This document provides details for a forthcoming $95 million Multiple Award Task Order Contract solicitation for Rapid Disaster Infrastructure work. Up to four 8(a) contractors will be awarded indefinite delivery, indefinite quantity contracts with a minimum guarantee of $2,500 each. Task orders will be competed within the contract pool and may be cost reimbursement, cost-plus-fixed-fee, or firm fixed price contracts. The base period is one year with four optional one-year extensions. Work will include time-sensitive flood recovery, infrastructure restoration, emergency management, and military construction projects requiring mobilization within three days. Projects may occur across six Midwestern states. The solicitation is expected to be released on January 31, 2019.

W9128F19R0027 Amendment No. 0002

View the file

Other files for this federal contract opportunity

Other files attached to $95M Multiple Award Task Order Contract (MATOC) for Rapid Disaster Infrastructure (RDI) 8(a), newest first.
File Type Posted
W9128F19R0027_Amendment_03.pdf PDF
Amendment__0003_Attch2_Cost_Spreadsheet_RDI__8a_27JUN19.xlsx XLSX spreadsheet
W9128F-19-R-0027_As-Built_Template_Attachment.pdf PDF
W9128F19R0027_Amendment_01.pdf PDF
01_33_00_E4025_Shop_Drawings_Template_Attachment.pdf PDF
Attch2_Cost_Spreadsheet_RDI__8a.xlsx XLSX spreadsheet
01_33_00_REGISTER.pdf PDF
W9128F19R0027_RDI_I_8a_MATOC_RFP__-.pdf PDF
Pre-Solicitation_Notice_RDI_8(a).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9128F19R0027

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

RDI I $95M 8(a) Regional MATOC

1. The purpose of this amendment is to correct the language in Sections 00 22 00, Supplementary Instructions and 01 11 00, Summary of Work.

2. The proposal due date and time remains unchanged on July 9, 2019 at 2 pm local (central) time.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 40

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Jun-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128F19R0027

X 9B. DATED (SEE ITEM 11)

07-Jun-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE

25-Jun-2019

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDEMENT 0002 - 01 11 00

REVISED 01 11 00 (AM#0002)

Section 01 11 00

SUMMARY OF WORK

1.0 INTRODUCTION

This is a solicitation for an Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC) for 8(a) contractors. The shared contract capacity of the MATOC is $95 million for an ordering period of five (5) years: one (1) base year and four (4) one (1) year options.

2.0 BACKGROUND

This MATOC will be executed in support of the RDI Program. The RDI Program is a successor to the Security, Disaster, Infrastructure and Construction (SDIC) Program, with the exception that RDI does not include Tenant Renovations in Secure Spaces (TRSS) activities.

RDI and SDIC contracts require very similar management, planning, and execution. It is imperative that RDI contractors be capable of administering time-sensitive and cost reimbursement type projects.

3.0 SCOPE

This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.

Projects may vary in size, complexity, and location, and will require a high degree of flexibility and adaptability. Contractors must respond quickly and effectively. The diverse scopes of work are time-sensitive, which necessitates a timely response in order to mitigate threat to life and property and/or operational impacts to the government. Examples include but are not limited to:

*Flood Recovery: flood control and water diversion projects, embankments, channel alignments and flood control structures in support of civil works missions.

*Infrastructure Recovery: restoration, repair, and demolition of facilities, utilities, real property systems, and other vital infrastructure requirements with time constraints that prohibit the use of other contract mechanisms.

*Emergency Management: response actions such as unwatering missions, debris recovery, temporary housing, and other actions to meet vital mission requirements.

*Military: construction of facilities, infrastructure, water and sanitation systems, electrical systems, natural gas and other energy systems, fences, lighting, and roads to support troop movements and other crucial military missions with time constraints that prohibit use of other contract mechanisms.

Each specific Task Order Request For Proposal will identify when the mobilization must commence; however, emergency recovery actions may require mobilization within three (3) days of Government Notification.

Projects may require incidental design and/or ecological/environmental, hazardous waste recovery, and munitions work.

This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in v a r i o u s l o c a t i o n s w i t h i n t h e U . S . ( d e f i n e d a s a l l 5 0 s t a t e s , D i s t r i c t o f C o l u m b i a , a n d o u t l y i n g a r e a s ) Nebraska, Iowa, Kansas, Missouri, South Dakota, and North Dakota.

(AM#0002) Individual Task Orders will further define specific project requirements once identified.

4.0 APPLICABLE DOCUMENTS

The Contractor shall comply with all applicable Federal, State, and Local requirements, codes, policies, statutes, etc. Task Orders will be performed at a variety of locations, to include civilian sites and military installations. Coordination with installation’s force protection, and other governmental entities will require the Contractor to obtain and be familiar with the appropriate and applicable documents. It is the Contractor’s responsibility to identify and comply with all applicable requirements. Applicable documents may include, but are not limited to: Unified Facility Criteria (UFC), International Building Code (IBC), National Fire Protection Association (NFPA), and the National Electric Code (NEC). When specified by Task Orders (TOs), the Contractor will also be required to follow military construction criteria.

