16-B-0004_JOTC_Bldg_Repl_Specs.pdf
PDF 2 MB Posted
- Solicitation number
- W9128A-16-B-0004
About this file
W9128A-16-B-0004_Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| abstract-16b4-form.pdf | ||
| 16-B-0004_AM-0004.pdf | ||
| 16-B-0004_AM-0003.pdf | ||
| 16-B-0004_AM-0002.pdf | ||
| W9128A-16-B-0004_Amendment_1.pdf | ||
| JOTC_Site_Visit_Map.pdf | ||
| W9128A-16-B-0004.pdf | ||
| 16-B-0004_JOTC_Bldg_Repl_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers
SPECIFICATIONS
TITLE OF PROJECT:
FY16 JOTC BUILDING REPLACEMENT, EAST RANGE
LOCATION:
SCHOFIELD BARRACKS
OAHU, HAWAII
DATE:
30 JUNE 2016
SUBMITTAL TYPE:
RTA
REVIEWED BY: _________________________________
CHIEF, REGIONAL ENGINEERING CENTER
APPROVED BY: _________________________________
CHIEF, ENGINEERING AND CONSTRUCTION DIVISION
This project was designed by the Honolulu District of the U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.
REGIONAL ENGINEERING CENTER
HONOLULU DISTRICT
JOTC1
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 32 00 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL SYSTEM (QCS)
01 45 04 CONTRACTOR QUALITY CONTROL
01 57 20 ENVIRONMENTAL PROTECTION
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION DEBRIS RECYCLING
01 78 00 CLOSEOUT SUBMITTALS
01 90 00 MISCELLANEOUS PROVISIONS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 83 13.00 20 LEAD IN CONSTRUCTION
DIVISION 03 - CONCRETE
03 20 00.00 10 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 35 43.00 10 POLISHEDCONCRETE FINISHING
DIVISION 05 - METALS
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 53 00 PLASTIC WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 90 00 PAINTS AND COATINGS
PROJECT TABLE OF CONTENTS Page 1
DIVISION 10 - SPECIALTIES
10 14 01 EXTERIOR SIGNAGE
10 44 16 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
DIVISION 26 - ELECTRICAL
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 00
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALIFICATIONS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Accepted Project Schedule
3.1.2 Schedule Status Reports
3.1.3 Default
3.2 BASIS FOR PAYMENT AND COST LOADING
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Critical Path Method
3.3.2 Level of Detail Required
3.3.2.1 Activity Durations
3.3.2.2 Procurement Activities
3.3.2.3 Mandatory Tasks
3.3.2.4 Government Activities
3.3.2.5 Activity Responsibility Coding (RESP)
3.3.2.6 Activity Work Area Coding
3.3.2.7 Modification Coding (MODF)
3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)
3.3.2.9 Phase of Work Coding (PHAS)
3.3.2.10 Category of Work Coding (CATW)
3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)
3.3.3 Scheduled Project Completion and Activity Calendars
3.3.3.1 Project Start Date
3.3.3.2 Schedule Constraints and Open Ended Logic
3.3.3.3 Early Project Completion
3.3.3.4 No Government Liability For Early Completion Delay Damages
3.3.4 Interim Completion Dates
3.3.4.1 Start Phase
3.3.4.2 End Phase
3.3.4.3 Phase "X" Hammock
3.3.5 Default Progress Data Disallowed
3.3.6 Out-of-Sequence Progress
3.3.7 Negative Lags and Start to Finish Relationships
3.3.8 Calculation Mode
3.3.9 Milestones
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Preliminary Project Schedule Submission
SECTION 01 32 00 Page 1
3.4.2 Initial Project Schedule Submission
3.4.3 Periodic Schedule Updates
3.4.4 Standard Data Exchange Format (SDEF)
3.5 SUBMISSION REQUIREMENTS
3.5.1 Data CD's
3.5.2 Narrative Report
3.5.3 Approved Changes Verification
3.5.4 Schedule Reports
3.5.4.1 Activity Report
3.5.4.2 Logic Report
3.5.4.3 Total Float Report
3.5.4.4 Earnings Report by CLIN
3.5.5 Network Diagram
3.5.5.1 Continuous Flow
3.5.5.2 Project Milestone Dates
3.5.5.3 Critical Path
3.5.5.4 Banding
3.5.5.5 S-Curves
3.6 PERIODIC SCHEDULE UPDATE MEETINGS
3.6.1 Update Submission Following Progress Meeting
3.6.2 Status of Activities
3.6.2.1 Start and Finish Dates
3.6.2.2 Remaining Duration (RD)
3.6.2.3 Percent Complete
3.6.2.4 Logic Changes
3.6.2.5 Other Changes
3.7 WEEKLY PROGRESS MEETINGS
3.8 REQUESTS FOR TIME EXTENSIONS
3.8.1 Justification of Delay
3.8.2 Submission Requirements
3.8.3 Additional Submission Requirements
3.9 DIRECTED CHANGES
3.10 OWNERSHIP OF FLOAT
