W9128F19Q0076 AM0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bidder_Inquiries_25_Apr_19.pdf | ||
| W9128F19Q0076_Final.pdf | ||
| SOW_Attach2of3_FE6_Fence_Sheet.pdf | ||
| SOW_Attach3of3_FE6_SWING_GATE_Sheet.pdf | ||
| SOW_Attach1of3_Site_Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W59XQG90657249
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
25 Apr 19: AMENDMENT: Jessica Jackson, Contract Specialist, 402.995.2052
The purpose of this amendment is to extend the deadline for quotes to Wednesday, 1 May at 1400hrs (Central). In addition, FAR Clause 52.225-9, Buy American -- Construction Materials is hereby incorporated at Section I.
All remaining terms and conditions are unchanged. The Government w ill not incur any additional costs as a result of this amendment.
1. CONTRACT ID CODE PAGE OF PAGES
1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Apr-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F19Q0076
X 9B. DATED (SEE ITEM 11)
12-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Apr-2019
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
dean.p.matuszewski@usace.army.milEMAIL:402-995-2854TEL:
DEAN P MATUSZEWSKI / CONTRACT SPECIALIST
W9128F19Q0076
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 25-Apr-2019 12:00 AM to 01-May-2019 05:00 PM.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
SCOPE OF WORK
SCOPE OF WORK
Outside Maintenance Security Fence Addition
Fort Peck, MT
1.0 Scope of Work
There is an existing fence around a portion of the Fort Peck Outside Maintenance Facility but does not secure the entire area. This work will consist of furnishing and installing chain link fencing, complete with all posts, braces, gates and all other appurtenances, connecting into the existing to fully secure the entire area. The period of Performance shall be 180 days after Notice to Proceed.
2.0 General
2.1 Standards and Regulations
The Contractor shall perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations.
Applicable regulations include, but are not limited to the following:
a. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated November 2014;
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf
b. Occupational Safety and Health Standards (29 CFR 1910);
2.1.1 Activity Hazard Analysis (AHA)
The contractor shall prepare the AHA in accordance with Paragraph 01.A.14 or 01.A.15 of the EM 385-1-1. If using Paragraph 01.A.15, prepare the AHA IAW Figure 1-2.
Note: Contractors and other individual employer’s typically use Job Safety Analyses (JSAs), Job Hazard Analyses (JHAs), or similar Risk Management assessment tools. The government considers equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA, commensurate with the type of services the contractor is performing.
2.1.2 Abbreviated Accident Prevention Plan (APP)
EM 385-1-1 in its entirety may be too complex for the type of work performed under these contracts; contractors may reference Appendix A, for abbreviated Accident Prevention Plan (APP). The contractor shall only need to submit items in Appendix A that are pertinent to the contract. The contractor shall use a qualified person to prepare the site-specific abbreviated Accident Prevention Plan (APP). The contractor shall prepare the APP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite.
2.2 Measurement and Payment
Payment items for the work under this contract for which contract job payments will be made are listed in the BID SCHEDULE and described below. The job price and payment constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required.
2.2.1 Furnish and Install Fence and Gates – CLIN 0001
2.2.1.1 Payment
Payment will be made for costs associated with the construction of the Security Fence in accordance with the drawing and specifications.
2.2.1.2 Unit of Measure
Unit of Measure: Job.
2.3 Location
The project is located at the US Army Corps of Engineers Maintenance Facility, 30 Judith Road, Fort Peck MT, 59223.
2.4 Staging Area
The government will provide limited space for the contractor to stage equipment and materials; contact the Contracting Officers Representative (COR) for staging needs.
2.5 Delivery, Storage, and Handling
Deliver to the job site materials in good condition and properly protected against damage to factory-finished surfaces. In general, all materials shall be delivered, stored and handled in a manner that protects them from damage, moisture, dirt, and intrusion of foreign materials. Materials delivered shall be checked against the specifications and approved samples.
2.6 Work Hours and Work Limits
The contractor is responsible for conducting business, between the hours of 0630 to1700 Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Working outside these work hours will need written permission from the COR.
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Independence Day 4 July Labor Day First Monday in September
Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If a wage determination applies the number of holidays specified on it, it has priority over this requirement.
2.7 Facilities
Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff. Toilet(s) shall be placed at the location directed by the Contracting Officer. To prevent overturning by high winds, all portable toilets shall be anchored down.
