15. CLIN 0007 calls for a quantity of 3 for all the spare parts tripling the price. The specifications call for a specific quantity for each item. Shouldn’t this be one lump sum?
Answer: The "LOT" of spare parts is as required in Section 48 19 23.04 26, paragraph 2.18.
16. Would the government accept early delivery of the transformers? This would reduce the risk and pricing of proposals.
Answer: The purpose of staged delivery, as indicated in the Time of Delivery Clause, is to avoid the necessity for on-site storage and the possible requirement of oil-filling for long-term storage. The CLIN for Economic Price Adjustment helps reduce the risk of changing materials prices in the outlying years.
17. Clause 52.211-16 references CLIN 0008 instead of 0009.
Answer: FAR 52.211-16 has been updated to identify CLIN 0009 in the solicitation via Amendment 0001.