3.11 TRANSFER OF SCHEDULE DATA INTO QCS
-- End of Section Table of Contents --
SECTION 01 32 00 Page 2
SECTION 01 32 00
PROJECT SCHEDULE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanical Systems in Construction
1.2 SUBMITTALS
Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Preliminary Project Schedule; G.
Initial Project Schedule; G.
Periodic Schedule Updates.
Two copies of the schedules showing codes, values, categories, numbers, items, etc., as required.
Periodic schedule updates schedules shall be submitted together with the monthly progress payment request.
SD-06 Test Reports
Narrative Report.
Schedule Status Reports.
Two copies of the reports showing numbers, descriptions, dates, float, starts, finishes, durations, sequences, etc., as required.
SD-07 Certificates
Qualifications.
Documentation showing qualifications of personnel preparing schedule reports.
1.3 QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status)
SECTION 01 32 00 Page 3 and preparation of reports. The authorized representative shall be experienced in scheduling projects similar in nature to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
The scheduling of the entire project, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule.
Prepare a Project Schedule for Government acceptance, as specified herein, pursuant to the Contract Clause, Schedule for Construction Contracts. The schedule shall show the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.1.1 Accepted Project Schedule
Use the accepted Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule. The schedule reflects calendar days and not dates for each activity. If the schedule is changed, submit a revised schedule reflecting the change within 7 calendar days.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the accepted schedule, the Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
SECTION 01 32 00 Page 4
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment.
Lack of an accepted schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates.
In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The Project Schedule to be prepared by the Contractor shall be electronically prepared using software capable of generating a data file in the Standard Data Exchange Format (SDEF). The Project Schedule shall consist of a network analysis system as described in this Section.
Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
The systems noted below are capable of generating a file in the Standard Data Exchange Format (SDEF). The SDEF file shall be used to input schedule data into QCS (section 01 45 00). See paragraph Transfer of Schedule Data into QCS. SDEF information is available on the QCS website http://www.rmssupport.com/qcs/guides.aspx
Vendor/System with SDEF support:
Deltek Open Plan
Primavera Systems PRIMAVERA PROFESSIONAL PROJECT MANAGEMENT (P6)
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval.
The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail.
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than
SECTION 01 32 00 Page 5
2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.
3.3.2.2 Procurement Activities
The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.2.3 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Submission of mechanical/electrical/information systems layout drawings.
b. Submission and approval of O & M manuals.
c. Submission and approval of as-built drawings.
d. Submission and approval of installed equipment lists.
e. Submission and approval of testing and air balance (TAB).
f. Submission of TAB specialist design review report.
g. Submission and approval of fire protection specialist.
h. Submission and approval of testing and balancing of HVAC plus commissioning plans and data. Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with ECB 2005-10 .
i. Air and water balancing.
j. HVAC commissioning.
k. Controls testing plan submission.
l. Controls testing.
m. Performance Verification testing.
n. Other systems testing, if required.
o. Contractor's pre-final inspection.
p. Correction of punchlist from Contractor's pre-final inspection.
q. Government's pre-final inspection.
r. Correction of punch list from Government's pre-final inspection.