5.0 ENVIRONMENTAL REQUIREMENTS

The Contractor shall be cognizant of all appropriate environmental laws, regulations, and guidelines. The Contractor shall ensure that all work activities performed by his personnel, subcontractors and suppliers are executed as required by these laws and regulations. Any incident of noncompliance noted by the Contractor shall immediately be brought to the attention of the Contracting Officer or Contracting Officer’s Representative (COR). A COR will be approved by the Contracting Officer and identified in each task order.

5.1 General

5.2 Permits/Approvals

The Contractor shall investigate requirements and obtain all applicable permits, licenses, approvals, certificates, etc., necessary to accomplish the work specified in the individual Task Orders. The Contractor shall notify the Contracting Officer or Contracting Officer’s Representative of any delay in obtaining the necessary permits or approvals.

5.3 Treatment Storage and/or Disposal of Hazardous Materials

Under this RDI MATOC, Treatment Storage and/or Disposal of Hazardous Materials must be incidental. The Contractor shall ensure on-site management, transportation, storage, treatment, and disposal of all hazardous/special waste materials complies with all applicable federal, state, and local laws and regulations.

6.0 SAFETYAND HEALTH

See Section 01 35 26 Governmental Safety Requirements. Individual Task Orders may contain additional requirements.

7.0 MANAGEMENT AND REPORTING INSTRUCTIONS

7.1 Work Plan (WP)

Immediately following Task Order award, the Contractor will submit a WP. The WP must be approved by the Government prior to start of on-site activities. Any deviation from the approved plan must be approved by the Contracting Officer or authorized representative.

The WP should fully describe activities that will be performed by the Contractor and shall contain, at a minimum, the following:

a. A Statement of work and objectives to be accomplished

b. A description of project implementation, to include the method of operation, type of equipment, personnel required, and other special considerations

c. A schedule that identifies requirements necessary to complete the required work, in addition to key milestones

d. Permits, licenses, certificates, and other pertinent compliance documents

e. An organizational chart and a roster of Key Personnel and their responsibilities

7.2 Work Breakdown Structure (WBS)

For each Task Order, the Contractor shall prepare and submit for approval a WBS compatible with the Construction Specifications Institute (CSI) format for construction activities. The approved WBS shall be used to report the cost and schedule statuses of all required tasks.

7.3 Integrated Master Schedule (IMS)

The Contractor shall prepare and submit an IMS for approval. The IMS shall be in the form of a Gantt chart and shall include a Critical Path Method (CPM) analysis. The schedule shall be resource-loaded and correlated to the approved WBS.

7.4 Contractor’s Progress, Status, and Management Report (CPSMR)

The Contractor shall prepare and submit a CPSMR. The CPSMR shall be used by the Government to review and evaluate the progress of work and to identify existing or potential problem areas. The Contractor shall report progress and document all key events on a weekly basis. The CPSMR shall include a summary of the events that occurred during the reporting period, and shall discuss performance, identifying problems and proposed solutions, corrective actions taken, and unresolved issues.

7.5 Cost Performance Report (CPR)

The Contractor shall implement and maintain a performance measurement system to support the gathering of cost and schedule data, for the purpose of determining program status. The approved WBS shall be used for reporting cost. The CPR presents the baseline against which actual cost and schedule performance is measured. Submittals shall include appropriate cost figures and related data necessary to accurately ensure daily project costs and schedule status. This report shall go beyond the usual reporting of ‘Expenditures to ate’ and ‘Estimated Cost to Complete’ by establishing earned value factors. This will ensure that the project stays on budget and schedule. From these figures the Contractor shall develop time-phased spending curves that correlates work progress and the rate of expenditure. The CPR shall be submitted weekly.

7.6 RDI Program Cost Reimbursement Principles and Processes

Principles:

a. An ability to accurately track all costs on a daily basis and perform reasonable forecasts is paramount to the integrity of cost reimbursable contract management.

Without this ability, there is significant damage to the viability of the program.

b. If costs are not tracked accurately or are omitted, those errors must be brought to the attention of the appropriate USACE representatives immediately for appropriate resolution.

c. Cost reimbursable contracts require procurement strategies to maintain expectations for cost, schedule, quality, and safety. For example, the prime contractor may need to self-perform higher risk elements of work under the cost reimbursement provisions and have subcontractors perform the well-defined/low risk elements of work under firm fixed price subcontracts.

Processes:

a. Project specific coordination will be held frequently (oftentimes on a daily basis) to support timely decision making. The contractor, and selected subcontractor representatives, shall participate in the coordination to support needed decision making.

b. Daily Decision Making. Daily planning and execution will be reviewed by appropriate representatives from USACE and frequently within on-site command posts. Further, the project will be managed and administered through daily work projections, daily cost reports, daily Quality Control Reports (QCRs) daily planning documents, and other deliverables necessary to perform the mission.

c. The RDI contractor shall adhere to the following RDI processes, which are not inclusive of all contract management and administration and other contract requirements:

1. Daily Work Projections

a) Coordination meetings occur between USACE and Contractor.

b) Contractor develops Work Projection Documents (WPDs) (reference Attachment 1) for both

Home and Field offices.

c) Contractor submits WPDs to USACE.

d) USACE reviews WPDs and identifies any issues and/or concerns.

e) Contractor and USACE resolve issues and/or concerns at the Field Level or request resolution from the Contracting Officer.

f) Contractor executes/procures work.