2.7.1 Protection of Existing Facilities and Works
The Contractor shall be responsible for the protection of the work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started. All work, storage of materials, and construction plant shall be kept within the limits of the areas assigned. Prior to construction operations, the Contractor shall confer with the Contracting Officer's Representative to determine the proximity of any possible under-ground obstructions, pipe or equipment which could be damaged as a result of construction operations. Existing utility lines that are shown on the drawings or the locations are otherwise made known to the Contractor shall be protected from damage, and if damaged, shall be repaired by the Contractor at no additional expense to the Government. In the event that the Contractor damages any existing utility lines that are not shown or the locations of which have not been made known to the Contractor, report thereof shall be made immediately to the Contracting Officer. If the Contracting Officer determines that repairs shall be made by the Contractor, such repairs will be ordered under CONTRACT CLAUSES clause entitled "Changes." The Contractor will be responsible for the protection of structures from any structural damage during the construction operations. Roads and surfaces shall be protected from damage by the work or if damaged shall be repaired with equal materials at no additional expense to the Government. At all times the work areas shall be kept in a condition conducive to safety of workmen and the public and neat in appearance. Waste or surplus materials shall not be allowed to accumulate in the construction areas.
2.7.2 Location of Underground Utilities
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
2.8 Environmental Compliance
The contractor shall be responsible for ensuring that the project is in full environmental compliance with all applicable Federal, State, Local, and Regional environmental laws and regulations.
2.9 Antiterrorism/Operation Security Requirements
2.9.1 Access and General Protection/Security Policy and Procedures
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
2.9.2 Pre-screen candidates using E-Verify Program. The Contractor must pre‐screen candidates using the E‐ verify Program (http://www.dhs.gov/E‐Verify) website to meet the established employment eligibility requirements.
The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the COR no later than three (3) business days after the initial contract award.
3.0 Submittals
Prior to commencement of work, the Contractor shall submit the following documents to the COR for review and approval:
a. Abbreviated Accident Prevention Plan (APP)
b. List of who will perform work on this contract;
c. Proof of Insurance for Contractors and Subcontractors;
d. Any additional submittals required by the specifications
4.0 Materials
All materials shall be in a new unused condition meeting the requirements of the specification.
5.0 Execution
Perform work in accordance with the drawings and Specification Section 32 31 13 CHAIN LINK FENCES AND GATES. Work includes furnishing and installation of approximately 2,512 ft of new FE6-TR-72 chain link fence, furnishing and installation of one new 24 ft double swing gate, and removal, relocation and installation of one existing 24 ft double swing gate. Contractor shall remove and reinstall an existing entrance gate to the location shown on the drawings to include any additional new hardware or materials required for the installation.
6.0 Contractor Quality Control (CQC)
CQC is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows:
6.1 Preparatory Phase
This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:
a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.
b. Review of the Contract drawings.
c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. Review of provisions that have been made to provide required control inspection and testing.
e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the Contract.
f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.
g. Review of the appropriate activity hazard analysis to assure safety requirements are met.
h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
j. Discussion of the initial control phase.
k. The Government needs to be notified at least 48 hours in advance of beginning the preparatory control phase.
Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
6.2 Initial Phase
This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:
a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing are in compliance with the contract.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government needs to be notified at least 48 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.
g. The initial phase for each definable feature of work is repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.
6.3 Follow-up Phase
Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.
7.0 Inspection and Tests
The government will provide inspection of all work in accordance with FAR 52.213-4 – Terms and Conditions – Simplified Acquisitions (Other Than Commercial Items). Contractor shall perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.
8.0 Point of Contact
The government will update this paragraph with POC information at time of award.
9.0 Drawings
Drawings may not reflect actual site conditions or show all equipment installed Therefore, field verification by the Contractor is highly recommended to determine actual site-specific conditions. The government is providing the following Drawings:
Sheet 01 – Site Plan Sheet 02 - FE6 Security Fence Details Sheet 03 – FE6 Double Swing Gate Detail
SECTION I - CONTRACT CLAUSES
The following have been added by full text:
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material.... ........... ___ ........ ....... ………. ___ ................ ........ ___ Domestic construction material... ........ ___ ............... .............. ___ .................. ...... ___ Item 2 Foreign construction material.... ......... ___ ............. ........ ……. ___ ............... ......... ___ Domestic construction material... ....... ___ .................. ............. ___ ................. ....... ___ Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
Instructions to Quoters – Other than Commercial Items
Please provide the following information with your quote:
Company’s Name as it appears on SAM:
Company’s Address as it appears on SAM:
CAGE CODE:
DUNS:
TIN:
NAICS. North American Industry Classification System (NAICS) code and small business size standard. The NAICS code and small business size standard for this acquisition appear in FAR 52.204-8 of the solicitation.
Submitting your quote. Submission of quotations. Submit quotations to the office specified in this solicitation at or before the exact time specified in this solicitation. Quotations may be submitted on the SF 18, letterhead stationery, or as otherwise specified in the solicitation.
Quotations are due by 1400hrs (CDT) on Wednesday, 1 May 2019. Send your completed quotation package to the attention of Ms. Jessica R. Jackson at jessica.r.jackson@usace.army.mil. Electronic quotations are preferred over paper responses, unless other arrangements have been made with the individual identified above. You may submit more than one quote. If you do, we will evaluate each separately.