SECTION 01 32 00 Page 6
s. Final inspection.
3.3.2.4 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.2.5 Activity Responsibility Coding (RESP)
Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, environmental permit approvals by State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.
3.3.2.6 Activity Work Area Coding
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.
Activities shall not have more than one Work Area Code. Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.
3.3.2.7 Modification Coding (MODF)
Assign Modification code to any activity or sequence of activities added to the schedule as a result of a Contract Modification. Key all Code values to the Government's modification numbering system. Activities shall not belong to more than one modification or claim item. The modification or claim number of each activity shall be identified by the Mod or Claim Number. Whenever possible, modifications shall be added to the schedule by adding new activities. Existing activities shall not normally be changed to reflect modifications.
Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer. Assign Activity codes for these activities with a Modification Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall
SECTION 01 32 00 Page 7 not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Modification Code.
3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.
3.3.2.9 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities based upon the phase of work in which the activity occurs. If the contract specifies construction phasing with separately defined performance periods, identify a Construction Phase Code to allow filtering and organizing the schedule accordingly. Each activity shall be identified with a single project phase and have only one Phase of Work code.
3.3.2.10 Category of Work Coding (CATW)
Assign Category of Work Code to all Activities based upon the category of work to which the activity belongs. Category of Work Code must include, but is not limited to: construction submittals, construction submittal approvals, Acceptance, Procurement, Fabrication, Delivery, Weather Sensitive Installation, Non-Weather Sensitive Installation, Start-Up, Test and Turnover. Assign a Category of Work Code to each activity. Each activity shall have only one Category of Work Code.
3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)
Assign a Definable Feature of Work Code to appropriate activities based on the definable feature of work to which the activity belongs. Definable Feature of Work is defined in Specification Section 01 45 00 QUALITY CONTROL SYSTEM. An activity shall not have more than one Definable Feature of Work Code. Not all activities are required to be Definable Feature of Work Coded.
3.3.3 Scheduled Project Completion and Activity Calendars
The schedule duration shall extend from NTP date to the required contract completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be the day after NTP is received by the Contractor. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Assign the Category of Work Code - Weather Sensitive Installation to those activities that are weather sensitive.
Original durations must account for anticipated normal adverse weather.
The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.
SECTION 01 32 00 Page 8
3.3.3.1 Project Start Date
The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Project"( or NTP). The "Start Project" activity shall have an "ES" constraint date equal to the date that the NTP was received, and a zero day duration.
3.3.3.2 Schedule Constraints and Open Ended Logic
Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have an "LF" constraint date equal to the contract completion date for the project, and with a zero day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero free float" or "zero total float" are typically prohibited. There shall only be 2 open ended activities: Start Project (or NTP) with no predecessor logic and End Project with no successor logic.
3.3.3.3 Early Project Completion
In the event the Preliminary or Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, the Contractor shall identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government will not accept an early completion schedule with zero float on the longest path. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.
3.3.3.4 No Government Liability For Early Completion Delay Damages
The Government shall be exempt from liability for early completion delay damages. No claim shall be made or allowed to the Contractor for any damages which may arise out of any delay in early completion.
3.3.4 Interim Completion Dates
Constrain contractually specified interim completion dates to show negative float when the calculated early finish date of the last activity in that phase is later than the specified interim completion date.
3.3.4.1 Start Phase
Include as the first activity for a project phase an activity called "Start Phase X" where "X" refers to the phase of work. The "Start Phase X" activity shall have an "ES" constraint date equal to the date on which the NTP was acknowledged, and a zero day duration.
SECTION 01 32 00 Page 9
3.3.4.2 End Phase
Include as the last activity for a project phase an activity called "End Phase X" where "X" refers to the phase of work. The "End Phase X" activity shall have an "LF" constraint date equal to the specified completion date for that phase and a zero day duration.