2. Change Management (fee bearing change):

a) In-Scope differing site condition is discovered.

b) Contractor notifies the Contracting Officer IAW clause 52.236-2 and holds meeting with USACE to discuss plans and resource requirements.

c) Contractor develops plan.

d) Contractor submits to USACE.

e) USACE reviews plan.

f) The Contracting Officer issues written direction

g) Contractor executes/procures change items.

3. Change Management (non-fee bearing):

a) In-Scope non-material differing site condition is discovered.

b) Contractor holds meeting with USACE to discuss plans and resource requirements.

c) Contractor develops plan.

d) Contractor submits to USACE COR and KO.

e) USACE reviews plan.

f) Contractor executes/procures change items.

4. Invoicing:

a) Contractor reconciles approved costs.

b) Contractor develops invoice.

c) Contractor submits invoice.

d) USACE reviews and approves invoice.

e) USACE makes payment.

f) Contractor manages unallowable/unreasonable costs that are billed by providing credit on subsequent invoice.

5. Cost Tracking/Forecasting:

a) Contractor establishes a USACE approved Cost Accounting System.

b) Contractor holds meetings with USACE to develop Work Breakdown Structure (WBS)/and Cost

Accounting procedures.

c) Contractor develops cost report.

d) Contractor submits cost report to USACE.

e) USACE reviews cost report.

f) Contractor develops cost forecast based on costs incurred.

g) Contractor manages cost overruns/underruns (errors) accordingly and in concurrence with

USACE.

h) Personnel who are authorized to expense money on cost reimbursable contracts must be identified and authorities clearly identified so that timely decisions are made so the project is not adversely impacted. Further, the Government must be included in spending decisions since it is responsible for reimbursement of all allowable, allocable, and reasonable costs.

6. Meetings

a) The Contractor shall attend and participate in required meetings as stated in the task orders.

Examples include: daily command post meetings, site visits, pre-proposal, post-award, and pre-construction conferences, in addition to other meetings the Government considers necessary to support project activities.

b) The Contractor may also be required to participate in support meetings and teleconferences for the purpose of discussing technical issues, project progress, and status.

c) The Contractor shall prepare and submit for review agendas and presentation materials for such meetings. The Contractor may be required to prepare minutes for meetings attended.

d) Specific requirements will be addressed in each Task Order.

7.7 Personnel Authorized to Expense Money

7.8 Personnel who are authorized to expense money on cost reimbursable contracts must be identified and authorities clearly identified. The Government must be included in spending decisions since it is responsible for reimbursement of all allowable, allocable, and reasonable costs.

7.9 Plans, Required

a) Work Plan (Section 6.1)

b) Site Safety and Health Plan (Section 01 35 26 General Safety Requirements)

c) Quality Control Plan (Section 01 45 00.00 10 Quality Control)

7.10 Reports, Required

a) Design Drawings/Specifications per Task Order

b) Site/Project Summary

c) Shop Drawings and/or As-Built Drawings

d) Survey Reports per Task Order basis

e) CPSMR

f) CPR

8.0 QUALITY MANAGEMENT (QM)

Quality Management (QM) refers to the combined QC/QA effort. The specific requirements for Contractor QC will be identified in the project Task Order. See Section 01 45 00.00 10 Quality Control.

9.0 CONSTRUCTION WITH INCIDENTAL DESIGN

The RDI Contractor shall manage and perform construction with incidental design work as defined in the Task Order. The following are typical “construction with incidental design” Task Order requirements: work performed under design memorandums, completion of working drawings, permitting, construction management, scheduling, inspection and testing, environmental protection coordination, construction quality control, technical reach-back for applicable construction activities, and project closeout.

10. ORGANIZATIONAL STAFF/STRUCTURE

10.1 General

The Contractor shall be capable of efficiently and effectively executing all RDI Task Order requirements.

10.2 Veteran’s Employment Emphasis for USACE Contracts

In addition to complying with the requirements outlined in FAR Clause 52.222-35, Equal Employment Opportunity for Veterans, all contractors, and subcontractors at all tiers, are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. However, no set-aside, evaluation preference, or incentive is applicable with regard to this paragraph.

The following resources are available to assist USACE contractors in their outreach efforts: Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx.

Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/ Department of Veterans Affairs - VOW to Hire Heroes Act http://benefits.va.gov/vow/

10.3 Operations Office

The Contractor shall establish an RDI Operations Office in which it will manage the RDI program and contract operations (see Paragraph: "Operations Manager"). The location of this office is at the discretion of the Contractor. Other functions of this office may include but are not limited to:

*Accounting and record keeping.

*Administration and management of Government-owned property acquired or operated by the Contractor under this contract.

*Quality control training and oversight necessary to ensure compliance with construction and environmental measures and RDI contract requirements.

*Billing of progress payments.

*Processing of submittals, RFP’s, and invoices.

