Am #0002 - 1

DEPARTMENT OF THE ARMY

Omaha District, Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901 :NOTICE: Failure to acknowledge : Solicitation No. W9128F 16 B 0015 :all amendments may cause rejec- :

:tion of the bid. See FAR : Date of Issue: 05 August 2016 :52.214-3 of Section 00 21 00 : Date of Opening: 07 September 2016

Amendment No. 0002 23 August 2016

SUBJECT: Amendment No. 0002 to Specifications and Drawings for Construction of Penstock Unwatering Piping Rehab, Oahe Dam, SD Solicitation No. W9128F 16 B 0015.

TO: Prospective Bidders and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 00 10 00 Page 1, item 11, delete “120” calendar days and substitute “240” calendar days.

(2) Section 00 73 00 Page 2, paragraph 1.1, delete “120 calendar days” and substitute “240 calendar days”.

(3) Section 01 12 00 Page 5,

a) Paragraph 1.11.1, delete the first sentence reading:

“Government personnel only will operate the overhead crane.” and substitute the following: “Contractor shall be allowed use of the 2 ton overhead crane and will operate the crane without assistance from the government. The operator must be certified in accordance with EM 385-1-1, Safety and Health Requirements Manual, para 16.B.02 and 16.B.05”

b) Delete paragraph 1.11.2 Working Hours.

(4) Section 01 30 00.24 Page 2, paragraph 1.10.a, add the following to the end of the paragraph: “Existing available power is 480 volt 3 phase with 100 amp breaker along with 120 volt single phase with 30 amp breaker. Any additional power requirements shall be furnished by the contractor by use of a generator or other means.”

(5) Section 09 97 02 Pages 11 and 12, delete paragraphs 1.3.3.4

PM-10 Monitoring and 1.3.3.5 TSP Monitoring and substitute “Not Used” in both paragraphs.

2. This amendment is a part of the bidding papers and its receipt shall be acknowledged on the Standard Form 1442. All other conditions and requirements of the specifications remain unchanged. If the bids have been mailed prior to receiving this amendment, you will notify the office where bids are opened, in the specified manner, immediately of its receipt and of any changes in your bid occasioned thereby.

Am #0002 - 2

a. Hand-Carried Bids shall be delivered to the U.S. Army Corps of

Engineers, Omaha District, Contracting Division, 1616 Capitol Avenue, Omaha, Nebraska 68102-4901.

b. Mailed Bids shall be addressed as noted in Item 8 on Page 00 10 00-1 of Standard Form 1442.

3. Bids will be received until 2:00 p.m., local time at place of bid opening, 07 September 2016.

U.S. Army Engineer District, Omaha Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901

23 August 2016

MFS/2184