3.3.4.3 Phase "X" Hammock
Include a hammock type activity for each project phase called "Phase X" where "X" refers to the phase of work. The "Phase X" hammock activity shall be logically tied to the earliest and latest activities in the phase.
3.3.5 Default Progress Data Disallowed
Do not automatically update Actual Start and Finish dates with default mechanisms that may be included in the scheduling software. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process shall match those dates provided from Contractor Quality Control Reports. Failure of the Contractor to document the AS and AF dates on the Daily Quality Control report for every in-progress or completed activity, and failure to ensure that the data contained on the Daily Quality Control reports is the sole basis for schedule updating shall result in the disapproval of the Contractor's updated schedule and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. Updating of the percent complete and the remaining duration of any activity shall be independent functions. Disable program features which calculate one of these parameters from the other.
3.3.6 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.
Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Correct out of sequence progress that continues for more than two update cycles by logic revision, as approved by the Contracting Officer.
3.3.7 Negative Lags and Start to Finish Relationships
Lag durations contained in the project schedule shall not have a negative value. Do not use Start to Finish (SF) relationships.
3.3.8 Calculation Mode
Schedule calculations shall retain the logic between predecessors and successors even when the successor activity starts and the predecessor activity has not finished. Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") will not be allowed.
3.3.9 Milestones
The schedule must include milestone activities for each significant project event including but not limited to: milestone activities for foundation/substructure construction complete; superstructure construction
SECTION 01 32 00 Page 10 complete; building dry-in or enclosure complete to allow the initiation of finish activities; permanent power complete; and building systems commissioning complete.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD, reports, and network diagrams required for each submission are contained in paragraph
SUBMISSION REQUIREMENTS.
3.4.1 Preliminary Project Schedule Submission
Submit the Preliminary Project Schedule, defining the Contractor's planned operations for the first 90 calendar days for accepted within 15 calendar days after the NTP is acknowledged. The accepted Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. Detail it for the first 90 calendar days. It may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as previously specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required Plan and Program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as other non-construction activities intended to occur within the first 90 calendar days. Schedule any construction activities planned for the first 90 calendar days after NTP. Constrain planned construction activities by Government acceptance of specified Program and Plan approvals. Activity code any activities that are summary in nature after the first 90 calendar days with Responsibility Code (RESP) and Feature of Work code (FOW1, FOW2, FOW3).
3.4.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after NTP. The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. The Initial Schedule shall be at a reasonable level of detail as determined by the Contracting Officer.
3.4.3 Periodic Schedule Updates
Based on the result of the meeting, specified in PERIODIC SCHEDULE UPDATE MEETINGS, submit periodic schedule updates. These submissions will enable the Contracting Officer to assess Contractor's progress. If the Contractor fails or refuses to furnish the information and project schedule data, which in the judgment of the Contracting Officer or authorized representative is necessary for verifying the Contractor's progress, the Contractor shall be deemed not to have provided an estimate upon which progress payment may be made.
3.4.4 Standard Data Exchange Format (SDEF)
A template SDEF compatible schedule file (sdef.prx) is available on the QCS website: www.rmssupport.com/qcs/guides.aspx. It is highly recommended that the QCS Program Help files related to Primavera found on this site be carefully reviewed prior to constructing the Project Schedule. Schedules that do not use this template will not generate a correct SDEF file.
SECTION 01 32 00 Page 11
3.5 SUBMISSION REQUIREMENTS
Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:
3.5.1 Data CD's
Provide two sets of data CD's containing the project schedule in the backup format. Each CD shall also contain all previous update backup files. Label each CD indicating the type of schedule (Preliminary, Initial, Update), full contract number, Data Date and file name. Each schedule shall have a unique file name as determined by the Contractor.
3.5.2 Narrative Report
Provide a Narrative Report with the Preliminary, Initial, and each Periodic Update submittal of the project schedule, as the basis of the progress payment request. The Narrative Report shall include: a description of activities along the 2 most critical paths where the total float is less than or equal to 20 work days, a description of current and anticipated problem areas or delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. The narrative report is expected to communicate to the Government, the Contractor's thorough analysis of the schedule output and its plans to compensate for any problems, either current or potential, which are revealed through that analysis. Identify and explain why any activities that, based on their calculated late dates, should have either started or finished during the update period but did not.