10.4 Key Personnel/Positions

Persons identified as “Key” by the Government are mandatory positions and shall not be replaced without notifying the Contracting Officer. Should it become necessary to replace the key management personnel, the Contractor shall provide a written request stating the reasons for the change and listing the name and qualifications of the proposed replacement to the Contracting Officer for approval. The Offeror shall obtain the Contracting Officer's written consent before making any substitutions for these designated personnel. Personnel shall meet or exceed the qualifications listed below:

Home Office (Corporate) Personnel

10.4.1 Accounting Manager

The Accounting Manager is responsible for ensuring that invoicing, billings, and related activities are performed in accordance with contract requirements, specific task order agreements, and contract management procedures (CMP’s). The Accounting Manager shall be experienced and responsible in all of the firm’s activities related to Procurement, Wage Rate Determinations, Government property, Subcontracting goals compliance, and compliance with applicable Federal, state, and local laws and regulations.

Qualifications:

The Accounting Manager shall have the following minimum qualifications:

*A college degree including or supplemented by a minimum of 24 semester hours in accounting, economics, business law, procurement, or management related curriculum; or certification as a Certified Professional Contracts Manager (CPCM) by the National Contracts Management Association.

*Four (4) years of Government accounting/billing experience in a position of increasing complexity and responsibility.

*Training in Government fiscal accounting/law.

*Shall be employed directly by the Prime Contractor.

http://www.fedshirevets.gov/index.aspx http://www.dol.gov/vets/ http://benefits.va.gov/vow/

10.4.2 Program Manager/Construction Operations Manager (PgmM/COM)

The PgmM/COM is responsible for the successful and efficient management of the contract and for the efficient construction work completed under the RDI Contract. The PgmM/COM is responsible for developing, implementing, and managing the quality control program and will ensure that Government quality and environmental requirements are achieved. The PgmM/COM will manage subcontracts, manpower, equipment, and other resources, and will ensure that Safety is the number one priority at jobsites.

The PgmM/COM shall be competent, experienced and knowledgeable in management of the construction-specific activities identified in this contract, and shall designate a Site Manager for each Task Order who shall be responsible for all on site management of construction duties per Task Orders. The PgmM/COM is the point of contact for the Government for this contract and the person the Contracting Officer contact to address either programmatic issues with the contract or site-specific issues that require higher level corporate involvement.

Qualifications:

The PgmM/COM shall have the following minimum qualifications:

*A college degree in a technical field (e.g. engineering, construction management, geology, chemistry, or related field).

*Four (4) years-experience in Program Management/Operations/Contract Management for other contracts/programs acceptable to the Government.

*A minimum of four (4) years’ work experience in Construction Project Management or in a combination of the Construction, with Incidental Design.

*Working knowledge of applicable Federal, state, and local construction laws and regulations and Federal labor laws.

*The ability to effectively communicate and manage customer expectations.

*The ability to locate, coordinate, and utilize resources.

*The ability to effectively manage subcontracts and cost reimbursable contracts.

*Shall be employed directly by the Prime Contractor at the time the proposal is submitted or a letter of intent for the Program Manager/Construction Operations Manager in accordance with 13 CFR 124.513(c)(2). (AM#0002)

10.4.3 Corporate Quality Control Manager (QCM)

The QCM shall have experience in development and oversight of corporate quality control programs and processes relevant to scope of work. The QCM is responsible for the development, implementation, oversight and enforcement of the firm’s Government approved QC program.

The Corporate Quality Control Manager shall have the following minimum qualifications:

*A minimum of four (4) years-experience in developing and implementing effective Quality Control programs with a construction focus.

*Expert knowledge of the USACE Quality Assurance/Control requirements and processes.

10.4.4 Corporate Safety and Health Manager (SHM)

The SHM shall be responsible for the development, implementation, oversight and enforcement of the firm’s health and safety program.

The Corporate Safety and Health Manager shall have the following minimum qualifications

*The SHM shall be an Industrial Hygienist certified by the American Board of Industrial Hygiene, or a Safety Professional certified by the Board of Certified Safety Professionals.

*A minimum of four (4) years-experience in developing and implementing safety and health programs at construction sites, operations, or equivalent.

*Documented experience: in supervising professional and technician level personnel; in developing worker exposure assessment programs and monitoring programs and techniques; in managing personal protective programs.

*Working knowledge of state and Federal occupational safety and health regulations and statutes.

*Expert knowledge of the USACE Safety and Health Requirements, EM 385-1-1 Manual, through documented experience construction operations contracted under the USACE, Naval Facilities Engineering Command, or other Department of Defense entities requiring the use of the EM 385-1-1 manual.

*Shall be employed directly by the Prime Contractor.

10.4.5 Procurement Specialist

The procurement specialist is responsible for identifying, planning, procuring, and managing equipment and materials required for each project. The Procurement Specialist will identify suppliers for materials and equipment; negotiate prices with suppliers, obtaining the best prices available, given project constraints such as geography and schedule; arrange for shipping/delivery/returns; ensure items delivered are of the type, quality, and serviceability agreed to; establish and maintain an adequate inventory of required materials; ensure invoices are complete and accurate; control equipment and materials costs and avoid waste;

additional procurement activities, as directed. Work to be performed in accordance with all applicable FAR requirements.