We will not consider any quote that we receive after the deadline unless we receive it before we issue a purchase order and considering it will not delay our purchase. In case of an emergency that delays our operations and makes submission or receipt of your quote impossible, we will extend the deadline by one working day.
As a minimum, quotations must show-
(1) The solicitation number;
(2) The time specified in the solicitation for receipt of quotations;
(3) The name, address, and telephone number of the quoter;
(4) A technical description of the items being quoted in sufficient detail to evaluate compliance with the requirements in the solicitation. This may include product literature, or other documents, if necessary;
(5) Terms of any express warranty;
(6) Price and any discount terms;
(7) “Remit to” address, if different than mailing address;
(8) A completed copy of the representations and certifications at FAR 52.204-8 if applicable.
(9) Acknowledgment of Solicitation Amendments;
(10) Past performance information, when included as an evaluation factor, to include recent and relevant contracts for the same or similar items and other references (including contract numbers, points of contact with telephone numbers and other relevant information); and
(11) If the quotation is not submitted on the SF 18, include a statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation. Quotations that fail to furnish required representations or information, or reject the terms and conditions of the solicitation may be excluded from consideration.
Terms and content of your quote. Your quote must be based on the terms of this RFQ. We might reject any quote that is not based on these terms in every respect. Your quote must contain all of the information described below.
Small Business Status. In order to submit a quote, you must know whether your company is a small business. The small business size standard that applies to this purchase is stated in FAR 52.204-8, along with the North American Industry Classification System (NAICS) code on which it is based.
Issuance of purchase order. Your quote should contain your best terms. The Contracting Officer may reject any or all quotes. After the evaluation of quotes, the Contracting Officer may negotiate final terms with one or more quoters of the Government’s choice before issuing a purchase order. The Contracting Officer will not negotiate with any quoters other than those of the Government’s choice and will not use the formal source selection procedures described in FAR Part 15.
The Contracting Officer may issue a purchase order to other than the quoter with the lowest price. We might issue multiple orders, purchasing various items or groups of items from different quoters. We might issue an order for less than the quantity on which your quote is based, at the quoted price, unless you tell us that you will not accept an order on that basis.
System for Award Management (SAM). Unless exempted by the Contracting Officer, you must register in SAM before we will issue a purchase order to you. If you do not register by the date set by the Contracting Officer, the Contracting Officer might issue the order to a different quoter. Once registered, you must remain registered throughout performance until final payment. Go to https://www.acquisition.gov for information on SAM registration and annual confirmation.
DUNS Number (Data Universal Numbering System Number). [This applies to all quote if the solicitation requires that you be registered in the System for Award Management (SAM).] Place the annotation “DUNS” or “DUNS+4” next to your name and address on the first page of your quote followed by the DUNS or DUNS+4 number that identifies the quoter’s name and address.
If you do not have a DUNS number, contact Dun and Bradstreet to obtain one. If you are located within the United States, you may contact Dun and Bradstreet by calling 1-866-705-5711 or via the internet at http://fedgov.dnb.com/webform.
If you are located outside the United States, you must contact the local Dun and Bradstreet office for a DUNS number. Tell Dun and Bradstreet that you are a quoter for a Government contract when contacting the local Dun and Bradstreet office.
The DUNS+4 is the DUNS number plus a 4-character suffix that you may use at your discretion to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts (see FAR Subpart 32.11) for your company.
Insurance Required (FAR 52.228-5):
In accordance with FAR 28.307-2, “Liability,” the contractor shall procure the following minimum insurance:
Type Amount Workman’s Compensation and Employer’s Liability Insurance $100,000 General Liability Insurance $1,000,000 per occurrence
And, when automobiles are used in connection with performing the contract:
Type Amount Automobile Liability Insurance $200,000 per person Bodily Injury $500,000 per occurrence Property Damage $ 20,000 per occurrence
And, when aircraft is used in connection with performing the contract:
Type Amount Aircraft Public and Passenger Liability Insurance $200,000 per person Bodily Injury (other than passenger injury) $500,000 per occurrence Property Damage $200,000 per occurrence Passenger Liability Bodily Injury $200,000 multiplied by the number of seats or passengers, whichever is greater
And, when contract performance involves use of vessels, the Contracting Officer shall require, as determined by the agency, vessel collision liability and protection and indemnity insurance. The contractor is responsible for contacting the state for compliance with its workman’s compensation laws.
State and Local Taxes. The U.S. Army Corps of Engineers is exempt from paying state and local taxes per Title 4 United States Code 104-107. The U.S. Army Corps of Engineers Tax ID Number is 62-1642142.
Contractors performing services for the U.S. Army Corps of Engineers are not exempt from state and local taxes in transactions with vendors, suppliers or subcontractors.
(End of Summary of Changes)