3.5.3 Approved Changes Verification
Include only those project schedule changes in the schedule submission that have been previously approved by the Contracting Officer. The Narrative Report shall specifically reference, on an activity by activity basis, all changes made since the previous period and relate each change to documented, approved schedule changes.
3.5.4 Schedule Reports
The format, filtering, organizing and sorting for each schedule report shall be as directed by the Contracting Officer. Typically reports shall contain: Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. The following lists typical reports that will be requested. One or all of these reports may be requested for each schedule submission.
3.5.4.1 Activity Report
A list of all activities sorted according to activity number.
3.5.4.2 Logic Report
A list of detailed predecessor and successor activities for every activity in ascending order by activity number.
SECTION 01 32 00 Page 12
3.5.4.3 Total Float Report
A list of all incomplete activities sorted in ascending order of total float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.
3.5.4.4 Earnings Report by CLIN
A compilation of the Contractor's Total Earnings on the project from the NTP to the data date. This report shall reflect the earnings of specific activities based on the agreements made in the schedule update meeting defined herein. Provided that the Contractor has furnished a complete schedule update, this report shall serve as the basis of determining progress payments. Group activities by CLIN item number and sort by activity number. This report shall: sum all activities coded to a particular CLIN and provide a CLIN item percent earned value; and complete and sum CLIN items to provide a total project percent complete. The printed report shall contain, for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Total Quantity, Quantity to Date, Percent Complete (based on cost), and Earnings to Date.
3.5.5 Network Diagram
The network diagram is required for the Preliminary, Initial and Periodic Updates. The network diagram shall depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:
3.5.5.1 Continuous Flow
Diagrams shall show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.
3.5.5.2 Project Milestone Dates
Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.
3.5.5.3 Critical Path
Clearly show the critical path.
3.5.5.4 Banding
Organize activities as directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by category of work, work area and/or responsibility.
3.5.5.5 S-Curves
Earnings curves showing projected early and late earnings and earnings to date.
3.6 PERIODIC SCHEDULE UPDATE MEETINGS
Conduct periodic schedule update meetings for the purposes of reviewing
SECTION 01 32 00 Page 13 the Contractor's proposed out of sequence corrections, determining causes for delay, correcting logic, maintaining schedule accuracy and determining earned value. Meetings shall occur at least monthly within five days of the proposed schedule data date and after the Contractor has updated the schedule with Government concurrence respecting actual start dates, actual finish dates, remaining durations and percent complete for each activity it intends to status. Provide a computer with the scheduling software loaded and a projector during the meeting which allows all meeting participants to view the proposed schedule update during the meeting.
The meeting and resultant approvable schedule update shall be a condition precedent to a formal submission of the update as described in SUBMISSION REQUIREMENTS and to the submission of an invoice for payment. The meeting will be a working interactive exchange which will allow the Government and the Contractor the opportunity to review the updated schedule on a real time and interactive basis. The Contractor's authorized scheduling representative will organize, sort, filter and schedule the update as requested by the Government. The meeting will last no longer than 8 hours. A rough draft of the proposed activity logic corrections and narrative report shall be provided to the Government 48 hours in advance of the meeting. The Contractor's Project Manager and Authorized Scheduler shall attend the meeting with the Contracting Officer's Representative.
3.6.1 Update Submission Following Progress Meeting
Submit a complete update of the project schedule containing all approved progress, revisions, and adjustments, pursuant to paragraph SUBMISSION REQUIREMENTS not later than 4 working days after the periodic schedule update meeting, reflecting only those changes made during the previous update meeting.
3.6.2 Status of Activities
Update information, including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete shall be subject to the approval of the Government prior to the meeting. As a minimum, address the following items on an activity by activity basis during each progress meeting.