*A minimum of three (3) years-experience in procurement activities of the type described above, for construction projects.

*Knowledge, experience, understanding of federal procurement guidelines is a requisite *Shall be employed directly by the Prime Contractor

10.4.6 Response Manager/Project Manager (RM/PM)

The RM/PM will plan and coordinate all activities required to comply with Task Order requirements in close coordination with USACE representatives. The RM/PM shall promptly report all obstacles to mission achievement. The RM/PM will also: coordinate submittals and other deliverables; provide administrative support, supervision, and management of Contractor personnel, equipment, and materials; and provide USACE with progress, financial, and other reports deemed necessary by the Government.

A RM/PM shall be appointed by the PgmM/COM for each RDI Task Order awarded. The

PgmM/COM shall furnish the RM/PM’s qualifications, experience and performance to the Contracting Officer for approval. The RM/PM shall be the point of contact for the Task Order, and shall be responsible for the management and execution of all construction activities in accordance with the approved statement of work, Contractor's approved submittals and all applicable Federal, state, and local laws and regulations.

The RM/PM shall have the following minimum qualifications:

*Four (4) years working experience as a RM/PM in the construction industry, with emphasis on swift and time-sensitive construction related response actions.

*Working knowledge of applicable Federal, state, and local construction laws and regulations *The ability to effectively communicate and to assist in management of customer expectations *Shall be directly employed by the Prime Contractor.

10.5 Field Personnel

10.5.1 Accounting/Financial Analyst

Responsible for specific Task Order financial management to include project set- up in the company accounting system, voucher preparation (with complete backup), and financial closeout. The Accounting/Financial Analyst shall be experienced in, and responsible for, all of the firm’s activities related to financial management, internal time keeping, travel and per diem, and invoicing /billing. The analyst is responsible for company compliance with Federal accounting and financial regulations.

Qualifications:

The Accounting/Financial Analyst shall have the following minimum qualifications:

*Associates degree or two (2) years equivalent experience in accounting, economics, business law, procurement, or management related curriculum.

*Two (2) years of experience in a position of increasing complexity and responsibility including cost reimbursement requirements.

*Working knowledge of the FAR.

10.5.2 Onsite Project Cost Tracker (PCT)

As part of site administration requirements for cost reimbursement Task Orders, the contractor may be required to provide daily on-site cost tracking. The PCT’s duties include daily tracking of all costs and maintenance of supporting documentation; utilization of schedules to project funding needs; reporting of variations once actual funding amounts are known; and reconciliation of home office and jobsite financial management records.

Qualifications:

The Onsite Project Onsite Project Cost Tracker shall have the following minimum qualifications:

*Four (4) years’ work experience in the construction industry, with emphasis on project cost tracking for cost reimbursable contracts/task orders.

*Working knowledge of the FAR

10.5.3 Site Superintendent

The Site Superintendent is the highest level manager responsible for the overall construction activities at the project site, including quality and production.

The Site Superintendent shall have the following minimum qualifications:

*A 4-year degree in Construction Management, or a related field, or ten (10) years of experience as a Superintendent on projects with a similar scope and size *Working knowledge of cost-reimbursement task orders.

10.5.4 Quality Control Specialist/CQC System Manager

The Quality Control Specialist is on-site at all times during construction and employed by the Prime Contractor.

Qualifications:

The Quality Control Specialist shall have the following minimum qualifications:

* Five (5) years of experience as a QCS on projects with a similar scope and size.

*Completion of the Construction Quality Management (CQM) for Contractors course.

10.5.5 Site Safety and Health Officer (SSHO)

The SSHO is the task-order level individual who establishes, approves, maintains, and monitors the Contractor's safety program and Accident Prevention Plan, and who is responsible for ensuring the Contractor complies with all Government safety requirements.

Qualifications:

Training, experience, and qualifications meeting requirements of with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs.

Appointment of SSHO:

For firm fixed price task orders, the Contractor shall submit a resume to the Administrative Contracting Officer (ACO), or to a person designated by the ACO or Contracting Officer, a resume for the proposed SSHO and an accompanying request to appoint the individual to that position, no later than one week after task order award.

For cost reimbursable task orders, the Contractor shall submit a resume to the Contracting Officer, or to a person designated by the Contracting Officer, a resume for the proposed SSHO and an accompanying request to appoint the individual to that position, no later than one week after task order award.

The Government reserves the right to reject any request if it determines that the individual does not meet the qualifications set forth in the task order or is otherwise unsuitable for the position. The

Contractor shall not appoint an individual to this position without approval of the Contracting Officer.

Unless otherwise allowed by task order or the Contracting Officer, the SSHO may not be "dual hatted," i.e., serve in more than one position, nor shall SSHO be assigned to any other duties aside from those inherent in their position, nor to any other projects. An Alternate SSHO may be appointed by the Contractor using the same processes and criteria describe above. An Alternate SSHO shall have qualifications and experience meeting or exceeding those of the primary individual appointed to that position. No individual may serve as an Alternate SSHO if serving in that capacity would result in dual-hatting, as described above.

