)

08 62 00 *TUBULAR DAYLIGHTING DEVICES

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

[*Am-4]

DIVISION 10 - SPECIALTIES

10 14 00.20 INTERIOR SIGNAGE

10 14 00.20AT INTERIOR SIGNAGE SCHEDULE

10 14 53 TRAFFIC SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 13 WIRE MESH PARTITIONS

<TEXT DELETED>

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 51 13 METAL LOCKERS

10 51 14 TA-50 MILITARY LOCKERS

10 81 13 BIRD CONTROL DEVICES

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 17.00 10 DRY PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL

00 01 10 - 4 PROJECT TABLE OF CONTENTS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) (CONTINUED)

23 11 25 FACILITY GAS PIPING

23 52 00.10 HEATING BOILERS

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 COOLING AND HEATING WATER PIPING SYSTEMS

23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT

[*Am-4]

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.02 FT CARSON COF - HVAC (BUILDING LEVEL CONTROLS ONLY)

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 08 00 APPARATUS INSPECTION AND TESTING

26 09 23.00 40 LIGHTING CONTROL DEVICES

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 14.10 10 FORT CARSON CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

[*Am-9]

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

[*Am-2]

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING

32 11 23 AGGREGATE BASE COURSES

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.03 CONCRETE PAVEMENT FOR ROADWAYS AND SITE FACILITIES

32 15 00 AGGREGATE SURFACING

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 00.00 10 CHAIN LINK FENCE

32 92 19 SEEDING

32 93 00 EXTERIOR PLANTS

00 01 10 - 5 PROJECT TABLE OF CONTENTS

DIVISION 33 - UTILITIES

33 05 23 TRENCHLESS UTILITY INSTALLATION

33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING

33 40 00 STORM DRAINAGE UTILITIES

33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

Standard_Form_30
Am-0009_W9128F-20-R-0031_Narrative
00 01 10 Table of Contents

File details come from the government source that posted it. Updated .