3.6.2.1 Start and Finish Dates
Accurately show the status of the AS and/or AF dates for each activity currently in-progress or completed since the last update. The Government may allow an AF date to be assigned with the percent complete less than 100% to account for the value of work remaining but not restraining successor activities. Only assign AS dates when actual progress occurs on an activity.
3.6.2.2 Remaining Duration (RD)
Update the estimated remaining duration (RD) for all incomplete activities independent of Percent Complete. Remaining Durations may exceed the activity Original duration (OD) or may exceed the activity's prior update RD if the Government considers the current OD or RD to be understated based on current progress, insufficient work crews actually manning the job, unrealistic OD or deficiencies that must be corrected that restrain successor activities.
SECTION 01 32 00 Page 14
3.6.2.3 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete.
To allow for proper schedule management, cost load the correction of punch list from Government pre-final inspection activity(ies) not less than 1 percent of the total contract value, which activity(ies) may be declared 100 percent complete upon completion and correction of all punch list work identified during Government pre-final inspection(s).
3.6.2.4 Logic Changes
Specifically identify and discuss all logic changes pertaining to NTP on change orders, change orders to be incorporated into the schedule, Contractor proposed changes in work sequence, corrections to schedule logic for out-of-sequence progress, and other changes that have been made pursuant to contract provisions. The Government will only approve logic revisions for the purpose of keeping the schedule valid in terms of its usefulness in calculating a realistic completion date, correcting erroneous logic ties, and accurately sequencing the work.
3.6.2.5 Other Changes
Other changes required due to delays in completion of any activity or group of activities include: 1) delays beyond the Contractor's control, such as strikes and unusual weather. 2) delays encountered due to submittals, Government Activities, deliveries or work stoppages which make re-planning the work necessary. 3) Changes required to correct a schedule that does not represent the actual or planned prosecution and progress of the work.
3.7 WEEKLY PROGRESS MEETINGS
a. The Government and the Contractor shall meet weekly (or as otherwise mutually agreed to) between the meetings described in paragraph PERIODIC SCHEDULE UPDATE MEETINGS for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. The then current and approved schedule update shall be used for the purposes of this meeting and for the production and review of reports. The Contractor's Project Manager and the Contracting Officer's Representative shall attend. The weekly progress meeting will address the status of RFI's, RFP's and Submittals.
b. Provide a bar chart produced by the scheduling software, organized by Total Float and Sorted by Early Start Date, and a two week "look-ahead" schedule by filtering all schedule activities to show only current ongoing activities and activities schedule to start during the upcoming two weeks, organized by Work Area Code (AREA) and sorted by Early Start Date.
c. The Government and the Contractor shall jointly review the reports. If it appears that activities on the longest path(s) which are currently driving the calculated completion date (driving activities), are not progressing satisfactorily and therefore could jeopardize timely project completion, corrective action must be taken immediately. Corrective action includes but is not limited to:
SECTION 01 32 00 Page 15 increasing the number of work crews; increasing the number of work shifts; increasing the number of hours worked per shift; and determining if Government responsibility coded activities require Government corrective action.
3.8 REQUESTS FOR TIME EXTENSIONS
In the event the Contractor believes it is entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the Contracting Officer: justification, project schedule data, and supporting evidence as the Contracting Officer may deem necessary. Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government.
In response to each Request For Proposal issued by the Government, the Contractor shall submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.
3.8.1 Justification of Delay
The project schedule shall clearly display that the Contractor has used, in full, all the float time available for the work involved with this request. The Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, or any interim milestone date.
3.8.2 Submission Requirements
Submit a justification for each request for a change in the contract completion date of less than 2 weeks based upon the most recent schedule update at the time of the NTP or constructive direction issued for the change. Such a request shall be in accordance with the requirements of other appropriate Contract Clauses and shall include, as a minimum:
a. A list of affected activities, with their associated project schedule activity number.
b. A brief explanation of the causes of the change.
c. An analysis of the overall impact of the changes proposed.
d. A sub-network of the affected area.