11.0 PROJECT CLOSEOUT

11.1 Warranty

The Contractor shall complete all inspections and commissioning requirements prior to Final Inspection. All warranties for firm fixed price task orders shall be issued in conjunction with the Final Report. Extended warranties offered by the Contractor and its subcontractors or suppliers may be accepted at the Government’s discretion. See Section 01 78 36.00 24 Warranty of Construction.

11.2 Final Report

For Task Orders, a draft copy of the Project Final Report shall be submitted 30 days after completion of the field work for each Task Order. The report shall include a summary of the work performed and all project documentation. The exact format and requirements will be specified on a Task Order basis.

Attachment 1: Work Authorization Document (Sample)

Work Projection Document

Primary Contractor's Name:

Contract Number:

Site Name & Location:

Report #: Delivery Order #: Date:

Subcontractor(s):

Government agencies on-scene:

WORK PROJECTION DOCUMENT - CONT'D.

3. Planned Equipment and expendable materials:

Item Quantity Duration Item Quantity Duration

1. Description of work to be performed by contractor(s), with an estimate of the percentage to be completed:

WORK PROJECTION DOCUMENT -

CONT'D

7. I ACKNOWLEDGE RECEIPT OF THIS WORK ORDER AND UNDERSTAND THAT ANY

MODIFICATION TO THE WORK ORDER MUST BE IN WRITING AND REVIEWED BY THE PROPER

GOVERNMENT REPRESENTATIVE. FURTHER CHANGES TO THE SCOPE OF THE PROJECT

SHALL BE APPROVED BY THE CONTRACTING OFFICER.

2. Number of personnel working on the project (both on-site and off-site):

Home Office:

Program Manager/Construction Operations Manager (PM/COM): __________ Others (specify):

Field Office:

Site Superintendent: ___________ Accounting/Financial Analyst:_________ On-site Project cost Tracker:___________ QC Specialist/CQC Manager:__________

SSHO:_________________

Engineers:______________ Technicians:_____________ Geologists:______________ Chemists:_______________ Operators:_______________ Laborers:________________ Others (specify):

Contractor's representative

-- End of Section --

AMENDMENT 0002 - INSTRUCTIONS

REVISED SECTION 00 22 00 (AM#0002)

Section 00 22 00

SUPPLEMENTARY INSTRUCTIONS

(Submission Requirements and Evaluation)

1.1 CONTRACT INFORMATION

1.2 INDEFINITE DELIVERY TYPE CONTRACTS

The Government intends to issue one solicitation and award a Multiple Award Task Order Contract (MATOC) for shared capacity of $95M to a target of up to four (4) (AM#0002) 8(a) contractors. Individual Task Orders will be solicited and competed within the MATOC pool. Task Orders within the MATOC may be Cost-Plus- Fixed-Fee (CPFF), or Firm Fixed Price (FFP).

The base period for this MATOC is one (1) year. There will be four (4) one-year option periods, making the total ordering period up to five (5) years from the date of award. The Government’s decision to exercise an option will be contingent upon satisfactory contractor past performance and an informal survey of current market conditions.

The minimum guarantee amount for this MATOC (to include all option periods) is $2,500.00.

1.3 TYPES OF PROJECTS

Projects will vary in size, complexity, and location, and will require a high degree of flexibility and adaptability.

The Contractor must respond quickly and effectively. All work will be time-sensitive in nature, necessitating an immediate response to mitigate threat to life and property and/or operational impacts to the government.

Work contemplated under this MATOC include, but are not limited to:

Flood Recovery Flood control and water diversion projects, embankments, channel alignments and flood control structures in support of civil works missions.

Infrastructure Recovery Restoration, repair, and demolition of facilities, utilities, real property systems, and other infrastructure requirement that cannot be performed in required timeframes with normal contract mechanisms to meet vital mission requirements.

Emergency Management Response actions such as unwatering missions, debris recovery, temporary housing, and other actions to meet vital mission requirements.

Military Construction of facilities, infrastructure, water and sanitation systems, electrical systems, natural gas and other energy systems, fences, lighting, and roads to support troop movements and other crucial military missions.NOTE:

Each Task Order Request for Proposal will identify when the contractor must mobilize; however, emergency recovery actions may require mobilization within three (3) days of Government Notification. Projects may require incidental design and/or ecological/environmental, hazardous waste recovery, and munitions work.

1.4 PROJECT LOCATIONS

Projects may occur in Nebraska, Iowa, South Dakota, North Dakota, Missouri, and Kansas. The Offeror shall be prepared to respond to any location within the states, as defined above.

1.5 TASK ORDERS

Individual Task Orders will be awarded under this MATOC using either the Tradeoff Source Selection Process (see FAR 15.101-1) or the Lowest Price Technically Acceptable (LPTA) Source Selection Process (see FAR 15.101-2).

The process will be determined at the Task Order level and will be communicated in the Task Order RFPs. Task Orders will be awarded as “Firm Fixed Price” (FFP), “Cost Plus Fixed Fee (CPFF),” or a combination of each contract type. Maximum Task Order award will be remaining contract capacity of the MATOC.

RDI Workload History

Average Range of Task Orders Issued: $400k – $5M

Please note that the Government will conduct a cost realism analysis in accordance with FAR 15.404-1(d) on individual Cost Reimbursement task orders during task order source selection so the Contractor(s) will be required to provide adequate cost information during the task order source selection process in order to do such analysis.

2.0 WHO MAY SUBMIT

This solicitation is open to Offerors registered as an 8(a) contractor in the System for Award Management (www.sam.gov). Only those Offerors with bona fide places of business within the project locations (Nebraska, Iowa, South Dakota, North Dakota, Missouri, and Kansas), are eligible to submit offers per 13 CFR § 124.507 (c) (2).

The Primary North American Industry Classification System (NAICS) code for this solicitation is 236220. This code has a Small Business size standard of $36.5 million dollars.

Proposals submitted must be sufficiently detailed to allow for an effective and equitable evaluation by the Government. There will be no public proposal opening. Proposals submitted will become, upon receipt, the property of the U.S. Government and will not be returned. After evaluation of proposals, electronic copies will be retained for the official paperless contract file. All other copies will be destroyed or forwarded to the Field and Areas Offices in support of their contract administration functions.

3.0 GENERAL PROPOSAL SUBMISSION INSTRUCTIONS

All Offerors shall submit electronic proposals, to include pricing information, to:

1. Glenda Canty whose e‐mail address is glenda.a.canty@usace.army.mil and

2. Doug Hadley whose e‐mail address is doug.e.hadley@usace.army.mil and

3. Tyler Hegge whose email address is tyler.hegge@usace.army.mil http://www.sam.gov/ mailto:glenda.a.canty@usace.army.mil mailto:doug.e.hadley@usace.army.mil mailto:tyler.hegge@usace.army.mil

Proposals without all required content may be deemed by the Government as non-responsive and the proposal may be rendered as ineligible for award. The Government will utilize the processes described in Section 00 22 00 to evaluate proposals. The Government intends to award up to four (4) contracts under this 8(a) Multiple Award Task Order Contract (MATOC). To be considered for award, Offerors shall submit complete and acceptable proposals prior to the date and time stated on the SF 1442. Do not assume that electronic communication is instantaneous.

Please make allowances for delays in transmittal.

3.1 PROPOSAL FORMAT

a. Submit proposals in PDF format identified by the Solicitation Number (W9128F19R0027), Company Name, and Volume identification. Each Volume will be submitted as a “separate file” when submitting. The proposal shall be submitted in Volumes as follows:

Volume I, Technical Evaluation Factors:

Table of Contents FACTOR 1: Previous Experience FACTOR 2: Core Competencies FACTOR 3: Key Personnel FACTOR 4: Past Performance

Volume II, Cost/Price:

Table of Contents Cost/Price Information Audit Information

Volume III, Required Documentation:

Table of Contents Cover Letter Completed SF 1442 Completed SF 30 Representations and Certifications Bond Letter Contractor Team Arrangement Requirements

TABLE 1: Evaluation Factors & Cost/Price

Volume

Technical Evaluation

Factor

Title

Page Limitations

I

Factor 1

Previous Experience 8 pages

Factor 2

Core Competencies 5 pages

Factor 3

Key Personnel

6 pages

Factor 4

Past Performance

No Page Limitation

II

Cost/Price

Cost Spreadsheet plus 515 additional pages (AM#0002)

III

Required Documents

No Page Limitation

b. Proposal Characteristics

All proposals shall contain the evaluation submission requirements stated herein. Page limits shall not exceed those listed above in Table 1. All pages that exceed these limits will be ignored (e.g., only the first eight (8) pages of Factor 3 will be evaluated, even if eight or more pages were submitted by an Offeror). Page limitations are per factor, i.e., an Offeror may not reduce the page count for one factor in order to submit additional pages for another factor.

Submit only that data which is necessary for proposal evaluation. Data submitted must reflect the Offeror’s interpretation of criteria contained in the RFP. Unnecessarily elaborate or voluminous brochures or other presentations are not desired and may be construed as an Offeror's lack of understanding of the RFP requirements.

Proposal clarity, organization, and cross-references are mandatory. Referenced information or materials not included within the proposal may be classified as non-conforming. Material omission(s) shall cause the technical proposal to be rendered as unacceptable for award. Proposals which are generic, vague, or lacking in detail may be considered unacceptable.

NOTE: Failure to include all required items may render the proposal non-responsive and ineligible for award.

i. Each Volume must contain a table of contents (not included in page count) and all pages of each factor shall be sequentially numbered (i.e. the first page submitted for evaluation of each factor shall be “1”).

All text must be legible and easily read. The page size of the Offeror’s proposal shall not exceed 8‐1/2 by 11 inches. Diagrams, charts and tables shall conform to the paper size. All text shall be typed single‐ spaced with minimum 10 point font. Margins (1‐inch) shall be clean and clear. All submissions shall be in Adobe PDF format. All Adobe PDF documents should have Optical Character Recognition (OCR) applied to all documents so that word searches can be conducted using Adobe‐compatible PDF software.

ii. Offeror shall submit a cover letter containing:

a. Solicitation number.

b. Name, title, address, email, telephone number and CAGE code of the Offeror.

c. Names, titles, emails, and telephone numbers of persons authorized to negotiate on the

Offeror’s behalf with the Government in connection with this RFP.

d. Name, title and signature of the person authorized to sign the proposal.

e. CAGE codes for each Contractor/Firm under a Contractor Team Arrangement (if applicable).

f. A statement specifying agreement with all terms, conditions and provisions included in the RFP.