Identify activities impacted in each justification for change by a unique activity code contained in the required data file.
3.8.3 Additional Submission Requirements
The Contracting Officer may request an interim update with revised activities for any requested time extension of over 2 weeks. Provide this disk within 4 days of the Contracting Officer's request.
SECTION 01 32 00 Page 16
3.9 DIRECTED CHANGES
If the NTP is issued for changes prior to settlement of price and/or time, submit proposed schedule revisions to the Contracting Officer within 2 weeks of the NTP being issued. The Contracting Officer will approve proposed revisions to the schedule prior to inclusion of those changes within the project schedule. If the Contractor fails to submit the proposed revisions, the Contracting Officer may furnish the Contractor with suggested revisions to the project schedule. The Contractor shall include these revisions in the project schedule until revisions are submitted, and final changes and impacts have been negotiated. If the Contractor has any objections to the revisions furnished by the Contracting Officer, advise the Contracting Officer within 2 weeks of receipt of the revisions. Regardless of the objections, the Contractor shall continue to update the schedule with the Contracting Officer's revisions until a mutual agreement in the revisions is reached. If the Contractor fails to submit alternative revisions within 2 weeks of receipt of the Contracting Officer's proposed revisions, the Contractor will be deemed to have concurred with the Contracting Officer's proposed revisions. The proposed revisions will then be the basis for an equitable adjustment for performance of the work.
3.10 OWNERSHIP OF FLOAT
Float available in the schedule, at any time, shall not be considered for the exclusive use of either the Government or the Contractor. However, in accordance with paragraph 3.3.3.4 above, the Government is specifically and expressly exempt from liability for early completion delay damages.
3.11 TRANSFER OF SCHEDULE DATA INTO QCS
Download the schedule date into the Quality Control System (QCS) (see Section 01 45 00) using the scheduling software's SDEF capability prior to exporting to RMS. This data is considered to be additional supporting data in a form and detail required by the Contracting Officer pursuant to FAR 52.232-5 - Payments under Fixed-Price Construction Contracts. The receipt of a proper payment request pursuant to FAR 52.232-27 - Prompt Payment for Construction Contracts is contingent upon the Government receiving both acceptable and approveable hard copies and electronic export from QCS of the application for progress payment.
-- End of Section --
SECTION 01 32 00 Page 17
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
1.1.2 Approving Authority
1.1.3 Work
1.2 SUBMITTALS
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2 Information Only
1.4 QUANTITY OF SUBMITTALS
1.4.1 Number Copies of Government Approved Submittals: 4
1.4.2 Number of Copies of Information Only Submittals: 3
1.4.3 Electronic Copies
1.5 APPROVED/ACCEPTED SUBMITTALS
1.6 APPROVED SAMPLES
1.7 DISAPPROVED OR REJECTED SUBMITTALS
1.8 INFORMATION ONLY SUBMITTALS
1.9 GOVERNMENT APPROVING AUTHORITY
1.9.1 Government Review Action Codes
1.9.2 Review Notations
1.10 WITHHOLDING OF PAYMENT
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 SUBMITTAL REGISTER
3.2 SCHEDULING
3.3 TRANSMITTAL FORM
3.3.1 Numbering
3.4 SUBMITTAL PROCEDURE
3.4.1 Procedures
3.4.2 Variations / Substitution Requests
3.4.2.1 Considering Variations
3.4.3 Proposing Variations
3.4.4 Warranting That Variations Are Compatible
3.4.5 Review Schedule Is Modified
3.5 CONTROL OF SUBMITTALS
3.5.1 Monthly Updates of Submittal Register
3.6 STAMPS
-- End of Section Table of Contents --
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
List of proposed Subcontractors
Network Analysis Schedule (NAS)
SECTION 01 33 00 Page 2
Submittal register
Schedule of prices
Accident Prevention plan
Quality Control(QC) plan
Environmental protection plan
Permits
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
SECTION 01 33 00 Page 3
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements.
This is the start of the file's text. The full file is on GovTribe.