Note: The cover letter is included in Volume III.

iii. Offerors shall submit a completed SF1442 with their proposal. Include DUNS number in block 14.

Note: The SF1442 is included in Volume III.

iv. Offerors shall submit acknowledgement of all amendments to the RFP in accordance with the instructions on the Standard Form 30 (amendment form).

Note: The acknowledgement of amendments are included in Volume III.

v. All Offerors shall complete the Representations and Certifications section in the System for Award Management (SAM) at www.sam.gov. If applicable, submit any additional information regarding Representations and Certifications that may not be documented in SAM.

Note: The SAM information is included in Volume III.

vii. Offerors shall submit a letter from their bonding company agent certifying the current maximum bonding capacity per project and the aggregate capacity. The bonding capacity shall demonstrate the capability as it relates to this solicitation.

Note: The bonding company letter is included in Volume III.

viii. For Contractor Team Arrangements, submit the information required by the below Paragraph 5 “Contractor Team Arrangements”.

Note: The contractor team arrangements information is included in Volume III.

3.3 SUBMITTAL REQUIREMENTS

In an effort to reduce paperwork and reduce cost, all proposals shall be submitted electronically via the AMRDEC SAFE website. All submissions shall be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software. The two (2) three (3) (AM#0002) volumes listed below shall be submitted as “SEPARATE” single files via AMRDEC. Offerors may use compression utilities such as 7-Zip, WinZip or PKZip to reduce file size and facilitate transmission when using AMRDEC. Offerors are encouraged to send both files in the same AMRDEC transmission, if possible.

AMRDEC supports file sizes up to 2GB.

Title the separate files in the following format:

W9128F19R0027_COMPANY NAME_ VOLUME_I_FACTORS_1-4

W9128F19R0027_COMPANY NAME_ VOLUME_II_COST/PRICE INFORMATION

W9128F19R0027_COMPANY NAME_ VOLUME_III_REQUIRED_DOCS

To submit proposals electronically via AMRDEC go to the following website: https://safe.amrdec.army.mil/SAFE/.

At the AMRDEC SAFE website select “Non-CAC Users” in order to register, access the site and submit your proposal(s). When completing the information for transmittal at the AMRDEC SAFE website, you will be asked to http://www.sam.gov/ https://safe.amrdec.army.mil/SAFE/ enter e-mail addresses for the recipients. When your proposal is submitted via the AMRDEC SAFE website, the website will provide notification of the submittal to the recipients. For this solicitation, the recipients will be:

1. Doug Hadley, whose e-mail address is doug.e.hadley@usace.army.mil and

2. Glenda Canty, whose e-mail address is glenda.a.canty@usace.army.mil and

3. Tyler Hegge, whose email address is tyler.hegge@usace.army.mil

4. After submitting your information, you will receive two (2) disclaimers:

1. “The files were successfully uploaded.”

2. “Your files cannot be downloaded by recipients until you verify your email address. Please check your email for further instructions.”

The Government will not receive your submission until you verify your email address via these email instructions.

Follow the instructions sent to your email to complete your submittal process. The AMERDEC SAFE website will generate an email to the Contract Specialist(s) notifying them that files have been uploaded into the system. The date and time of delivery is based upon the date and time of uploading the proposal into AMERDEC SAFE website. For the purposes of determining whether the proposal was received “late” in accordance with FAR 15.208, the date and time the file(s) are uploaded into the AMRDEC SAFE website will be the time and date the Government received the proposal. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal. Electronic Proposals shall be received via AMRDEC No Later Than (NLT) the date and time indicated in Block 13 of the SF 1442 for this solicitation or as identified in subsequent amendments.

The Government will not be responsible for proposals delivered to any location or to anyone other than those designated to receive proposals on its behalf. The Offeror is responsible for ensuring that the proposal is submitted so as to reach the designated recipient and is responsible for allowing sufficient time for the proposal to be received in accordance with the information provided.

Failure to submit a complete proposal IAW instructions and requirements may result in the entire offer being rejected.

NOTE: ONLY in the unusual case that the AMRDEC website is “down” (not operational), the Offeror should email their proposal to the aforementioned individuals prior to the proposal due date and time.

4.0 INQUIRIES/QUESTIONS

Prospective Offerors shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions. See section “BIDDER INQUIRIES” in this solicitation for the Quick Add Key and instructions on how to use ProjNet.

NOTE: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions shall be rejected.

5.0 CONTRACTOR TEAM ARRANGEMENTS

5.1 CONTRACTOR TEAM ARRANGMENTS OTHER THAN JOINT VENTURE/ MENTOR-PROTÉGÉ

Requirements:

All Offerors proposing a team arrangement (to include teaming arrangements with an AE firm) other than a Joint Venture/Mentor-Protégé, shall submit the following information:

a. A listing of the team arrangement members’ corporate name…